Method for controlling hydraulic fracturing roof-cutting pressure relief of extraction roadway under influence of working face mining

Through hydraulic fracturing technology, the cutting and pressure relief control is carried out above the coal mine working surface, which solves the problem of difficult control of the stability of the extraction tunnel, and improves the stability of the tunnel and the coal recovery rate.

CN118979755APending Publication Date: 2024-11-19CHINA COAL XIYANG ENERGY CO LTD HUANGYANHUI COAL MINE
View PDF 0 Cites 5 Cited by

Patent Information

Application Number
CN202411175407.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-26
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

During the mining process of the coal mine working face, the stability of the extraction tunnel is difficult to control, resulting in the instability of the tunnel. The existing technologies such as directional pre-cracking and blasting and drilling pressure relief methods have safety hazards or are not conducive to tunnel maintenance.

Method used

Using hydraulic fracturing technology, by comprehensively determining the key layers above the working surface, determining the drilling arrangement plan and fracturing parameters, conducting hydraulic fracturing top pressure relief control, cutting off the mining stress propagation path, forming a low-stress zone, ensuring Roadway stability.

Benefits of technology

It effectively reduces tunnel deformation, improves coal recovery rate and safe and stable production capacity of mines, reduces coal losses, and has important engineering application value.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118979755A_ABST
    Figure CN118979755A_ABST
Patent Text Reader

Abstract

The invention discloses a hydraulic fracturing roof-cutting pressure relief control method for an extraction roadway under the influence of working face mining, and the method comprises the following steps: providing a hydraulic fracturing roof-cutting pressure relief control thought based on the working face and roadway geological conditions of a coal mine; comprehensively judging the occurrence distribution of the key layer of the top plate of the coal mine working face to obtain the key layer based on a hydraulic fracturing top cutting pressure relief control thought; based on the key layer, a hydraulic fracturing top-cutting pressure relief drill hole arrangement scheme is obtained; on the basis of the hydraulic fracturing drill hole arrangement scheme, hydraulic fracturing initiation pressure and fracturing time are calculated respectively; and on the basis of the hydraulic fracturing initiation pressure and the fracturing time, hydraulic fracturing top cutting pressure relief control is carried out on the extraction roadway. The high-position and low-position thick and hard sandstone above the working face is pre-split in advance, the propagation path of mining-induced stress in the coal pillar side direction is cut off, the influence of the mining-induced stress on the roadway is reduced, the deformation of the extraction roadway is effectively controlled, and the method has important engineering application value and wide popularization prospects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of coal mining, and in particular relates to a hydraulic fracturing and top cutting and pressure relief control method for a pumping tunnel under the influence of mining on a working face. Background Art

[0002] In order to improve the coal recovery rate in the mining area, the coal mine working face uses a small coal pillar with a width of 12m as a protective coal pillar between the return air chute and the extraction roadway. During the mining process of the working face, the stability of the extraction roadway is difficult to control due to the mining of the adjacent working face, which seriously affects the safe and efficient production of the mine. However, there are two main reasons for the instability of the roadway: first, the lateral support pressure of the working face will increase the stress of the surrounding rock of the extraction roadway, and the deformation will be further aggravated; second, the breaking and instability of the overburden above the goaf will also produce additional stress, which will cause the deformation of the extraction roadway to increase. The hard roof is a rock layer that generates force source and effectively transmits stress, so the control of the hard rock roof is crucial. At present, the use of directional pre-splitting blasting technology for roof cutting can alleviate the stress concentration of the coal pillar, which is conducive to the maintenance of the roadway. However, this method has a great safety hazard for gas extraction roadways. At the same time, strengthening support can also play a role in protecting the roadway, but it cannot fundamentally weaken the power source affecting the roadway. The use of drilling pressure relief technology can place the tunnel surrounding rock within the stress reduction zone, but this approach may also cause the expansion of the tunnel surrounding rock plastic zone, which is not conducive to the maintenance of the tunnel. Therefore, in order to solve the problem that the deformation of the extraction tunnel is difficult to control under the influence of mining, it is urgent to study a safer and more efficient top cutting pressure relief control method. Summary of the invention

[0003] In order to solve the above technical problems, the present invention proposes a hydraulic fracturing and top cutting and pressure relief control method for the extraction tunnel under the influence of working face mining, so as to solve the problems existing in the above prior art.

