Through the upper and lower plate ore body and the same area as the plate filling mining method, combined with the upper approach and mechanized layered filling, safe and efficient mining of deep mines is achieved, and the problems of high cost and small capacity of thick ore body are solved, and the problems of high mining costs and small capacity are improved. Productivity and resource recovery rate.
Patent Information
- Application Number
- CN202411171659.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-26
- Publication Date
- 2024-11-22
AI Technical Summary
In deep metal mine mining, the safe, efficient and continuous mining of thick, broken ore bodies faces huge challenges. The existing mining methods are costly and small in capacity, making it difficult to meet the production needs of large-scale ore mining, and it is difficult to break through safe production. The fundamental requirement and technical bottleneck of 'large production capacity and low cost'.
The upper and lower plate ore body and the same area of the plate filling mining method is adopted. Through the mechanized layering-projection joint arrangement of the upper plate ore body, it is divided into two areas, the upper plate ore body and the lower plate ore body are simultaneously mined, and the upper plate ore body is used to fill and Mechanization combines layered filling to achieve simultaneous mining of multiple segments and multiple mining sites, reducing costs and ore losses, and improving safety production efficiency.
The number of mining sites increased, cost decreased, high resource recovery rate, large production capacity and low waste rock mixing rate have been achieved, meeting the demand for low-cost and large-capacity mining of thick ore bodies, improving the safety production efficiency and mining efficiency in the middle section, and solving the problem of Poor rock stability, high ground pressure, rock burst and other complex engineering geology problems.
Smart Images

Figure CN118997762A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of mining, and in particular relates to a plate-type filling mining method in the same area of upper and lower plate ore bodies. Background Art
[0002] With large-scale resource mining, my country's shallow mineral resources have become exhausted. In the future, my country's mineral resource development will gradually enter the deep ore deposits within the second depth space (1000~2000 m), and deep mining of metal mines will become the norm. However, deep mining inevitably has the problem of "three highs and one disturbance", especially for thick and broken ore bodies, which poses a huge threat to the safe, efficient and continuous mining of ore.
[0003] Mechanized upward horizontal stratified filling mining method and upward approach filling mining method are currently the most widely used mining methods in underground metal mining in my country, especially in steeply inclined or inclined thick and unstable ore bodies. However, the upward horizontal stratified filling mining method has the disadvantages of high cost, small capacity and high labor intensity. When the upward approach filling mining method with a smaller exposed space is adopted, the cost of ore mining increases and the ore output capacity is low, which cannot meet the production capacity requirements of large-scale ore mining. Whether it is mechanized upward stratified filling mining method or upward approach filling mining method, if the segmented transportation tunnels and the connecting tunnels of the upper and lower plates cannot be reasonably arranged according to the mining technical conditions of the ore body, it is difficult to break through the fundamental requirements of safe production and the major technical bottleneck of "large production capacity and low cost". Summary of the invention
[0004] The main purpose of the present invention is to provide a pan-area filling mining method for the same area of the upper and lower plate ore bodies. The mining method adopts an upward mechanized stratification-access joint layout according to the mining technical conditions of the upper and lower plate ore bodies to achieve simultaneous mining of two areas. At the same time, the number of operating mining areas is increased, thereby reducing costs and ore losses while improving the safety production efficiency of the middle section.
[0005] To this end, the present invention provides a pan-area filling mining method for the upper and lower plate ore bodies in the same area. The ore body is divided into an upper plate ore body and a lower plate ore body according to intercalated stones, the middle section of the planned mining area is divided into sections, and the sections are divided into layers. The upper plate ore body is mined by an upward approach filling mining method, and the lower plate ore body is mined by a mechanized upward layered filling mining method. During the mining operation, the sections of the upper and lower plates are mined from bottom to top. In one pan area, the lower plate ore body and the upper plate ore body are mined simultaneously. The one-step upward layered mining field of the lower plate ore body is first mined to the level of the upper section, and then the two-step upward layered mining field of the lower plate ore body and the upper plate ore body approach mining field are mined. The one-step upward layered mining field is mined through the lower plate segmented transportation level tunnel and the mining field connecting road, and the two-step upward layered mining field and the upper plate approach mining field are mined through the upper plate segmented transportation level tunnel and the mining field connecting road.
