Fabricated quick-plugging flat-connection water steel pipe pile construction platform and construction method

By adopting the cyclonic connection assembly and pin connection technology on the water steel pipe pile platform, the problems of inaccurate positioning and difficult welding of steel pipe piles are solved, the construction efficiency and positioning accuracy are improved, and the construction quality and safety are improved.

CN118997147APending Publication Date: 2024-11-22CCCC SECOND NAVIGATION BUREAU MUNICIPAL CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411198743.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-29
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

In the field of water construction, the existing steel pipe pile platforms are inaccurately positioned, have large measurement workloads, and are difficult to weld, resulting in low construction efficiency and reduced connection quality, posing safety and quality hazards.

Method used

The prefabricated quick plug-and-extraction flat-connected water-mounted steel pipe pile construction platform is adopted. By installing a cyclonic connection assembly on the steel pipe pile, the positioning block, the connecting hinge and the rotary connection block are used to achieve rapid connection and disassembly between the steel pipe piles. The braces and oblique braces are connected by pins to reduce welding and measurement work.

Benefits of technology

The construction efficiency and positioning accuracy of the steel pipe pile construction platform are improved, the measurement project volume is reduced, the rapid connection and demolition is achieved, the construction difficulty is reduced, and the construction quality and safety are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997147A_ABST
    Figure CN118997147A_ABST
Patent Text Reader

Abstract

The invention discloses an assembly type quick-inserting-pulling flat-connection water steel pipe pile construction platform and a construction method. The assembly type quick-inserting-pulling flat-connection water steel pipe pile construction platform comprises steel pipe piles, rotary connection assemblies, cross braces and inclined braces. Wherein rotary connecting assemblies are detachably installed on the steel pipe piles, and the cross braces and the inclined braces between the steel pipe piles are detachably connected through the rotary connecting assemblies. The problems that the steel pipe pile positioning efficiency is low, and the connecting workload of longitudinal and transverse inclined struts is large are solved, and the construction efficiency and quality of a steel pipe pile construction platform are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of water construction, and more specifically, to an assembled quick-plug and parallel-connected water steel pipe pile construction platform. Background Art

[0002] At present, in the field of water and offshore construction, it is necessary to set up a steel pipe pile construction platform. The existing steel pipe pile platform construction is generally carried out after measurement and layout, and steel pipe piles are driven. Each steel pipe pile needs to be positioned. Affected by the water (sea) construction conditions, there are problems such as inaccurate positioning and large measurement workload. After the steel pipe piles are driven, the horizontal and diagonal braces are welded, which requires the cooperation of lifting equipment. The water (sea) construction is difficult, resulting in low platform construction efficiency and slow progress. If the platform is set up in a large area, in order to reduce the investment in turnover materials, the platform is generally used in turnover. According to the construction organization arrangement, after the construction of the steel pipe pile platform in a certain construction area is completed, the horizontal and diagonal braces are removed, the steel pipe piles are pulled up, and moved to the next construction area on the existing platform for driving, and a large number of measurements and welding work are repeated. At the same time, as the number of welding times increases, the connection quality between the components will also decrease, and there are safety and quality risks. Summary of the invention

[0003] The purpose of the present invention is to provide an assembled quick-plug and pull-out flat-jointed water steel pipe pile construction platform and a construction method, so as to solve the problems of low steel pipe pile positioning efficiency and large workload of connecting vertical and horizontal diagonal braces, and improve the construction efficiency and quality of the steel pipe pile construction platform.

[0004] The technical solution adopted by the present invention to solve this technical problem is: an assembled quick-plug-in and parallel-connected water steel pipe pile construction platform, comprising: steel pipe piles, a rotary connection assembly, cross braces and diagonal braces; wherein the steel pipe piles are detachably equipped with a rotary connection assembly, and the cross braces and diagonal braces between the steel pipe piles are detachably connected through the rotary connection assembly.

[0005] As a further solution of the present invention, the steel pipe pile includes a pile body and a pile cap.

