Prefabricated structure for leveling cementation layer of dam asphalt concrete panel and construction method

Through the modular design of prefabricated rectangular prefabricated units and the strict control of mix ratio and temperature in the factory, the problems of difficulty in the construction of the dam asphalt concrete panel leveling and bonding layer are solved and the quality is not easy to ensure, achieving rapid, controllable and environmentally friendly construction Effect.

CN118997070APending Publication Date: 2024-11-22NORTHWEST ENGINEERING CORPORATION LIMITED +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202411174497.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-26
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

During the construction process of the existing dam asphalt concrete panel leveling and cementing layer, there are problems such as aggregate separation, temperature loss, uneven paving thickness, and failure to meet the requirements, which leads to high construction difficulty, long cycle and difficult quality assurance. Especially on slopes and surfaces, it is more difficult to pave.

Method used

Prefabricated rectangular prefabricated units are used to carry out the construction of the leveling glue layer. Through prefabricated and modular design in the factory, the prefabricated units of each layer are spliced ​​along the length of the rectangle, and there are splicing seams between the adjacent two prefabricated units. And it is closely laid from bottom to top at the construction site to ensure that the splicing seams are aligned vertically with bisectors.

Benefits of technology

It improves construction speed and quality controllability, shortens construction cycle, reduces environmental impact and costs, and improves the flexibility and adaptability of the overall project.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997070A_ABST
    Figure CN118997070A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of asphalt concrete face rock-fill dams, and discloses a dam asphalt concrete face leveling cementing layer prefabricated structure and a construction method.The dam asphalt concrete face leveling cementing layer prefabricated structure comprises a plurality of rectangular prefabricated units which are spliced into a plurality of layers in the length direction, and a splicing seam is formed between every two adjacent prefabricated units of each layer; the construction period is greatly shortened, the quality of the leveling cementing layer can be ensured, the leveling cementing layer has good durability and stability, conditions are created for laying an asphalt concrete impermeable layer, the stability and integrity of an upper layer structure are ensured, and normal operation and the service life of a dam are ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of asphalt concrete panel rockfill dams, and in particular relates to a prefabricated structure and a construction method for a leveling bonding layer of an asphalt concrete panel of a dam. Background Art

[0002] The structure of asphalt concrete panel can be divided into three layers, namely, leveling bonding layer, anti-seepage layer and sealing layer. Among them, the leveling bonding layer is mainly used for foundation leveling and improving the bonding effect between the anti-seepage layer and the foundation surface, creating conditions for laying the anti-seepage layer and ensuring the stability and integrity of the upper structure. At the same time, it has a certain permeability and can quickly drain the water seepage from the anti-seepage layer to avoid damage to the asphalt concrete panel.

[0003] The production process of the leveling bonding layer of the asphalt concrete panel of the existing dam technology is to produce a certain ratio of asphalt mixture using an asphalt mixing plant, and then unload the mixture into a dump truck with insulation facilities and transport it to the paving site. Aggregate separation, leakage, excessive temperature loss and other phenomena are prone to occur during transportation. This affects the quality of paving and rolling. Since the reservoir panel is often composed of flat surfaces and curved surfaces, and the paving on slopes and curved surfaces requires higher construction technology and greater construction difficulty, paving is more difficult, and local narrow areas require manual paving, resulting in uneven paving thickness, compaction and flatness that do not meet the requirements, which in turn affects the impermeability of the entire asphalt concrete panel. At the same time, due to the narrow working surface on the dam top and the large size of the paver traction trolley, mutual interference between the traction trolley and the vibrating roller traction machine often occurs, affecting the rolling operation, extending the construction period, and the construction quality is not easy to guarantee. Summary of the invention

[0004] The purpose of the present invention is to provide a prefabricated structure and construction method for a dam asphalt concrete panel leveling bonding layer, so as to improve the construction quality and efficiency of the asphalt concrete panel leveling bonding layer.

[0005] The technical solution adopted by the present invention is a prefabricated structure of a leveling bonding layer of an asphalt concrete panel of a dam, comprising a plurality of rectangular prefabricated units, wherein the plurality of prefabricated units are spliced ​​into a plurality of layers along the length direction of the rectangle, and a splicing seam is provided between two adjacent prefabricated units of each layer, and the splicing seams between two adjacent layers are staggered with each other.

[0006] Preferably, the joint seam of each layer is aligned with the perpendicular bisector of the prefabricated units of two adjacent layers along the length direction of the rectangle.

