Variable-diameter chimney slip form construction method based on BIM (Building Information Modeling) and with circular exterior and square interior
The modeling and design and verification of chimney sliding mold equipment through BIM technology has solved the problems of chimney height, narrowness and variable diameter construction, achieved the synchronous improvement of sliding mold equipment, improved construction safety and efficiency, and reduced cost and material consumption.
Patent Information
- Application Number
- CN202410923802.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-20
- Publication Date
- 2024-11-15
AI Technical Summary
The chimney is high and there is a sightseeing elevator shaft in the cylinder, and the working space is narrow. It is difficult to arrange vertical transportation machinery for personnel up and down during construction. The cylinder walls are changing in diameter, and the safety risks are high. The synchronization between the outer concrete structure and the outer concrete platform Difficulties in construction and coordination.
Using the BIM-based variable diameter outer circular inner square chimney sliding form construction method, the sliding form equipment modeling design and verification are carried out through BIM technology, and the total vertical load and concrete molding strength of the sliding form equipment are calculated to realize the inner ring of the sliding form equipment. Improve simultaneously with the outer ring to reduce construction safety risks, and optimize construction plans through the BIM system to improve construction efficiency.
Improve construction safety, reduce construction costs, solve the problem of complex construction organizational relationship between sliding form equipment and building partitions, and achieve efficient and continuous concrete pouring and smooth and seamless surface, with less material consumption, construction safety and quality high quality.
Smart Images

Figure BDA0004937486890000071 
Figure BDA0004937486890000081 
Figure BDA0004937486890000082
Abstract
Description
Technical Field
[0001] The invention relates to the field of construction, and in particular to a sliding form construction method for a chimney with a variable diameter outer circle and inner square based on BIM. Background Art
[0002] The chimney of Chengdu Wanxing Environmental Protection Power Plant Phase III project is a multi-tube chimney, which is a structure with a total height of 132m. It has a reinforced concrete sleeve-type appearance. The inner wall of the smoke pipe is painted with 0M-5 anti-corrosion paint, and the outer wall is wrapped with 180mm thick glass wool, which is fixed with an outer wrapping plate. The inside of the smoke pipe is a rectangular cylinder with a 3T elevator inside. On the one hand, it is used for regular monitoring by environmental protection department staff, and on the other hand, visitors can take the elevator to the sightseeing platform on the 125m floor, from which they can overlook the surrounding landscape.
[0003] The difficulty of construction is as follows:
[0004] 1. The chimney is relatively high, and a sightseeing elevator shaft is set up inside the chimney. The working space is narrow, and it is difficult to arrange the vertical transportation machinery for personnel during construction;
[0005] Second, there are many floors in the chimney, a total of 17 floors, including 12 concrete floors and 5 steel floors; the relationship between the cylinder wall slipform and the floor construction organization is complicated;
[0006] 3. The chimney is very close to the adjacent buildings under construction and the main construction passages of the entire site, posing a high safety risk;
[0007] Fourth, the cylinder wall has many diameter changes, and there are many door and window openings and embedded parts in the cylinder wall. The safety risk is high during the empty sliding period, so accurate positioning is required to prevent omissions;
[0008] 5. The synchronous construction and coordination of the outer concrete structure and the outer concrete platform is a difficult point; Summary of the invention
[0009] The present invention provides a device for solving the above-mentioned problem and realizing fully automatic laying and conveying of light-curing pipeline repair materials with a large diameter in the process of municipal pipeline repair.
[0010] In order to achieve the above-mentioned purpose, the technical solution adopted by the present invention is: a sliding form construction method of a chimney with a variable diameter outer circle and inner square based on BIM, and the method steps are as follows:
[0011] Step S1, using BIM technology to model and design the sliding form equipment and verify the calculation;
[0012] Firstly, the sliding form equipment is modeled and designed for the variable diameter chimney with outer circle and inner square;
[0013] Then, the total vertical load N of the slipform equipment is calculated through the BIM system;
[0014] Secondly, the BIM system uses a calculation formula to calculate whether the jack can meet the construction needs. The calculation formula is as follows:
[0015] n=N / P
[0016] Where, n is the minimum number of supporting rods or jacks; N is the total vertical load (KN); P is the allowable bearing capacity of a single jack (the allowable bearing capacity of the supporting rod or half of the rated lifting capacity of the jack, whichever is smaller);
[0017] Step S2: Conduct no-load and load tests before construction, and input the test data into the BIM system for verification;
[0018] Step S3, calculating the sliding speed and concrete demoulding strength through the BIM system;
[0019] When the support rod is not likely to become unstable, the demoulding strength of the concrete can be controlled by the following formula:
[0020] V=(Hha) / T
[0021] Where, V is the template sliding speed m / h; H is the template height m; h is the thickness of each pouring layer m; α is the distance from the surface to the template opening after the concrete is fully poured, which is 0.1m; T is the time required for the concrete to reach the demoulding strength h;
[0022] Step S4, perform initial sliding according to the BIM calculation results, and feed back the initial sliding test results to the BIM system for inspection;
[0023] Step S5, debugging and various inspections;
[0024] Step S5, normal sliding;
[0025] Step S6: After the sliding is completed, the sliding is stopped and the sliding formwork equipment is dismantled.
[0026] Preferably, when modeling is performed in step S1, the slipform equipment consists of an inner ring lifting platform, an outer ring lifting platform and a gallery bridge, the inner ring lifting platform is erected on the top of the square inner tube of the chimney, the outer ring lifting platform is erected on the top of the circular outer tube of the chimney, and the inner ring lifting platform and the outer ring lifting platform are connected by a gallery bridge and a radiating beam.
[0027] Preferably, in step S1, the BIM method for performing total vertical load is as follows:
[0028] a. Calculate the load of the sliding form equipment
[0029] The system calculates the load of the sliding formwork equipment in the corresponding range of each gantry according to statistics;
[0030] b. Calculate the construction load of the operating platform:
[0031] Operation platform construction load = construction load standard value + personnel and auxiliary equipment load
[0032] In the formula, the standard value of construction load = 1.5KN / m*operating platform area m 2 , 1.5KN / m is the parameter value for calculating the number of support rods based on the standard value of construction load on the operating platform in Appendix A.0.1 of the Technical Standard for Sliding Formwork Engineering (2005);
[0033] In the formula, the load of personnel and auxiliary equipment is calculated based on the number of construction personnel, hydraulic equipment, welding equipment on the slipform equipment, and the amount of concrete, steel bars and other materials allowed to be stacked on the platform;
[0034] c. Calculate the friction resistance load between steel formwork and concrete:
[0035] Friction resistance load = contact area of steel formwork * friction coefficient
[0036] Total vertical load N = slipform equipment load + operating platform construction load + friction resistance between steel formwork and concrete.