[0004] To achieve the above-mentioned purpose, the present invention provides a method for controlling hydraulic fracturing and top cutting pressure relief in a drainage tunnel under the influence of mining at a working face, comprising:

[0005] Based on the geological conditions of coal mine working faces and tunnels, a hydraulic fracturing and top cutting pressure relief control strategy is proposed;

[0006] Based on the hydraulic fracturing and roof cutting and pressure relief control idea, the occurrence distribution of the key layer of the roof of the coal mine working face is comprehensively determined to obtain the key layer;

[0007] Based on the key layers, a hydraulic fracturing and top cutting and pressure relief drilling arrangement plan is determined;

[0008] Based on the hydraulic fracturing drilling arrangement plan, respectively calculating the hydraulic fracturing initiation pressure and the hydraulic fracturing time;

[0009] Based on the hydraulic fracturing initiation pressure and fracturing time, hydraulic fracturing top cutting and pressure relief control is carried out on the extraction tunnel.

[0010] Optionally, the conditions for determining the key layer include:

[0011]

[0012] Where q1 is the self-weight load of the first layer of controlled rock formation, unit: kN / m 2 ;q i Controlling rock formation deadweight load for the i-th layer; (q1) n The n-layer rock load controlled by the first layer; (q1) n+1 is the n+1 layer rock load controlled by the first layer; l' n+1 is the breaking step length of the n+1th layer, in m; l'1 is the breaking step length of the first layer, in m; l' i is the breaking step length of the i-th layer.

[0013] Optionally, the expression for determining the fracturing layer position based on the key layer is:

[0014]

[0015] In the formula, h represents the height of the caving zone, M represents the mining height, and K p Represents the coefficient of expansion.

[0016] Optionally, the arrangement of the fracturing drilling includes:

[0017] The first borehole is constructed toward the goaf side, with an angle of 20° with the axial direction of the tunnel, and the hole opening position is 1m away from the coal seam on the working face side. The borehole diameter is 75mm, the borehole spacing is 12m, the borehole length is 30m, and the borehole elevation angle is 45°;

[0018] The second borehole was constructed in the vertical tunnel toward the roof above the extraction tunnel. The hole opening position was 0.5m away from the coal pillar on the roof. The borehole diameter was 75mm, the borehole spacing was 12m, the borehole length was 28m, the borehole elevation angle was 48°, and the angle between the borehole and the axial direction of the tunnel was 90°.

[0019] Optionally, the expression for calculating the fracturing pressure considering the circumferential stress around the borehole is:

[0020]

[0021] In the formula, P is the fracture initiation pressure, Rt is the tensile strength of rock, α is the pore water pressure contribution coefficient, and P is h represents the pore water pressure, σ Z represents the vertical stress, σ X Represents horizontal stress.

[0022] Optionally, the fracturing time is determined as:

[0023] L1+v y t>L c +ΔL+v g t

[0024] In the formula, v y Indicates the fracturing construction speed, m / d; v g Indicates the working face advancement speed, unit: m / d; L c It represents the influence distance of the advanced support pressure of the working face, and the unit is: m; ΔL represents the redundancy coefficient; L1 represents the distance between the hydraulic fracturing construction site and the working face, and the unit is: m; t represents the hydraulic fracturing construction time, and the unit is: d.