[0006] Specifically, during the mining project, two stratified mining field communication roads are arranged from the lower plate segmented transport level tunnel in each plate area, and the stratified mining field communication roads are pulled through along the vein at the lower boundary of the lower plate ore body to realize the simultaneous mining and layer change of one-step upward stratified mining field; the upper plate segmented transport level tunnel is arranged outside the vein of the upper plate ore body, and two access mining field communication roads are arranged from the upper plate segmented transport level tunnel in each plate area, passing through the upper plate ore body to the upper plate boundary of the lower plate ore body, and then the access mining field communication road is pulled along the vein at the upper plate boundary of the lower plate ore body to realize the simultaneous mining and layer change of two-step upward stratification; at the same time, the access mining field communication road is constructed along the vein at the lower boundary of the upper plate ore body, and the access mining field is arranged perpendicular to the direction of the upper plate ore body, so as to realize the simultaneous mining and layer change of two-step upward stratification with the lower plate ore body.
[0007] Specifically, when dividing the mining area, the first-step upward stratified mining area and the second-step upward stratified mining area are arranged perpendicular to the ore body direction in the lower plate ore body, and the approach mining area is arranged perpendicular to the ore body direction in the upper plate ore body.
[0008] Specifically, the one-step upward stratified mining area of the lower plate ore body is first mined to the level of the upper segment, and then the two-step upward stratified mining area of the lower plate ore body and the access mining area of the upper plate ore body are mined; the one-step upward stratified mining areas of the two segments are alternately arranged and mined at the same time until the ore blocks are mined; the one-step upward stratified mining area is mined through the lower plate project, and the two-step upward stratified mining area and the access mining area of the upper plate are mined through the upper plate project.
[0009] Specifically, after the first-step upward stratified mining area of the lower ore body is mined and filled, the layer is changed and the mining operation of the previous layer is carried out; after the second-step upward stratified mining area of the lower ore body and the access mining area of the upper ore body are mined and filled, the layer is changed and the mining operation of the previous layer is carried out, and the mining and filling operation process is repeated until the mining operation of the entire middle section ore body is completed.
[0010] Specifically, the mining operation includes four processes: rock drilling, blasting ore, ventilation and prying, and ore transportation. Horizontal blastholes are drilled with a rock drilling rig, followed by charging and blasting. After the ore collapses, local fans are used to enhance ventilation, and then the prying trolley enters the mining area to conduct a roof safety inspection. The collapsed ore is transported to the chute by a shovel loader via the mining area connecting road, the segmented transport tunnel, and the chute connecting road.
[0011] Specifically, the rock drilling process uses a drilling rig to drill horizontal blastholes with a grid density of 0.8 m×1.0 m, a blasthole diameter of 42 mm, and a depth of 4 m. No. 2 rock emulsion explosives and electronic detonator micro-difference blasting are used for blasting.
[0012] Specifically, two filling ventilation shafts are arranged in the upper and lower plates of the mining area, which are used for ventilation of the one-step upward stratified mining area of the lower plate ore body and the two-step upward stratified mining area of the lower plate ore body and the upward access mining area of the upper plate ore body respectively.
[0013] Specifically, during the filling operation, the lower plate mine is mechanized to move upward to the horizontal layered mining area, and the mining is carried out in layers, one is mined and one is filled. After the lower plate ore body is mined in the first layered mining area, the cementing filling method is used and the surface is cemented. The second layer of the lower plate ore body is mined in the second layered mining area, and the non-cementing filling method is used but the surface is cemented. An artificial false bottom of reinforced concrete is constructed in the first layer.
[0014] Specifically, when filling the stope of the upward approach, the first layer is constructed with reinforced concrete artificial bottom, the first step approach adopts cementing filling method, and the second step approach adopts non-cementing filling method, and both are filled to the top. Specifically, before the formal mining, 45m is the middle section, and the middle section ore body is divided into three sections according to the vertical height of 15m; the section is divided into three layers according to each layer of 4.5-5m, and each section is divided into three panels with a width of 80m. The vertical ore body direction is divided into several stopes arranged at intervals.
