Miniature pipe jacking construction equipment and process for narrow road section
Through the combined design of hydraulic drive and steel work well, the safety and high cost of traditional micro-pipe construction equipment in a rich environment of sandy silt layers and groundwater is solved, and safe and reliable pipe propulsion and cost reduction are achieved. Effect.
Patent Information
- Application Number
- CN202411087477.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2024-11-22
AI Technical Summary
Traditional micro-pipe top construction equipment can easily cause motor short circuits in environments with abundant sandy silt layers and groundwater, endangering the safety of construction workers. At the same time, the production cycle of the work well is long and costly.
Using a combination design of support base, main drive chamber, hydraulic column and steel work well, the main drive chamber is driven by hydraulic column to propel the top tube to avoid short circuit of the motor, and use adjustable drive components and connecting components to prevent the top tube from deviating. Steel work wells reduce cost and production cycle.
It effectively avoids equipment short circuit caused by groundwater splashing during overhead pushing, reduces the cost and production cycle of the work well, and improves the movement accuracy and safety of the overhead pipe.
Smart Images

Figure CN118998440A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of engineering construction, and in particular to micro-pipe jacking construction equipment and technology for narrow road sections. Background Art
[0002] In recent years, problems such as imperfect urban sewage pipe network construction and many defects in sewage pipe networks have become increasingly prominent, which has further accelerated the process of urban sewage pipe network construction and investigation and remediation. Urban sewage pipe network construction is often characterized by limited site, many above-ground cables and underground pipelines, and large traffic flow on existing roads. Traditional construction techniques such as excavation (with support or without support), jacking, and traction pipes have limitations and no longer meet existing construction conditions.
[0003] A small rotary underground pipe jacking device disclosed in announcement number CN202510838U belongs to underground pipe jacking device. It is mainly suitable for jacking of trenchless underground pipes. It includes a fixing mechanism, an electric screw propulsion device installed at the front end of the fixing mechanism, an electric control box for controlling the electric screw propulsion device, a jacking pipe connected to the output shaft of the electric screw propulsion device, and a threaded top installed at the front end of the jacking pipe; the jacking pipe is composed of a short jacking pipe and a long jacking pipe detachably connected thereto; it also includes a water tank, a micro-electric pressurized water supply device, and a water supply pipe led out of the micro-electric pressurized water supply device, and the water outlet end of the water supply pipe is connected to the threaded top. The beneficial effects are: the equipment is simple and easy to operate; it solves the problem of not needing to dig large preparatory pits and damage the road surface when laying new pipelines in campuses, factories, and communities.
[0004] In the prior art, an electric spiral propulsion device is used to drive the top pipe and the embedded pipe to spirally propel the soil, thereby excavating the soil. However, in the actual excavation process, since most of the construction sites are sandy silt layers with abundant groundwater, and in the construction process, they are all driven by motors. During the pushing process, water in the soil may be sprayed and splashed onto the motor, causing the motor to short-circuit. In severe cases, leakage may occur, endangering the safety of construction workers. In addition, most working wells use a disposable reinforced concrete structure, which not only has a long production cycle, but also increases the construction cost. Summary of the invention
[0005] The purpose of the present invention is to provide a micro-pipe jacking construction equipment and process for narrow road sections to solve the following technical problems:
[0006] (1) How to optimize the driving mode of micro-pipe jacking;
[0007] (2) How to reduce the construction cost of the working well.
[0008] The purpose of the present invention can be achieved through the following technical solutions:
[0009] A micro-pipe jacking construction device for narrow road sections, comprising a support base and a steel working well, and also comprising:
[0010] The main drive compartment is set on the support base and is used for jacking work;
[0011] A driving assembly is arranged in the main driving compartment and is used to drive the jacking pipe to rotate;
[0012] A connecting assembly, disposed on the supporting base, and used for connecting with the driving assembly;
[0013] The hydraulic column is arranged on one side of the main driving compartment and is used to drive the horizontal movement of the main driving compartment.
[0014] Furthermore, baffles are fixedly connected at both ends of the support base; one end of the hydraulic column away from the main drive compartment is fixedly connected to the side wall of the baffle; one end of the hydraulic column away from the baffle is fixedly connected to the main drive compartment; and a cushion is fixedly connected to the top of the main drive compartment.
