Connecting device for side span box girder and pier of river-crossing bridge and construction method of connecting device
By using connecting steel frames, press plates, abutment brackets, rollers and balance components in bridge connections, the problem of midline deviation caused by thermal expansion and contraction of box girders is solved, and efficient docking and stable connection between bridge box girders and bridge piers is achieved. Shortened the construction period.
Patent Information
- Application Number
- CN202411040477.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-31
- Publication Date
- 2024-11-26
AI Technical Summary
In the prior art, thermal expansion and contraction of bridge box girders during temperature changes in day and night leads to a midline deviation, affecting the construction period and the stability of the connecting components.
A connecting device for the side span box girder and piers of the river bridge is designed, including connecting steel frames, press plates, abutment brackets, rollers, balance components and laser rangefinders, through which the thermal expansion and contraction of the box girder are reduced. The resulting deviation ensures the accuracy of the butt of the box girder and the bridge piers, and is balanced and corrected by a laser rangefinder and counterweight tank.
It effectively reduces the deviation adjustment workload when connecting the box girder and the bridge pier, shortens the construction period, and ensures the stability and accuracy of the connecting components, avoiding the impact of thermal expansion and contraction on cast-in-place and reinforcement ribs.
Smart Images

Figure CN119021096A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of side span pier connection, and in particular to a connection device for a side span box girder and a pier of a river-crossing bridge and a construction method thereof. Background Art
[0002] The side span pier connection refers to the construction of the box girder on the middle span pier to be connected with the side span pier after the construction is completed.
[0003] The existing methods are to build a docking box girder on the side span pier in advance, and then connect it to the box girder on the middle span pier through reinforcing members, and then cast it in situ. However, when performing cast-in-situ construction and connection, the construction period is long, and the box girder is prone to thermal expansion and contraction when the temperature is high during the day and night, which causes the box girder to deviate from the center line of the docking box girder, which affects the direct cast-in-situ and reinforcement connection between the two and affects the construction period. Summary of the invention
[0004] The object of the present invention is to provide a connecting device and a construction method for a side span box girder of a river-crossing bridge and a pier, so as to solve the problem that when the box girder on the middle span pier is connected with the butt-jointed box girder on the side span pier, the center lines of the two may deviate and become unable to align due to the thermal expansion and contraction of the box girder, thus affecting the construction of the connecting components and cast-in-place of the two.
[0005] The embodiments of the present invention are implemented by the following technical solutions:
[0006] The present invention provides a connecting device for a side span box girder and a pier of a river-crossing bridge and a construction method thereof, comprising a pier, a box girder is arranged on one side of the top of the pier, a side span pier is arranged on one side of the pier, a connecting steel frame is arranged at one end of the box girder close to the side span pier, a pressure plate is connected to the top of one end of the connecting steel frame, abutment brackets are arranged on both sides of one end of the connecting steel frame, rollers are connected to the upper and lower sides of one end of the connecting steel frame, and a balancing assembly is arranged near the top of both ends of the box girder.
[0007] Preferably, the pressing plate further includes a tension rod, and the tension rod is arranged to penetrate the pressing plate.
[0008] Preferably, one end of the tie rod away from the pressure plate is connected to the top of the side span pier.
[0009] Preferably, rollers connecting the upper and lower sides of the steel frame are respectively attached to the bottom of the pressure plate and the top of the side span pier.
[0010] Preferably, the connecting steel frames are arranged to be close to and fit toward the center.
[0011] Preferably, the abutment bracket is arranged on both sides of one end of the connecting steel frame, and the upper and lower ends of the abutment bracket are respectively connected to the top of the pressure plate and the side span pier.
[0012] Preferably, the connecting steel frame further comprises a limiting block, which is a protrusion on the upper and lower sides of one end of the connecting steel frame that is close to and fits with the length of the roller.