[0006] As a further solution of the present invention, the pile body is provided with a fixing hole for connecting and fixing the rotary connection assembly;

[0007] The rotary connection assembly includes a positioning block, a connecting hinge, a rotating connection block and a fixing unit; the upper and lower ends of the positioning block are connected to the fixing unit, and the fixing unit is provided with a fixing hole. The positioning block and the fixing unit are sleeved on the steel pipe pile, and the fixing unit is connected to the steel pipe pile through bolts and fixing holes. The connecting hinge connects the positioning block and the rotating connection block so that the rotating connection block can rotate relative to the positioning block, which is convenient for adjusting the direction of the rotating connection block. A limiting connection port is provided on the rotating connection block, and the horizontal brace and diagonal brace are connected to the limiting connection port of the rotating connection block through a pin shaft.

[0008] As a further solution of the present invention, the rotating connection block is provided with four or eight groups of limit connection ports arranged at equal intervals.

[0009] As a further solution of the present invention, the horizontal brace and the diagonal brace have the same structure and are both retractable structures.

[0010] As a further solution of the present invention, the horizontal brace and the diagonal brace are both composed of an external square tube and an internal square tube, the external square tube is provided with limiting blocks around it, and the internal square tube is provided with limiting grooves around it, the limiting blocks of the external square tube are located in the limiting grooves of the internal square tube, the internal square tube and the external square tube are provided with fixing holes, and the internal square tube and the external square tube are fixed by bolts and the fixing holes.

[0011] The present invention also provides a construction method using an assembled quick-plug and pull-out flat-jointed water steel pipe pile construction platform, comprising:

[0012] S1. According to the construction plan, determine the area where the platform is to be erected, put the surveying ship and the pile-driving ship in place, stake out the positions of the steel pipe piles at both ends of each row at one time, and drive the steel pipe piles at both ends. After the steel pipe piles at both ends are driven, assemble the rotary connection assembly. According to the connection requirements, install the horizontal brace, diagonal brace and hand chain hoist in the corresponding horizontal brace and diagonal brace limit connection port of the rotary connection assembly to facilitate the later horizontal brace and diagonal brace connection construction. After the assembly is completed, install the upper and lower rotary connection assemblies, fix them to the steel pipe piles with bolts after installation, and then install the caps, the upper and lower rotary connection assemblies and the upper rotary The connection assembly and the pile cap are connected by a hand winch, which is convenient for adjusting the height of the swing connection assembly. After adjusting the two swing connection assemblies to the designed height by the hand winch, the swing connection assembly is fixed by bolts and fixing holes on the steel pipe piles. After the positioning and installation of the swing connection assembly of each pile is completed, the installation of the horizontal braces and diagonal braces is started. The lengths of the horizontal braces and diagonal braces are adjusted according to the connection requirements. Finally, they are hoisted into the limiting connection port of the corresponding swing connection assembly through the hand winch on the corresponding swing connection assembly and connected by a pin shaft to complete the construction of the steel pipe pile foundation of the water platform.

[0013] As a further solution of the present invention, it also includes:

[0014] Step S2: When the construction content of this area is completed and the construction platform needs to be moved, if there is enough rotation space, the whole platform is rotated, one end is fixed by a tugboat, and the steel pipe pile is pulled out from this end, and the steel pipe pile at the other end is retained as the axis, and the whole row of horizontal braces, diagonal braces and slewing assembly is dragged by a tugboat to rotate to the designated position;

[0015] If the rotation space is not sufficient for the rotation of the entire row, the connection between the completed side steel pipe pile and the rotary connection assembly will be released, and the connection at the farthest end will be retained. The horizontal connection and diagonal brace will be released, and only the horizontal brace and diagonal brace connection between each row in the longitudinal direction will be retained. The completed side steel pipe pile will be pulled out, and the farthest end steel pipe pile will be retained as the rotation axis. The steel pipe pile will be pulled out to the specified height and the steel pipe pile and the rotary connection assembly will be fixed with bolts again. Through the connection of the horizontal brace and the diagonal brace, it is ensured that there is enough clearance between the pulled out steel pipe pile and the seabed to ensure normal rotation. After all the steel pipe piles are pulled out and fixed, proceed to the next construction area, and the farthest end steel pipe pile will be measured and fixed. After positioning is completed, the entire row of steel pipe piles is rotated and translated with the unpulled steel pipe piles as the axis. After rotating to the specified position, the connection between the farthest steel pipe pile in the next construction area and the rotary connection assembly is released, and the farthest steel pipe in the next construction area is driven. After the driving of this steel pipe pile is completed, the remaining steel pipe piles have been positioned due to the rotary connection assembly and the connection between the transverse brace and the diagonal brace. The connection between each pile and the rotary connection assembly is released in turn, and the steel pipe piles are driven. The connection between the steel pipe piles and the rotary connection assembly and the horizontal connection and the diagonal brace are completed, and the steel pipe pile foundation construction is completed again. This process is repeated until the construction is completed.