[0025] To achieve the above-mentioned purpose, the present invention also provides a hydraulic fracturing equipment, including a special hydraulic fracturing packer, a water injection steel pipe, a tee, a high-pressure hose, a high-pressure water injection pump, a pressure gauge, a stop valve and a manual pump. The hydraulic fracturing equipment is used to implement the various steps of the hydraulic fracturing top cutting and pressure relief control method of the extraction tunnel under the influence of working face mining.

[0026] Compared with the prior art, the present invention has the following advantages and technical effects:

[0027] The present invention effectively solves the problem of the stability of the extraction tunnel under the influence of the working face mining by implementing the hydraulic fracturing top cutting and pressure relief control method. By pre-hydraulic fracturing above the working face, the propagation path of the mining stress to the coal pillar side is cut off, which significantly reduces the adverse effects of high-level coarse-grained sandstone and low-level medium-grained sandstone on the stability of the tunnel. By reasonably determining the fracturing layer, drilling arrangement, fracturing pressure and time, the effect of hydraulic fracturing and construction safety are further improved. Practical application results have proved that the invention not only improves the coal recovery rate and reduces coal losses, but also significantly improves the safe and stable production capacity of the mine, and has important engineering application value and broad promotion prospects. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] The drawings constituting a part of the present application are used to provide a further understanding of the present application. The illustrative embodiments and descriptions of the present application are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:

[0029] Figure 1 The principle of stress transfer of hydraulic fracturing and top cutting in the extraction tunnel according to the embodiment of the present invention;

[0030] Figure 2 It is a plan view of the hydraulic fracturing drilling arrangement of the extraction tunnel according to an embodiment of the present invention;

[0031] Figure 3It is a cross-sectional view of the AA arrangement of hydraulic fracturing drilling holes in the extraction tunnel according to an embodiment of the present invention;

[0032] Figure 4 This is a BB cross-sectional view of the hydraulic fracturing drilling arrangement of the extraction tunnel according to an embodiment of the present invention;

[0033] Figure 5 This is a CC cross-sectional view of the hydraulic fracturing drilling arrangement of the extraction tunnel according to an embodiment of the present invention. DETAILED DESCRIPTION

[0034] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.

[0035] It should be noted that the steps shown in the flowcharts of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and that, although a logical order is shown in the flowcharts, in some cases, the steps shown or described can be executed in an order different from that shown here.

[0036] Embodiment 1

[0037] Aiming at the problem that the additional load generated by the fracture and sinking of high-level coarse-grained sandstone and the hanging top of low-level medium-grained sandstone during the mining process of the working face may cause large deformation of the extraction roadway, it is proposed to use hydraulic fracturing technology to control the top cutting and pressure relief. By pre-cracking the high and low thick and hard sandstone above the working face in advance, the propagation path of the mining stress to the side of the coal pillar is cut off, reducing its impact on the roadway, thereby effectively controlling the deformation of the roadway and achieving the purpose of effective control of the extraction roadway.

[0038] In the present embodiment, a method for controlling hydraulic fracturing and top cutting and pressure relief in a drainage tunnel under the influence of mining at a working face is provided, and the method comprises the following steps: based on the geological conditions of the coal mine working face and the tunnel, a hydraulic fracturing and top cutting and pressure relief control idea is proposed; based on the hydraulic fracturing and top cutting and pressure relief control idea, the distribution of the key layer of the roof of the coal mine working face is comprehensively determined to obtain the key layer; based on the key layer, a hydraulic fracturing and top cutting and pressure relief drilling arrangement scheme is determined; based on the hydraulic fracturing drilling arrangement scheme, the hydraulic fracturing initiation pressure and fracturing time are respectively calculated; based on the hydraulic fracturing initiation pressure and fracturing time, hydraulic fracturing and top cutting and pressure relief control is performed on the drainage tunnel.

