Goaf impervious water storage structure and construction method thereof
By building a water-resistant water storage structure in the goaf and using the dam body and filler to form a leak-proof structure, the problems of water-storage leakage and water resource waste during coal mining are solved, and the effective protection and ecology of water resources are achieved. Environmental security.
Patent Information
- Application Number
- CN202411249760.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-06
- Publication Date
- 2024-11-22
AI Technical Summary
During coal mining, traditional water storage spaces are likely to cause water storage leakage in the upper goaf area when mining the lower coal seam, and do not have an anti-seepage effect on high-mineralization mine water or sewage, causing waste of water resources and ecological environment pollution.
The anti-seepage water storage structure is constructed in the goaf area, including the dam body, the first filler body and the second filler body, and a compact anti-seepage structure is formed by isolating the space and the fluid filling material, and the mold laying is completed by filling mining brackets. The mold is solid and the filling is formed to form fillers of different heights to prevent water leakage.
Effectively prevent mine water leakage, reduce water resource waste, protect the ecological environment of the mining area, and at the same time improve construction speed and safety, and meet efficient production requirements.
Smart Images

Figure CN118997277A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of underground water storage structures in coal mine goaf areas, and specifically relates to an anti-seepage water storage structure in a goaf area, and also relates to a construction method of an anti-seepage water storage structure in a goaf area. Background Art
[0002] During coal mining, artificial drainage to ensure safety and the natural drainage of coal-bearing aquifers caused by mining have caused a large amount of water resource loss. Based on the country's call for green coal development, research on the coordinated development of coal resource development and ecological environment and water resource protection has become increasingly important. After more than 20 years of continuous technical research, the National Energy Group's coal green mining technology research and development team pioneered the coal mine underground reservoir technology. Mine water is stored underground, which has the dual benefits of energy conservation, emission reduction and water resource protection.
[0003] The underground water reservoir technology in coal mines is to seal the goaf with coal pillars or artificial dams during the coal mining process and store the mine water in a closed space. It not only solves the problems of high construction and operation costs of surface water treatment plants, but also avoids the waste of water resources caused by draining mine water to the surface. At the same time, it can effectively reduce the workload of the mine drainage system and open up a new way to coordinate coal mining with the protection and utilization of water resources.
[0004] Mine water is stored in the goaf in the water storage space constructed in the traditional way. For multi-coal seam mining, when the lower coal seam is mined, the roof of the lower coal layer collapses and cracks appear in the roof, which can easily cause water leakage and loss in the goaf of the upper coal layer. Moreover, when the underground water storage space stores highly mineralized mine water (also known as mine brackish water) or sewage, the traditional way of constructing the water storage space does not have the effect of preventing leakage, which can easily cause the loss of highly mineralized mine water or sewage, which is not conducive to the ecological environment protection of the mining area. Summary of the invention
[0005] The first purpose of the present invention is to provide an anti-seepage water storage structure for goaf areas, which can not only store mine water underground, but also solve the problem that the traditional way of constructing water storage space has no anti-seepage effect, which can easily cause the loss of water stored in the goaf and is not conducive to the ecological environment protection of the mining area.
[0006] In order to achieve the above-mentioned purpose, the technical solution adopted by the present invention is: an anti-seepage water storage structure in the goaf area, including a dam body, multiple first filling bodies, multiple second filling bodies, a top plate and a bottom plate; the dam body is continuously distributed around the goaf area, the upper part of the dam body is connected to the top plate, and the lower part of the dam body is arranged on the bottom plate; the first filling body and the second filling body are both arranged on the bottom plate in the goaf area, and the multiple first filling bodies and the multiple second filling bodies are arranged at intervals.
[0007] As a preferred technical solution of the present invention, the width of the first filling body is not less than the width of the second filling body.
[0008] As a preferred technical solution of the present invention, the dam body is a coal pillar dam body or an artificial dam body.
[0009] As a preferred technical solution of the present invention, when the dam body is an artificial dam body, the dam body construction includes a lane-retaining construction method and a lane-free construction method.
[0010] The second object of the present invention is to provide a method for constructing an anti-seepage water storage structure in a goaf, which is used to construct the above-mentioned anti-seepage water storage structure in the goaf.