[0016] The present invention has at least the following beneficial effects: The present invention has the technical characteristics of high construction efficiency, high operability, high positioning accuracy, etc., specifically:

[0017] High construction efficiency: The horizontal braces and diagonal braces are fixed on the rotary connection assembly and connected by pins. After the angle and length are determined, they can be quickly connected and removed, eliminating welding and cutting operations, greatly improving construction efficiency.

[0018] High operability: The connection and cutting of horizontal and diagonal braces do not require welding machines, gas cylinders and other equipment and can be done manually.

[0019] High positioning accuracy: It reduces the amount of measurement work and the measurement frequency. After the two ends of the pile foundation are positioned, the positions of the remaining pile foundations are determined, which improves the construction efficiency and the positioning accuracy of the steel pipe piles.

[0020] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a structural schematic diagram of the rotary connection assembly of the present invention;

[0022] Figure 2 It is a schematic diagram of the connection between the rotary connection assembly and the horizontal brace / diagonal brace of the present invention;

[0023] Figure 3 It is a front view of the rotary connection assembly of the present invention;

[0024] Figure 4 It is a schematic diagram of the connection engineering of the steel pipe pile and the rotary connection assembly of the present invention;

[0025] Figure 5 It is a schematic diagram of the steel pipe pile, the rotary connection assembly and the horizontal brace / diagonal brace connection of the present invention;

[0026] Figure 6 It is a schematic diagram of the horizontal brace / diagonal brace structure of the present invention;

[0027] Figure 7 is a top view of the horizontal brace / diagonal brace structure of the present invention;

[0028] Figure 8 It is an overall schematic diagram of the assembled quick-plug and pull-out flat-jointed water steel pipe pile construction platform of the present invention;

[0029] Fig. 9 It is a flow chart of steel pipe pile injection of the present invention;

[0030] Fig.10 This is a flow chart of steel pipe pile rotation when the rotation space is sufficient in the present invention;

[0031] Fig.11 This is a flow chart of steel pipe pile rotation when the rotation space is insufficient in the present invention;

[0032] Fig.12 It is a flow chart of the steel pipe pile injection after the present invention is rotated into place.

[0033] Among them, 1-steel pipe pile, 2-swivel connection assembly, 3-cross brace, 4-diagonal brace, 5-pile body, 6-pile cap, 7-fixing hole, 8-positioning block, 9-connecting hinge, 10-rotating connection block, 11-fixing unit, 12-limiting connection port, 13-external square tube, 14-internal square tube, 15-limiting block, 16-limiting groove, 17-bolt, 18-pin shaft. DETAILED DESCRIPTION

[0034] The present invention is described in detail and completely below in conjunction with the accompanying drawings. A person of ordinary skill in the art will be able to implement the present invention based on these descriptions. Before describing the present invention in conjunction with the accompanying drawings, it should be particularly pointed out that the technical solutions and technical features provided in each part of the present invention, including the following description, can be combined with each other without conflict.

[0035] In addition, the embodiments of the present invention involved in the following description are generally only a part of the embodiments of the present invention, rather than all the embodiments. Therefore, based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0036] The present invention is further described in detail below in conjunction with the accompanying drawings and implementations, and its specific implementation process is as follows:

[0037] like Figures 1 to 8 As shown, the present invention provides an assembled quick-plug-in parallel-connected water steel pipe pile construction platform, comprising: a steel pipe pile 1, a rotary connection assembly 2, a horizontal brace 3 and an oblique brace 4; wherein the steel pipe pile 1 is detachably mounted with a rotary connection assembly 2, and a plurality of steel pipe piles 1 are lowered according to the requirements of the construction platform, and the horizontal brace 3 and the oblique brace 4 between the steel pipe piles 1 are detachably connected via the rotary connection assembly 2.

