Double-layer jet grouting stiffening core composite pile of bag extrusion expansion body and construction method and device of double-layer jet grouting stiffening core composite pile
By using the bag extrusion expansion technology and the double-layer rotary spout core composite pile device in the construction of composite piles, the problem of waste of materials and insufficient bearing capacity in the construction of cement soil composite piles is solved, and efficient pile foundation reinforcement and Environmental protection.
Patent Information
- Application Number
- CN202411257770.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-09
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-09-09
AI Technical Summary
The existing Jinxin cement-soil composite pile construction technology has problems of cement-soil material waste and environmental pollution, and the pile foundation bearing capacity is not significantly improved.
The construction device and method of double-layer rotary jet core composite piles using the capsule extrusion expansion body. By injecting gelled materials with different condensation speeds into the inside and outside of the pile pipe, and using the air bag to control the air pressure, the expansion body is extruded to improve the piles. Body diameter and interface friction resistance are combined with concrete hardening to form a strong core to improve pile body strength and bearing capacity.
It significantly improves the bearing capacity and construction efficiency of composite piles, reduces material waste and environmental pollution, enhances the compressive strength and stiffness of the pile body, and reduces pile foundation settlement.
Smart Images

Figure CN118997165A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of composite pile foundations used in projects such as building construction, bridges, roads, and the like, and in particular to a double-layer rotary jet reinforced core composite pile with a bag extrusion expansion body and a construction method and device thereof. Background Art
[0002] my country has a vast area of soft soil, which covers many provinces. The treatment of soft soil foundation is crucial to engineering construction. At present, flexible piles represented by cement soil mixing piles and rigid piles represented by concrete pipe piles and concrete cast-in-place piles are the main means of treating soft soil foundations in my country. Although cement soil mixing piles are low in cost and convenient in construction, they have disadvantages such as low pile strength and rigidity, low bearing capacity, and large pile foundation settlement. They can no longer meet the needs of strengthening complex soft soil foundations in major projects such as high-rise buildings, high-grade highways and railways. Although concrete piles have overcome the shortcomings of cement soil mixing piles, their cost is relatively high.
[0003] In recent years, my country has inserted concrete pile cores into cement-soil mixing piles, thus forming a strong-core cement-soil composite pile. This pile foundation is composed of two materials with different hardnesses, cement soil and strong core, and it has the advantages of both cement-soil piles and concrete piles. Moreover, compared with the use of simple cement-soil mixing piles, the use of strong-core cement-soil composite piles to reinforce soft soil foundations can also significantly reduce the cost of the project. Therefore, strong-core cement-soil composite piles have been gradually promoted and applied in engineering.
[0004] However, in the existing construction technology, after cement is injected into the soil and stirred into cement soil, the concrete core is quickly inserted into the cement soil when it is in liquid or semi-liquid state. At this time, the cement soil will inevitably be squeezed out from the top of the pile to the surface, which not only causes the waste of cement soil materials, but also causes environmental pollution at the construction site. In addition, under this construction method, the cement soil cannot be further squeezed and diffused into the soil around the pile through the insertion of the core. Therefore, after the cement hardens and forms the composite pile, although the pile body strength and stiffness are greatly improved, and the pile foundation settlement is significantly reduced, the interface friction resistance between the cement soil and the soil around the pile is slightly increased, resulting in an insignificant increase in the pile foundation bearing capacity. Summary of the invention
[0005] The purpose of the present invention is to overcome the shortcomings of the above-mentioned strong core cement soil composite pile construction technology and provide a composite pile foundation reinforcement technology with strong bearing capacity, convenient construction and good economy.
[0006] In order to solve the above technical problems, the technical solution adopted by the present invention is:
[0007] A double-layer rotary jet reinforced core composite pile construction device with bag extrusion and expansion comprises a pile pipe, a plurality of grouting ports and lateral stirring blades are arranged at the lower part of the pile pipe, a plurality of flap pile tips are hinged at the bottom of the pile pipe, and the flap pile tips are arranged along the circumference of the pile pipe; a plurality of bottom stirring blades are arranged at the outer periphery of the flap pile tip; a sleeve is arranged at the inner side of the pile pipe, a first grouting piece and a second grouting piece are installed between the pile pipe and the sleeve, and the first grouting piece and the second grouting piece are connected with the grouting port; the first grouting piece and the second grouting piece are fixedly connected to the pile pipe and rotatably connected to the sleeve; a drainage board is installed circumferentially inside the sleeve, an air bag is installed at the inner side of the drainage board, and a pore water pressure sensor is arranged at the bottom of the air bag.
[0008] As a further improvement, a number of first grouting bins are connected in series from top to bottom to form a first grouting piece, and a number of second grouting bins are connected in series from top to bottom to form a second grouting piece; the first grouting piece and the second grouting piece are arranged at intervals from each other along the circumference of the pile pipe; wherein, the first grouting bins on the same layer are connected to each other through the first connecting pipe, and the second grouting bins on the same layer are connected to each other through the second connecting pipe.