[0015] Specifically, the length of the first-step upward stratified stope and the second-step upward stratified stope of the lower ore body is 65-80 m, and the length of the access route of the upper ore body is 18-20 m.
[0016] Specifically, an upper wall segmented transport tunnel and a lower wall segmented transport tunnel are arranged 40-50 m away from the upper wall boundary and the lower wall boundary of the ore body respectively.
[0017] Compared with the prior art, the present invention has the following beneficial effects: (1) Based on the mining technical conditions of the upper and lower ore bodies, an upward mechanized stratification-access joint layout is adopted to achieve simultaneous mining in two areas. At the same time, the number of operating stopes is increased, which reduces costs and ore losses while improving the safety production efficiency of the middle section.
[0018] (2) The amount of mining work is reduced and the resource recovery rate is high: connecting tunnels are arranged along the direction of the ore vein in both the upper and lower plates, which is conducive to the recovery of the ore body in the broken upper plate and improves the resource recovery rate; only two mining field connecting tunnels connected to the ore body are arranged in one plate area, avoiding the arrangement of a mining field connecting tunnel in each mining field, and the amount of mining work is greatly reduced.
[0019] (3) High mining efficiency and large production capacity: Multiple sections and multiple mines are mined simultaneously, and the number of mines mined at the same time increases. The same self-propelled equipment can serve all the mines in the disk area at the same time, with high efficiency in shoveling and hauling ore, low cost investment, and high construction safety assurance, meeting the production needs of low-cost and high-capacity mining of thick and large ore bodies.
[0020] (4) Improved stability and safety of mining operations: The first-step upward stratification stopes and the second-step upward stratification stopes are arranged perpendicular to the ore body direction in the lower ore body. The first-step upward stratification stope is one segment height ahead of the second-step upward stratification stope. This arrangement allows multiple stopes to operate at different elevations at the same time, reducing mutual interference between simultaneous mining in the stopes. This not only improves the stability of the stopes, but also ensures safe mining and improves mining efficiency.
[0021] (5) The waste rock mixing rate is low and can better adapt to the morphological changes of multi-layer ore bodies: On the one hand, the combined layout method can apply different mining methods and adopt different stope layout forms according to different ore body conditions, and share the mining project volume, which can effectively reduce the waste rock mixing rate; for ore bodies with irregular boundaries, the stopes are arranged perpendicular to the ore body direction, and the stope structure parameters can be adjusted according to the ore body boundary. It has strong flexibility, high resource recovery rate, and reduces the waste rock mixing rate.
[0022] The mining scheme proposed in the present invention can realize simultaneous mining and layer change in multiple mining areas, effectively solving the complex engineering geological conditions such as poor stability of the upper and lower surrounding rocks, high ground pressure, rock bursts, etc. in the middle section of mining, greatly reducing the amount of mining and cutting projects and improving safety production efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0024] Figure 1 It is a front view of an ore body mined by a plate-type filling mining method in the same area of an upper and lower plate ore body provided by an embodiment of the present invention; Figure 2 It is a main view and a top view of an ore body mined by a plate-type filling mining method in the same area of an upper and lower plate ore body provided by an embodiment of the present invention; Figure 3 for Figure 2 B1-B1 section diagram in; Figure 4 for Figure 2 B2-B2 section view in; Among them: 1. Lower plate segmented transport tunnel; 2. Layered mining field connecting road; 3. Lower plate mine lower plate along vein layered mining field connecting road; 4. One-step upward layered mining field; 5. Two-step upward layered mining field; 6. Lower plate mine upper plate along vein layered mining field connecting road; 7. Upper plate mine along vein access mining field connecting road; 8. Access mining field; 9. Upper plate mine and lower plate mine connecting tunnel; 10. Upper plate mine filling ventilation shaft; 11. Access mining field connecting road; 12. Upper plate segmented transport tunnel; 13. Return air tunnel; 14. Lower plate mine filling ventilation shaft; 15. Upper and middle section cemented filling body; 16. Reinforced concrete artificial false bottom; 17. Cemented filling body; 18. Non-cemented filling body; 19. Top-connected cemented filling body. DETAILED DESCRIPTION
[0025] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0026] In the description of the present invention, it is to be understood that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, “axial”, “radial”, “circumferential”, etc., indicating orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.