[0015] Further, the connecting assembly includes a connecting base; the side wall of the connecting base is fixedly connected with connecting teeth; the driving assembly includes a first gear; the first gear is rotatably connected to the inner side wall of the main driving bin; the bottom of the main driving bin is rotatably connected with a telescopic column; the telescopic column is arranged through the main driving bin; a support column is slidably connected inside the telescopic column; the end of the support column away from the telescopic column is rotatably connected with a second gear; the first gear is meshingly connected with the second gear; the end of the telescopic column away from the support column is fixedly connected with a connecting gear; the connecting gear is meshingly connected with the connecting teeth; the side wall of the first gear is fixedly connected with a driving rod; the end of the driving rod away from the first gear is fixedly connected with a clamping tube; a jacking pipe head is clamped on the clamping tube.
[0016] Furthermore, a hand crank is rotatably connected to the side wall of the main drive bin; a fixed plate is fixedly connected to the top of the main drive bin; the hand crank passes through the main drive bin and the fixed plate; a rotation spring is fixedly connected to the side wall of the fixed plate; the end of the rotation spring away from the fixed plate is fixedly connected to the hand crank; a pressure rod is fixedly connected to the side of the hand crank away from the rotation spring; a pressure wheel is rotatably connected to the end of the pressure rod; a telescopic spring is fixedly connected inside the telescopic column; and the end of the telescopic spring away from the telescopic column is fixedly connected to the support column.
[0017] Furthermore, a limiting groove is provided in the middle of the connecting base; one end of the connecting gear away from the telescopic column is fixedly connected to a limiting block; and the limiting block is slidably connected in the limiting groove.
[0018] Furthermore, a water discharge hole is opened in the middle of the limit groove; the water discharge holes are arranged in multiple groups and are equidistantly arrayed in the limit groove; a top hole is opened on the side wall of the baffle plate; a monitor is arranged on the side wall of the baffle plate above the top hole; and a sensor is fixedly connected to the end of the top pipe.
[0019] Furthermore, the steel working well is made of steel material; a working hole is opened on the side wall of the steel working well; a pull hook is fixedly connected to the side wall of the steel working well; the pull hook is arranged in multiple groups; a storage rack is fixedly connected to the inner wall of the steel working well; a top pipe body is placed in the storage rack; a connecting well is movably connected to the top of the steel working well.
[0020] A micro-pipe jacking construction process for a narrow road section comprises the following steps:
[0021] S1, first conduct geological exploration and testing, and then excavate the foundation pit after completion;
[0022] S2, after the excavation is completed, the steel working shaft is installed into the foundation pit, and then the jacking equipment is installed and the operation is carried out;
[0023] S3: After the jacking reaches the end point, a series of tests such as water pressure test are carried out to ensure that the pipeline quality meets the standards;
[0024] S4: After the project is completed, the foundation pit will be filled and the surface will be restored.
[0025] Beneficial effects of the present invention:
[0026] (1) The present invention can eliminate the traditional motor by setting up the main drive compartment and the hydraulic column, so as to avoid the groundwater sprayed out during jacking causing equipment short circuit and posing danger to the workers. In addition, by setting up the drive component and the connecting component, the jacking pipe can be adjusted in coordination with the advancement of the hydraulic column to avoid the jacking pipe from deviating from its position during the movement.
[0027] (2) The present invention can reduce the cost of the working pit by setting up the steel working pit, shorten the production cycle, and the steel working pit can be recycled. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] The present invention will be further described below in conjunction with the accompanying drawings.
[0029] Figure 1 It is a schematic diagram of the overall structure of the main drive compartment in the present invention;
[0030] Figure 2 It is a schematic diagram of the overall structure of the baffle in the present invention;
[0031] Figure 3 It is a cross-sectional view of the overall structure of the connecting base in the present invention;
[0032] Figure 4 yes Figure 3 The enlarged view of point A in the middle;
[0033] Figure 5 It is a cross-sectional view of the overall structure of the center column driving bin of the present invention;
[0034] Figure 6 It is a schematic diagram of the overall structure of the driving component in the present invention;
[0035] Figure 7 It is a schematic diagram of the overall structure of the steel working well and the connecting well in the present invention;
[0036] Figure 8 It is a schematic diagram of the overall structure of the connecting well in the present invention.
