Secondary lining construction method for drainage tunnel of waterlogging treatment project

Through hydraulic automatic walking integrated lining trolley and specific waterproofing measures, the problems of low efficiency and insufficient waterproofing capacity in secondary lining construction of drainage tunnels in Zhongnan Road area are solved, achieving more efficient construction and more stable waterproofing effects.

CN118979770APending Publication Date: 2024-11-19THE 5TH ENGINEERING CO LTD OF CHINA RAILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411410681.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-10
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

The existing technology cannot effectively adapt to the harsh hydrological conditions and frequent rainfall of the secondary lining construction of drainage tunnels in the flood control project in Zhongnan Road area, resulting in low construction efficiency and insufficient waterproofing capacity.

Method used

The construction of hydraulic automatic walking integrated lining trolley is first laid with geotextile buffer layer and waterproof plate, and vibrating through steel bars and insert tamping rods to ensure the stability and waterproofness of the concrete, and deformation during construction joints and deformation. The intermediary buried water stop and steel-edged rubber water stop are used at the joints.

Benefits of technology

It improves construction efficiency and waterproofing capabilities, ensures the stability and waterproofness of the tunnel structure, reduces the impact of moisture penetration and external pressure on the waterproof plate, and extends the service life of the waterproof layer.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118979770A_ABST
    Figure CN118979770A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of drainage tunnel secondary lining construction, in particular to a drainage tunnel secondary lining construction method for a waterlogging treatment project, which comprises the following steps: laying a geotechnical cloth buffer layer, fixing by adopting a hidden nail ring, then laying a waterproof plate, firstly arching a wall when the waterproof plate is annularly laid, and pressing an upper waterproof plate by a lower waterproof plate, the staggered distance between a waterproof plate lap joint seam and a construction seam should not be smaller than 100 cm, the allowable deviation is-5 cm, a steel bar shaping radian clamp is manufactured on a steel plate outside a hole, a steel bar is bent and formed outside the hole and conveyed into the hole to be installed, waterproof construction is conducted on the construction seam and a deformation seam of secondary lining, a lining formwork and a water tank culvert formwork are manufactured, and the construction seam and the water tank culvert formwork are manufactured. An integral steel mould trolley is adopted as an inner mould of a lining formwork, supporting and reinforcing are stable through a reinforcing device of the trolley, when concrete is poured, bottom plate concrete is poured firstly, then tunnel body secondary lining concrete is poured, and tunnel body inverted arch concrete construction concrete pouring is conducted on a tunnel body part firstly, and then tunnel body arch wall concrete construction concrete pouring is conducted.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of secondary lining construction of drainage tunnels, in particular to a secondary lining construction method for drainage tunnels used in waterlogging control projects. Background Art

[0002] The terrain of the Zhongnan Road area is low, and the existing box culverts cross the community plots, with many bends, small local sections, and insufficient drainage capacity. In 2020, the area suffered a heavy rainstorm that occurred once in 50 years. The former Monkey King Welding Wire Factory was flooded and the water accumulated more than 2 meters deep, seriously affecting the normal life of citizens. In order to completely solve the problem of waterlogging, the drainage tunnel of the waterlogging control project in the Zhongnan Road area adopts a straight wall semicircular arch section with a clearance of 4.5m*5.5m. The upper part is designed as a rainwater channel and the lower part is a sewage pipe space. The secondary lining of the drainage tunnel is reinforced concrete, and it is planned to be constructed using a hydraulic automatic walking integral lining trolley. Because the straight wall steel bars of the tunnel are connected to the reinforcement of the lower sewage chamber, the lining trolley only constructs the outer ring tunnel lining, and the lower sewage pipe space adopts secondary structure construction. The secondary lining construction of the tunnel in the existing technology cannot adapt to the construction conditions in the application scenario. Therefore, it is necessary to design a drainage tunnel secondary lining construction method for the waterlogging control project in the Zhongnan Road area. Summary of the invention

[0003] The purpose of the present invention is to provide a secondary lining construction method for a drainage tunnel in a waterlogging control project, which can adapt to the severe hydrological conditions in Yichang area and the possible frequent rainfall and floods, and improve the waterproofing ability during construction.