[0037] Preferably, in step S1, the method for calculating the allowable bearing capacity P of the support rod is as follows;
[0038] According to Appendix A of the Technical Specifications for Sliding Formwork Engineering (GB / T50113-2019):
[0039] P=(α / K)×(99.6-0.22L0)
[0040] Where, P is the allowable bearing capacity of the supporting rod (kN); α is the working condition coefficient of the split platform area, which is 0.8; K is the safety factor, which is 2.0; L0 is the empty length of the supporting rod (cm), which is 100cm.
[0041] Preferably, in step S5, the concrete is trial-mixed and an early strength growth curve is made, which is divided into strength values of 1h, 2h, 3h, 6h, 12h, 24h, 48h, 72h and 7 days. The BIM system designs the construction schedule according to the growth curve, and reduces the pause by taking measures such as thin layer concrete pouring and slight lifting with jacks. Continuous sliding should be carried out within the specified time. During the sliding process, the interval between two liftings should be kept at about 0.5 hours, and the number of intermediate liftings should be appropriately increased or decreased according to the temperature and concrete strength. The intermediate lifting height is 1-2 jack strokes.
[0042] Preferably, in step S5, when the sliding stops, within the height range from the jack to the concrete surface, the two support rods are tied together with φ12 hook bars with a spacing of no more than 300 mm, the hook bars are spot welded firmly to the support rods, and a φ48*3.2 steel pipe is added on both sides of the original support rod in the middle of the vertical wall of the steel formwork, and then the four steel pipes are welded into a diamond lattice column with φ20 "S"-shaped steel bars. When the width of the hole is greater than 2.5 m, ф48×3.5 steel pipes are added on both sides of the support rods, which are welded into lattice columns with φ25 steel bars, and the support rods of two to three lifting frames are connected with φ25 steel bars to form an integrated whole.
[0043] Preferably, in step S1, the internal force, section strength, deflection and overall stability of the enclosure around the steel formwork are verified by calculation using the BIM system to verify whether the enclosure meets the requirements.
[0044] Preferably, in step S1, the strength, shear force and deflection of the beams of the lifting frame are checked by calculation using the BIM system, the load analysis of the columns of the lifting frame is performed, and the bearing capacity, strength, shear resistance and deflection of the hanging scaffolding are checked, so as to check whether the lifting frame meets the requirements.
[0045] Preferably, in step S1, the strength, deflection and support reaction force of the panel on the operating platform are verified by calculation using a BIM system to verify whether the panel meets the requirements.
[0046] Preferably, in step S1, the load, bending, shear, deflection and support reaction of the small beams and main beams on the operating platform of the slipform equipment are checked by calculation using the BIM system to verify whether the main beams and small beams meet the requirements.
[0047] Compared with the prior art, the advantages of the present invention are:
[0048] (1) The present invention designs a slipform device for a chimney with a circular outer surface and a square inner surface. The slipform construction of the chimney is achieved by synchronously lifting the inner ring lifting platform and the outer ring lifting platform of the slipform device. There is no need to worry about the chimney being close to adjacent buildings under construction and the main construction passages of the entire site, and the safety risk is low.
[0049] (2) BIM technology can be used to present the building model in three-dimensional form, making the design more intuitive. It can also coordinate data and information among all project participants to ensure the smooth progress of the project and reduce construction costs. The use of BIM technology can reduce the difficulty of synchronous construction and coordination of the outer concrete structure and the inner concrete platform, and can also solve the complex relationship between the slipform equipment and the floor interlayer construction organization.
[0050] (3) It can simulate the construction process before actual construction, help discover potential problems through verification, and help optimize the design plan and construction plan through data analysis to avoid construction loopholes, greatly improving construction safety.
[0051] (4) The construction method of the present invention has the advantages of high degree of mechanization, fast construction speed, remarkable comprehensive benefits, high construction continuity, fast speed, good concrete continuity, smooth surface, no construction joints, low material consumption, saving a large amount of tie rods, safe construction, and high quality. It is a construction technology that can be widely adopted and promoted. BRIEF DESCRIPTION OF THE DRAWINGS
[0052] Figure 1 It is a structural schematic diagram of the sliding mode equipment of the present invention;
[0053] Figure 2 It is a schematic diagram of the cross-sectional structure of the sliding form equipment of the present invention;
[0054] Figure 3 It is a schematic diagram of the partial structure of the sliding mode equipment of the present invention;
[0055] Figure 4 It is a schematic diagram of the cross-sectional structure of the chimney body of the present invention;
[0056] Figure 5 This is a diagram of the attachment position of the chimney tower crane of the present invention;
[0057] Figure 6 This is a real picture of the chimney of the Chengdu Wanxing Environmental Protection Power Plant Phase III project of the present invention.
[0058] In the figure: 1. Outer ring lifting platform; 2. Inner ring lifting platform; 3. Corridor bridge; 4. Radiating beam; 5. Scaffolding; 6. Chimney; 7. Lifting frame; 8. Table; 9. Main beam; 10. Steel formwork; 11. Circle. DETAILED DESCRIPTION
[0059] Example:
[0060] The chimney of the Chengdu Wanxing Environmental Protection Power Plant Phase III project is extremely high and large in diameter, making construction extremely difficult. Figure 4-Figure 6 .
[0061] The main structure of this building is designed to have a service life of 50 years. The building structure safety level is level 2, the seismic wall seismic level is level 2, and the calculated embedded part of the structure is the top of the foundation; the outer wall diameter of the chimney is 16.2 meters, of which the outer wall diameter remains unchanged, and the inner wall changes suddenly according to the structural height. For detailed relevant information, please see the table below; the clearance size in the elevator shaft is 2.8 meters * 2.5 meters (outer wall size is 3.5 meters * 3.2 meters), and the shaft wall thickness is 350mm from beginning to end.
[0062] Table 1 Chimney parameters
[0063] Serial number Section (elevation) Chimney wall thickness Concrete strength grade Remark 1 -0.3m~26m 600mm C40 2 26m~53m 500mm C40, C35 Among them, 26m~35m is C40 3 53m~80m 400mm C35, C30 Among them, 53m~62m is C35 4 80m~128.5m 300mm C30 5 128.5m~131.5m 200mm C30
[0064] The present invention will be further described below: A sliding form construction method for a chimney with a variable diameter outer circle and inner square based on BIM, the method steps are as follows:
[0065] Step S1, using BIM technology to model and design the sliding form equipment and verify the calculation;
[0066] The sliding form equipment is modeled and designed for the variable diameter chimney 6 with an outer circle and an inner square. The sliding form equipment consists of an inner ring lifting platform 2, an outer ring lifting platform 1 and a gallery bridge 3. Figures 1 to 5 The inner ring lifting platform 2 is erected on the top of the square inner tube of the chimney 6, and the outer ring lifting platform 1 is erected on the top of the circular outer tube of the chimney 6. The inner ring lifting platform 2 and the outer ring lifting platform 1 are connected through a gallery bridge 3 and a radiation beam 4. The sliding formwork construction of the chimney 6 is realized by synchronously lifting the inner ring lifting platform 2 and the outer ring lifting platform 1 through the sliding formwork equipment. The structural connection between the inner ring lifting platform 2 and the outer ring lifting platform 1 is realized through the gallery bridge 3 and the radiation beam 4. The gallery bridge 3 can also be used as a personnel circulation channel and a material transportation channel.