[0038] The present technical solution may also include the following technical details to better achieve the technical effect: the steel pipe pile 1 includes a pile body 5 and a pile cap 6. The presence of the pile cap 6 facilitates the injection of the steel pipe pile 1. At the same time, the pile cap 6 plays a limiting role to prevent the steel pipe pile 1 from slipping off the rotary connection assembly 2 during the installation process.

[0039] The technical solution may also include the following technical details to better achieve the technical effect: the pile body 5 is made of seamless steel pipe, and the pile body 5 is provided with fixing holes 7 for connecting and fixing the rotary connection assembly 2, and the position and spacing of the fixing holes 7 are determined according to the construction accuracy requirements;

[0040] The rotary connection assembly 2 includes a positioning block 8, a connecting hinge 9, a rotating connection block 10 and a fixing unit 11; the upper and lower ends of the positioning block 8 are connected to the fixing unit 11, and the fixing unit 11 is provided with a fixing hole 7. The positioning block 8 and the fixing unit 11 are sleeved on the steel pipe pile 1. The positioning block 8 plays a fixing and positioning role during the transportation of the steel pipe pile 1. The fixing unit 11 is connected to the steel pipe pile 1 through bolts 17 and fixing holes 7. The steel pipe pile 1 is provided with a plurality of fixing holes 7. The rotary connection assembly 2 is fixed to the steel pipe pile 1 through bolts 17. The sheet pile is positioned at a designated position; the connecting hinge 9 connects the positioning block 8 and the rotating connecting block 10, so that the rotating connecting block 10 can rotate freely relative to the positioning block 8, which is convenient for adjusting the direction of the rotating connecting block 10. The rotating connecting block 10 is provided with a horizontal brace 3 and an oblique brace 4 limiting connecting port 12 (the number is determined according to construction requirements). The horizontal brace 3 and the oblique brace 4 are connected to the limiting connecting port 12 of the rotating connecting block 10 through a pin shaft 18. According to construction requirements, a four-way rotating connecting block 10 or an eight-way rotating connecting block 10 can be equipped to meet the convenience of construction and the force requirements of the structure.

[0041] The technical solution may also include the following technical details to better achieve the technical effect: the rotating connection block 10 is provided with four or eight groups of horizontal braces 3, diagonal braces 4, and position limiting connection ports 12 arranged at equal intervals, such as Figure 1 and Figure 2 , which is a schematic diagram of a rotating connection block 10 with four sets of limiting connection ports 12 .

[0042] The technical solution may further include the following technical details to better achieve the technical effect: the transverse brace 3 and the diagonal brace 4 have the same structure and are both retractable structures.

[0043] The technical solution may also include the following technical details to better achieve the technical effect: the horizontal brace 3 and the diagonal brace 4 are both composed of an external square tube 13 and an internal square tube 14, the external square tube 13 is provided with a limiting block 15 around it, and the internal square tube 14 is provided with a limiting groove 16 around it, the limiting block 15 of the external square tube 13 is located in the limiting groove 16 of the internal square tube 14, the internal square tube 14 and the external square tube 13 are provided with a fixing hole 7, and the internal square tube 14 and the external square tube 13 are fixed by bolts 17 and the fixing holes 7. The structure of the horizontal brace 3 and the diagonal brace 4 can ensure the verticality and stability of the horizontal brace 3 and the diagonal brace 4, and the length of the horizontal brace 3 and the diagonal brace 4 can be adjusted according to the construction requirements, and they are fixed with bolts 17 after the length adjustment is completed.