[0039] Further, the control principle of hydraulic fracturing and top pressure relief: The control principle of hydraulic fracturing and top pressure relief in the extraction tunnel is as follows: Figure 1As shown in the figure. As the working face is mined, the drainage tunnel deforms under the action of the advanced support pressure in front of the working face and the influence of the fracture instability of the overburden in the goaf. The coarse-grained sandstone forms a masonry beam structure after fracture, which affects the drainage tunnel in the form of arc triangle hanging plate instability on the side of the goaf near the drainage tunnel, while the medium-grained sandstone forms a suspended roof on the side of the coal pillar after fracture and instability, which affects the drainage tunnel in the form of additional load. Based on this, by fracturing the roof, on the one hand, it is necessary to cut off the hard suspended roof on the side of the goaf, "structurally separate" the roof of the goaf from the roof above the tunnel, and make the roof rock layer of the goaf fully collapse, relieve the influence of the additional load of the suspended roof of the medium-grained sandstone, and limit the structural activity of the coarse-grained sandstone rock layer, thereby reducing the bearing capacity of the coal pillar; on the other hand, the fracturing cracks formed by fracturing form a weak structure in the rock layer above the tunnel, so that the lateral stress is transferred to the deep part, and a low stress area is formed near the tunnel, thereby ensuring that the drainage tunnel maintains good surrounding rock stability during the working face mining process.

[0040] Furthermore, the roof hydraulic fracturing technology solution includes the following contents:

[0041] (1) Critical layer identification

[0042] Due to the differences in the stratification characteristics of coal-bearing strata, each rock layer plays a different role in roof activity. Usually, thick and hard rock layers play a major controlling role in roof activity and exist as key bearing layers; while weak rock layers have little effect on roof destructive movement and can be regarded as loads acting on key bearing layers. According to the definition of roof key layers, when there are multiple hard rock layers in the overlying rock layer activity of the mining area, the rock layer that controls all or part of the rock mass activity is called a key layer, of which the former is the main key layer and the latter is the sub-key layer.

[0043] Assume that the working face is covered by m layers of bedrock, and the bedrock is a loose cover layer, of which the 1st and n+1th layers of bedrock are hard rock layers. According to the key layer theory, if the following three conditions are met at the same time, the n+1th layer of bedrock is the main key layer, and the 1st layer is the sub-key layer.

[0044]

[0045] Where q1 is the self-weight load of the first layer of controlled rock formation, kN / m 2 ;q i is the self-weight load of the rock layer controlled by the i-th layer, kN / m 2 ; (q1) n is the rock load of n layers controlled by the first layer, kN / m 2 ; (q1) n+1 The n+1 layer rock load controlled by the first layer, kN / m 2 ; l' n+1is the breaking step length of the n+1th layer, m; l'1 is the breaking step length of the 1st layer, m; l' i is the breaking step length of the i-th layer, m.

[0046] According to the working face column chart and the physical and mechanical parameters of the coal and rock mass in the mine geological report, a comprehensive judgment is made on the distribution of the key layers of the working face roof. The characteristic parameters of the roof rock strata are shown in Table 1.

[0047] Table 1

[0048]

[0049] Note: h is thickness, H is burial depth, γ is bulk density, E is elastic modulus, σ t is the tensile strength, l' is the breaking distance.

[0050] The load q1 of the first layer of mudstone itself is:

[0051] q1=γ1h1=26.3×4=105.2kPa

[0052] Considering the effect of the medium-grained sandstone in the second rock layer on the first rock layer, the load of the first rock layer is:

[0053]

[0054] According to the calculation results, the medium-grained sandstone in the second layer has no effect on the load of the first layer due to its own high strength and thick rock layer. Therefore, the medium-grained sandstone is the first hard rock layer.

[0055] Calculate the fracture step distance of the first rock layer according to the fixed-support beam at both ends:

[0056]

[0057] Starting from this hard rock layer, recalculate as above.