[0011] In order to achieve the above object, the technical solution adopted by the present invention is: a method for constructing an anti-seepage water storage structure in a goaf area, which is specifically implemented according to the following steps:
[0012] Step 1, arranging a dam body on the bottom plate around the goaf, with the top of the dam body arranged below the top plate; using the first layer of flexible template as the top mold of the flexible template isolation space, and using the second layer of flexible template as the bottom mold of the flexible template isolation space; the top mold is installed on the lower edge of the rear extension beam of the filling and mining support, and the bottom mold is laid on the bottom plate of the goaf; and setting a pouring port on the top mold;
[0013] Step 2: In the workshop at the rear end of the flexible mold filling and mining support, the top mold and the bottom mold are extended by sewing with a portable sewing machine; after the top mold and the bottom mold pass through the rotating baffle and the clamping mold mechanism on the filling and mining support, they are fixed by the clamping mold mechanism; at the same time, the top mold at the end of the working surface and the edge of the top mold are sewn to form a disposable closed flexible mold isolation space equal to the periphery of the cross section of the space to be poured;
[0014] Step 3: During mining, the coal mining face moves along with the flexible mold filling mining support, and the flexible mold isolation space continues to stretch and lay backwards;
[0015] Step 4: When the mining reaches a step distance of 1m-10m, a space to be poured is formed in the goaf;
[0016] Step 5, passing the filling delivery pipe through the filling port and connecting it with the isolation space of the flexible mold, and tying and connecting the filling delivery pipe and the filling port;
[0017] Step 6, injecting the fluid filling material into the flexible mold isolation space of the space to be cast through the delivery pipe and the injection port to form a first filling body or a second filling body;
[0018] Step 7, after the flexible mold isolation space is filled, the filled flexible mold isolation space is squeezed by the rotating baffle of the filling and mining support, and the filling material of the flexible mold isolation space is squeezed, dehydrated and reinforced again to improve the strength and self-supporting ability of the filling body;
[0019] Step 8: After the fluid filling material solidifies, the clamping mechanism is unlocked, and the working face is normally pulled to mine coal, and the rotating baffle is not retracted at this time; as the working face is pushed to mine, the rotating baffle reaches the maximum retractable amount, and the rotating baffle is retracted;
[0020] Step 9, repeating the above steps 1-8 until the fluid filling material is used to fill the goaf of the entire working surface, forming a plurality of first filling bodies and second filling bodies.
[0021] The technical solution of the present invention also has the following characteristics:
[0022] As a preferred technical solution of the present invention, the fluid filling material is gangue concrete or concrete or foam concrete.
[0023] As a preferred technical solution of the present invention, the dam body and the first filling body or the dam body and the second filling body can be filled simultaneously.
[0024] As a preferred technical solution of the present invention, the strength of the filling material of the dam body is not lower than the strength of the filling materials of the first filling body and the second filling body.
[0025] The beneficial effects of the present invention are as follows: (1) The anti-seepage water storage structure of the goaf of the present invention has a dam body constructed around it and a filling body of different heights constructed on the entire cross-section of the goaf bottom plate, forming a dense anti-seepage structure around the goaf and on the bottom plate, which can not only store mine water underground, but also solve the problem of mine water leakage, reduce the leakage and loss of mine water, and benefit the ecological environment protection of the mining area. (2) The method for constructing the anti-seepage water storage structure of the goaf of the present invention, as the working face is pushed for mining, the filling and mining support is used to complete the laying, fixing and clamping of the mold, forming a disposable flexible mold isolation space of different heights in the goaf, and the flexible mold isolation space in each step is filled at the same time. After filling, the filling body has good integrity, and this operation method is safe and reliable, with a fast construction speed, meeting the requirements of safe and efficient production. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:
[0027] Figure 1 This is a structural schematic diagram of an anti-leakage coal mine goaf underground water storage structure of the present invention
[0028] Figure 2 It is a schematic diagram of the mutual position relationship between an anti-leakage coal mine goaf underground water storage structure and a comprehensive mechanized coal mining working face and goaf of the present invention;
[0029] Figure 3It is a schematic elevation diagram of an anti-leakage coal mine goaf underground water storage structure constructed according to the present invention;
[0030] Figure 4 It is a schematic elevation diagram of an anti-leakage coal mine goaf underground water storage structure BB of the present invention.
[0031] In the figure, 1. dam body, 2. first filling body, 3. second filling body, 4. space to be poured, 5. flexible mold filling mining support, 6. slurry conveying pipe, 7. top plate, 8. bottom plate, 9. flexible mold isolation space, 10. top mold, 11. bottom mold, 12. pouring port, 13. goaf, 14. coal mining working face, 15. rear extension beam, 16. clamping mechanism, 17. filling material, 18. rotating baffle. DETAILED DESCRIPTION
[0032] The technical solution of the present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0033] Example 1
[0034] like Figure 1 As shown, an anti-seepage water storage structure for goaf area of the present invention comprises a dam body 1, a plurality of first filling bodies 2, a plurality of second filling bodies 3, a top plate 7 and a bottom plate 8. The dam body 1 is continuously distributed around the goaf area 13, the upper part of the dam body 1 is in contact with the top plate 7, and the lower part of the dam body 1 is arranged on the bottom plate 8; the first filling body 2 and the second filling body 3 are both arranged on the bottom plate 8 in the goaf area 13, and the plurality of first filling bodies 2 and the plurality of second filling bodies 3 are arranged at intervals.