[0009] A further improvement is that the first grouting part includes a first grouting bin in the middle, a first grouting channel is formed at the bottom of the first grouting bin, and a first interface matching the first grouting channel is formed at the top; the first grouting bin is opened on the side opposite to the spraying port, and a first sealing gasket is fixed on the outer periphery of the opening, and a first steel ball is installed on the side opposite to the casing of the first grouting bin; the second grouting part has the same structure as the first grouting part.
[0010] A further improvement is that the sleeve includes an end sleeve, the top of the end sleeve is threadedly connected to the top sleeve, a pressure plate is arranged at the bottom of the end sleeve, a first supporting plate is formed at the bottom of the pile pipe, the first supporting plate is located below the pressure plate, and several groups of steel balls are installed between the pressure plate and the first supporting plate; a guide plate is arranged on the side wall of the end sleeve to separate the first grouting part and the second grouting part, a guide groove is formed between adjacent guide plates, and the first grouting part and the second grouting part are located in the guide groove; a second supporting plate is arranged on the upper part of the top sleeve, a limiting plate is fixed to the second supporting plate, a limiting groove is formed between adjacent limiting plates, a centering device located in the limiting groove is arranged on the top surface of the second supporting plate, and a third steel ball is installed at the outer end of the centering device.
[0011] A method for constructing a double-layer rotary grouting reinforced core composite pile with a bag extrusion expansion body, using the above-mentioned double-layer rotary grouting reinforced core composite pile construction device with a bag extrusion expansion body for construction, specifically comprising the following steps:
[0012] Step 1: Construction preparation: Survey the physical and mechanical parameters of each soil layer and the groundwater level at the construction site, level the site, measure and lay out, and mark the positions of the foundation piles; the physical and mechanical parameters include gravity γ, water content w, cohesion c, internal friction angle Elastic modulus E and Poisson's ratio μ;
[0013] Step 2, stirring grouting: the pile pipe is aligned with the foundation pile point and vertically sunk and the soil is stirred. After reaching the preset depth, the first cementitious material is injected and the first cementitious material and the soil are evenly mixed; after the pile pipe continues to sink to the preset depth, the second cementitious material is injected and the soil is evenly mixed; wherein the setting speed of the first cementitious material is faster than that of the second cementitious material and the first cementitious material is above the second cementitious material;
[0014] Step 3: Bag extrusion and expansion: before the first cementitious material is initially set, the pile pipe, the first grouting piece, the second grouting piece and the casing are taken out; after the first cementitious material is initially set, a first stirring body is formed, and the thickness h1 of the first stirring body is sufficient to ensure that the second cementitious material will not leak to the surface when the air bag applies the designed air pressure p0 to the second cementitious material; when the first stirring body hardens, the compressive strength f cu,1 When the second gelling material is not fractured and the second gelling material is not solidified, a designed air pressure p0 is applied in the air bag to squeeze and expand the second gelling material outward;
[0015] Step 4: Drainage and pore water pressure monitoring: Use drainage boards and water pumps to pump water, and monitor the pore water pressure of the second cementitious material and the surrounding soil at the same time;
[0016] Step 5: Bag pressure relief, recovery and pouring of concrete: After the second cementitious material reaches the initial setting state to form a second mixing body and the pore water pressure is released to meet the requirements, the air pressure in the air bag is released, the air bag and the pore water pressure sensor are recovered, holes are left in the second mixing body, and the mixed concrete is poured in the holes to form a strong core after hardening.
[0017] Further improvement, in step three,
[0018] The thickness h1 of the first stirring body satisfies the following conditions:
[0019]
[0020] The first mixing body needs to be hardened to a compressive strength f cu,1 The following conditions must be met:
[0021]
[0022] Where D1 is the diameter of the airbag before expansion; D2 is the diameter of the second stirring body before expansion; f1 is the interface friction between the first stirring body and the surrounding soil; p0 is the air pressure applied to the airbag.
[0023] Further improvement, the ultimate bearing capacity of the double-layer jet-jet reinforced core composite pile is P f for:
[0024]
[0025] In the formula, h 2-i is the thickness of the i-th soil layer in the layered foundation; f 2-i is the interfacial friction between the second stirring body and the i-th soil layer, c i and are the interfacial bonding force and interfacial friction angle between the second stirring body and the i-th soil layer, respectively; α i is the interface normal stress loss coefficient; D ′ 2-i is the diameter of the second mixing body in the i-th layer of soil after the airbag is pressurized and expanded, and D2 is the diameter of the second mixing body before expansion; the ultimate bearing capacity of the double-layer jet-jet reinforced core composite pile is P f Not less than the required ultimate bearing capacity.