[0004] The present invention is implemented by the following technical solution: A secondary lining construction method for a drainage tunnel in a waterlogging control project comprises the following steps: Step 1: Before the construction of the tunnel invert and arch wall secondary lining, the surveying team shall first check the clearance of the tunnel initial support section.

[0005] Step 2: First lay the geotextile buffer layer, fix it with concealed nails, and then lay the waterproof board.

[0006] Step 3: When laying the waterproof board in a circumferential direction, first arch the back wall, and the lower waterproof board presses the upper waterproof board. The staggered distance between the lap joint of the waterproof board and the construction joint should not be less than 100cm, and the allowable deviation is -5cm.

[0007] Step 4: Use steel plates to make steel bar shaping arc cards outside the hole. The steel bars are bent into shape outside the hole and transported into the hole for installation.

[0008] Step 5: Carry out waterproof construction on the construction joints and deformation joints of the secondary lining.

[0009] Step 6: Make the lining formwork and the water box culvert formwork, use the integral steel formwork trolley as the inner formwork of the lining formwork, and use the trolley's own reinforcement device to support and reinforce it securely. The head template is processed into semi-finished products using 5cm thick wooden boards and 10cm*10cm square wood, assembled on site according to the corresponding positions, and fastened using the trolley reinforcement system. For each construction cycle of the arch wall and the second lining concrete, the survey team will lay out the starting mileage, center line, level and two ends, and the construction personnel will proceed according to the survey team's layout line.

[0010] Step 7, when pouring concrete, first pour the bottom plate concrete, then pour the second lining concrete of the tunnel body. For the tunnel body part, first pour the tunnel invert concrete, then pour the tunnel body arch wall concrete. During the pouring process, an inserted tamping rod must be used for vibration.

[0011] In order to better realize the present invention, further, the concealed nail ring fixing method is to use nails with thermoplastic round washers to fix the buffer layer flatly and straightly on the base layer, with an arch spacing of 65cm, a side wall spacing of 90cm, and a bottom spacing of 125cm, arranged in a plum blossom shape, and fixed in rows left and right and up and down. The waterproof board is fixed with a heat sealer so that the waterproof board is firmly bonded to the plastic gasket after melting.

[0012] In order to better implement the present invention, further, the steel bar installation requires that a positioning steel bar must be set every 3 meters or 4 meters, first ensure the position of the end positioning bar, and then adjust the spacing of the middle positioning bar to ensure accurate positioning of the steel bar.

[0013] In order to better realize the present invention, further, the construction joint adopts a centrally embedded waterstop, and the deformation joint adopts a centrally embedded steel-edged rubber waterstop plus caulking material.

[0014] In order to better realize the present invention, further, the water culvert template adopts a wooden mold as an inner mold, and uses 1.2 cm thick wood plywood and 10 cm*10 cm square wood to process into semi-finished products, which are assembled at the corresponding positions on site.

[0015] In order to better realize the present invention, further, the height from the concrete feeding port to the concrete pouring surface shall not be greater than 2m to prevent concrete segregation. Concrete pouring shall be carried out alternately on both sides to prevent bias pressure.

[0016] In order to better realize the present invention, further, the insert vibrator is used during tamping and should be inserted into the concrete vertically or slightly inclined, inserted slightly faster and pulled out slightly slower, and tamped while being lifted to avoid voids in the concrete.

[0017] In order to better realize the present invention, further, after the concrete lining is completed, the strength when demolding needs to meet the strength required by the specification, that is, it reaches 8MPa or above, and its surface and edges are not damaged by demolding before it can be removed.

[0018] Compared with the prior art, the present invention has the following advantages and beneficial effects: 1. In the secondary lining construction method of the present invention, a thermostat is used to melt the waterproof board when laying it, and the waterproof board is firmly bonded to the plastic gasket, thereby improving the laying quality of the waterproof board and avoiding problems such as loosening of the waterproof board.