[0067] The total vertical load N of the slipform equipment is calculated through the BIM system. The formula is as follows:
[0068] Total vertical load N = slipform equipment load + operating platform construction load + friction resistance between steel formwork 10 and concrete
[0069] a. Calculate the load of the sliding form equipment
[0070] The system calculates the load of the sliding formwork equipment in the corresponding range of each gantry according to statistics;
[0071] In this embodiment, 36 sets of door frames are planned to be arranged on the outer wall of the chimney 6. According to statistical calculations, the template load (including safety protection equipment, etc.) of the corresponding range of each set of door frames is 8.075KN / set, and its load is 80.75*36=290.7KN
[0072] b. Calculate the construction load of the operating platform:
[0073] Operation platform construction load = construction load standard value + personnel and auxiliary equipment load
[0074] In the formula, the standard value of construction load = 1.5KN / m*operating platform area m 2 , 1.5KN / m is the parameter value for calculating the number of support rods based on the standard value of the construction load on the operating platform in Appendix A.0.1 of the Technical Standard for Sliding Formwork Engineering (2005);
[0075] The operating platform area of the slipform equipment is 3.14*16.2*1.6*2=162.78m2
[0076] Then, the standard value of construction load is 162.78*1.5=244.17KN
[0077] In the formula, the load of personnel and auxiliary equipment is calculated based on the number of construction personnel, hydraulic equipment, welding equipment on the slipform equipment, and the amount of concrete, steel bars and other materials allowed to be stacked on the platform;
[0078] ①、Staff: 25 people × 0.8KN / person = 20KN
[0079] ②, Hydraulic equipment, welding machines and other tools: 10KN
[0080] ③. The platform allows the stacking of concrete, steel bars and other materials (evenly placed) 25KN
[0081] ④. Other possible items: 10KN
[0082] Personnel and auxiliary equipment load ∑=20+10+25+10=65KN
[0083] c. Calculate the friction resistance load between the steel formwork 10 and the concrete:
[0084] Friction resistance load = contact area of steel template 10 * friction coefficient
[0085] The contact area of the steel template 10 is: 3.14*16.2*1.2*2=122.08m 2
[0086] Then, the friction resistance load is: 122.08*3KN / m=366.24KN
[0087] Total vertical load N = a + b + c = 290.7 + (244.17 + 65) + 366.24 = 966.11 KN
[0088] The BIM system uses calculation formulas to calculate whether the jack can meet the construction needs;
[0089] Calculation formula: n = N / P
[0090] Where, n is the minimum number of supporting rods or jacks; N is the total vertical load (KN); P is the allowable bearing capacity of a single jack (the allowable bearing capacity of the supporting rod or half of the rated lifting capacity of the jack, whichever is smaller);
[0091] Among them, the calculation method of the allowable bearing capacity of the support rod is as follows;
[0092] According to Appendix A of the Technical Specifications for Sliding Formwork Engineering (GB / T50113-2019):
[0093] P=(α / K)×(99.6-0.22L0)
[0094] Where, P is the allowable bearing capacity of the support rod (kN); α is the working condition coefficient of the split platform area, which is 0.8; K is the safety factor, which is 2.0; L0 is the empty length of the support rod (cm), which is 100cm;
[0095] After calculation, P = 31.04kN, which is the allowable load capacity of the support rod or jack;
[0096] This embodiment project uses GYD-60 ball hydraulic jack, and its related indicators are as follows
[0097] Compared with the commonly used GYD-35 small-tonnage jack, the GYD-60 ball hydraulic jack adopts a multi-row structure of steel balls to ensure the clamping effect and has the advantage of large lifting capacity. Since the 48*3.5 steel pipe is selected as the support rod, its pressure stability is better than 25 round steel. At the same time, it also greatly reduces the tonnage of the support rod, providing a strong condition for the tooling of the support rod and facilitating construction. It is an upgraded product of the GYD35 small-tonnage jack.
[0098] Technical parameters:
[0099] 1. Maximum lifting capacity: 60KN
[0100] 2. Working lifting capacity 30KN
[0101] 3. Actual working stroke range 20-30mm
[0102] 4. Oil cylinder capacity: 0.35L
[0103] 5. Rated working pressure 8Mpa
[0104] 6. Mass: 23.5Kg
[0105] 7. Overall dimensions: 160*160*298mm
[0106] 8. Installation size of base: 120*120.4--17 holes
[0107] 9. Support rod size 48*3.5mm (mild steel pipe)
[0108] According to the design performance of the jack, the allowable bearing capacity of a single jack is 1 / 2 of the rated bearing capacity, [P0] = 30KN
[0109] n=N / P0=966.11 / 30=32.2 units
[0110] Therefore, 36 GYD-60 jacks are used on the six walls of the chimney to meet the construction needs. Similarly, 12 jacks are arranged on the square inner tube elevator shaft to meet the load requirements.
[0111] Step S2: Conduct no-load and load tests before construction, and input the test data into the BIM system for verification;
[0112] No-load and load test process: set up temporary assembly platform → install lifting frame 7 → install inner and outer rings 11 → install inner formwork → tie vertical steel bars and horizontal steel bars below the lifting beam → install outer formwork → install inner and outer cantilever tripods, railing platform, hydraulic platform → install jacks and hydraulic equipment → no-load test, oil line pressurization and exhaust → install support rods → comprehensive overhaul → install hangers and protective nets, safety nets;
[0113] Step S3, calculating the sliding speed and concrete demoulding strength through the BIM system;
[0114] When the support rod is not likely to become unstable, the demoulding strength of the concrete can be controlled by the following formula:
[0115] V=(Hha) / T
[0116] Where, V is the template sliding speed m / h; H is the template height m; h is the thickness of each pouring layer m; α is the distance from the surface to the template opening after the concrete is fully poured, which is 0.1m; T is the time required for the concrete to reach the demoulding strength h;
[0117] Through calculation, in this embodiment, the slipform equipment operates continuously for 24 hours, the initial setting time of concrete is controlled at about 4 hours, and the final setting time is controlled at about 8 hours. According to the weather, vertical transportation of concrete, and the binding of steel bars, the sliding speed V should be greater than 0.1 m / hour and should be no less than 3 meters per day.