[0026] Further improvements, D ′ 2-i The method of determining is as follows:
[0027]
[0028] In the formula, μ i is the Poisson's ratio of the i-th layer of soil in the layered foundation; E i is the elastic modulus of the i-th soil layer.
[0029] As a further improvement, in step 5, before releasing the air pressure to recover the airbag, the pore water pressure monitored by the pore water pressure sensor must meet the following conditions:
[0030]
[0031] Where: u w The pore water pressure obtained by the pore water pressure sensor; h w is the water head height between the pore water pressure sensor and the groundwater level; γ w is the weight of water;
[0032] The concrete volume Q required for core pouring construction is estimated by the following formula:
[0033]
[0034] Where n is the number of soil layers that the second mixing body passes through; h 1-i is the thickness of the i-th soil layer; D ′ 1-i is the diameter of the stiffener in the i-th layer of soil after expansion,
[0035]
[0036] A double-layer rotary jet reinforced core composite pile with a bag extrusion expansion body comprises a first stirring body, and a second stirring body is connected to the bottom of the first stirring body; the first stirring body is formed by condensing a cementitious material with a fast coagulation and hardening speed, and the second stirring body is formed by condensing a cementitious material with a slow hardening speed; a stiff core is formed in the middle of the second stirring body and the first stirring body, wherein the diameter of the stiff core inside the second stirring body is greater than the diameter of the stiff core inside the first stirring body; the cementitious material with a fast coagulation and hardening speed is fast-hardening cement or polymer cement; the cementitious material with a slow hardening speed is slow-setting cement.
[0037] The beneficial effects of the present invention are:
[0038] 1. The present invention arranges airbags along the entire length of the pile body. In this way, according to the design requirements of the pile foundation bearing capacity, combined with the construction method of the present invention, the entire length of the second stirring body can be extruded and expanded, thereby increasing the diameter of the pile body and greatly improving the normal stress and interface friction resistance of the pile-soil interface, thereby greatly improving the bearing capacity of the composite pile.
[0039] 2. The present invention pours concrete or other materials in the center of the first stirring body and the second stirring body, hardens them to form a strong core, thereby improving the strength and rigidity of the pile body, thereby greatly reducing the settlement of the pile foundation.
[0040] 3. The first stirring body of the present invention is located at the top of the pile and solidifies and hardens quickly, so that the first stirring body can not only play a role of rapid load-bearing, but also when the air bag is used to extrude and expand the second stirring body that has not yet initially solidified, the solidified and hardened first stirring body can also play a role of sealing, thereby preventing the slurry of the second stirring body from being squeezed out of the ground, thereby avoiding waste of construction materials and pollution of the construction surface environment.
[0041] 4. The present invention arranges a plurality of grouting parts along the bottom of the pile pipe. The grouting parts are composed of a plurality of grouting bins. The grouting parts at different positions are connected in series to form a whole, thereby ensuring that the cementitious material can be uniformly injected into the soil. Combined with the stirring blades on the side of the pile pipe and the tip of the flap pile, the cementitious material and the soil can be uniformly mixed. In addition, the grouting bins can be connected in series in various forms, thereby achieving the effects of simultaneous grouting of various cementitious materials, grouting of different soil layers with different cementitious materials, etc., which can not only greatly improve the bearing capacity of the pile body, but also carry out customized construction according to design requirements or site conditions to improve construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] Figure 1 This is a structural principle diagram of the composite pile construction device of the present invention.
[0043] Figure 2 It is a schematic diagram of the connection of the components at the bottom of the composite pile construction device of the present invention.
[0044] Figure 3 It is a schematic structural diagram of the first grouting member 6 of the present invention.
[0045] Figure 4 It is a cross-sectional view of the bottom position of the composite pile construction device of the present invention.
[0046] Figure 5 This is a schematic diagram of the connection between the first grouting piece 6 and the second grouting piece 7 of the present invention.
[0047] Figure 6 It is a schematic diagram of the arrangement of the centering device 10 of the present invention.
[0048] Figure 7 This is the state of the second stirring body 15 after the rotary spray stirring is completed.
[0049] Figure 8 It is a schematic diagram of the force applied to the second stirring body 15 of the present invention and its deformation before and after expansion.
[0050] Fig. 9 This is the pile body shape used for homogeneous foundation of the present invention.
[0051] Fig.10 This is the pile body shape used for layered foundation of the present invention.
[0052] Fig.11 It is a construction flow chart of the present invention.