[0007] The present invention also provides a construction method for a prefabricated structure of a dam asphalt concrete panel leveling bonding layer, comprising the following steps: S1. Prefabricated unit preparation: prefabricate the prefabricated units in the factory according to the design and construction requirements, and transport the prefabricated units to the construction site; S2. Base treatment: clean up the construction area, repair and compact the upstream slope of the dam body, and spray a layer of emulsified asphalt or diluted asphalt on the surface to ensure good bonding between the prefabricated unit and the base; S3. Laying and leveling the bonding layer: According to the design requirements, the prefabricated units are laid from the bottom of the reservoir to the top of the dam. When laying, it is necessary to ensure that the two adjacent prefabricated units are tightly fitted, and the joints of each layer are aligned with the perpendicular bisectors of the two adjacent layers of prefabricated units along the length direction of the rectangle.

[0008] The beneficial effects of the present invention are: Fast construction speed: Due to the prefabrication and modular design, there is no need for on-site paving and rolling, which solves the difficulties of paving on slopes and curved surfaces and greatly shortens the construction period.

[0009] Controllable quality: The prefabricated units are pressed and produced in the factory, which can strictly control the mix ratio accuracy and temperature, ensure the performance and quality of the leveling bonding layer, have good durability and stability, and ensure the stability and service life of the asphalt concrete panel and dam.

[0010] Energy saving and environmental protection: The prefabricated unitized leveling bonding layer reduces waste and noise during on-site construction and reduces the impact on the environment.

[0011] Cost saving: Prefabricated unitized leveling bonding layer can reduce on-site construction personnel and management costs, and is safe and reliable, thereby reducing the overall project cost.

[0012] High flexibility: The prefabricated unitized leveling bonding layer can be designed and adjusted according to actual project needs, with high flexibility and adaptability. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 A schematic diagram of a prefabricated structure for the leveling and bonding layer of an asphalt concrete panel is provided; Figure 2 This is a schematic diagram of the structure of Embodiment 2 of the present invention; Figure 3 This is a schematic diagram of the structure of Example 3 of the present invention.

[0014] In the figure: 1. Prefabricated asphalt concrete panel leveling bonding layer; 11. Prefabricated unit; 12. Joint; 2. Cushion material; 3. Mortar slope consolidation; 4. Asphalt concrete anti-seepage layer; 5. Sealing layer; 6. Extrusion side wall. DETAILED DESCRIPTION

[0015] The present invention is described in detail below with reference to the accompanying drawings and specific embodiments.

[0016] Example 1 like Figure 1As shown, the prefabricated structure of the leveling bonding layer of the dam asphalt concrete panel of the present invention includes a plurality of rectangular prefabricated units 11, and the plurality of prefabricated units 11 are spliced ​​into a plurality of layers along the length direction of the rectangle, and a splicing seam 12 is provided between two adjacent prefabricated units 11 of each layer, and the splicing seams 12 between two adjacent layers are staggered with each other.

[0017] The joint seam 12 of each layer is aligned with the perpendicular bisector of the prefabricated units 11 of the two adjacent layers along the length direction of the rectangle.

[0018] The size of the prefabricated unit 11 is a×h. When in use, the size of the prefabricated unit 11 can be adjusted according to actual conditions.

[0019] The present invention also provides a construction method for a dam asphalt concrete panel leveling bonding layer, comprising the following steps: S1. Preparation of prefabricated unit 11: prefabricating prefabricated unit 11 in a factory according to design and construction requirements, and transporting prefabricated unit 11 to the construction site; S2. Base treatment: clean the construction area, repair and compact the upstream dam slope of the dam body, and spray a layer of emulsified asphalt or diluted asphalt on the surface to ensure good bonding between the prefabricated unit 11 and the base; S3. Laying and leveling the bonding layer: According to the design requirements, the prefabricated units 11 are laid from bottom to top from the reservoir bottom to the dam top. When laying, it is necessary to ensure that the two adjacent prefabricated units 11 are tightly fitted, and the joint seams 12 of each layer are aligned with the perpendicular bisectors of the prefabricated units 11 of the two adjacent layers along the length direction of the rectangle.

[0020] Among them, step S1 specifically includes the following steps: preparation of prefabricated unit 11: according to the design and construction requirements, carry out testing of the physical and mechanical properties of raw materials, select suitable asphalt, aggregate and filler, and conduct mix ratio tests to determine the recommended mix ratio, prefabricate the prefabricated unit 11 in the factory, ensure that the quality meets the project requirements, and transport the prefabricated unit 11 to the construction site.

[0021] Example 2 On the basis of Example 1, the prefabricated structure of the leveling bonding layer of the dam asphalt concrete panel in this embodiment is applied to the mortar slope consolidation, such as Figure 2 As shown, the dam body includes a cushion material 2, a mortar slope consolidation 3, a prefabricated asphalt concrete panel leveling bonding layer 1, an asphalt concrete anti-seepage layer 4, and a sealing layer 5 which are laid in sequence.