[0044] like Figures 9 to 12As shown, an assembled quick-plug and pull-out parallel-connected water steel pipe pile construction platform and construction method are shown. The area where the platform is to be erected is determined according to the construction plan, and the surveying ship and the pile-driving ship are in place. The positions of the steel pipe piles at both ends of each row are set out at one time, and the steel pipe piles at both ends are driven. After the steel sheet piles at both ends are driven, a rotary connection assembly is assembled. According to the connection requirements, the horizontal braces, diagonal braces and hand winches are installed in the corresponding horizontal brace and diagonal brace limit connection ports of the rotary connection assembly to facilitate the later horizontal brace and diagonal brace connection construction. After the assembly is completed, the upper and lower rotary connection assemblies are installed, and they are fixed to the steel pipe piles by bolts after installation, and then the caps are installed. The upper and lower rotary connection assemblies and the upper rotary connection assembly are connected to the pile cap through a hand winch, which is convenient for adjusting the height of the rotary connection assembly. After the two rotary connection assemblies are adjusted to the designed height by the hand winch, the rotary connection assembly is fixed by bolts and fixing holes on the steel pipe piles. After the positioning and installation of the rotary connection assembly of each pile is completed, the horizontal braces and diagonal braces are installed. The lengths of the horizontal braces and diagonal braces are adjusted according to the connection requirements. Finally, they are hoisted to the corresponding limit connection port of the rotary connection assembly through the hand winch on the corresponding rotary connection assembly and connected through a pin shaft to complete the construction of the steel pipe pile foundation of the water platform. When the construction content of this area is completed and the construction platform needs to be transferred, if there is enough rotation space, the entire platform will be rotated, one end will be fixed by a tugboat, and the steel pipe piles will be pulled out from this end, and the steel pipe piles at the other end will be retained as the axis. The entire row of horizontal braces, diagonal braces and rotary assembly will be dragged by a tugboat to rotate to the specified position; if the rotation space is not sufficient for the entire row to rotate, the connection between the steel pipe piles on the completed side and the rotary connection assembly will be released (the connection at the farthest end will be retained), the horizontal connection and diagonal braces will be released, and only the horizontal brace and diagonal brace connections between each row in the longitudinal direction will be retained, and the steel pipe piles on the completed side will be pulled out (the farthest steel pipe piles will be retained as the rotation axis). The steel pipe piles and the rotary connection assembly will be bolted again at the specified height of the pull-out, and the connection between the horizontal braces and diagonal braces will ensure that the pulled-out steel pipe piles are connected to the sea. There is enough clearance on the bottom surface to ensure normal rotation. After all the steel pipe columns are lifted and fixed, the farthest steel pipe piles in the next construction area are measured and positioned. After positioning is completed, the unlifted steel pipe piles are used as the axis to rotate and translate the entire row of steel pipe piles. After rotating to the specified position, the connection between the farthest steel pipe piles in the next construction area and the rotary connection assembly is released, and the farthest steel pipe in the next construction area is driven. After the pile is driven, due to the connection between the rotary connection assembly and the horizontal and diagonal braces, the remaining steel pipe piles are positioned. The connection between each pile and the rotary connection assembly is released in turn, and steel sheet piles are driven. The connection between the steel pipe piles and the rotary connection assembly and the horizontal connection and diagonal braces is completed, and the steel pipe pile foundation construction is completed again. This process is repeated until the construction is completed.

[0045] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation modes. They can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the embodiments shown and described herein.

Claims

1. An assembled quick-plug and pull-out flat-jointed water-based steel pipe pile construction platform, It is characterized in that include: Steel pipe piles, a rotary connection assembly, a horizontal brace and an oblique brace; wherein the steel pipe piles are detachably mounted with a rotary connection assembly, and the horizontal braces and the oblique braces between the steel pipe piles are detachably connected via the rotary connection assembly.

2. The assembled quick-plug and pull-out flat-jointed water steel pipe pile construction platform as claimed in claim 1, It is characterized in that The steel pipe pile comprises a pile body and a pile cap.

3. The assembled quick-plug and pull-out flat-jointed water steel pipe pile construction platform as claimed in claim 1 or 2, It is characterized in that The pile body is provided with a fixing hole for connecting and fixing the rotary connection assembly; The rotary connection assembly includes a positioning block, a connecting hinge, a rotating connection block and a fixing unit; the upper and lower ends of the positioning block are connected to the fixing unit, and the fixing unit is provided with a fixing hole. The positioning block and the fixing unit are sleeved on the steel pipe pile, and the fixing unit is connected to the steel pipe pile through bolts and fixing holes. The connecting hinge connects the positioning block and the rotating connection block so that the rotating connection block can rotate relative to the positioning block, which is convenient for adjusting the direction of the rotating connection block. A limiting connection port is provided on the rotating connection block, and the horizontal brace and diagonal brace are connected to the limiting connection port of the rotating connection block through a pin shaft.