[0037] Description of the drawings: 1. Support base; 2. Main drive compartment; 21. Cushion; 22. Hand crank; 23. Fixed plate; 24. Rotating spring; 25. Pressure rod; 26. Pressure wheel; 3. Connecting assembly; 31. Connecting base; 32. Drain hole; 33. Limiting groove; 34. Connecting teeth; 4. Baffle; 41. Top hole; 42. Monitor; 5. Drive assembly; 52. First gear; 53. Drive rod; 54. Card tube; 56. Second gear; 57. Telescopic column; 571. Telescopic spring; 572. Support column; 58. Connecting gear; 59. Limiting block; 6. Steel working well; 61. Working hole; 62. Draw hook; 63. Storage rack; 64. Jacking pipe body; 7. Connecting well; 8. Hydraulic column; 9. Jacking pipe head; 91. Sensor. DETAILED DESCRIPTION
[0038] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0039] See also Figure 1-Figure 8 As shown, the present application provides a micro-pipe jacking construction equipment for narrow road sections, including a support base 1 and a steel working well 6, and also includes:
[0040] The main driving compartment 2 is arranged on the supporting base 1 and is used for the jacking work;
[0041] A driving assembly 5 is arranged in the main driving compartment 2 and is used to drive the jacking pipe to rotate;
[0042] A connecting assembly 3, arranged on the supporting base 1, and used for connecting with the driving assembly 5;
[0043] A hydraulic column 8 is provided at one side of the main driving compartment 2 and is used to drive the horizontal movement of the main driving compartment 2;
[0044] During operation, in the prior art, an electric screw driving device is used to drive the top pipe and the embedded pipe to advance spirally, thereby excavating the soil. However, in the actual excavation process, since most of the construction sites are sandy silt layers with abundant groundwater, and in the construction process, they are all driven by motors. During the pushing process, water in the soil may be sprayed, thereby splashing onto the motor, causing the motor to short-circuit. In severe cases, leakage may occur, endangering the safety of construction workers. Moreover, most working wells adopt a disposable reinforced concrete structure. This structure not only has a long production cycle, but also increases the construction cost. In order to prevent such incidents from happening, first, a steel working well 6 is installed in the foundation pit. The steel working well 6 is a rigid material. On the one hand, it can be waterproof. On the other hand, the construction is relatively convenient and can be circulated. After use, the jacking construction equipment is installed in the steel working well 6. The construction equipment includes a support base 1 and a main driving compartment 2. The support base 1 is connected to the bottom of the steel working well 6. After the connection, the jacking pipe is installed at the main driving compartment 2. The hydraulic column 8 is used to drive the main driving compartment 2 and the jacking pipe to perform jacking work. During the jacking process, the jacking pipe may be offset. At this time, the angle of the jacking pipe can be adjusted by setting the driving component 5 and the connecting component 3. The traditional motor can be eliminated by setting the main driving compartment 2 and the hydraulic column 8 to avoid the groundwater sprayed during jacking causing equipment short circuit and causing danger to the staff. In addition, the driving component 5 and the connecting component 3 can be set to cooperate with the advancement of the hydraulic column 8 to adjust the jacking pipe to avoid deviation from its position during movement.
[0045] like Figure 1 and Figure 2 As shown, the two ends of the support base 1 are fixedly connected with baffles 4; the end of the hydraulic column 8 away from the main drive compartment 2 is fixedly connected to the side wall of the baffle 4; the end of the hydraulic column 8 away from the baffle 4 is fixedly connected to the main drive compartment 2; the top of the main drive compartment 2 is fixedly connected with a cushion 21;
[0046] During operation, the worker can sit on the cushion 21 on the main driving compartment 2 and be driven by the hydraulic column 8 to perform jacking work.