[0053] The labels in the figure are:
[0054] 1-pile pipe, 1a-spraying port, 1b-first support plate, 2-lateral stirring blade, 3-bottom stirring blade, 4-valve pile tip, 5-steel ball, 6-first grouting piece, 6a-first sealing pad, 6b-first steel ball, 6c-first grouting channel, 6d-first interface, 6e-first connecting pipe, 6f-first grouting pipe, 6g-first grouting chamber, 7-second grouting piece, 7a-second sealing pad, 7b-second steel ball, 7c-second grouting channel, 7d-second interface, 7e-first Second connecting pipe, 7f-second grouting pipe, 7g-second grouting chamber, 8-end sleeve, 8a-pressure plate, 8b-guide groove, 9-top sleeve, 9a-second supporting plate, 9b-limiting groove, 10-centering device, 10a-third steel ball, 10b-connecting rod, 11-drainage board, 12-air bag, 13-air pipe, 14-first stirring body, 15-second stirring body, 16-strength core, 17-pore water pressure sensor, 18-stirring body before expansion, 19-air bag before expansion. DETAILED DESCRIPTION
[0055] The following further describes the implementation of the present invention in conjunction with the accompanying drawings and examples. It should be noted that the examples do not limit the scope of protection claimed by the present invention.
[0056] Example 1
[0057] A double-layer rotary jet reinforced core composite pile construction device with bag extrusion and expansion, such as Figure 1 and Figure 2 As shown, it mainly includes a pile pipe 1 and an end sleeve 8. Three rows of spraying ports 1a and three rows of lateral stirring blades 2 are arranged at the bottom of the pile pipe 1. Eight spraying ports 1a are evenly arranged in each row. A valve pile tip 4 is hinged below the pile pipe 1. Three rows of bottom stirring blades 3 are arranged on the periphery of the valve pile tip 4. In this embodiment, the total outer diameter of the pile pipe 1 and the lateral stirring blades 2 is 800mm, and the inner diameter of the end sleeve 8 is 320mm. A first grouting piece 6 and a second grouting piece 7 are installed between the pile pipe 1 and the end sleeve 8. The first grouting piece 6 and the second grouting piece 7 have the same structure.
[0058] like Figure 3 As shown, the first grouting member 6 is composed of a plurality of first grouting bins 6g, the first grouting bins 6g are connected through a first grouting channel 6c with a diameter of not less than 5 cm, a first sealing pad 6a is installed at the contact between the first grouting bin 6g and the inner wall of the pile pipe 1, and a plurality of groups of second first steel balls 6b are evenly inlaid at the contact between the first grouting bin 6g and the end sleeve 8, and all the first grouting bins 6g are connected to the grouting port 1a. In this embodiment, the first grouting member 6 is composed of three first grouting bins 6g, and the diameter of the first grouting channel 6c is 6 cm.
[0059] like Figure 4 and Figure 5 As shown, in this embodiment, the four first grouting parts 6 are connected to the first connecting pipe 6e through the second interface 6d at the top, and the center of the first grouting chamber 6g is in the same plane as the grouting port 1a. The end sleeve 8 is threadedly connected to the top sleeve 9, and a pressure plate 8a is arranged at the bottom of the end sleeve 8. Several groups of steel balls 5 are fixed between the pressure plate 8a and the first support plate 1b. The side wall of the end sleeve 8 is provided with a guide groove 8b for separating the first grouting part 6 and the second grouting part 7. An air bag 12 and a drainage plate 11 are arranged in the center of the end sleeve 8 and the top sleeve 9, and a pore water pressure sensor 17 is arranged at the bottom of the air bag 12. A second support plate 9a and a limit groove 9b are arranged on the upper part of the top sleeve 9, and a centering device 10 is arranged on the top surface of the second support plate 9a.
[0060] like Figure 6 As shown, third steel balls 10a are installed at both ends of the centering device 10, and are fixed as a whole by connecting rods 10b, and there is no gap between the centering device 10 and the top sleeve 9 and the pile pipe 1. The end sleeve 8 and the top sleeve 9 are restricted to the center of the pile pipe 1 by the centering device 10 and the first grouting parts 6 and 7, thereby ensuring that the airbag 12 is centered.