[0035] Different from the traditional way of constructing water storage space, the present invention provides an anti-seepage water storage structure for goaf areas, which has a dam body 1 constructed around it and a first filling body 2 and a second filling body 3 of different heights constructed on the entire section of the bottom plate 8 of the goaf 13, forming a dense anti-seepage structure around the goaf 13 and on the bottom plate 8, which can not only store mine water underground, but also solve the problem of mine water leakage, reduce the leakage and loss of mine water, and is beneficial to the protection of the ecological environment in the mining area.
[0036] Example 2
[0037] like Figure 1 As shown, different from Example 1, in Example 2, in an anti-seepage water storage structure for a goaf of the present invention, the width of the first filling body 2 is not less than the width of the second filling body 3, and the dam body 1 is a coal pillar dam body or an artificial dam body; the coal pillar dam body is a dam body formed by the coal body underground, and the artificial dam body is a dam body formed by filling.
[0038] Example 3
[0039] Combination Figures 2 to 4The method for constructing an anti-seepage water storage structure in a goaf area of the present invention is specifically implemented according to the following steps:
[0040] Step 1, arrange the bottom plate 8 at the bottom of the goaf 13, arrange the dam body 1 around the goaf 13 on the bottom plate 8, and arrange the top of the dam body 1 below the top plate 7; use the first layer of flexible template as the top mold 10 of the flexible mold isolation space 9, and use the second layer of flexible template as the bottom mold 11 of the flexible mold isolation space 9; the top mold 10 is installed on the lower edge of the rear extension beam 15 of the filling and mining support 5, and the bottom mold 11 is laid on the bottom plate 8 of the goaf 13; set the injection port 12 on the top mold 10;
[0041] Step 2, in the workshop at the rear end of the flexible mold filling and mining support 5, a portable sewing machine is used to sew the top mold 10 and the bottom mold 11 to extend and lengthen; after the top mold 10 and the bottom mold 11 pass through the rotating baffle 18 and the clamping mechanism 16 on the filling and mining support 5, they are fixed by the clamping mechanism 16; at the same time, the edges of the top mold 10 and the top mold 11 at the end of the working surface are sewn to form a disposable closed flexible mold isolation space 9 equal to the cross-sectional periphery of the space 4 to be poured; the flexible mold isolation space 9 is a closed body, which is the same length and width as the space 4 to be poured, and the height of the flexible mold isolation space 9 is determined according to the filling body;
[0042] Step 3, during mining, the coal mining face 14 moves along with the flexible mold filling mining support 5, and the flexible mold isolation space 9 continues to stretch and lay backwards;
[0043] Step 4, when the mining reaches a step distance of 1m-10m, a space 4 to be poured is formed in the goaf 13;
[0044] Step 5, passing the filling delivery pipe 6 through the filling port 12 to communicate with the flexible mold isolation space 9, and tying the filling delivery pipe 6 and the filling port 12 to connect;
[0045] Step 6, injecting the fluid filling material 17 into the flexible mold isolation space 9 of the to-be-cast space 4 through the delivery pipe 6 and the pouring port 12; forming the first filling body 2 or the second filling body 3; the fluid filling material 17 is gangue concrete or concrete or foam concrete, and the filling material strength of the dam body 1 is not lower than the filling material strength of the first filling body 2 and the second filling body 3; the dam body 1 and the first filling body 2 and the second filling body 3 can also be filled at the same time;
[0046] Step 7, after the flexible mold isolation space 9 is filled, the rotating baffle 18 of the filling and mining support 5 is used to squeeze the filled flexible mold isolation space 9, and the filling material 17 of the flexible mold isolation space 9 is squeezed, dehydrated, and reinforced again to improve the strength and self-supporting ability of the filling body;
[0047] Step 8, after the fluid filling material 17 solidifies, the clamping mechanism 16 is unlocked, and the working face is normally pulled to mine coal, and the rotating baffle 18 is not retracted at this time; as the working face is pushed to mine, the rotating baffle 18 is retracted when the rotating baffle reaches the maximum retractable amount;
[0048] Step 9, repeating the above steps 1-8 until the fluid filling material 17 is used to fill the goaf 13 of the entire working face, forming a plurality of first filling bodies 2 and second filling bodies 3.
[0049] The present invention provides a method for constructing an anti-seepage water storage structure in a goaf. As the working face is mined, a filling and mining support is used to complete mold laying, mold fixing, and mold clamping, so as to form disposable flexible mold isolation spaces of different heights in the goaf. The flexible mold isolation spaces in each step are filled simultaneously. After filling, the filling body has good integrity. In addition, this operation method is safe and reliable, and the construction speed is fast, which meets the requirements of safe and efficient production.