[0047] like Figure 3-Figure 6As shown, the connecting assembly 3 includes a connecting base 31; the side wall of the connecting base 31 is fixedly connected with a connecting tooth 34; the driving assembly 5 includes a first gear 52; the first gear 52 is rotatably connected to the inner side wall of the main driving compartment 2; the bottom of the main driving compartment 2 is rotatably connected with a telescopic column 57; the telescopic column 57 is arranged throughout the main driving compartment 2; a support column 572 is slidably connected in the telescopic column 57; the end of the support column 572 away from the telescopic column 57 is rotatably connected with a second gear 56; the first gear 52 is meshed with the second gear 56; the end of the telescopic column 57 away from the support column 572 is fixedly connected with a connecting gear 58; the connecting gear 58 is meshed with the connecting tooth 34; the side wall of the first gear 52 is fixedly connected with a driving rod 53; the end of the driving rod 53 away from the first gear 52 is fixedly connected with a clamping tube 54; the clamping tube 54 is clamped with a jacking head 9;
[0048] During operation, when the hydraulic column 8 drives the main driving chamber 2 to perform the pushing work, if the jacking head 9 is found to be offset, the driving assembly 5 can be used to adjust the jacking head 9. When adjustment is needed, the main driving chamber 2 is driven to move, and the connecting gear 58 at the bottom can be driven to move during the movement. When the connecting gear 58 moves, it is driven by the connecting teeth 34 connected to the side wall of the base 31 to rotate, and the rotation drives the telescopic column 57 to rotate. When the telescopic column 57 rotates, it will drive the support column 572 to rotate, thereby driving the second gear 56 to rotate, and then the first gear 52 is driven to rotate through the second gear 56, thereby driving the driving rod 53 on the first gear 52 and the jacking head 9 to rotate. The jacking head 9 is set as an inclined surface, and the angle can be adjusted during rotation to avoid offset.
[0049] like Figure 5 and Figure 6 As shown, the side wall of the main driving compartment 2 is rotatably connected with a hand crank 22; the top of the main driving compartment 2 is fixedly connected with a fixing plate 23; the hand crank 22 passes through the main driving compartment 2 and is arranged on the fixing plate 23; the side wall of the fixing plate 23 is fixedly connected with a rotation spring 24; the end of the rotation spring 24 away from the fixing plate 23 is fixedly connected to the hand crank 22; the side of the hand crank 22 away from the rotation spring 24 is fixedly connected with a pressure rod 25; the end of the pressure rod 25 is rotatably connected with a pressure wheel 26; a telescopic spring 571 is fixedly connected inside the telescopic column 57; the end of the telescopic spring 571 away from the telescopic column 57 is fixedly connected to the support column 572;
[0050] When the main drive chamber 2 is in operation, the second gear 56 is disconnected from the first gear 52 and the second gear 56 is engaged with the first gear 52. When the main drive chamber 2 is in operation, the second gear 56 is disconnected from the first gear 52 and the second gear 56 is engaged with the first gear 52. When the main drive chamber 2 is in operation, the second gear 56 is disconnected from the first gear 52 and the second gear 56 is engaged with the first gear 52.
[0051] like Figure 3 As shown, a limiting groove 33 is provided in the middle of the connecting base 31; one end of the connecting gear 58 away from the telescopic column 57 is fixedly connected to a limiting block 59; and the limiting block 59 is slidably connected in the limiting groove 33;
[0052] During operation, when moving, the limiting groove 33 and the limiting block 59 can prevent the connecting gear 58 from being offset, thereby affecting the rotation of the driving second gear 56 .
[0053] like Figure 3 As shown, a water discharge hole 32 is provided in the middle of the limit groove 33; the water discharge holes 32 are provided in multiple groups and are arranged in an equidistant array in the limit groove 33; a top hole 41 is provided on the side wall of the baffle plate 4; a monitor 42 is provided on the side wall of the baffle plate 4 above the top hole 41; and a sensor 91 is fixedly connected to the end of the top pipe;
[0054] During operation, groundwater may spray onto the connecting base 31 during the jacking process. The water in the connecting base 31 can be discharged through the drain hole 32 to prevent groundwater from remaining on the connecting base 31. The jacking head 9 is provided with a sensor 91. The sensor 91 and the monitor 42 can be used to locate and monitor the pipeline jacking posture and position in real time.
[0055] like Figure 7 and Figure 8 As shown, the steel working well 6 is made of steel material; a working hole 61 is opened on the side wall of the steel working well 6; a hook 62 is fixedly connected to the side wall of the steel working well 6; the hook 62 is provided in multiple groups; a rack 63 is fixedly connected to the inner wall of the steel working well 6; a top pipe body 64 is placed in the rack 63; a connecting well 7 is movably connected to the top of the steel working well 6;
[0056] During operation, the working well of the steel material can be recycled and is easy to install. After the steel working well 6 is placed in the foundation pit through the hook 62, the jacking work begins. Multiple sets of jacking pipes are needed during work. The jacking pipe body 64 can be taken through the rack 63, and whether to install the connecting well 7 can be selected according to the depth of the foundation pit.