[0013] Preferably, the balancing assembly includes a counterweight water tank and a laser rangefinder. The counterweight water tank is arranged at the top of the box beam near both ends, and the laser rangefinder is arranged at the bottom of the box beam near both ends.
[0014] Preferably, a discharge valve controlled by an electrical wire is provided on one side of the counterweight water tank.
[0015] The technical solution of the embodiment of the present invention has at least the following advantages and beneficial effects:
[0016] 1. The connecting steel frame provided in the device can reduce the construction of the butt-jointed box beams on the side span piers, and can also avoid the increase in workload caused by the deviation between the box beams and the butt-jointed box beams, making it difficult to connect and adjust the components when the two are directly connected.
[0017] 2. The device is also equipped with a balancing component, which enables the box girder to detect the distance from the ground surface through a laser rangefinder when it is connected to the steel frame due to thermal expansion and contraction, and then discharge the counterweight water tank to enable the two ends of the box girder to be balanced and corrected. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.
[0019] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0020] Figure 2 For the present invention Figure 1 A schematic diagram of the enlarged structure at A in the middle;
[0021] Figure 3 It is a front view structural schematic diagram of the connecting steel frame of the present invention;
[0022] Figure 4 It is a schematic diagram of the top view of the structure of the connecting steel frame of the present invention;
[0023] Figure 5It is a partial front view structural schematic diagram of the box girder and the connecting steel frame of the present invention;
[0024] Icons: pier 1, box girder 101, side span pier 2, connecting steel frame 3, pressure plate 301, tension rod 3011, roller 302, abutment bracket 303, limit block 304, counterweight water tank 4, laser rangefinder 401. DETAILED DESCRIPTION
[0025] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0026] Combine the following Figures 1 to 5 The present invention is described in detail.
[0027] A device for connecting a side span box girder and a pier of a river-crossing bridge and a construction method thereof, comprising a pier 1, a box girder 101 is arranged on one side of the top of the pier 1, a side span pier 2 is arranged on one side of the pier 1, a connecting steel frame 3 is arranged on one end of the box girder 101 close to the side span pier 2, a pressure plate 301 is connected to the top of one end of the connecting steel frame 3, abutment brackets 303 are arranged on both sides of one end of the connecting steel frame 3, rollers 302 are connected to the upper and lower sides of one end of the connecting steel frame 3, and a balancing assembly is arranged near the top of both ends of the box girder 101.
[0028] First, the box girder 101 is gradually built on one side of the pier 1 to complete the construction of the bridge. Then, when the box girder 101 is built close to the side span pier 2, a connecting steel frame 3 is extended at one end of the box girder 101 close to the side span pier 2, and then the end of the connecting steel frame 3 close to the side span pier 2 is extended to the top of the side span pier 2, and then the pressure plate 301 is connected to the top of one end of the connecting steel frame 3 through the tension rod 3011 at the top of the side span pier 2, and then the upper and lower sides of one end of the connecting steel frame 3 are limited by the limit blocks 304 to limit the connecting rollers 302, and the rollers 302 on the upper and lower sides are respectively fitted with the bottom of the pressure plate 301 and the top of the side span pier 2, so that the pressure plate 301 can press one end of the connecting steel frame 3, so that the box girder 101 will not shake up and down due to thermal expansion and contraction.
[0029] Furthermore, the pressure plate 301 also includes a tension rod 3011, which is arranged to pass through the pressure plate 301, and the end of the tension rod 3011 away from the pressure plate 301 is connected to the top of the side span pier 2, and the rollers 302 on the upper and lower sides of the connecting steel frame 3 are respectively fitted on the bottom of the pressure plate 301 and the top of the side span pier 2, and the connecting steel frame 3 is arranged to be inclined and close to the center, and the abutment bracket 303 is fitted on both sides of one end of the connecting steel frame 3, and the upper and lower ends of the abutment bracket 303 are respectively connected to the pressure plate 301 and the top of the side span pier 2, and the connecting steel frame 3 also includes a limit block 304, which is a protrusion on the upper and lower sides of one end of the connecting steel frame 3 that is close to the fit and matches the length of the roller 302.