[0027] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0028] See also Figures 1 to 4, a filling mining method with mechanized upward stratification-route joint arrangement of upper and lower plate ore bodies in the same area. The ore body is divided into upper plate ore body and lower plate ore body according to the interlayer stone. The lower plate ore body is a thick and large ore body. The middle section of the planned mining area is divided into sections, and the sections are divided into layers. The upper plate ore body with poor ore rock stability is mined by the upward route filling mining method, and the lower plate ore body with thick ore body is mined by the mechanized upward stratification filling mining method. During the mining operation, the upper and lower plate ore bodies are mined by the mechanized upward stratification filling mining method. Each section of the lower plate is mined from bottom to top. Within one plate area, the lower plate ore body and the upper plate ore body are mined simultaneously. The lower plate ore body is first mined to the upper section level in the first-step upward stratified stope, and then the lower plate ore body is mined in the second-step upward stratified stope and the upper plate ore body access stope. The first-step upward stratified stope is mined through the lower plate segment transport tunnel 1 and the stope connecting road, and the second-step upward stratified stope and the upper plate access stope are mined through the upper plate segment transport tunnel 12 and the stope connecting road.
[0029] In the present application, the lower plate ore body is arranged with one-step and two-step upward stratified mining areas, and the upper plate ore body is arranged with the approach mining area. The one-step upward stratified mining area is one segment height ahead of the two-step upward stratified mining area, and the two segments and the one-step upward stratified mining areas are arranged alternately, and the two segments can be mined at the same time. The one-step upward stratified mining area constructs the lower plate segment transportation level tunnel and the mining area connecting road for mining, and the two-step upward stratified mining area and the upper plate approach mining area construct the upper plate segment transportation level tunnel and the mining area connecting road for mining. The approach mining is one-time filling and one-time mining, and mining is carried out from bottom to top. The working face operates in a cycle, rock drilling and blasting, ore extraction, and roof protection. After the approach mining is completed, filling operations are carried out. Such a mining scheme can realize the simultaneous mining of multiple mining areas and the simultaneous layer change, which effectively solves the problems of complex engineering geological conditions such as poor stability of the upper and lower plate surrounding rocks, high ground pressure, rock bursts, etc. in the middle section of mining, greatly reduces the amount of mining and cutting engineering, and improves safety production efficiency.
[0030] See also Figures 1 to 4 , the method specifically includes the following contents: Before the formal mining, 45m is the middle section, and the middle section ore body is divided into three sections according to the vertical height of 15m; the section is divided into three layers according to each layer of 4.5~5m, and each section is divided into three panels with a width of 80m. The vertical ore body direction is divided into several stopes arranged at intervals.
[0031] Stope division: Each panel area is divided into two areas for mining. The first area is the lower plate ore body mining area. The one-step upward stratified stope 4 (mine room) and the two-step upward stratified stope 5 (mine pillar) are arranged perpendicular to the ore body strike, with a length of 65-80 m. The lower plate ore body of a panel area is first mined in the one-step upward stratified stope 4, and then in the two-step upward stratified stope 5. The one-step upward stratified stope 4 is 15 m higher than the two-step upward stratified stope 5, that is, one segment height. The two segments of the one-step upward stratified stope 4 are alternately arranged and mined at the same time until the ore block is mined. The second area is the upper plate ore body mining area. The approach length is 18-20 m vertically arranged in the ore body strike. The upper plate ore with poor ore rock stability is mined by the upward approach filling mining method, and the approach width is 4-4.5 m, access height 4.5-5m, one mining and one filling, the first-step upward stratified stope 4 is mined through the lower plate engineering, the second-step upward stratified stope 5 and the upper plate access stope are mined through the upper plate engineering. The lower plate ore with thick ore body is mined by mechanized upward stratified filling mining method. The width of the mine room is 6-8m, and the mining height is 4.5-5m. During the mining process, the mining technical parameters are adjusted according to the stability of the surrounding rock.