[0118] Step S4, perform initial sliding according to the BIM calculation results, and feed back the initial sliding test results to the BIM system for inspection;
[0119] The initial slip process is as follows: before pouring concrete, pour a cement mortar bonding layer of about 20mm thick, and then pour concrete in layers, with each layer pouring thickness of 200-300mm, compacted with an inserted vibrator, the first layer pouring height is 200mm and completed within 1 hour; the second layer pouring height is 200mm and completed within 1 hour, the third layer pouring height is 200mm, completed within 1 hour, the fourth layer pouring 300mm fills the formwork and is completed within 1.5 hours. The total height of the four layers is about 900mm and the time is within 4.5 hours, and the fastest should not be less than 4 hours (the initial setting time of concrete should not exceed 2 hours).
[0120] Step S5, debugging and various inspections;
[0121] Step S5: Normal Sliding
[0122] When the concrete strength reaches between initial setting and final setting, that is, the bottom concrete strength reaches 0.3-0.35Mpa (when the concrete penetration resistance value is 0.30kN / cm-1.05kN / cm), the trial lifting can be carried out. During the trial lifting, the formwork should be raised by 5cm, that is, the jack is lifted 1-2 strokes. When the concrete does not collapse after being demolded and is not lifted by the formwork (finger marks can be seen when pressed with fingers, and the mortar does not stick to fingers), the initial lifting can be carried out to see whether it slides smoothly. If there are some places that have not risen, use a jack to push it up, and then start to slide one stroke until it rises to 300mm high.
[0123] Sliding schedule: Normally sliding to 26m → Construction of 8m and 17m floor structures → Sliding to 53m → Construction of 26m and 44m floor structures → Sliding to 80m → Construction of 62m floor structure → Sliding to 107m → Construction of 80m and 98m floor structures → Sliding to 129m → Construction of 116 floor structures → Sliding to 131.5m;
[0124] In the normal sliding stage, the sliding speed is controlled at 150mm / hour. When pouring the previous layer of concrete, the next layer of concrete should be in a plastic state. When designing the mix ratio of concrete, the initial setting time is generally controlled at about 3 hours, and the final setting time is generally controlled at 4 to 7 hours.
[0125] In order to effectively control the sliding time, the concrete should be trial-mixed first, and an early strength growth curve should be made, which is divided into strength values of 1h, 2h, 3h, 6h, 12h, 24h, 48h, 72h and 7 days.
[0126] During sliding: take measures such as pouring thin layers of concrete and lifting the jack slightly to reduce pauses. Sliding should be continuous within the specified time. During the sliding process, the interval between two lifts should be kept at about 0.5 hours, and the number of intermediate lifts should be appropriately increased or decreased according to the temperature and concrete strength. The intermediate lifting height is 1-2 jack strokes.
[0127] Since the chimney 6 of the present scheme is round on the outside and square on the inside, the square inner tube is used as an elevator shaft for installing a sightseeing elevator. Door and window holes connected to the sightseeing elevator will be opened on the upper part of the outer tube of the chimney 6, and a sightseeing platform will be built. Since the door and window holes are prone to air sliding, structural columns need to be welded when the sliding stops to prevent the sliding formwork equipment from air sliding or tilting.
[0128] When the slide stops: within the height range from the jack to the concrete surface, the two support rods are tied with φ12 hook bars, with a spacing of no more than 300mm, and the hook bars are spot welded firmly to the support rods. A φ48*3.2 steel pipe is added to each side of the original support rod in the middle of the vertical wall of the steel formwork 10, and then the four steel pipes are welded into a diamond lattice column with φ20 "S" type steel bars. When the support rod is vacant and the height exceeds 1.5m, the support rod is also reinforced in the above method at (the reserved opening of the beam nest, the door and window openings).
[0129] When the width of the hole is greater than 2.5m, such as the smoke pipe hole and D1 (5.3*5.3), D7 (5.3*3.05) and the 128.5m frame column, add ф48×3.5 steel pipes on both sides of the support rod, weld them into lattice columns with φ25 steel bars, and connect the support rods of two to three lifting frames 7 with Ф25 steel bars to form a whole;
[0130] Step S6: After the sliding is completed, the sliding is stopped and the sliding formwork equipment is dismantled.
[0131] 1. Perform circle 11 verification:
[0132] The enclosure 11 is the lateral support of the steel formwork 10 in the slipform system. It is set along the perimeter of the steel formwork 10 structure, one on the upper and one on the lower. The enclosure 11 is made of 8# channel steel and is divided into two sections, the upper and lower. The formwork is fixed on the enclosure 11, so the enclosure 11 bears horizontal loads (concrete side pressure, impact force and wind load) and vertical loads (self-weight and friction of the formwork and enclosure 11) at the same time.
[0133] The calculation of the enclosure 11 can be considered as a three-span continuous beam supported on the lifting frame 7. Since the concrete rims are poured in sequence, the load acting on the enclosure 11 is not evenly distributed on each span. According to the most unfavorable situation, it can be approximately considered that the load is only arranged on two spans. Since the enclosure 11 is subjected to horizontal and vertical loads at the same time, it must be considered as a continuous beam subjected to bidirectional bending.
[0134] (1) Calculation of internal forces:
[0135] M x =0.117×H×L 2
[0136] M y =0.117×V×L 2
[0137] Wherein, H is the horizontal load borne by the enclosure 11; V is the vertical load borne by the enclosure 11; L is the spacing of the lifting frame 7; the calculation of the template side pressure is the same as the template calculation, and the converted concrete side pressure is 6.0KN / m 2 ;M x - horizontal internal force; M y -Vertical internal forces.
[0138] When pouring concrete, the horizontal concentrated load of concrete on the side of the formwork is considered to be 2KN, and the formwork dumping load is 4KN / m 2 ; Frictional resistance between formwork and concrete: 2KN / m for steel formwork 2 ;
[0139] Self-weight of formwork and enclosure 11: Formwork 0.33KN / m 2 , enclosure 11 weight 0.2KN (20Kg) / m
[0140] The enclosure 11 is made of 8# channel steel, with a maximum calculated length of 1600mm (the spacing between engineering lifting frames 7 is not greater than 1.6m), and the load-bearing width of each enclosure 11 is 0.6m (1.2m high template).
[0141] Horizontal load q x =1.2×6.0×0.6+1.4×4×0.6=7.68KN / m
[0142] Vertical load q y =1.2×2×0.6+1.2×0.33×0.6+1.2×0.2=1.92KN / m
[0143] The cross-sectional resistance moment calculated based on 8# channel steel as a ring 11 is as follows:
[0144] (2) Verification of cross-sectional strength
[0145] No. 8 channel steel, Wx = 25.3 × 10 3 mm 3 , Wy=5.79×10 3 mm 3
[0146] M X =0.117×q x ×L 2 =0.117×7.68×1.6 2 =2.30KN.m
[0147] M y =0.117×q y ×L 2 =0.117×1.92×1.6 2 =0.575KN.m
[0148] σ=Mx / Wx+My / Wy=2.30×10 6 / 25300+0.575×10 6 / 5790=190.22N / mm 2 ≤205N / mm 2 Meets the requirements.