[0022] The cushion material 2 is laid on the rockfill of the dam to support and level the asphalt concrete panel, so that the water pressure on the panel is evenly transmitted to the rockfill, preventing the panel from being damaged due to excessive deformation gradient; it is also the second anti-seepage line of the dam, which plays both anti-seepage and drainage roles to prevent water accumulation from damaging the structure.

[0023] The mortar slope fixing 3 is the slope protection material of the cushion material 2, and its surface needs to be sprayed with emulsified asphalt.

[0024] The prefabricated asphalt concrete panel leveling bonding layer 1 is the prefabricated structure of the dam asphalt concrete panel leveling bonding layer of Example 1.

[0025] The asphalt concrete anti-seepage layer 4 is a key component of the anti-seepage panel, which is used to prevent water leakage. It has good anti-seepage performance and certain flexibility, and can adapt to the deformation of the dam.

[0026] The sealing layer 5 is used to seal the entire structure, protect the underlying structural layer from the influence of the external environment, and prevent the lower structure from aging. The material is asphalt mastic.

[0027] Example 3 On the basis of Example 1, the prefabricated structure of the leveling bonding layer of the dam asphalt concrete panel in this embodiment is applied to the extruded wall, such as Figure 3 As shown, the dam body includes a cushion material 2, an extruded side wall 6, a prefabricated asphalt concrete panel leveling bonding layer 1, an asphalt concrete anti-seepage layer 4, and a sealing layer 5 which are laid in sequence.

[0028] The cushion material 2 is laid on the rockfill of the dam to support and level the asphalt concrete panel, so that the water pressure on the panel is evenly transmitted to the rockfill, preventing the panel from being damaged due to excessive deformation gradient; it is also the second anti-seepage line of the dam, which plays both anti-seepage and drainage roles to prevent water accumulation from damaging the structure.

[0029] The extruded side wall 6 is a low-strength, semi-permeable concrete wall made by extrusion equipment, and after the strength meets the requirements, the cushion material 2 and other rockfill bodies are filled, which can improve the construction efficiency, improve the rolling quality of the cushion material 2, simplify the process and reduce the cost.

[0030] The prefabricated asphalt concrete panel leveling bonding layer 1 is the prefabricated structure of the dam asphalt concrete panel leveling bonding layer of Example 1.

[0031] The asphalt concrete anti-seepage layer 4 is a key component of the anti-seepage panel, which is used to prevent water leakage. It has good anti-seepage performance and certain flexibility, and can adapt to the deformation of the dam.

[0032] The sealing layer 5 is used to seal the entire structure, protect the underlying structural layer from the influence of the external environment, and prevent the lower structure from aging. The material is asphalt mastic.

[0033] Components and structures not described in detail in the embodiments are well-known components and common structures or common means in the industry and are not described one by one here.

Claims

1. A prefabricated structure for leveling and bonding layer of asphalt concrete panel of dam, characterized in that: It comprises a plurality of rectangular prefabricated units (11), wherein the plurality of prefabricated units (11) are assembled into a plurality of layers along the length direction of the rectangle, a joint seam (12) is provided between two adjacent prefabricated units (11) in each layer, and the joint seams (12) between two adjacent layers are staggered.

2. The prefabricated structure of the leveling bonding layer of the dam asphalt concrete panel according to claim 1 is characterized in that: The joint seam (12) of each layer is aligned with the perpendicular bisector of the prefabricated units (11) of two adjacent layers along the length direction of the rectangle.

3. A construction method for a prefabricated structure of a dam asphalt concrete panel leveling bonding layer as claimed in claim 1 or 2, characterized in that: The following steps are involved: S1. Prefabricated unit (11) preparation: prefabricating the prefabricated unit (11) in a factory according to design and construction requirements, and transporting the prefabricated unit (11) to the construction site; S2. Base treatment: clean the construction area, repair and compact the upstream slope of the dam body, and spray a layer of emulsified asphalt or diluted asphalt on the surface to ensure good bonding between the prefabricated unit (11) and the base; S3. Laying and leveling the bonding layer: According to the design requirements, the prefabricated units (11) are laid from bottom to top from the reservoir bottom to the dam top. When laying, it is necessary to ensure that two adjacent prefabricated units (11) are tightly fitted, and the joint seam (12) of each layer is aligned with the perpendicular bisector of the prefabricated units (11) of the two adjacent layers along the length direction of the rectangle.

Citation Information

Patent Citations

  • Asphalt road paving base block, asphalt road structure and construction method thereof

    CN111218875A

  • Asphalt concrete seepage prevention structure

    CN206157670U

  • Restoration of a dam wall uses rows of prefabricated components with fresh asphalt concrete inserted between the component structure and the dam wall when each row is complete for a joint-free seal

    DE19935315A1