[0030] At the same time, the bottom of the pressure plate 301 is connected to the support bracket 303, and the support bracket 303 is attached to both sides of one end of the connecting steel frame 3 to limit the two sides of the connecting steel frame 3 so that it will not shake left and right due to thermal expansion and contraction. Because of the contact setting of the roller 302, the connecting steel frame 3 can expand and contract forward and backward to release the changes of the connecting steel frame 3 caused by thermal expansion and contraction, and will not be squeezed and damaged due to forced limitation. Then, the connecting steel frame 3 is cast in place based on the connecting steel frame 3 to complete the docking connection with the side span pier 2, so that there is no need to build a docking box girder on the side span pier 2 to complete the connection with the box girder 101, which greatly reduces the construction period. At the same time, there is no need to cause deviations due to thermal expansion and contraction when aligning the box girder 101 with the docking box girder on the side span pier 2, and it is difficult to adjust the connecting components such as the tension rods and reinforcement ribs of the two.
[0031] Furthermore, the balancing assembly includes a counterweight water tank 4 and a laser rangefinder 401. The counterweight water tank 4 is arranged at the top of the box beam 101 near both ends, and the laser rangefinder 401 is arranged at the bottom of the box beam 101 near both ends. A discharge valve controlled by an electrical wire is arranged on one side of the counterweight water tank 4.
[0032] Finally, when the box girder 101 completes the setting of the connection steel frame 3, a counterweight water tank 4 will be set near the top of both ends of the box girder 101. Then, when the box girder 101 is tilted due to thermal expansion and contraction, the distance from the ground will be detected by the laser rangefinder 401, so as to control the discharge of the counterweight water tank 4 to balance the two ends of the box girder 101.
[0033] Further, the steps are as follows;
[0034] The first step is to gradually build the box beam 101 on both sides of the pier 1 until the box beam 101 is close to the side span pier 2;
[0035] In the second step, when the box girder 101 is close to the side span pier 2, a connecting steel frame 3 is extended and arranged at the four corners of the side of one end of the box girder 101 close to the side span pier 2, and then the connecting steel frames 3 are tilted and brought close to form a triangular steel frame, which is extended to the top of the side span pier 2;
[0036] In the third step, when the connecting steel frame 3 extends to the top of the side span pier 2, the pressing plate 301 is set above the end of the connecting steel frame 3 by connecting the tie rod 3011, and the roller 302 is connected between the upper and lower limit blocks 304 at one end of the connecting steel frame 3, so that the pressing plate 301 and the bottom of the side span pier 2 are supported by the roller 302, so that the pressing plate 301 can press one end of the connecting steel frame 3, so that it will not shake up and down due to the thermal expansion and contraction of the box girder 101;
[0037] In the fourth step, based on the pressing plate 301, abutting bracket 303 is arranged at the bottom of the pressing plate 301 to connect with the top of the side span pier 2, and at the same time, it will fit on both sides of one end of the connecting steel frame 3, so as to increase the stability of the pressing plate 301 and limit both sides of one end of the connecting steel frame 3, so that the box girder 101 will not shake left and right due to thermal expansion and contraction;
[0038] In the third step, the rollers 302 reduce the forward and backward movement of the box girder 101 due to thermal expansion and contraction, so that the box girder 101 can release the thermal expansion and contraction changes forward and backward, so that the pads on the bridge will only be subjected to the forward and backward force, and will not be subjected to the up and down and left and right shaking, which will cause the pads to be damaged;
[0039] The fifth step is to install steel bars and molds in the connecting steel frame 3 for cast-in-place after the connection between the connecting steel frame 3 and the side span pier 2 is completed, so as to complete the docking with the side span pier 2, thereby avoiding the box girder 101 from being unable to align with the docking box girder on the side span pier 2 due to thermal expansion and contraction during docking, thereby affecting the cast-in-place.