[0019] 2. During tunnel construction, the present invention first pours the bottom plate concrete to provide a solid foundation for construction, and then pours the secondary lining concrete of the tunnel body, thereby avoiding delays in the construction period due to the unformed tunnel body during bottom plate construction, thereby improving construction efficiency and ensuring structural stability.

[0020] 3. In the construction method of the present invention, when laying the waterproof board, the upper drainage board is pressed by the lower waterproof board, so as to ensure that the drainage boards are more tightly connected, reduce the possibility of water penetration from the joints, increase waterproofness, and also increase the compressive resistance of the waterproof board, thereby improving its stability in dealing with external pressure. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Other features, objects and advantages of the present invention will become more apparent from the detailed description of non-limiting embodiments with reference to the following drawings: Figure 1 It is a schematic diagram of the construction process of the present invention. DETAILED DESCRIPTION

[0022] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0023] Embodiment 1: like Figure 1 As shown, a secondary lining construction method for a drainage tunnel in a waterlogging control project comprises the following steps: Step 1: Before the construction of the tunnel invert and arch wall secondary lining, the surveying team shall first check the clearance of the initial support section of the tunnel.

[0024] The excess or shortage parts should be processed in advance, and re-measured after processing. The next process can only be carried out after passing the inspection of the supervisor.

[0025] Before waterproof board construction, exposed steel bar heads, iron wires, anchor pipes and anchor rods and other sharp objects on the initial support surface must be cut off and hammered flat, and smoothed with mortar, and no sharp objects should appear. After being inspected and qualified by the supervision engineer, the next process can be entered.

[0026] Step 2: First lay the geotextile buffer layer, fix it with concealed nails, and then lay the waterproof board.

[0027] The buffer layer is fixed flatly and straightly on the base layer using nails with thermoplastic round washers. The arch spacing is 65cm, the side wall is 90cm, and the bottom is 125cm. They are arranged in a plum blossom shape and fixed in rows left and right and up and down. The waterproof board is fixed with a heat sealer so that the waterproof board can be firmly bonded to the plastic gasket after melting.

[0028] Step 3: When laying the waterproof board in a circumferential direction, first arch the back wall, and the lower waterproof board presses the upper waterproof board. The staggered distance between the lap joint of the waterproof board and the construction joint should not be less than 100cm, and the allowable deviation is -5cm.

[0029] The ratio of the laying length of the waterproof board to the arc length of the initial support base surface is 10:8, and the number of hanging points should be reasonable. The overlap width of the waterproof board shall not be less than 15cm. The edge of the waterproof board laid in sections shall reserve at least 60cm of overlap margin, and the allowable deviation is -10mm. When the waterproof board weld is double-welded, the width of each weld shall not be less than 15mm. There should be no leakage, false welding, welding scorch and welding penetration in the weld. If there is leakage or false welding in the weld, it should be repaired. If there is welding scorch, welding penetration, and exposed fixing points, homogeneous materials should be used for covering welding. The overlap width of the geotextile shall not be less than 5cm. The buffer layer should be smooth, without bulges or wrinkles.

[0030] After the upper waterproof board is pressed by the lower waterproof board, it can ensure that the drainage boards are more tightly connected, reduce the possibility of water penetration from the joints, increase waterproofness, and increase the compressive strength of the waterproof board, improving its stability when dealing with external pressure. The mutual compaction between the upper and lower waterproof boards can also reduce the risk of damage to the waterproof board by external factors, such as collision or external force extrusion of the waterproof board, thereby extending the service life of the waterproof layer.

[0031] Step 4: Use steel plates to make steel bar shaping arc cards outside the hole. The steel bars are bent into shape outside the hole and transported into the hole for installation.

[0032] Set a positioning steel bar every 3 meters or 4 meters. First ensure the position of the end positioning bar, and then adjust the spacing of the middle positioning bars.

[0033] The main reinforcement is connected by straight threaded sleeves, and the joints of the same cross-section reinforcement do not exceed 50%. The installation of the inner layer reinforcement is determined by the surveyor, who determines the clearance control points of the inner layer reinforcement. The control points are set on the installed outer layer reinforcement to form an accurate reinforcement skeleton in sections.