[0061] Example 2
[0062] A double-layer rotary jet reinforced core composite pile with bag extrusion expansion, comprising a first stirring body 14 and a second stirring body 15. In this embodiment, the diameters D2 of the first stirring body 14 and the second stirring body 15 before extrusion expansion are both 800 mm, and the total length h2 of the second stirring body 15 is 10 m. The cementitious material of the first stirring body 14 is a mineral powder-based polymer with an initial setting time of 30 min, and the cementitious material of the second stirring body 15 is a slow-setting cement with an initial setting time of 240 min. The second stirring body 15 passes through three layers of soil, which are, from top to bottom: ① plain fill, thickness 3 m, elastic modulus E1 = 50 MPa, Poisson's ratio μ1 = 0.30, pile-soil interface bonding force c1 = 100 kPa, interface friction angle ② Muddy clay, thickness 5m, elastic modulus E2 = 30MPa, Poisson's ratio μ2 = 0.33, pile-soil interface bonding force c1 = 50kPa, interface friction angle ③ Fine sand, thickness 2m, elastic modulus E3 = 100MPa, Poisson's ratio μ3 = 0.30, pile-soil interface bonding force c1 = 120kPa, interface friction angle like Figure 7 As shown, the airbag 12 for extrusion and expansion is arranged in the center of the first stirring body 14 and the second stirring body 15 along the entire length, and the drain board 11 is arranged on the periphery of the airbag 12. The drain board 11 is a plurality of flexible drain boards arranged along the circumference of the airbag or set as a whole, and a pore water pressure sensor 17 is arranged at the bottom of the airbag 12. In this embodiment, the diameter D1 of the airbag 12 before extrusion and expansion is 300 mm, and the drain board 11 uses a plastic drain board. After the compressive strength of the first stirring body 14 meets the requirements, the airbag 12 is used for extrusion and expansion, and the second stirring body 15 is expanded in the soil into a cylindrical hardened body with a vertical diameter change. After the airbag 12 is recovered, the center of the second stirring body 15 is formed into a hole with a vertical diameter change, and concrete, cement mortar and other materials are poured in the hole, and a strong core 16 is formed after hardening.
[0063] The hardened first stirring body 14 plays a plugging role to ensure that the slurry of the second stirring body 15 does not leak to the surface when the second stirring body 15 is squeezed and expanded. To this end, the thickness of the first stirring body 14 should meet the following conditions:
[0064]
[0065] In the formula, D1 is the diameter of the airbag 12 before expansion; D2 is the diameter of the second stirring body 15 before expansion; f1 is the interface friction resistance between the first stirring body 14 and the surrounding soil; p0 is the air pressure applied to the airbag 12.
[0066] In this embodiment, the air pressure p0=0.8MPa, the interface friction resistance between the first stirring body 14 and the surrounding soil f1=100kPa, and it is calculated that h1 needs to be greater than 0.75m. In this embodiment, h1=1.0m.
[0067] The compressive strength f of the first stirring body 14 cu,1 The following conditions must be met:
[0068]
[0069] In the formula, D1 is the diameter of the airbag 12 before expansion; D2 is the diameter of the second stirring body 15 before expansion; and p0 is the air pressure applied to the airbag 12.
[0070] In this embodiment, after calculation, the first stirring body 14 needs to be hardened to a compressive strength f cu,1 The initial setting time of the slow-setting cement used in the second stirring body 15 is 240 minutes. When the first stirring body is stirred for 180 minutes, the second stirring body 15 has not yet reached the initial setting state. At this time, the designed air pressure p0 = 0.8MPa is applied to the airbag 12 to squeeze and expand the second stirring body 15 outward. The compressive strength of the first stirring body 14 is 450kPa, which meets the requirements.
[0071] like Figure 8 to Figure 10 As shown, in the i-th layer of soil in the layered foundation, the diameter D of the second stirring body 15 after being pressurized and expanded by the airbag 12 is ′ 2-i The diameter D of the core 16 ′ 1-i It can be estimated by the following formula:
[0072]
[0073] In the formula, μ i is the Poisson's ratio of the i-th soil layer; E i is the elastic modulus of the i-th soil layer.
[0074] In this embodiment, after calculation, the diameters of the second stirring body 15 and the stiffening core 16 in each soil layer are: ① plain fill, D ′ 2-1 =806.2mm, D ′ 1-1 =316.3mm; ② silty clay, D ′ 2-1 =810.6mm, D ′ 1-1 =327.3mm; ③ Fine sand, D ′ 2-1 =803.1mm, D ′ 1-1 =308.2mm.
[0075] The ultimate bearing capacity of the double-layer jet-jet reinforced core composite pile with bag extrusion and expansion fIt can be estimated by the following formula:
[0076]
[0077] In the formula, h 2-i is the thickness of the i-th soil layer; f 2-i is the interfacial friction between the second stirring body 15 and the i-th soil layer, c i and are the interfacial bonding force and interfacial friction angle between the second stirring body 15 and the i-th layer of soil respectively; α i is the interface normal stress loss coefficient.
[0078] In this embodiment, the interface normal stress loss coefficient α i Both are taken as 0.50. After calculation, the ultimate bearing capacity P f =3422.3kN, while the ultimate bearing capacity of the conventional composite pile without expansion under the same conditions is about 2236.8kN. Therefore, compared with the conventional composite pile, the bearing capacity of the double-layer jet-jet composite pile with expanded body by bag extrusion of the present invention can be increased by 53.0%.