[0040] In the sixth step, when the box girder 101 is built and the side span pier 2 is connected, a counterweight water tank 4 will be installed near the top of both ends of the box girder 101. If the box girder 101 tilts up and down due to thermal expansion and contraction during the construction of the connecting steel frame 3, it will affect the laser rangefinder 401, measure the distance to the ground, and then discharge the counterweight water tank 4 on one side to make the weight at both ends of the box girder 101 equal to maintain balance correction.
[0041] The following is a specific implementation process of the present invention. First, a box girder 101 is gradually built on one side of the pier 1 to complete the construction of the bridge. Then, when the box girder 101 is built close to the side span pier 2, a connecting steel frame 3 is extended at one end of the box girder 101 close to the side span pier 2, and then the end of the connecting steel frame 3 close to the side span pier 2 is extended to the top of the side span pier 2. Then, a pressure plate 301 is connected to the top of one end of the connecting steel frame 3 through a tension rod 3011 at the top of the side span pier 2. Then, the upper and lower sides of one end of the connecting steel frame 3 are limited by a connecting roller 302 through a limit block 304. The rollers 302 on the upper and lower sides are respectively attached to the bottom of the pressure plate 301 and the top of the side span pier 2, so that the pressure plate 301 can press one end of the connecting steel frame 3, so that the box girder 101 will not shake up and down due to thermal expansion and contraction. At the same time, a stop block 304 is connected at the bottom of the pressure plate 301. By leaning on the bracket 303, the two sides of the connecting steel frame 3 are limited by abutting the bracket 303 against the two sides of one end of the connecting steel frame 3, so that it will not shake left and right due to thermal expansion and contraction. Because of the contact setting of the roller 302, the connecting steel frame 3 can expand and contract forward and backward to release the changes of the connecting steel frame 3 caused by thermal expansion and contraction, and will not be squeezed and damaged due to forced limitation. Then, the connecting steel frame 3 is cast in place as a basis to complete the docking connection with the side span pier 2, so that there is no need to build a docking box girder on the side span pier 2 to complete the connection with the box girder 101, which greatly reduces the construction period. At the same time, there is no need to cause deviations due to thermal expansion and contraction when aligning the box girder 101 with the docking box girder on the side span pier 2, and it is difficult to adjust the connecting components such as the tension rods and reinforcement ribs of the two.
[0042] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A device for connecting a side span box girder and a pier of a river-crossing bridge, comprising a pier (1), a box girder (101) being arranged on one side of the top of the pier (1), a side span pier (2) being arranged on one side of the pier (1), and characterized in that a connecting steel frame (3) is arranged on one end of the box girder (101) close to the side span pier (2), a pressure plate (301) is connected above one end of the connecting steel frame (3), abutment brackets (303) are arranged on both sides of one end of the connecting steel frame (3), rollers (302) are connected on the upper and lower sides of one end of the connecting steel frame (3), and a balancing assembly is arranged near the top of both ends of the box girder (101).
2. A connecting device for a side span box girder and a bridge pier of a river-crossing bridge according to claim 1, It is characterized in that The pressing plate (301) further comprises a pair of tie rods (3011), and the pair of tie rods (3011) are arranged to penetrate the pressing plate (301).
3. A connecting device for a side span box girder and a bridge pier of a river-crossing bridge according to claim 2, It is characterized in that One end of the tie rod (3011) away from the pressure plate (301) is connected to the top of the side span pier (2).
4. The connecting device for a side span box girder and a bridge pier of a river-crossing bridge according to claim 1, It is characterized in that The rollers (302) on the upper and lower sides of the connecting steel frame (3) are respectively attached to the bottom of the pressing plate (301) and the top of the side span pier (2).
5. The connecting device for a side span box girder and a bridge pier of a river-crossing bridge according to claim 1, It is characterized in that The connecting steel frame (3) is arranged to be close to and fit closely with the center.