[0032] Mining project: two stratified stope contact roads 2 are arranged from the lower wall segmented transport level 1 in each panel area, and the lower wall ore lower wall vein stratified stope contact road 3 is arranged along the vein at the lower boundary of the lower wall ore body to connect the stratified stope contact road 2, so as to realize the simultaneous mining and layer change of single stopes in one step; the upper wall segmented transport level 12 is arranged outside the upper wall vein of the ore body, and two access stope contact roads 11 are arranged from the upper wall segmented transport level 12 in each panel area, passing through the upper wall ore body to the upper wall boundary of the lower wall ore body, and then in the lower wall segmented transport level 12, two access stope contact roads 11 are arranged, which pass ... At the upper boundary of the upper plate ore body, a stratified mining field connecting road 6 along the vein of the lower plate mine is arranged, and an access mining field connecting road 11 is connected to realize simultaneous mining of two-step even-numbered mining fields and simultaneous layer change; at the same time, an access mining field connecting road 7 along the vein of the upper plate mine is constructed at the lower boundary of the upper plate ore body, and an access mining field 8 is arranged perpendicular to the direction of the upper plate ore body, and simultaneous mining and simultaneous layer change are achieved with the two-step even-numbered mining fields of the lower plate ore body; the stratified mining field connecting road 6 along the vein of the lower plate mine is connected to the access mining field 8 through a connecting tunnel 9 between the upper plate mine and the lower plate mine.
[0033] Mining operation: The first step upward stratified stope 4 of the lower plate mine is mined to the upper segment level (height 15m), and then the second step upward stratified stope 5 of the lower plate mine and the upper plate mine access stope 8 are mined. The mining operation includes four processes: rock drilling, blasting ore, ventilation prying, and ore transportation. The horizontal blasthole is drilled with a rock drilling trolley, and then charged and blasted. After the ore collapse is completed, the ventilation is enhanced with a local fan, and then the prying trolley enters the stope to check the roof safety. The collapsed ore is transported to the chute by the shovel loader through the stope connection road, the segmented transport lane, and the chute connection road; when mining in the first step upward stratified stope 4, personnel and equipment enter the stope through the lower plate segmented transport lane 1 and the stope connection road. When mining in the second step upward stratified stope 5 and the upper plate access stope, personnel and equipment enter the stope through the upper plate segmented transport lane 12 and the stope connection road. Filling operation: mechanized upward horizontal stratified mining area of the lower plate mine, stratified mining, one mining and one filling, the first step odd-numbered upward stratified mining area uses cementing filling method and cementing surface after mining, the second step even-numbered upward stratified mining area of the lower plate mine uses non-cementing filling method but cementing surface, and the first layer constructs reinforced concrete artificial false bottom 16; the upper approach mining area, the first layer constructs reinforced concrete artificial false bottom 16, the first step approach adopts cementing filling method to form a cementing filling body 17, and the second step approach adopts non-cementing filling method to form a non-cementing filling body 18. In this application, both the first step approach and the second step approach are filled and connected to the top, and then a top-connected cementing filling body 19 is formed. When the corresponding mining area of the upper middle section is mined and filled, the upper middle section cementing filling body 15 can be formed; After the mining and filling of the first-step upward stratified mining area 4 of the lower plate mine is completed, the layer is changed and the mining operation of the previous layer is carried out; after the mining and filling of the second-step upward stratified mining area 5 of the lower plate mine and the access mining area of the upper plate mine are completed, the layer is changed and the mining operation of the previous layer is carried out. The stratified mining method and filling method of the upper stratified mining area and the access mining area of the lower plate mine are the same as above, and this cycle is repeated until the mining operation of the middle section of the ore body is completed.