[0057] See also Figure 1-Figure 8 As shown, the present application provides a micro-pipe jacking construction process for narrow road sections, comprising the following steps:
[0058] S1, first conduct geological exploration and testing, and then excavate the foundation pit after completion;
[0059] S2, after the excavation is completed, the steel working well 6 is installed into the foundation pit, and then the jacking equipment is installed and the operation is carried out;
[0060] S3: After the jacking reaches the end point, a series of tests such as water pressure test are carried out to ensure that the pipeline quality meets the standards;
[0061] S4: After the project is completed, the foundation pit will be filled and the surface will be restored.
[0062] When working, before the operation, the geology is first explored, and then the soil mechanical properties are tested. After the test is completed, BIM is combined with the site to realize ultrasonic monitoring, and the pre-established model is reflected in the model in real time in 3D. After completion, the foundation pit is excavated. After the excavation is completed, the steel working shaft 6 is installed into the foundation pit, and then the jacking equipment is installed inside and fixed. After the fixation is completed, the main driving compartment 2 is driven to perform jacking operations. When the jacking reaches the end point, the end pipeline is connected to the existing pipeline, and the pipeline is subjected to water pressure test and function test to ensure that the quality of the pipeline meets the standards. Finally, the foundation pit is filled and the surface is restored to its original state.
[0063] Working principle of the present invention: In the prior art, an electric spiral propulsion device is used to drive the top pipe and the embedded pipe to spirally propel the soil, thereby excavating the soil. However, in the actual excavation process, since most of the construction sites are sandy silt layers with abundant groundwater, and in the construction process, they are all driven by motors. During the pushing process, water in the soil may be sprayed and splashed onto the motor, causing the motor to short-circuit. In severe cases, leakage may occur, endangering the safety of construction workers. Moreover, most working wells adopt a disposable reinforced concrete structure. This structure not only has a long production cycle, but also increases the construction cost. In order to prevent such incidents from happening, first, a steel working well 6 is installed in the foundation pit. The steel working well 6 is a rigid material. On the one hand, it can be waterproof. On the other hand, the construction is relatively convenient and can be carried out. Recycling, after installation is completed, the jacking construction equipment is installed in the steel working shaft 6. The construction equipment includes a support base 1 and a main driving compartment 2. The support base 1 is connected to the bottom of the steel working shaft 6. After connection, the jacking pipe is installed at the main driving compartment 2, and the hydraulic column 8 is used to drive the main driving compartment 2 and the jacking pipe to perform jacking work. During the jacking process, the jacking pipe may be offset. At this time, the angle of the jacking pipe can be adjusted by setting the driving component 5 and the connecting component 3. The traditional motor can be eliminated by setting the main driving compartment 2 and the hydraulic column 8 to avoid groundwater spraying during jacking causing equipment short circuit and causing danger to the staff. In addition, the driving component 5 and the connecting component 3 can be set to cooperate with the advancement of the hydraulic column 8 to adjust the jacking pipe to avoid deviation from its position during movement.
[0064] Among them, the working well of steel materials can be recycled and is easy to install. After the steel working well 6 is placed in the foundation pit through the hook 62, the jacking work begins. Multiple sets of jacking pipes are needed during the work. The jacking pipe body 64 can be taken through the rack 63, and whether to install the connecting well 7 can be selected according to the depth of the foundation pit.
[0065] The above is a detailed description of an embodiment of the present invention, but the content is only a preferred embodiment of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.
Claims
1. A micro-pipe jacking construction device for narrow road sections, comprising a support base (1) and a steel working well (6), It is characterized in that Also includes: A main drive compartment (2) is arranged on the support base (1) and is used for performing jacking work; A driving assembly (5) is arranged in the main driving compartment (2) and is used to drive the jacking pipe to rotate; A connecting assembly (3) is arranged on the supporting base (1) and is used for connecting to the driving assembly (5); A hydraulic column (8) is arranged on one side of the main driving compartment (2) and is used to drive the horizontal movement of the main driving compartment (2).