4. The assembled quick-plug and pull-out flat-jointed water steel pipe pile construction platform as claimed in claim 3, It is characterized in that The rotating connection block is provided with four or eight groups of limit connection ports arranged at equal intervals.

5. The assembled quick-plug and pull-out flat-jointed water steel pipe pile construction platform as claimed in claim 1, It is characterized in that The transverse brace and the diagonal brace have the same structure and are both retractable structures.

6. The assembled quick-plug and pull-out flat-jointed water steel pipe pile construction platform as claimed in claim 1, It is characterized in that The transverse brace and the diagonal brace are both composed of an external square tube and an internal square tube. Limiting blocks are arranged around the external square tube, and limiting grooves are arranged around the internal square tube. The limiting blocks of the external square tube are located in the limiting grooves of the internal square tube. Fixing holes are arranged on the internal square tube and the external square tube, and the internal square tube and the external square tube are fixed by bolts and fixing holes.

7. A construction method using the assembled quick-plug and pull-out flat-jointed water steel pipe pile construction platform as claimed in any one of claims 1 to 6, It is characterized in that include: S1. According to the construction plan, determine the area where the platform is to be erected, put the surveying ship and the pile-driving ship in place, stake out the positions of the steel pipe piles at both ends of each row at one time, and drive the steel pipe piles at both ends. After the steel pipe piles at both ends are driven, assemble the rotary connection assembly. According to the connection requirements, install the horizontal brace, diagonal brace and hand chain hoist in the corresponding horizontal brace and diagonal brace limit connection opening of the rotary connection assembly. After the assembly is completed, install the upper and lower rotary connection assemblies, fix them to the steel pipe piles with bolts, and then install the caps. The upper and lower rotary connection assemblies and the upper rotary The connection assembly is connected to the pile cap by a hand winch. After the two rotary connection assemblies are adjusted to the designed height by the hand winch, the rotary connection assembly is fixed by bolts and fixing holes on the steel pipe piles. After the positioning and installation of the rotary connection assemblies of each pile are completed, the installation of horizontal braces and diagonal braces is started. The lengths of the horizontal braces and diagonal braces are adjusted according to the connection requirements. Finally, they are hoisted into the limiting connection port of the corresponding rotary connection assembly by the hand winch on the corresponding rotary connection assembly and connected by a pin shaft to complete the construction of the steel pipe pile foundation of the water platform.

8. The construction method according to claim 7, It is characterized in that Also includes: Step S2: When the construction content of this area is completed and the construction platform needs to be moved, if there is enough rotation space, the whole platform is rotated, one end is fixed by a tugboat, and the steel pipe pile is pulled out from this end, and the steel pipe pile at the other end is retained as the axis, and the whole row of horizontal braces, diagonal braces and slewing assembly is dragged by a tugboat to rotate to the designated position; If the rotation space is not sufficient for the rotation of the entire row, the connection between the completed side steel pipe pile and the rotary connection assembly will be released, and the connection at the farthest end will be retained. The horizontal connection and diagonal brace will be released, and only the horizontal brace and diagonal brace connection between each row in the longitudinal direction will be retained. The completed side steel pipe pile will be pulled out, and the farthest end steel pipe pile will be retained as the rotation axis. The steel pipe pile will be pulled out to the specified height and the steel pipe pile and the rotary connection assembly will be fixed with bolts again. Through the connection of the horizontal brace and the diagonal brace, it is ensured that there is enough clearance between the pulled out steel pipe pile and the seabed to ensure normal rotation. After all the steel pipe piles are pulled out and fixed, proceed to the next construction area, and the farthest end steel pipe pile will be measured and fixed. After positioning is completed, the entire row of steel pipe piles is rotated and translated with the unpulled steel pipe piles as the axis. After rotating to the specified position, the connection between the farthest steel pipe pile in the next construction area and the rotary connection assembly is released, and the farthest steel pipe in the next construction area is driven. After the driving of this steel pipe pile is completed, the remaining steel pipe piles have been positioned due to the rotary connection assembly and the connection between the transverse brace and the diagonal brace. The connection between each pile and the rotary connection assembly is released in turn, and the steel pipe piles are driven. The connection between the steel pipe piles and the rotary connection assembly and the horizontal connection and the diagonal brace are completed, and the steel pipe pile foundation construction is completed again. This process is repeated until the construction is completed.