[0058] q2=γ2h2=25.6×5.7=145.92kPa

[0059] Considering the effect of the third rock layer on the second rock layer, the load of the second rock layer is:

[0060]

[0061] Calculating up to the 4th rock layer, the load of the 2nd rock layer is:

[0062]

[0063] Similarly, when calculating up to the fifth rock layer, the load of the second rock layer is:

[0064]

[0065] According to the calculation results, the fifth layer of coarse-grained sandstone is the second hard rock layer.

[0066] Therefore, we can know that the influence of the 3rd and 4th layers on the load of the 2nd layer should be considered. The 5th layer has no effect on the load of the 2nd layer due to its own strength and thickness. Therefore, the load on the 2nd layer is 245.95kPa.

[0067] Calculate the fracture step distance of the second rock layer according to the fixed-support beam at both ends:

[0068]

[0069] The fracture step distance of the second layer was found to be 25.6m.

[0070] The load q5 of the fifth layer of coarse-grained sandstone itself is:

[0071] q5=γ5h5=26.0×16.5=429kPa

[0072] Due to the lack of data on rock layers above the coarse-grained sandstone, the load q5 of the coarse-grained sandstone itself is used to calculate the minimum fracture step L5 of 53.56m, which is larger than the fracture step L2 of the second layer. According to the calculation results, the top rock layer of the working face is mainly hard sandstone, among which the key layer is the coarse-grained sandstone and the medium-grained sandstone below.

[0073] (2) Determination of the length of the overhanging top of the lateral overburden

[0074] The suspended span l at the end along the lateral direction after the hard rock layer of the working face roof is broken i , can be calculated according to the plate yield line analysis method, see formula 4 for details. Related research believes that when s / l i >6, it can be considered that l i Approximately equal to l i '; Based on this, the lateral breaking length of the curved plate structure is simplified, and according to the main contradiction of the research problem, it can be further simplified to a rectangular beam of unit width.

[0075]

[0076] In the formula, l i ' is the breaking pressure step distance of the hard rock layer of the roof, m; s is the width of the working face, m. It is known that the breaking pressure step distance of medium-grained sandstone is 25.6m, and the width of the working face is 219m. Substituting into the above formula, the lateral overhang length of medium-grained sandstone is 26.9m.

[0077] (3) Determination of fracturing layer position: After coal seam mining, the overburden will form a caving zone and a fissure zone. Due to the different lithology and thickness of the rock formation, its fracture characteristics are different. Therefore, the hard rock formation in the caving zone is the rock formation that needs to be fractured to prevent the formation of hanging roof and possible rock formation structure. p Substituting =1.22 into Formula 5 for calculation, we obtain the height of the caving zone to be 20m.

[0078]

[0079] According to the identification of key layers, the 5.7m thick medium-grained sandstone and 16.5m thick coarse-grained sandstone above the coal seam are the key rock layers that affect the surrounding rock control of the extraction tunnel. According to the obtained caving zone height, the fracturing range is determined as: the entire thickness of the medium-grained sandstone layer and the 6.2m coarse-grained sandstone layer.

[0080] (4) Determination of drilling angle

[0081] For the top cutting fracturing hole, a reasonable top cutting fracture position is required to ensure that the roof can fall smoothly in the goaf after fracturing. In view of the fact that the construction location is selected in the return air chute, the top cutting position is located outside the coal pillar, which can ensure that the top cutting rock layer slides into the goaf, and the drilling elevation angle can be arbitrary. Therefore, considering the two aspects of the fracturing upper rod construction strength and the drilling length, the top cutting fracturing drilling elevation angle is determined to be 45°. At the same time, considering that there is a 6.2m anchor cable support above the roadway, in order to ensure that the hydraulic fracturing top cutting does not damage the anchor body, it is determined that the fracturing drill hole has an angle of 20° with the roadway axis. For the weakened fracturing hole, it is necessary to ensure that the weak structure of the rock layer after fracturing is located above the roadway, so the fracturing hole elevation angle is determined to be 45°.