[0079] Example 3
[0080] A construction method for a double-layer rotary jet reinforced core composite pile with bag extrusion and expansion, such as Fig.11 , the steps are as follows:
[0081] S1. Construction preparation: Survey the soil density γ, moisture content w, cohesion c, and internal friction angle of each soil layer at the construction site Physical and mechanical parameters such as elastic modulus E and Poisson's ratio μ, as well as groundwater level, site leveling, measurement and layout, and marking of foundation pile locations.
[0082] In this embodiment, ① plain fill, γ1 = 17.5 kN / m 3 , moisture content w1 = 30.2%, cohesion c1 = 30 kPa, internal friction angle E1=50MPa, Poisson's ratio μ1=0.30; ② Muddy clay, γ2=17.8kN / m 3 , moisture content w2 = 50.8%, cohesion c2 = 20kPa, internal friction angle E2=30MPa, Poisson's ratio μ2=0.30; ③ Fine sand, γ3=18.2kN / m 3 , moisture content w3 = 50.8%, cohesion c3 = 20 kPa, internal friction angle E3 = 100 MPa, Poisson's ratio μ3 = 0.30. The groundwater level is 5.0 m below the surface.
[0083] S2. Positioning of construction machinery and tools and pre-mixing and sinking: Use a tower crane or a hoist to align the construction machinery and tools with the foundation pile point, and let the pile pipe 1 sink vertically by static pressure or free fall. At the same time, use a motor to drive the pile pipe 1 to rotate, so that the lateral mixing blades 2 and the bottom mixing blades 3 mix the soil.
[0084] S3, construction of the first mixing body: calculate the required thickness h1 of the first mixing body 14, and after calculation, h1=1.0m in this embodiment. When the pile pipe 1 sinks to the specified depth of 0.5m, the first grouting member 6 is used to inject the prepared first cementitious material into the stratum through the first grouting pipe 6f and the spraying port 1a at the grouting pressure p1. In this embodiment, the first cementitious material is selected as a mineral powder-based polymer. Repeat the sinking and rising of the pile pipe 1, and then use the lateral stirring blade 2 and the bottom stirring blade 3 to mix the first cementitious material and the soil evenly.
[0085] S4, construction of the second mixing body: after the first mixing body 14 is constructed to the designed thickness h1, the second grouting member 7 is used to inject the prepared second cementitious material into the stratum through the second grouting pipe 7f and the grouting port 1a at the grouting pressure p2. In this embodiment, the second cementitious material is slow-setting cement. The pile pipe 1 is repeatedly sunk and raised, and then the second cementitious material is uniformly mixed with the soil using the lateral mixing blades 2 and the bottom mixing blades 3;
[0086] S5, bag squeezing and expanding: After the construction of the second mixing body 15 is completed, the pile pipe 1, the first grouting piece 6, the second grouting piece 7, the end sleeve 8 and the top sleeve 9 are taken out by a crane or a tower crane, and the drainage board 11, the pore water pressure sensor 17 and the air bag 12 are left in the first mixing body 14 and the second mixing body 15 to discharge the water in the soil and eliminate the excess pore water pressure. Figure 7 The hardened first stirring body 14 plays a plugging role to ensure that the slurry of the second stirring body 15 does not leak to the surface when the second stirring body 15 is squeezed and expanded. Before the air bag 12 is pressurized, the second stirring body 15 has not yet reached the initial setting state, while the first stirring body 14 hardens to the compressive strength f cu,1 Reach 450kPa, meeting the requirements.
[0087] S6. Drainage and pore water pressure monitoring: Use the drainage board 11 and the water pump to pump water, and monitor the pore water pressure of the second stirring body 15 and the surrounding soil through the pore water pressure sensor 17. To ensure that the excess pore water pressure is fully dissipated, before releasing the air pressure recovery airbag 12, the pore water pressure monitored by the pore water pressure sensor 17 must meet the following conditions:
[0088]
[0089] Where: u w The pore water pressure sensor 17 monitors the pore water pressure;w is the water head height between the pore water pressure sensor 17 and the groundwater level; γ w The weight of water.
[0090] In this embodiment, the water head height between the pore water pressure sensor 17 and the groundwater level is 5.0 m. After 24 hours of drainage, the pore water pressure u monitored by the pore water pressure sensor 17 is w =80kPa, Meet the requirements.
[0091] S7, bag pressure relief recovery and pouring concrete: After the second mixing body 15 reaches the initial setting state and the pore water pressure is released to meet the requirements, the air pressure in the air bag 12 is released so that the second mixing body 15 can maintain its shape. The air bag 12 and the pore water pressure sensor 17 are recovered, and a hole is left in the second mixing body 15. The mixed concrete is poured in the hole to form a strong core 16 after hardening. The concrete volume Q required for the pouring construction of the strong core (16) can be estimated by the following formula:
[0092]
[0093] Where n is the number of soil layers that the second stirring body (15) passes through; h 1-i is the thickness of the i-th soil layer.
[0094] In this embodiment, the concrete pouring volume Q = 0.875m 3 .