[0034] When installing steel bars, protective pads should be installed, with no less than 4 per square meter, so that the template trolley can be smoothly positioned. When welding steel bars distributed in the hole, a submerged template or iron sheet should be placed underneath to prevent the waterproof board from being burned.

[0035] Step 5: Carry out waterproof construction on the construction joints and deformation joints of the secondary lining.

[0036] The construction joint uses embedded waterstop, and the expansion joint uses embedded steel-edged rubber waterstop plus caulking material.

[0037] Step 6: The lining formwork uses an integral steel formwork trolley as the inner formwork, and the trolley's own reinforcement device is used to support and reinforce it securely. The head formwork is processed into semi-finished products using 5cm thick wooden boards and 10cm*10cm square wood, assembled on site according to the corresponding positions, and fastened using the trolley reinforcement system. For each construction cycle of the arch wall and the second lining concrete, the survey team will lay out the starting mileage, center line, level and two end heads, and the construction personnel will proceed according to the survey team's layout line.

[0038] The formwork trolley is assembled in a spacious area outside the tunnel and paved with steel rails to move into the tunnel for construction. After the assembly of the formwork trolley is completed, the engineering department organizes relevant departments to inspect the clearance, steel structure, traveling equipment and hydraulic equipment. Before the formwork trolley is in place, it must be rust-free, cleaned, and coated with a release agent.

[0039] The water culvert formwork uses a wooden formwork as the inner formwork, and uses 1.2cm thick plywood and 10cm*10cm square wood to process into semi-finished products, which are then assembled on site according to corresponding positions.

[0040] Each section is assembled 30 meters and the construction is carried out in cycles. The surveying team will lay out the starting mileage, center line, level and two ends of each construction cycle, and the construction personnel will carry out the work according to the surveying team's layout line.

[0041] Step 7, when pouring concrete, first pour the bottom plate concrete, then pour the second lining concrete of the tunnel body. For the tunnel body part, first pour the tunnel invert concrete, then pour the tunnel body arch wall concrete. During the pouring process, an inserted tamping rod must be used for vibration.

[0042] Before pouring, check whether there is any gap between the template and the inverted arch. If there is any gap, fill it with cement mortar to prevent leakage from affecting the appearance quality of concrete. The top surface of the inverted arch on both sides should be roughened and cleaned, and the area of ​​fresh concrete should not be less than 75%, and it should be washed with high-pressure water to ensure that there is no debris and loose slag.

[0043] The height from the concrete feeding port to the concrete pouring surface shall not be greater than 2m to prevent concrete segregation. Concrete pouring should be carried out alternately on both sides to prevent biased pressure.

[0044] The transportation, pouring and interval time of concrete should not exceed the initial setting time of concrete. The pouring of concrete should be continuous, and the upper layer of concrete should be poured before the initial setting of the bottom layer of concrete. When an accident occurs, the bottom layer of concrete has already initially set, and the next pouring should be treated as a construction joint: on the front joint surface, bury the jointed steel bars and make them about half exposed outside the concrete. First, chisel off the mortar film on the construction joint surface, and the loose stones or loose concrete layer on the surface, and rinse it with pressurized water to make it fully moist without stagnant water.

[0045] When tamping, use an insert vibrator and insert it into the concrete vertically or slightly tilted. Insert it slightly faster and pull it out slightly slower, and tamp while lifting to avoid voids in the concrete.

[0046] When the concrete surface stops sinking, no significant bubbles appear, the surface is flat and shiny, and the corners of the formwork are filled with concrete, it indicates that the concrete is dense. The second lining concrete strength of the arch wall reaches 8MPa before demolding. After demolding, the concrete surface should be moisturized and maintained in time, and the watering maintenance time should not be less than 14 days.

[0047] After the concrete lining is completed, the strength when the formwork is removed needs to meet the strength requirements of the specification, that is, it must reach above 8MPa, and its surface and edges must not be damaged due to formwork removal before it can be removed.