[0149] (3) The deflection is calculated as follows
[0150] I x =346×10 4 mm 4
[0151] I y =37.4×10 4 mm 4
[0152] ωmax=5×F×L 4 / (384×E×I)≤[ω]=l / 500
[0153] ωmax=5×Fx×L 4 / (384×E×Ix)+5×Fy×L 4 / (384×E×Iy)
[0154] =5×7.68×1600 4 / (384×206×10 3 ×346×10 4 )+5×1.92×1600 4 / (384×206×10 3 ×37.4×10 4 )=3.046mm≤[ω]=l / 500=1600 / 500=3.2mm meets the requirements
[0155] (4) Overall stability verification
[0156] The calculation formula is as follows:
[0157] σ=Mx / ψxWx+My / ψyWy≤[σ]=205N / mm 2
[0158] In this embodiment, L = 1600 mm; ix = 78.6 mm, iy = 21.1 mm, Lx / ix = 1600 / 78.6 = 20.35, ψx = 0.969, Ly / iy = 1600 / 21.1 = 75.83, ψy = 0.605, therefore, σ = Mx / ψxWx + My / ψyWy = 2.30 × 10 6 / (39700×0.969)+0.575×10 6 / (7800×0.605)=182N / mm 2 , ≤[σ]=205N / mm 2 , which meets the requirements.
[0159] 2. Check the lifting frame 7:
[0160] The lifting frame 7 is the main load-bearing component of the slipform device. Various horizontal and vertical loads in the slipform construction are transmitted to the lifting frame 7 through the template and the enclosure 11, and then transmitted to the steel support rod through the hydraulic jack on the lifting frame 7, and finally transmitted to the solidified concrete structure. The lifting frame 7 is composed of columns and beams. The beam is made of double-channel steel 12# channel steel. The two columns of the lifting frame 7 must be kept parallel and connected to the beam at a 90° angle and welded. The height of the lifting frame 7 is determined according to the height of the template and the construction operation height.
[0161] In this implementation project, a lifting frame 7 of 1.80m×1.2m is used, and the net distance between the columns is: 1.4m.
[0162] Calculation of beams:
[0163] Force analysis, the calculation formula is as follows:
[0164] M=P×L / 4
[0165] In the formula, M is the bending moment of the beam; P is the lifting force of the jack, which is 30KN; L is the span of the beam, which is the distance between the center axes of the two columns, 1.2m;
[0166] Considering the rigid connection between the beam and the column, the bending moment M can be calculated as the beam fixed at both ends:
[0167] M=30×1.2 / 4=9KN.m
[0168] (1) Beam strength verification:
[0169] 12# double groove channel steel: Wx=2×62.1×10 3 mm 3 , Ix=2×391×10 4 mm 4 , A=2×15.7×10 2 mm 2 ;
[0170] σmax=Mx / Wx=9×10 6 / 2×62.1×10 3 ×1.05=69.01N / mm 2 ≤[f]=205N / mm 2
[0171] Meets the requirements!
[0172] (2) Beam shear force verification:
[0173] Qmax=14.6KN
[0174] τmax=Qmax[bh0 2 -(b-δ)h 2 ] / (8Izδ)=14.6×10 3 ×[53×126 2 -(53-5.5)×108 2 ] / (8×3910000
[0175] ×5.5)=24.39N / mm2≤[τ]=125N / mm 2 , meets the requirements!
[0176] (3) Calculation of beam deflection:
[0177] ωmax=0.96mm≤[ω]=l / 500=1.8mm, meets the requirements!
[0178] (4) Calculation of columns
[0179] Load analysis - Because the concrete in the composite steel formwork is poured in four layers, considering the initial setting time, only the upper two layers of concrete (60cm in total) have not initially set, generating lateral pressure. Therefore, only the upper adjustment rod is subject to lateral pressure, while the lateral pressure on the lower adjustment rod can be ignored. The scheme conducts load analysis based on the lateral pressure generated by the 320×600 beam.
[0180] Load combination
[0181]
[0182] Lower hanging part: bearing capacity limit state design value S bearing = 0.9max[1.2G4k+1.4Q2k, 1.35G4k+1.4×0.7Q2k] = 0.9max[1.2×14.4+1.4×4, 1.35×14.4+1.4×0.7×4] = 0.9max[22.88, 23.36] = 0.9×23.36 = 21.024kN / m 2
[0183] Lower hanging part: Normal service limit state design value S positive = G4k = 14.4 kN / m 2
[0184] N side = 14.4 × 0.6 (height of two layers of unset concrete) × 1.291 (column spacing) = 11.16 kN
[0185] The tensile force on the column is:
[0186] N pull = 30 (force on the silo support rod) / 2 = 15 kN
[0187] The column material is 14# channel steel. Through force analysis: column load (upper adjustment rod transfers side pressure 11.16kN, tension 30 / 2=15kN)
[0188] (1) Column strength verification
[0189] σmax=N / A+Mmax / W=15000 / 1850+3.83×106 / 80.5×10 3 =55.69N / mm2≤[f]=205N / mm 2
[0190] Meets the requirements!
[0191] (2) Shear resistance calculation
[0192] Qmax=6.38kN
[0193] τmax=Qmax / (8Izδ)[bh02-(b-δ)h2]=6380×[58×1402-(58-6)×1212] / (8×5640000×6)=8.85N / mm 2 ≤[τ]=125N / mm 2 , meets the requirements!
[0194] (3) Deflection verification
[0195] νmax=1.763mm≤[ν]=lx / 400=1400 / 400=3.5mm
[0196] Meets the requirements!
[0197] (4) Column tensile strength calculation:
[0198] N = 30 (force on the silo support rod) / 2 = 15 kN
[0199] The columns are 14# channel steel
[0200] σ=N / A=15KN / 1850mm2=8.11N / mm 2 ≤205N / mm 2
[0201] Meets the requirements!
[0202] 3. Perform panel 8 verification:
[0203]
[0204] Take the longitudinal unit width of the beam b = 1000mm and calculate according to the third-span continuous beam:
[0205] W=bh 2 / 6 = 1000 × 15 × 15 / 6 = 37500 mm 3 , I = bh 3 / 12=1000×15×15×15 / 12=281250mm 4
[0206] The design value of the linear load in the beam section direction borne by panel 8 is:
[0207] q1=γ0×[1.3×(G 1k +(G 2k +G 3k )×h)+1.5×Q 1k ]×b=1.1×[1.3×(0.1+(24+1.5)×0.6)+1.5
[0208] ×2.5]×1=26.147kN / m
[0209] (1) Strength verification
[0210] q 1静 =γ0×1.3×(G 1k +(G 2k +G 3k )×h)×b=1.1×1.3×(0.1+(24+1.5)×0.6)×1=22.022kN
[0211] / m
[0212] q 1活 =γ0×1.5×Q 1k ×b=1.1×1.5×2.5×1=4.125kN / m
[0213] M max =0.1q 1静 L 2 +0.117q 1活 L 2 =0.1×22.022×0.235 2 +0.117×4.125×0.235 2 =0.148kN·m
[0214] σ=M max / W=0.148×10 6 / 37500=3.954N / mm 2 ≤[f]=15N / mm 2
[0215] Meet the requirements!