Claims
1. A double-layer rotary jet reinforced core composite pile construction device with bag extrusion and expansion, characterized in that: The invention comprises a pile pipe (1), wherein a plurality of grouting ports (1a) and lateral stirring blades (2) are arranged at the lower part of the pile pipe (1), a plurality of flap pile tips (4) are hingedly connected at the bottom of the pile pipe (1), and the flap pile tips (4) are arranged along the circumference of the pile pipe (1); a plurality of bottom stirring blades (3) are arranged at the outer periphery of the flap pile tips (4); a sleeve is arranged at the inner side of the pile pipe (1), and a first grouting member (6) and a second grouting member (7) are installed between the pile pipe (1) and the sleeve, and the first grouting member (6) and the second grouting member (7) are connected to the grouting port (1a); the first grouting member (6) and the second grouting member (7) are fixedly connected to the pile pipe (1) and rotatably connected to the sleeve; a drainage board (11) is installed at the inner side of the sleeve along the circumference, an air bag (12) is installed at the inner side of the drainage board (11), and a pore water pressure sensor (17) is arranged at the bottom of the air bag (12).
2. The double-layer rotary jet reinforced core composite pile construction device with bag extrusion and expansion as claimed in claim 1 is characterized in that: A plurality of first grouting bins (6g) are connected in series from top to bottom to form a first grouting member (6), and a plurality of second grouting bins (7g) are connected in series from top to bottom to form a second grouting member (7); the first grouting member (6) and the second grouting member (7) are arranged at intervals along the circumference of the pile pipe (1); wherein the first grouting bins (6g) at the same layer are connected to each other via a first connecting pipe (6e), and the second grouting bins (7g) at the same layer are connected to each other via a second connecting pipe (7e).
3. The double-layer rotary jet reinforced core composite pile construction device with bag extrusion and expansion as claimed in claim 1 is characterized in that: The first grouting component (6) comprises a first grouting chamber (6g) in the middle, a first grouting channel (6c) being formed at the bottom of the first grouting chamber (6g), and a first interface (6d) being matched with the first grouting channel (6c) being formed at the top; the first grouting chamber (6g) is opened on the side opposite to the grouting port (1a), and a first sealing gasket (6a) is fixed on the outer periphery of the opening; a first steel ball (6b) is installed on the side opposite to the casing of the first grouting chamber (6g); and the second grouting component (7) has the same structure as the first grouting component (6).
4. The double-layer rotary jet reinforced core composite pile construction device with bag extrusion and expansion as claimed in claim 1 is characterized in that: The sleeve comprises an end sleeve (8), the top of the end sleeve (8) is threadedly connected to a top sleeve (9), a cushion plate (8a) is arranged at the bottom of the end sleeve (8), a first supporting plate (1b) is formed at the bottom of the pile pipe (1), the first supporting plate (1b) is located below the cushion plate (8a), and a plurality of groups of steel balls (5) are installed between the cushion plate (8a) and the first supporting plate (1b); the side wall of the end sleeve (8) is arranged to separate the first grouting piece (6) and the second grouting piece (7) A guide plate, a guide groove (8b) is formed between adjacent guide plates, and the first grouting piece (6) and the second grouting piece (7) are located in the guide groove (8b); a second supporting plate (9a) is arranged on the upper part of the top sleeve (9), a limiting plate is fixed to the second supporting plate (9a), a limiting groove (9b) is formed between adjacent limiting plates, a centering device (10) located in the limiting groove (9b) is arranged on the top surface of the second supporting plate (9a), and a third steel ball (10a) is installed at the outer end of the centering device (10).
5. A construction method for double-layer rotary jet reinforced core composite piles with bag extrusion and expansion, characterized in that: The construction is carried out using the double-layer rotary jet reinforced core composite pile construction device with bag extrusion and expansion as described in any of claims 1 to 4, which specifically includes the following steps: Step 1: Construction preparation: Survey the physical and mechanical parameters of each soil layer and the groundwater level at the construction site, level the site, measure and lay out, and mark the positions of the foundation piles; the physical and mechanical parameters include gravity γ, water content w, cohesion c, internal friction angle Elastic modulus E and Poisson's ratio μ; Step 2, stirring grouting: the pile pipe (1) is aligned with the foundation pile point and vertically sunk downward and the soil is stirred. After reaching a preset depth, the first cementitious material is injected and the first cementitious material and the soil are evenly mixed. After the pile pipe (1) continues to sink and reaches a preset depth, the second cementitious material is injected and the soil is evenly mixed. The first cementitious material has a faster setting speed than the second cementitious material and the first cementitious material is located above the second cementitious material. Step 3: Bag extrusion and expansion: before the first cementitious material is initially set, the pile pipe (1), the first grouting piece (6), the second grouting piece (7) and the casing are taken out; after the first cementitious material is initially set, a first stirring body (14) is formed, and the thickness h1 of the first stirring body (14) is such that when the air bag (12) applies a designed air pressure p0 to the second cementitious material, the second cementitious material will not leak to the surface; when the first stirring body (14) hardens to a compressive strength f cu,1 When the second gelling material is not fractured by the second gelling material and the second gelling material is not solidified, a designed air pressure p0 is applied in the air bag (12) to squeeze and expand the second gelling material outward; Step 4: Drainage and pore water pressure monitoring: using the drainage board (11) in conjunction with a water pump to pump water, while monitoring the pore water pressure of the second cementitious material and the surrounding soil; Step 5, bag pressure relief, recovery and pouring of concrete: After the second cementitious material reaches an initial setting state to form a second mixing body (15), and the pore water pressure is released to meet the requirements, the air pressure in the air bag (12) is released, the air bag (12) and the pore water pressure sensor (17) are recovered, and a hole is left in the second mixing body (15), and the mixed concrete is poured in the hole, which forms a stiff core (16) after hardening.