[0048] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Any simple modification or equivalent change made to the above embodiment based on the technical essence of the present invention shall fall within the protection scope of the present invention.

Claims

1. A secondary lining construction method for a drainage tunnel in a waterlogging control project, characterized in that: The following steps are involved: Step 1: Before the construction of the tunnel invert and arch wall secondary lining, the surveying team shall first check the clearance of the tunnel primary support section; Step 2: First lay the geotextile buffer layer, fix it with concealed nails, and then lay the waterproof board; Step 3: When laying the waterproof board in a circular direction, first arch the back wall, and the lower waterproof board presses the upper waterproof board. The distance between the lap joint of the waterproof board and the construction joint should not be less than 100cm, and the allowable deviation is -5cm; Step 4: Use steel plates to make steel bar shaping arc cards outside the hole, bend the steel bars outside the hole, and transport them into the hole for installation; Step 5: Waterproof the construction joints and deformation joints of the secondary lining; Step 6: Make the lining formwork and the water box culvert formwork, use the integral steel formwork trolley as the inner mold of the lining formwork, and use the reinforcement device of the trolley to support and reinforce it securely; The stopper template is made of 5cm thick wood and 10cm*10cm square wood processed into semi-finished products, assembled on site according to the corresponding position, and fastened using the trolley reinforcement system. For each construction of a cycle of arch wall and second lining concrete, the survey team will lay out the starting mileage, center line, level and two end heads, and the construction personnel will proceed according to the survey team's layout line; Step 7, when pouring concrete, first pour the bottom plate concrete, then pour the second lining concrete of the tunnel body. For the tunnel body part, first pour the tunnel invert concrete, then pour the tunnel body arch wall concrete. During the pouring process, an inserted tamping rod must be used for vibration.

2. The secondary lining construction method for drainage tunnels in waterlogging control projects according to claim 1 is characterized in that: The concealed nail ring fixing method is to use nails with thermoplastic round washers to fix the buffer layer flatly and straightly on the base layer. The arch spacing is 65cm, the side wall is 90cm, and the bottom is 125cm. They are arranged in a plum blossom shape and fixed in rows left and right and up and down. The waterproof board is fixed with a heat sealer so that the waterproof board can be firmly bonded to the plastic gasket after melting.

3. The secondary lining construction method for drainage tunnels in waterlogging control projects according to claim 1 is characterized by: The steel bar installation requires that a positioning steel bar must be set every 3 meters or 4 meters. First, ensure the position of the end positioning bar, and then adjust the spacing of the middle positioning bar to ensure accurate positioning of the steel bar.

4. The secondary lining construction method for drainage tunnels in waterlogging control projects according to claim 1 is characterized by: The construction joint adopts a centrally embedded waterstop, and the expansion joint adopts a centrally embedded steel-edged rubber waterstop plus caulking material.

5. The secondary lining construction method for drainage tunnels in waterlogging control projects according to claim 1 is characterized in that: The water culvert template uses a wooden mold as an inner mold, and uses 1.2cm thick plywood and 10cm*10cm square wood to process into semi-finished products, which are assembled on site according to corresponding positions.

6. The secondary lining construction method for drainage tunnels in waterlogging control projects according to claim 1, characterized in that: The height from the concrete feeding port to the concrete pouring surface shall not be greater than 2m to prevent concrete segregation; Concrete pouring should be carried out alternately on both sides to prevent bias pressure.

7. The secondary lining construction method for drainage tunnels in waterlogging control projects according to claim 1 is characterized in that: During the tamping, an insert vibrator is used and should be inserted into the concrete vertically or slightly inclined. It should be inserted slightly faster and pulled out slightly slower, and tamping should be done while being lifted to avoid voids in the concrete.

8. The secondary lining construction method for drainage tunnels in waterlogging control projects according to claim 1, characterized in that: After the concrete lining is completed, the strength when the formwork is removed must meet the strength requirements of the specification, that is, it must reach 8MPa or above, and its surface and edges must not be damaged due to formwork removal before it can be removed.