[0050] The above description shows and describes several preferred embodiments of the invention, but as mentioned above, it should be understood that the invention is not limited to the form disclosed herein, and should not be regarded as excluding other embodiments, but can be used in various other combinations, modifications and environments, and can be modified within the scope of the invention concept described herein through the above teachings or the technology or knowledge of the relevant field. Changes and modifications made by those skilled in the art should be within the scope of protection of the claims attached to the invention without departing from the spirit and scope of the invention.
Claims
1. The anti-seepage water storage structure in the goaf is characterized by: The invention comprises a dam body (1), a plurality of first filling bodies (2), a plurality of second filling bodies (3), a top plate (7) and a bottom plate (8); the dam body (1) is continuously distributed around the goaf (13), the upper part of the dam body (1) is in contact with the top plate (7), and the lower part of the dam body (1) is arranged on the bottom plate (8); the first filling body (2) and the second filling body (3) are both arranged on the bottom plate (8) in the goaf (13), and the plurality of first filling bodies (2) and the plurality of second filling bodies (3) are arranged at intervals.
2. The anti-seepage water storage structure for goaf according to claim 1, characterized in that: The width of the first filling body (2) is not less than the width of the second filling body (3).
3. The anti-seepage water storage structure for goaf according to claim 1, characterized in that: The dam body (1) is a coal pillar dam body or an artificial dam body.
4. The anti-leakage underground water storage structure in coal mine goaf according to claim 3, characterized in that: When the dam body 1 is an artificial dam body, the dam body construction includes a lane-retaining construction method and a lane-free construction method.
5. A method for constructing an anti-seepage water storage structure in a goaf, characterized in that: Follow the steps below to implement it: Step 1, arranging a bottom plate (8) at the bottom of the goaf (13), arranging a dam body (1) around the goaf (13) on the bottom plate (8), and arranging the top of the dam body (1) below the top plate (7); using a first layer of flexible template as a top mold (10) of the flexible mold isolation space (9), and using a second layer of flexible template as a bottom mold (11) of the flexible mold isolation space (9); the top mold (10) is installed at the lower edge of the rear extension beam (15) of the filling and mining support (5), and the bottom mold (11) is laid on the bottom plate (8) of the goaf (13); and providing a pouring port (12) on the top mold (10); Step 2, in a workshop at the rear end of the flexible mold filling and mining support (5), a portable sewing machine is used to sew the top mold (10) and the bottom mold (11) to extend the length; after the top mold (10) and the bottom mold (11) pass through the rotating baffle (18) and the clamping mechanism (16) on the filling and mining support (5), they are fixed by the clamping mechanism (16); at the same time, the edges of the top mold (10) and the top mold (11) at the end of the working surface are sewn to form a disposable closed flexible mold isolation space (9) equal to the cross-sectional periphery of the space to be poured (4); Step 3, during mining, the coal mining face (14) moves along with the flexible mold filling mining support (5), and the flexible mold isolation space (9) continues to stretch and lay backwards; Step 4, when the mining reaches a step distance of 1m-10m, a space (4) to be poured is formed in the goaf (13); Step 5, passing the filling delivery pipe (6) through the filling port (12) to communicate with the flexible mold isolation space (9), and tying and connecting the filling delivery pipe (6) and the filling port (12); Step 6, injecting the fluid filling material (17) into the flexible mold isolation space (9) of the space to be cast (4) through the delivery pipe (6) and the injection port (12) to form a first filling body (2) or a second filling body (3); Step 7, after the flexible mold isolation space (9) is filled, the filled flexible mold isolation space (9) is squeezed by the rotating baffle (18) of the filling and mining support (5), and the filling material (17) of the flexible mold isolation space (9) is squeezed, dehydrated and reinforced again to improve the strength and self-supporting ability of the filling body; Step 8, after the fluid filling material (17) solidifies, the clamping mechanism (16) is unlocked, and the working face is normally pulled to mine coal, and the rotating baffle (18) is not retracted at this time; as the working face is pushed to mine, the rotating baffle (18) is retracted when the rotating baffle reaches the maximum retractable amount; Step 9, repeating the above steps 1 to 8 until the fluid filling material (17) is used to fill the entire goaf (13) of the working face, forming a plurality of first filling bodies (2) and second filling bodies (3).
6. The method for constructing an anti-seepage water storage structure in a goaf according to claim 5, characterized in that: The fluid filling material (17) is gangue concrete or concrete or foam concrete.
7. The method for constructing an anti-seepage water storage structure in a goaf according to claim 6, characterized in that: The dam body (1) and the first filling body (2) or the dam body (1) and the second filling body (3) can be filled simultaneously.
8. The method for constructing an anti-seepage water storage structure in a goaf according to claim 7, characterized in that: The strength of the filling material of the dam body (1) is not lower than the strength of the filling materials of the first filling body (2) and the second filling body (3).