[0082] (5) Determination of fracturing drilling layout

[0083] like Figure 2-Figure 4 As shown, boreholes are constructed in the extraction tunnel and the return air chute, which are divided into borehole A (i.e. the first borehole) and borehole B (i.e. the second borehole). Borehole A is mainly used for fracturing the high coarse-grained sandstone and low medium-grained sandstone roof of the return air chute, and borehole B is mainly responsible for fracturing the high coarse-grained sandstone roof on the solid coal side of the extraction tunnel.

[0084] Borehole A is constructed toward the goaf side, with an angle of 20° with the axial direction of the tunnel, and the hole opening position is 1m away from the coal seam on the working face side. The borehole diameter is 75mm, the borehole spacing is 12m, the borehole length is 30m, and the borehole elevation angle is 45°.

[0085] Borehole B is constructed vertically toward the roof of the extraction roadway, and the hole opening position is located 0.5m from the roof to the coal pillar. The borehole diameter is 75mm, the borehole spacing is 12m, the borehole length is 28m, the borehole elevation angle is 48°, and the angle between the borehole and the axial direction of the roadway is 90°.

[0086] Backward fracturing was adopted, starting from the bottom of the hole, and fracturing was carried out every 3m. The fracturing time of each section was controlled at 25 to 30min. Borehole A was fractured 8 times and borehole B was fractured 4 times.

[0087] (6) Determination of fracturing pressure

[0088] Without considering the defects of the rock itself, according to the maximum tensile stress criterion, the fracture initiation pressure P is:

[0089] P=σ θmin +Rt+αP h (6)

[0090] In the formula, σ θmin represents the minimum circumferential stress of the hole wall; Rt represents the tensile strength of the rock; P h —pore water pressure; α represents the pore water pressure contribution coefficient.

[0091] According to elastic mechanics, the circumferential stress around the borehole is:

[0092]

[0093] When r=r0:

[0094] σ θ =(σ Z +σ X )+2(σ Z -σ X )cos2θ (8)

[0095] therefore:

[0096]

[0097] When σ Z >σ X :

[0098] or Time θ The minimum value is obtained, that is, the circumferential stress at the top and bottom of the hole wall is the smallest.

[0099] When σ Z <σ X :

[0100] When θ=0 or θ=π, σ θ The minimum value is obtained, that is, the circumferential stress on both sides of the hole wall is the minimum.

[0101] Substituting equation 9 into equation 6, we can get

[0102]

[0103] According to the buried depth of 375m, the vertical stress σ is obtained Z is 9.4MPa; according to the ground stress measurement results, the horizontal stress σ X The tensile strength of coarse-grained sandstone is 2.26MPa, the pore water pressure is 5MPa, and the pore water pressure contribution coefficient is 1. The fracture pressure P of coarse-grained sandstone is 30.68MPa. The tensile strength of medium-grained sandstone is 2.17MPa, and the fracture pressure P of medium-grained sandstone is 30.59MPa.

[0104] (7) Reasonable determination of fracturing time

[0105] According to the hydraulic fracturing pressure relief principle, hydraulic fracturing is to create cracks in the coal rock mass through pore water pressure before the mining stress affects it, change the coal rock mass structure, and achieve the purpose of stress transfer and pressure relief. Therefore, the reasonable time for hydraulic fracturing should follow the following principles:

[0106] The construction must be carried out outside the influence range of the advanced support pressure of the working face, that is:

[0107] L1+v y t>L c +ΔL+v g t (11)

[0108] Where: v y Indicates the fracturing construction speed, m / d; v g Indicates the working face advancement speed, m / d; L c It represents the distance of influence of the advance support pressure of the working face, m; ΔL is the redundancy coefficient, which is generally 3 to 5 m; L1 is the distance between the hydraulic fracturing construction site and the working face, m; t is the hydraulic fracturing construction time, d.