[0216] (2) Deflection verification
[0217] The standard value of the linear load in the beam section direction borne by panel 8 is:
[0218] q2=1×(G 1k +(G 2k +G 3k )×h)×b=1×(0.1+(24+1.5)×0.6)×1=15.4kN / m
[0219] ν max =0.677q2L 4 / (100EI)=0.677×15.4×235 4 / (100×6000×281250)=0.188mm≤[ν]=
[0220] L / 400=235 / 400=0.588mm
[0221] Meet the requirements!
[0222] (3) Calculation of support reaction force
[0223] Design value (ultimate limit state)
[0224] R1=R4=0.4q 1静 L+0.45q 1活 L=0.4×22.022×0.235+0.45×4.125×0.235=2.506kN
[0225] R2=R3=1.1q 1静 L+1.2q 1活 L=1.1×22.022×0.235+1.2×4.125×0.235=6.856kN
[0226] Standard value (normal use limit state)
[0227] R1′=R4′=0.4q2L=0.4×15.4×0.235=1.448kN
[0228] R2′=R3′=1.1q2L=1.1×15.4×0.235=3.981kN
[0229] 4. Check the beam
[0230]
[0231]
[0232] (1) Calculation of load on each small beam line at the bottom of the beam
[0233] Calculate the linear load on each small beam at the bottom of the beam separately, among which the load on the floor slab on the side of the beam is the load from the bottom vertical bar to half of the side of the beam.
[0234] Design value of beam deadweight: q2=γ0×1.3×G 1k × beam width / (number of small beams - 1) = 1.1 × 1.3 × (0.3-0.1) × 0.705 / 3 = 0.067 kN / m
[0235] 1) Calculation of the design value of the left beam line load
[0236] The load transferred from the bottom panel of the beam to the small beam line on the left is: q 1左 =R1 / b=2.506 / 1=2.506kN / m
[0237] Self-weight of small beam: q2=0.067kN / m
[0238] The left side formwork of the beam transfers the load q to the left side beam 3左 =γ0×1.3×G 1k ×(beam height-plate thickness)=1.1×1.3×0.5×(0.6-0.12)=0.343kN / m
[0239] The load q is transferred from the left floor slab to the left small beam 4左 =γ0×[1.3×(G 1k +(G 2k +G 3k )×h)+1.5×Q 1k ]×(distance from the left side upright to the center line of the beam - beam width / 2) / 2=1.1×[1.3×(0.5+(24+1.1)×0.12)+1.5×2.5]×(0.6-0.705 / 2) / 2=1.132kN / m
[0240] Total load of the left beam q 左 =q 1左 +q2+q 3左 +q 4左 =2.506+0.067+0.343+1.132=4.049kN / m
[0241] 2) Calculation of design value of middle beam line load
[0242] The maximum linear load transferred from the bottom panel of the beam to the middle beam is: q 1中 =Max[R2,R3] / b=Max[6.856,6.856] / 1=6.856kN / m
[0243] Self-weight of small beam: q2=0.067kN / m
[0244] Total load of the middle beam q 中=q 1中 +q2=6.856+0.067=6.923kN / m
[0245] 3) Calculation of design value of right beam line load
[0246] The load transferred from the bottom panel of the beam to the small beam line on the right is: q 1右 =R4 / b=2.506 / 1=2.506kN / m
[0247] Self-weight of small beam: q2=0.067kN / m
[0248] The right side formwork of the beam transfers the load q to the right side small beam 3右 =γ0×1.3×G 1k ×(beam height-plate thickness)=1.1×1.3×0.5×(0.6-0.12)=0.343kN / m
[0249] The load q is transferred from the floor slab on the right side of the beam to the small beam on the right side 4右 =γ0×[1.3×(G 1k +(G 2k +G 3k )×h)+1.5×Q 1k ]×((l b - distance between the left side upright and the center line of the beam) - beam width / 2) / 2 = 1.1×[1.3×(0.5+(24+1.1)×0.12)+1.5×2.5]×((1.2-0.6)-0.705 / 2) / 2 = 1.132 kN / m
[0250] Total load on the right beam q 右 =q 1右 +q2+q 3右 +q 4右 =2.506+0.067+0.343+1.132=4.049kN / m
[0251] 4) Calculation of the maximum linear load design value of each beam
[0252] The maximum load of the beam q=Max[q 左 ,q 中 ,q 右 ]=Max[4.049,6.923,4.049]=6.923kN / m
[0253] 5) Calculation of the standard value of the maximum linear load of each beam
[0254] Refer to the calculation steps of the design value of the small beam line load and substitute the standard load value to obtain:
[0255] The maximum load standard value of the small beam is: q'=Max[q 左',q 中 ',q 右 ']=Max[2.169,4.028,2.169]=4.028kN / m
[0256] To simplify the calculation, the second-span continuous beam and cantilever beam can be calculated separately.
[0257] (2) Bending resistance calculation
[0258] M max =max[0.125ql1 2 ,0.5ql2 2 ]=max[0.125×6.923×0.9 2 , 0.5×6.923×0.2 2 ]=0.701k
[0259] N·m
[0260] σ=M max / W=0.701×10 6 / 4110=170.548N / mm 2 ≤[f]=205N / mm 2
[0261] Meet the requirements!
[0262] (3) Shear resistance calculation
[0263] V max =max[0.625ql1, ql2]=max[0.625×6.923×0.9, 6.923×0.2]=3.894kN
[0264] τ max =V max / (8I z δ)[bh0 2 -(b-δ)h 2 ]=3.894×1000×[40×40 2 -(40-5)×35 2 ] / (8×82200×5)
[0265] =25.02N / mm 2 ≤[τ]=125N / mm 2
[0266] Meet the requirements!
[0267] (4) Deflection verification
[0268] ν1=0.521q'l1 4 / (100EI)=0.521×4.028×900 4 / (100×206000×8.22×10 4 )=0.813mm
[0269] ≤[ν]=l1 / 400=900 / 400=2.25mm
[0270] ν2=q'l2 4 / (8EI)=4.028×200 4 / (8×206000×8.22×10 4 )=0.048mm≤[ν]=2l2 / 400=2
[0271] ×200 / 400=1mm
[0272] Meet the requirements!
[0273] (5) Calculation of support reaction
[0274] Ultimate limit state
[0275] R max =max[1.25qL1,0.375qL1+qL2]=max[1.25×6.923×0.9,0.375×6.923×0.9+6.923×0.