[0034] Compared with the existing method, the present invention has the following beneficial effects: (1) The amount of mining work is reduced and the resource recovery rate is high: both the upper and lower plates are arranged along the direction of the ore vein, which is conducive to the recovery of the ore body in the broken upper plate and improves the resource recovery rate; only two mining field connecting tunnels connected to the ore body are arranged in one plate area, avoiding the arrangement of a mining field connecting tunnel in each mining field, and the amount of mining work is greatly reduced.
[0035] (2) High mining efficiency and large production capacity: Multiple sections and multiple mining areas are mined simultaneously, and the number of mining areas mined at the same time increases. The same self-propelled equipment can serve all mining areas in the disk area at the same time, with high efficiency in shoveling and hauling ore, low cost investment, and high construction safety assurance, meeting the production needs of low-cost and high-capacity mining of thick and large ore bodies.
[0036] (3) Improved stability and safety of mining operations: The lower ore body is arranged with one-step upward stratification and two-step upward stratification stopes perpendicular to the ore body direction. The one-step upward stratification stope 4 is one segment height ahead of the two-step upward stratification stope. This arrangement allows multiple stopes to operate at different elevations at the same time, reducing mutual interference between simultaneous mining in the stopes. This not only improves the stability of the stopes, but also ensures safe stopes and improves mining efficiency.
[0037] (4) The waste rock mixing rate is low and can better adapt to the morphological changes of multi-layer ore bodies: On the one hand, the combined layout method can apply different mining methods and adopt different stope layout forms according to different ore body conditions, and share the mining project volume, which can effectively reduce the waste rock mixing rate; for ore bodies with irregular boundaries, the stopes are arranged perpendicular to the ore body direction, and the stope structure parameters can be adjusted according to the ore body boundary. It has strong flexibility, high resource recovery rate, and reduces the waste rock mixing rate.
[0038] The mining scheme proposed in the present invention can realize simultaneous mining and layer change in multiple mining areas, effectively solving the complex engineering geological conditions such as poor stability of the upper and lower surrounding rocks, high ground pressure, rock bursts, etc. in the middle section of mining, greatly reducing the amount of mining and cutting projects and improving safety production efficiency.
[0039] The rock drilling process uses a rock drilling trolley to drill horizontal blastholes, with a grid density of 0.8 m×1.0 m, a blasthole diameter of 42 mm, and a depth of 4 m. No. 2 rock emulsion explosives and electronic detonator micro-difference blasting are used for blasting. Two filling ventilation shafts are arranged in the upper and lower plates of the mining area, which are used for the ventilation of the mining area of the first step of the lower plate mine, the second step of the lower plate mine, and the upper plate mine. Local fans are used for forced ventilation in some areas.
[0040] The lower plate mine is upwardly layered in one step (the first step). The odd-numbered mining areas use the mining area connecting roads and segmented transport tunnels of the lower plate to carry out mining and ore-excavation processes, realizing synchronous mining and synchronous layer change; the lower plate mine is upwardly layered in two steps (the second step). The even-numbered mining areas and the upper plate mine's upward approach mining areas use the mining area connecting roads and segmented transport tunnels of the upper plate to carry out mining and ore-excavation processes, realizing synchronous mining and synchronous layer change until the middle section mining is completed.
[0041] Specifically, in the mining project, at 40-50 m away from the upper wall boundary and the lower wall boundary of the ore body, an upper wall segmented transport tunnel 12 and a lower wall segmented transport tunnel 1 are arranged respectively, which are used for the transportation of personnel, equipment and ore in the segmented stope, with a cross-sectional size of 4.2 m×3.6 m; after the opening of the lower wall segmented transport tunnel 1 is changed to a 15% downhill excavation of the stratified stope contact tunnel to the lower wall of the ore body, a stratified stope contact road along the vein is constructed along the lower wall boundary of the lower wall ore body, with a cross-sectional size of 3.6 m×3.6 m, which is used for excavating the one-step singular upward stratified stope of the lower wall ore body; after the opening of the upper wall segmented transport tunnel 12 is changed to a 15% downhill excavation to the upper wall of the ore body, the slope is changed to pass through the upper wall ore body to the upper boundary of the lower wall ore body, and a stratified stope contact road and an approach stope contact road 7 are constructed along the upper boundary of the lower wall ore body and the lower boundary of the upper wall ore body, respectively, with a cross-sectional size of 3.6 m×3.6 m, used for excavating the two-step even-number upward stratified stope of the lower plate ore body and the access stope of the upper plate ore body, so as to realize the simultaneous mining and layer change of the two-step even-number upward stratified stope of the lower plate ore body and the access stope of the upper plate ore body.