[0109] According to the working face operation procedures, the working face advancement speed is 4.8m / d, and the advance impact range is about 25m. Considering the production and construction safety issues of the working face, the fracturing construction speed is 12m / d. The distance between the starting point of hydraulic fracturing construction and the working face should be greater than 25m.

[0110] Furthermore, the roof hydraulic fracturing process and procedures include:

[0111] (I) Installation work

[0112] Step-1: Assemble the packer, connect the two capsules and the small capillary in the middle of the capsules, connect the long small capillary to the packer, and tighten the joint;

[0113] Step-2: Send the packer to the borehole. Both capsules are put into the borehole, pressurized and expanded, check whether the packer is expanded, check whether there is water dripping at the joint, if normal, depressurize the packer and proceed to the next step. If abnormal, check the cause.

[0114] Step-3: Put the packer in front and the water injection steel pipe in the back, thread them one by one in order, and extend them into the borehole to be fractured until the packer touches the bottom of the hole. Check whether the sealing ring of each steel pipe is intact. The steel pipe needs to be tightened with a wrench. During the tightening process of the steel pipe, the upper steel pipe does not move, and only the lower steel pipe is rotated.

[0115] Step-4: Install a tee at the tail of the water injection steel pipe at the end of the borehole, one for connecting the steel pipe, one for connecting the high-pressure hose, and one for installing the pressure relief valve;

[0116] Step-5: Connect a pressure gauge (tee) and two stop valves in series at the end of the first high-pressure pipeline, and then connect it to the liquid supply pipeline.

[0117] Step-6: Check that the pressure relief valve at the end of the steel pipe is open and the stop valve in the high-pressure pipeline is closed.

[0118] (II) Fracturing work

[0119] Step-1: Use a manual pump to supply fluid to the packer. The manual pump pumps the water pressure to 10MPa to fully expand the packer. Observe the reading of the pressure gauge, which should not drop significantly within 15s and remain stable.

[0120] Step-2: Set up the alarm and close the pressure relief valve at the end of the steel pipe;

[0121] Step-3: Slowly open the stop valve of the pipeline and inject water into the borehole. Use the gradual pressure increase method to increase the pressure to 28-35MPa. The fracturing time for each section is 30 minutes; record the time, water pressure, and phenomena during the fracturing process.

[0122] If the pump pressure drops significantly (below 10MPa), or the water output from the adjacent borehole is relatively large, it means that the hydraulic fracture has caused a fracturing short circuit, and the pump can be stopped in advance.

[0123] Step-4: After fracturing, slowly close the stop valve of the high-pressure pipeline, open the pressure relief valve at the end of the steel pipe to release water, and after the water is released to a state without water pressure, slowly open the manual pump valve to release the pressure of the packer. During this process, strictly observe the changes in the water output of the water discharge pipe. If the water output increases, the manual pump water discharge valve should be temporarily closed. If the water output decreases, open the manual pump water discharge valve again. Continue to release the pressure until a stream of water flows out of the borehole, proving that the packer has completely shrunk back to its original shape;

[0124] Step-6: Drag the packer out of the hole for 3-5m and perform the second fracturing until the 4th stage of fracturing is completed. Note that when dragging the packer outward, it should be pulled out synchronously with the small capillary to prevent the small capillary from being entangled on the steel pipe or twisting, causing the equipment to get stuck.

[0125] The above are only preferred specific implementations of the present application, but the protection scope of the present application is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed in the present application should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.

Claims

1. A method for controlling hydraulic fracturing and top cutting pressure relief in a drainage tunnel under the influence of mining at a working face, characterized in that: The following steps are involved: Based on the geological conditions of coal mine working faces and tunnels, a hydraulic fracturing and top cutting pressure relief control strategy is proposed; Based on the hydraulic fracturing and roof cutting and pressure relief control idea, the occurrence distribution of the key layer of the roof of the coal mine working face is comprehensively determined to obtain the key layer; Based on the key layer, determine the arrangement plan of hydraulic fracturing and top cutting and pressure relief drilling holes; Based on the hydraulic fracturing drilling arrangement plan, respectively calculating the hydraulic fracturing initiation pressure and the hydraulic fracturing time; Based on the hydraulic fracturing initiation pressure and fracturing time, hydraulic fracturing top cutting and pressure relief control is carried out on the extraction tunnel.