2. A micro pipe jacking construction equipment for narrow road sections according to claim 1, It is characterized in that The two ends of the support base (1) are fixedly connected to baffles (4); one end of the hydraulic column (8) away from the main drive compartment (2) is fixedly connected to the side wall of the baffle (4); one end of the hydraulic column (8) away from the baffle (4) is fixedly connected to the main drive compartment (2); and a cushion (21) is fixedly connected to the top of the main drive compartment (2).
3. The micro-pipe jacking construction equipment for narrow road sections according to claim 2, It is characterized in that The connecting assembly (3) comprises a connecting base (31); a connecting tooth (34) is fixedly connected to a side wall of the connecting base (31); the driving assembly (5) comprises a first gear (52); the first gear (52) is rotatably connected to an inner side wall of a main driving compartment (2); a telescopic column (57) is rotatably connected to the bottom of the main driving compartment (2); the telescopic column (57) is arranged to penetrate the main driving compartment (2); a support column (572) is slidably connected to the inside of the telescopic column (57); the support column (572) is away from the telescopic column (57). One end of the telescopic column (57) is rotatably connected to a second gear (56); the first gear (52) is meshingly connected to the second gear (56); one end of the telescopic column (57) away from the support column (572) is fixedly connected to a connecting gear (58); the connecting gear (58) is meshingly connected to the connecting teeth (34); a driving rod (53) is fixedly connected to the side wall of the first gear (52); one end of the driving rod (53) away from the first gear (52) is fixedly connected to a clamping tube (54); a jacking head (9) is clamped on the clamping tube (54).
4. The micro-pipe jacking construction equipment for narrow road sections according to claim 3, It is characterized in that A hand crank (22) is rotatably connected to the side wall of the main drive bin (2); a fixed plate (23) is fixedly connected to the top of the main drive bin (2); the hand crank (22) passes through the main drive bin (2) and the fixed plate (23); a rotation spring (24) is fixedly connected to the side wall of the fixed plate (23); an end of the rotation spring (24) away from the fixed plate (23) is fixedly connected to the hand crank (22); a pressure rod (25) is fixedly connected to the side of the hand crank (22) away from the rotation spring (24); a pressure wheel (26) is rotatably connected to the end of the pressure rod (25); a telescopic spring (571) is fixedly connected inside the telescopic column (57); an end of the telescopic spring (571) away from the telescopic column (57) is fixedly connected to the support column (572).
5. The micro-pipe jacking construction equipment for narrow road sections according to claim 4, It is characterized in that A limiting groove (33) is provided in the middle of the connection base (31); one end of the connection gear (58) away from the telescopic column (57) is fixedly connected to a limiting block (59); and the limiting block (59) is slidably connected in the limiting groove (33).
6. The micro-pipe jacking construction equipment for narrow road sections according to claim 5, It is characterized in that A water discharge hole (32) is provided in the middle of the limiting groove (33); a plurality of water discharge holes (32) are arranged in an array in the limiting groove (33) at equal intervals; a top hole (41) is provided on the side wall of the baffle plate (4); a monitor (42) is provided on the side wall of the baffle plate (4) above the top hole (41); and a sensor (91) is fixedly connected to the end of the top pipe.
7. A micro pipe jacking construction equipment for narrow road sections according to any one of claims 1 to 6, It is characterized in that The steel working well (6) is made of steel material; a working hole (61) is opened on a side wall of the steel working well (6); a draw hook (62) is fixedly connected to the side wall of the steel working well (6); a plurality of draw hooks (62) are provided; a storage rack (63) is fixedly connected to the inner wall of the steel working well (6); a top pipe body (64) is placed in the storage rack (63); and a connecting well (7) is movably connected to the top of the steel working well (6).
8. A micro-pipe jacking construction process for narrow road sections. It is characterized in that The following steps are involved: S1, first conduct geological exploration and testing, and then excavate the foundation pit after completion; S2, after the excavation is completed, the steel working well (6) is installed into the foundation pit, and then the jacking equipment is installed and the operation is carried out; S3: After the jacking reaches the end point, a series of tests such as water pressure test are carried out to ensure that the pipeline quality meets the standards; S4: After the project is completed, the foundation pit will be filled and the surface will be restored.