6. The method for constructing double-layer jet-jet reinforced core composite piles with bag extrusion and expansion as claimed in claim 5, characterized in that: In the step 3, the thickness h1 of the first stirring body (14) satisfies the following conditions: The first stirring body (14) needs to be hardened to a compressive strength f cu,1 The following conditions must be met: In the formula, D1 is the diameter of the airbag (12) before expansion; D2 is the diameter of the second stirring body (15) before expansion; f1 is the interface friction resistance between the first stirring body (14) and the surrounding soil; and p0 is the air pressure applied to the airbag (12).
7. The method for constructing double-layer jet-jet reinforced core composite piles with bag extrusion and expansion as claimed in claim 6, characterized in that: The ultimate bearing capacity of the double-layer jet-jet reinforced core composite pile is P f for: In the formula, h 2-i is the thickness of the i-th soil layer in the layered foundation; f 2-i is the interfacial friction between the second stirring body (15) and the i-th soil layer, c i and are the interfacial bonding force and interfacial friction angle between the second stirring body (15) and the i-th layer of soil respectively; α i is the interface normal stress loss coefficient; D ′ 2-i is the diameter of the second stirring body (15) in the i-th layer of soil after the airbag (12) is pressurized and expanded, and D2 is the diameter of the second stirring body (15) before expansion; so that the ultimate bearing capacity of the double-layer jet-jet reinforced core composite pile is P f Not less than the required ultimate bearing capacity.
8. The method for constructing double-layer jet-jet reinforced core composite piles with bag extrusion and expansion as claimed in claim 7, characterized in that: D ′ 2-i The method of determining is as follows: In the formula, μ i is the Poisson's ratio of the i-th layer of soil in the layered foundation; E i is the elastic modulus of the i-th soil layer.
9. The method for constructing double-layer rotary jet reinforced core composite piles with bag extrusion and expansion as described in any one of claims 5 to 8, characterized in that: In step 5, before releasing the air pressure recovery airbag (12), the pore water pressure monitored by the pore water pressure sensor (17) must meet the following conditions: Where: u w The pore water pressure is monitored by the pore water pressure sensor (17); w is the water head height between the pore water pressure sensor (17) and the groundwater level; γ w is the density of water; p0 is the air pressure applied to the airbag (12). The concrete volume Q required for pouring the core (16) is estimated by the following formula: Where n is the number of soil layers that the second stirring body (15) passes through; h 1-i is the thickness of the i-th soil layer; D ′ 1-i is the diameter of the stiffener (16) in the i-th layer of soil after expansion, 10. A double-layer jet-jet reinforced core composite pile with bag extrusion and expansion, characterized in that: The invention comprises a first stirring body (14), wherein the bottom of the first stirring body (14) is connected to a second stirring body (15); the first stirring body (14) is formed by condensing a cementitious material with a fast coagulation and hardening speed, and the second stirring body (15) is formed by condensing a cementitious material with a slow hardening speed; a stiff core (16) is formed in the middle of the second stirring body (15) and the first stirring body (14), wherein the diameter of the stiff core (16) inside the second stirring body (15) is greater than the diameter of the stiff core (16) inside the first stirring body (14); the cementitious material with a fast coagulation and hardening speed is fast-hardening cement or polymer cement; and the cementitious material with a slow hardening speed is slow-setting cement.
Citation Information
Patent Citations
Construction method for variable-section composite pile
CN111364454A
Wedge-shaped composite pile and construction method thereof
CN111877386A
Underground gravel sand layer expansion type grouting pipe and grouting method thereof
CN114908733A
Design and construction method of variable-diameter concrete-filled steel tube mixing composite pile
CN116657594A
Multi-level expanding body rigid composite pile, construction equipment and construction method
CN117230788A