6. The connecting device for a side span box girder and a bridge pier of a river-crossing bridge according to claim 1, It is characterized in that The abutment bracket (303) is arranged to fit on both sides of one end of the connecting steel frame (3), and the upper and lower ends of the abutment bracket (303) are respectively connected to the pressure plate (301) and the top of the side span pier (2).
7. The connecting device for a side span box girder and a bridge pier of a river-crossing bridge according to claim 1, It is characterized in that The connecting steel frame (3) further comprises a limiting block (304), wherein the limiting block (304) is a protrusion on the upper and lower sides of one end of the connecting steel frame (3) that is close to and fits with the length of the roller (302).
8. The connecting device for a side span box girder and a bridge pier of a river-crossing bridge according to claim 1, It is characterized in that The balancing assembly comprises a counterweight water tank (4) and a laser rangefinder (401); the counterweight water tank (4) is arranged at the top of the box beam (101) near both ends, and the laser rangefinder (401) is arranged at the bottom of the box beam (101) near both ends.
9. A connecting device for a side span box girder and a bridge pier of a river-crossing bridge according to claim 8, It is characterized in that A discharge valve controlled by an electrical wire is arranged on one side of the counterweight water tank (4).
10. A construction method for connecting a side span box girder and a bridge pier of a river-crossing bridge according to any one of claims 1 to 9, the steps of which are as follows; The first step is to gradually build a box girder (101) on both sides of the pier (1) until the box girder (101) is close to the side span pier (2); The second step is to extend and set a connecting steel frame (3) at the four corners of the side of one end of the box girder (101) close to the side span pier (2) when the box girder (101) is close to the side span pier (2), and then make them tilt and close to form a triangular steel frame, which extends to the top of the side span pier (2); The third step is that when the connecting steel frame (3) extends to the top of the side span pier (2), the pressing plate (301) is arranged above the end of the connecting steel frame (3) by connecting the tension rod (3011), and the roller (302) is connected between the upper and lower limit blocks (304) at one end of the connecting steel frame (3), so that the pressing plate (301) and the bottom of the side span pier (2) are fitted with the roller (302) to support it, so that the pressing plate (301) can press one end of the connecting steel frame (3) so that it will not shake up and down due to the thermal expansion and contraction of the box beam (101); In the fourth step, based on the pressing plate (301), a support bracket (303) is arranged at the bottom of the pressing plate (301) to connect with the top of the side span pier (2), and at the same time, it will fit on both sides of one end of the connecting steel frame (3), so as to increase the stability of the pressing plate (301) and limit both sides of one end of the connecting steel frame (3), so that the box beam (101) will not shake left and right due to thermal expansion and contraction; In the third step, the rollers (302) are arranged to reduce the forward and backward movement of the box beam (101) due to thermal expansion and contraction, so that the box beam (101) can release the change of thermal expansion and contraction forward and backward, so that the pads on the bridge are only subjected to the forward and backward force, and will not be subjected to the up and down and left and right shaking, which will cause the pads to be damaged; Step 5: After the connection between the connecting steel frame (3) and the side span pier (2) is completed, the connecting steel frame (3) is directly used as a basis to set up steel bars and molds in the connecting steel frame (3) for cast-in-place, so that it can be connected with the side span pier (2) to avoid the box girder (101) being unable to align with the connecting box girder on the side span pier (2) due to thermal expansion and contraction during the connection, resulting in deviation and affecting the cast-in-place. In the sixth step, when the box girder (101) is completed and the side span pier (2) is connected, a counterweight water tank (4) is respectively arranged at the top of the box girder (101) near both ends. If the box girder (101) tilts up and down due to thermal expansion and contraction during the construction of the connecting steel frame (3), it will affect the laser rangefinder (401) to measure the distance to the ground, and then discharge the counterweight water tank (4) on one side, so that the weight at both ends of the box girder (101) is equal to maintain balance correction.