[0276] 2]=7.788kN
[0277] Similarly, the design values of the linear loads on each small beam are substituted into the above steps, and the design values of the maximum support reaction forces on each small beam supported by the bottom of the beam are R1 = 4.555 kN, R2 = 7.788 kN, R3 = 7.788 kN, and R4 = 4.555 kN.
[0278] Normal use limit state
[0279] R max '=max[1.25q'L1,0.375q'L1+q'L2]=max[1.25×4.028×0.9,0.375×4.028×0.9+4.028
[0280] ×0.2]=4.531kN
[0281] Similarly, we can get:
[0282] The standard values of the linear loads on each small beam are substituted in accordance with the above steps, and the standard values of the maximum support reaction forces on each small beam supported by the bottom of the beam are R1'=2.44kN, R2'=4.531kN, R3'=4.531kN, R4'=2.44kN respectively.
[0283] 5. Verification of main beam 9
[0284] Main beam type Steel pipe Main beam section type (mm) Φ48×2.8 Main beam calculation section type (mm) Φ48×2.8 <![CDATA[Design value of flexural strength of main beam [f] (N / mm 2 )]]> 205 <![CDATA[Design value of shear strength of main girder [τ] (N / mm 2 )]]> 125 <![CDATA[Section modulus W of main girder (cm 3 )]]> 4.25 <![CDATA[Elastic modulus E of the main beam (N / mm 2 )]]> 206000 <![CDATA[Moment of inertia I of the main beam cross-section (cm 4 )]]> 10.19 Number of main beams in adjustable bracket 2 <![CDATA[Uneven stress coefficient K of the main beam s > 0.5
[0285] The main beam 9 is combined with two beams, and the main beam 9 has a force unevenness coefficient K s =0.5, then:
[0286] Ultimate limit state
[0287] Design value of concentrated force on single main beam 9:
[0288] P1=R1×K s =4.555×0.5=2.278kN, P2=R2×K s =7.788×0.5=3.894kN, P3=R3×K s =7.788×0.5
[0289] =3.894kN,P4=R4×K s =4.555×0.5=2.278kN
[0290] The design value of the deadweight of a single main beam 9 is: q = 1.1 × 1.3 × 0.031 = 0.045 kN / m
[0291] Normal use limit state
[0292] Standard value of concentrated force on a single main beam 9:
[0293] P1'=R1'×K s =2.44×0.5=1.22kN, P2'=R2'×K s =4.531×0.5=2.266kN,P3'=R3'×K s =4.531
[0294] ×0.5=2.266kN,P4'=R4'×K s =2.44×0.5=1.22kN
[0295] Standard value of deadweight of single main beam 9: q'=1×0.031=0.031kN / m
[0296] (1) Bending calculation
[0297] σ=M max / W=0.223×10 6 / 4250=52.525N / mm 2 ≤[f]=205N / mm 2
[0298] Meet the requirements!
[0299] (2) Shear resistance calculation
[0300] V max =3.911kN
[0301] τ max =2V max / A=2×3.911×1000 / 398=19.654N / mm 2 ≤[τ]=125N / mm 2
[0302] Meet the requirements!
[0303] (3) Deflection verification
[0304] ν max =0.048mm≤[ν]=L / 400=400 / 400=1mm
[0305] Meet the requirements!
[0306] (4) Calculation of support reaction
[0307] Ultimate limit state of bearing capacity:
[0308] The support reaction forces are R1 = 0.317 kN, R2 = 5.874 kN, R3 = 5.884 kN, R4 = 0.323 kN
[0309] The reaction force of the main beam 9 support on the vertical column is P1 = R1 / K s =0.317 / 0.5=0.634kN, P2=R2 / K s =5.874 / 0.5=11.748kN, P3=R3 / K s =5.884 / 0.5=11.767kN, P4=R4 / K s =0.323 / 0.5=0.647kN
[0310] 6. Frame anti-overturning verification
[0311]
[0312] Standard value of wind line load of supporting scaffold 5: q wk =l' a ×ω fk =0.9×0.278=0.25kN / m:
[0313] Standard value of horizontal force generated by wind load on the outer formwork of the support:
[0314] F wk =l' a×H m ×ω mk =0.9×1×0.336=0.302kN
[0315] Standard value of overturning moment M of supporting scaffold 5 calculation unit under wind load Tk :
[0316] M Tk =0.5H 2 q wk +HF wk =0.5×18 2 ×0.25+18×0.302=45.976kN.m
[0317] Refer to "Safety Technical Standards for Coupler-Type Steel Pipe Scaffolding in Construction" T / CECS 699-2020, Article 5.3.13, the calculation formula is as follows:
[0318] B 2 l' a (g k1 +g k2 )+2ΣG jk b j ≥3γ0M Tk
[0319] g k1 ——Standard value of deadweight of evenly distributed frame surface load kN / m 2
[0320] g k2 ——Standard value of deadweight of evenly distributed material surface load such as formwork on the upper part of the frame kN / m 2
[0321] G jk ——Standard value of the deadweight of materials piled on the calculation unit of the supporting scaffold 5 kN
[0322] b j ——The horizontal distance m from the materials piled on the calculation unit of the supporting scaffold 5 to the tipping origin
[0323] After calculation, B 2 l' a (g k1 +g k2 )+2ΣG jk b j =B 2 l' a [qH / (l' a ×l' b )+G 1k ]+2×G jk ×B / 2=9.4 2×0.9×[0.15×18 / (0.9×1.2)+0.5]+2×1×9.4 / 2=247.972kN.m≥3γ0M Tk =3×1.1×45.976=151.719kN.m
[0324] Meet the requirements!
[0325] 7. Aspect Ratio Verification
[0326] Article 6.9.7 of the Technical Standard for Safety of Fastener-type Steel Pipe Scaffolding in Construction (T / CECS 699-2020) states that when the height-to-width ratio of the full-height support frame is greater than 2, the full-height support frame shall be rigidly connected to the structural columns around and in the middle of the support frame. In areas without structural columns, measures such as embedded steel pipes shall be taken to rigidly connect the frame to the building structure. The height-to-width ratio of the support frame shall not be greater than 3.
[0327] H / B=18 / 9.4=1.915≤2
[0328] Meet the requirements!
[0329] The present invention can present the building model in three-dimensional form through BIM technology, making the design more intuitive, coordinating data and information between all project participants, ensuring the smooth progress of the project, reducing construction costs, and using BIM technology to reduce the difficulty of synchronous construction and coordination of the outer concrete structure and the inner concrete platform, and can also solve the complex relationship between the slipform equipment and the floor interlayer construction organization. It can simulate the construction process before the actual construction, help discover potential problems through verification, and help optimize the design plan and construction plan through data analysis to avoid construction loopholes, greatly improving construction safety.