[0042] Specifically, in the mining operation, the rock drilling process uses a rock drilling trolley to drill horizontal blastholes, with a grid density of 0.8 m×1.0 m, a blasthole diameter of 42 mm, and a depth of 4 m. No. 2 rock emulsion explosives and electronic detonator micro-difference blasting are used for blasting. Two filling ventilation shafts are arranged in the upper and lower plates of the mining area, namely the upper plate mine filling ventilation shaft 10 and the lower plate mine filling ventilation shaft 14. Each filling ventilation shaft is connected to the corresponding return air level tunnel 13. Among them, the upper plate mine filling ventilation shaft 10 is used for the ventilation of the mining area of the lower plate mine in the two-step upward stratified mining and the upper plate mine in the upward access mining. The lower plate mine filling ventilation shaft 14 is used for the one-step singular upward stratified mining of the lower plate mine, and local fans are used for forced ventilation in some areas.
[0043] In the first step of the upward stratification of the lower wall mine, the odd-numbered mining areas utilize the mining area connecting roads and segmented transport tunnels of the lower wall to carry out mining, ore discharge and other processes, realizing synchronous mining and synchronous layer change; in the second step of the upward stratification of the lower wall mine, the even-numbered mining areas and the upward approach mining areas of the upper wall mine utilize the mining area connecting roads and segmented transport tunnels of the upper wall to carry out mining, ore discharge and other processes, realizing synchronous mining and synchronous layer change until the middle section mining is completed.
[0044] This method adopts the upward mechanized layering-access joint layout according to the mining technical conditions of the upper and lower ore bodies, realizes the simultaneous mining of two areas, and increases the number of operating stopes, while reducing costs and ore losses and improving the safety production efficiency of the middle section. Unless otherwise stated, any technical solution disclosed in the present invention disclosed above, if it discloses a numerical range, then the disclosed numerical range is a preferred numerical range, and any technician in the field should understand that the preferred numerical range is only a numerical value with a more obvious technical effect or representative value among many implementable numerical values. Since there are too many numerical values to be exhaustive, the present invention discloses some numerical values to illustrate the technical solution of the present invention, and the numerical values listed above should not constitute a limitation on the scope of protection of the present invention.
[0045] The above embodiments are merely examples for clearly illustrating the present invention, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the embodiments here. The obvious changes or modifications derived therefrom are still within the scope of protection of the present invention.
Claims
1. A method of plate-type filling mining in the same area of the upper and lower plate ore bodies, It is characterized in that The ore body is divided into the upper plate ore body and the lower plate ore body according to the interbedded rocks. The middle section of the planned mining area is divided into sections, and the sections are divided into layers. The upper plate ore body is mined by the upward approach filling mining method, and the lower plate ore body is mined by the mechanized upward layered filling mining method. During the mining operation, the sections of the upper and lower plates are mined from bottom to top. In one plate area, the lower plate ore body and the upper plate ore body are mined at the same time. The first-step upward layered mining area of the lower plate ore body is mined to the level of the upper section first, and then the second-step upward layered mining area of the lower plate ore body and the upper plate ore body approach mining area are mined; the first-step upward layered mining area is mined through the lower plate segment transportation level tunnel and the mining area connecting road, and the second-step upward layered mining area and the upper plate approach mining area are mined through the upper plate segment transportation level tunnel and the mining area connecting road.