2. The hydraulic fracturing and top cutting and pressure relief control method for the extraction tunnel under the influence of mining in the working face according to claim 1 is characterized in that: The criteria for determining the key layer include: Where q1 is the self-weight load of the first layer of controlled rock formation, unit: kN / m 2 ;q i Controlling rock formation deadweight load for the i-th layer; (q1) n The n-layer rock load controlled by the first layer; (q1) n+1 is the n+1 layer rock load controlled by the first layer; l' n+1 is the breaking step length of the n+1th layer, in m; l'1 is the breaking step length of the first layer, in m; l' i is the breaking step length of the i-th layer.

3. The hydraulic fracturing and top cutting and pressure relief control method for the extraction tunnel under the influence of mining in the working face according to claim 2 is characterized in that: The expression for determining the fracturing layer based on the key layer is: In the formula, h represents the height of the caving zone, M represents the mining height, K p Represents the coefficient of expansion.

4. The method for controlling hydraulic fracturing and top cutting and pressure relief in a drainage tunnel under the influence of mining at a working face according to claim 1, characterized in that: The layout of fracturing drilling includes: The first borehole is constructed toward the goaf side, with an angle of 20° with the axial direction of the tunnel, and the hole opening position is 1m away from the coal seam on the working face side. The borehole diameter is 75mm, the borehole spacing is 12m, the borehole length is 30m, and the borehole elevation angle is 45°; The second borehole was constructed in the vertical tunnel toward the roof above the extraction tunnel. The hole opening position was 0.5m away from the coal pillar on the roof. The borehole diameter was 75mm, the borehole spacing was 12m, the borehole length was 28m, the borehole elevation angle was 48°, and the angle between the borehole and the axial direction of the tunnel was 90°.

5. The method for controlling hydraulic fracturing and top cutting and pressure relief in a drainage tunnel under the influence of mining at a working face according to claim 4, characterized in that: The expression for calculating the fracturing pressure considering the circumferential stress around the borehole is: In the formula, P is the fracture initiation pressure, Rt is the tensile strength of rock, α is the pore water pressure contribution coefficient, and P is h represents the pore water pressure, σ Z represents the vertical stress, σ X Represents horizontal stress.

6. The method for controlling hydraulic fracturing and top cutting and pressure relief in a drainage tunnel under the influence of mining at a working face according to claim 5, characterized in that: The expression for determining the fracturing time is: L1+v y t>L c +ΔL+v g t In the formula, v y Indicates the fracturing construction speed, m / d; v g Indicates the working face advancement speed, unit: m / d; L c It represents the influence distance of the advanced support pressure of the working face, and the unit is: m; ΔL represents the redundancy coefficient; L1 represents the distance between the hydraulic fracturing construction site and the working face, and the unit is: m; t represents the hydraulic fracturing construction time, and the unit is: d.

7. A hydraulic fracturing device for use in the method according to any one of claims 1 to 6, characterized in that: It includes a packer, a water injection steel pipe, a tee, a high-pressure rubber hose, a pressure gauge, a stop valve and a manual pump.

Citation Information

Cited By

  • Coal roadway gas extraction and roof cutting method based on directional fracturing

    CN119712206A

  • Coal roadway gas extraction and roof cutting method based on directional fracturing

    CN119712206B

  • Cooperative control method for large-mining-height fully mechanized coal mining face coal wall caving

    CN119754766A

  • Method and device for processing roof of fully mechanized coal mining face

    CN119957245A

  • Directional three-dimensional hydraulic fracturing coal caving method for large-dip-angle double-hard fully-mechanized caving face

    CN120575865A