[0330] The above is a detailed introduction to the BIM-based variable diameter outer circle inner square chimney slipform construction method provided by the present invention. Specific examples are used in this article to illustrate the principles and implementation methods of the present invention. The description of the above embodiments is only used to help understand the method of the present invention and its core idea; at the same time, for those skilled in the art, according to the idea of the present invention, there will be changes in the specific implementation method and application scope, and changes and improvements to the present invention will be possible without exceeding the concept and scope specified in the attached claims. In summary, the content of this specification should not be understood as a limitation on the present invention.
Claims
1. A sliding form construction method for a chimney with a variable diameter outer circle and inner square based on BIM, characterized in that: The steps are as follows: Step S1, using BIM technology to model and design the sliding form equipment and verify the calculation; Firstly, the sliding form equipment is modeled and designed for the variable diameter chimney with outer circle and inner square; Then, the total vertical load N of the slipform equipment is calculated through the BIM system; Secondly, the BIM system uses a calculation formula to calculate whether the jack can meet the construction needs. The calculation formula is as follows: n=N / P Where, n is the minimum number of supporting rods or jacks; N is the total vertical load (KN); P is the allowable bearing capacity of a single jack (the allowable bearing capacity of the supporting rod or half of the rated lifting capacity of the jack, whichever is smaller); Step S2: Conduct no-load and load tests before construction, and input the test data into the BIM system for verification; Step S3, calculating the sliding speed and concrete demoulding strength through the BIM system; When the support rod is not likely to become unstable, the demoulding strength of the concrete can be controlled by the following formula: V=(Hha) / T Where, V is the template sliding speed m / h; H is the template height m; h is the thickness of each pouring layer m; α is the distance from the surface to the template opening after the concrete is fully poured, which is 0.1m; T is the time required for the concrete to reach the demoulding strength h; Step S4, perform initial sliding according to the BIM calculation results, and feed back the initial sliding test results to the BIM system for inspection; Step S5, debugging and various inspections; Step S5, normal sliding; Step S6: After the sliding is completed, the sliding is stopped and the sliding formwork equipment is dismantled.
2. According to the BIM-based sliding form construction method of a chimney with a variable diameter outer circle and inner square, the method is characterized by: When modeling in step S1, the sliding formwork equipment consists of an inner ring lifting platform, an outer ring lifting platform and a gallery bridge. The inner ring lifting platform is erected on the top of the square inner tube of the chimney, and the outer ring lifting platform is erected on the top of the circular outer tube of the chimney. The inner ring lifting platform and the outer ring lifting platform are connected by a gallery bridge and a radial beam.
3. According to the BIM-based sliding form construction method of a chimney with a variable diameter outer circle and inner square, the method is characterized by: In step S1, the BIM method for total vertical load is as follows: a. Calculate the load of the sliding form equipment The system calculates the load of the sliding formwork equipment in the corresponding range of each gantry according to statistics; b. Calculate the construction load of the operating platform: Operation platform construction load = construction load standard value + personnel and auxiliary equipment load In the formula, the standard value of construction load = 1.5KN / m*operating platform area m 2 , 1.5KN / m is the parameter value for calculating the number of support rods based on the standard value of construction load on the operating platform in Appendix A.0.1 of the Technical Standard for Sliding Formwork Engineering (2005); In the formula, the load of personnel and auxiliary equipment is calculated based on the number of construction personnel, hydraulic equipment, welding equipment on the slipform equipment, and the amount of concrete, steel bars and other materials allowed to be stacked on the platform; c. Calculate the friction resistance load between steel formwork and concrete: Friction resistance load = contact area of steel formwork * friction coefficient Total vertical load N = slipform equipment load + operating platform construction load + friction resistance between steel formwork and concrete.
4. The sliding form construction method of a chimney with a variable diameter outer circle and inner square based on BIM according to claim 1 is characterized by: In step S1, the calculation method of the allowable bearing capacity P of the support rod is as follows; According to Appendix A of the Technical Specifications for Sliding Formwork Engineering (GB / T50113-2019): P=(α / K)×(99.6-0.22L0) Where, P is the allowable bearing capacity of the supporting rod (kN); α is the working condition coefficient of the split platform area, which is 0.8; K is the safety factor, which is 2.0; L0 is the empty length of the supporting rod (cm), which is 100cm.
5. The sliding form construction method of a chimney with a variable diameter outer circle and inner square based on BIM according to claim 1 is characterized by: In step S5, the concrete is trial-mixed and an early strength growth curve is made, which is divided into strength values of 1h, 2h, 3h, 6h, 12h, 24h, 48h, 72h and 7 days. The BIM system designs the construction schedule according to the growth curve, and reduces the pause by taking measures such as thin layer concrete pouring and slight lifting of the jack. Continuous sliding should be carried out within the specified time. During the sliding process, the interval between two liftings should be kept at about 0.5 hours, and the number of intermediate liftings should be appropriately increased or decreased according to the temperature and concrete strength. The intermediate lifting height is 1-2 jack strokes.
6. The sliding form construction method of a chimney with a variable diameter outer circle and inner square based on BIM according to claim 1 is characterized by: In step S5, when the slide stops, within the height range from the jack to the concrete surface, the two support rods are tied with φ12 hook bars, with a spacing of no more than 300 mm, the hook bars are spot welded firmly to the support rods, and a φ48*3.2 steel pipe is added on both sides of the original support rod in the middle of the vertical wall of the steel formwork, and then the four steel pipes are welded into a diamond lattice column with φ20 "S"-shaped steel bars. When the width is greater than 2.5m, ф48×3.5 steel pipes are added on both sides of the support rods, and φ25 steel bars are welded into a lattice column form, and the support rods of two to three lifting frames are connected with φ25 steel bars to form an integral whole.
7. The sliding form construction method of a chimney with a variable diameter outer circle and inner square based on BIM according to claim 1 is characterized by: In step S1, the BIM system is used to calculate the internal force, section strength, deflection, and overall stability of the enclosure around the steel formwork to verify whether the enclosure meets the requirements.
8. The sliding form construction method of a chimney with a variable diameter outer circle and inner square based on BIM according to claim 1 is characterized by: In step S1, the strength, shear force and deflection of the beams of the lifting frame are checked by calculation using the BIM system, the load analysis of the columns of the lifting frame is performed, and the bearing capacity, strength, shear resistance and deflection of the hanging scaffolding are checked to verify whether the lifting frame meets the requirements.
9. The sliding form construction method of a chimney with a variable diameter outer circle and inner square based on BIM according to claim 1 is characterized by: In step S1, the strength, deflection and support reaction force of the panel on the operating platform are verified by calculation using the BIM system to verify whether the panel meets the requirements.
10. The sliding form construction method of a chimney with a variable diameter outer circle and inner square based on BIM according to claim 1 is characterized by: In step S1, the load, bending, shear, deflection and support reaction force of the small beams and main beams on the operating platform of the slipform equipment are checked by calculation using the BIM system to check whether the main beams and small beams meet the requirements.