2. The same-region plate-type filling mining method for upper and lower plate ore bodies according to claim 1, Features: During the mining project, two stratified mining field communication roads are arranged from the lower plate segmented transport level tunnel in each plate area, and the stratified mining field communication roads are pulled through along the vein at the lower boundary of the lower plate ore body to realize the simultaneous mining and layer change of one-step upward stratified mining field; the upper plate segmented transport level tunnel is arranged outside the vein of the upper plate ore body, and two access mining field communication roads are arranged from the upper plate segmented transport level tunnel in each plate area, passing through the upper plate ore body to the upper plate boundary of the lower plate ore body, and then the access mining field communication road is pulled along the vein at the upper plate boundary of the lower plate ore body to realize the simultaneous mining and layer change of two-step upward stratification; at the same time, the access mining field communication road along the vein is constructed at the lower boundary of the upper plate ore body, and the access mining field is arranged perpendicular to the direction of the upper plate ore body, so as to realize the simultaneous mining and layer change of the two-step upward stratification of the lower plate ore body.
3. The same-region plate-type filling mining method for upper and lower plate ore bodies according to claim 2, Features: When dividing the mining area, the first-step upward stratified mining area and the second-step upward stratified mining area are arranged perpendicular to the ore body direction in the lower plate ore body, and the approach mining area is arranged perpendicular to the ore body direction in the upper plate ore body.
4. The same-region plate-type filling mining method for upper and lower plate ore bodies according to claim 3, Features: The two sections are alternately arranged one step upward toward the stratified stope and mined simultaneously until all the ore blocks are mined.
5. The same-region plate-type filling mining method for upper and lower plate ore bodies according to claim 4, Features: After the mining and filling of the first-step upward stratified mining area of the lower ore body is completed, the layer is changed and the mining operation of the previous layer is carried out; after the mining and filling of the second-step upward stratified mining area of the lower ore body and the access mining area of the upper ore body are completed, the layer is changed and the mining operation of the previous layer is carried out, and the mining and filling operation process is repeated until the mining operation of the entire middle section of the ore body is completed.
6. The same-region plate-type filling mining method for upper and lower plate ore bodies according to claim 4, Features: The mining operation includes four processes: rock drilling, blasting ore, ventilation and prying, and ore transportation. Horizontal blastholes are drilled with a rock drilling trolley, followed by charging and blasting. After the ore collapses, local fans are used to enhance ventilation, and then the prying trolley enters the mining area to conduct a roof safety inspection. The collapsed ore is transported to the chute by a shovel loader via the mining area connecting road, the segmented transport tunnel, and the chute connecting road.
7. The same-region plate-type filling mining method for upper and lower plate ore bodies according to claim 6, Features: The rock drilling process uses a drilling rig to drill horizontal blastholes with a grid density of 0.8 m×1.0 m, a blasthole diameter of 42 mm, and a depth of 4 m. No. 2 rock emulsion explosives and electronic detonator micro-difference blasting are used for blasting.
8. The same-region plate-type filling mining method for upper and lower plate ore bodies according to claim 4, Features: Two filling ventilation shafts are arranged in the upper and lower plates of the mining area, which are used for ventilation of the one-step upward stratified mining area of the lower plate ore body and the two-step upward stratified mining area of the lower plate ore body and the upward access mining area of the upper plate ore body respectively.
9. The same-region plate-type filling mining method for upper and lower plate ore bodies according to claim 4, Features: During the filling operation, the lower plate mine is mechanized to move upward to the horizontal layered mining area, and the mining is carried out in layers, with one mining and one filling. After the first step of the lower plate ore body is mined in the upward layered mining area, the cementing filling method is used to glue the surface. The second step of the lower plate ore body is mined in the upward layered mining area, and the non-cementing filling method is used but the surface is glued. The first layer is constructed with a reinforced concrete artificial false bottom.
10. The same-region panel filling mining method for upper and lower ore bodies according to claim 9, Features: When filling the upward approach site, the first layer is constructed with an artificial false bottom of reinforced concrete, the first step approach adopts a cemented filling method, and the second step approach adopts a non-cemented filling method, and both are filled to the top.