Concrete composite floor warehouse top equipment and steel structure installation construction method
By installing embedded support and mechanical equipment in advance during the construction of the combined floor slab, the problems of inaccurate installation positioning and long construction cycle of the warehouse roof equipment and steel structures in the existing technology are solved, and more efficient installation process and cost savings are achieved. .
Patent Information
- Application Number
- CN202411330765.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-24
- Publication Date
- 2024-11-26
AI Technical Summary
In the existing construction methods, the installation of mechanical equipment and steel structures on the roof of the concrete reservoir of industrial buildings has problems such as inaccurate positioning, long construction cycle and high cost, especially when the position of the embedded parts is offset and the elevation changes, which affects the overall installation quality. and process flow.
During the construction of the combined floor slab, mechanical equipment and steel structures are installed in advance through welding of embedded support and synchronous nail welding to ensure positioning accuracy, and centralized lifting is used for large cranes to shorten the construction cycle and reduce costs.
It improves the positioning accuracy of mechanical equipment and steel structure installation, shortens the construction cycle, saves construction costs, reduces later rectification items, and reduces crane costs, especially suitable for high-reservoir projects.
Smart Images

Figure CN119021480A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of industrial building construction, and in particular to a concrete composite floor slab roof equipment and a steel structure installation construction method. Background Art
[0002] Over the past thirty years, with the development of my country's building structure design and construction technology, more and more industrial building concrete storage tanks have adopted corrugated steel plates and reinforced concrete composite floor slabs. However, in order to meet the needs of production processes, it is necessary to install process production machinery and steel structures on the top of the tank. The existing construction method is to install machinery and steel structures after the construction of the composite floor slab is completed and the concrete curing period expires. The entire construction period is long, and there is a risk of inaccurate positioning of machinery and steel structures due to the offset of the embedded parts. Summary of the invention
[0003] The purpose of the present invention is to provide a method for installing roof equipment and steel structures of a concrete composite floor slab in response to the above-mentioned problems, improve the traditional construction technology for installing roof mechanical equipment and steel structures, and adopt a method of installing mechanical equipment and steel structures during the construction of the composite floor slab, thereby improving the accuracy of the installation and positioning of mechanical equipment and steel structures, and saving construction time and construction costs.
[0004] The technical solution of the present invention is as follows:
[0005] A concrete composite floor slab roof equipment and steel structure installation construction method, comprising the following steps:
[0006] Installation of steel beams on the roof of the warehouse and laying of corrugated steel plates;
[0007] Install mechanical equipment and embedded steel structure supports according to the process layout drawing and fix them to the steel beams on the roof by welding;
[0008] Install mechanical equipment and steel structures, and perform stud welding;
[0009] Rebar laying, concrete pouring and maintenance, and waterproofing layer construction.
[0010] Furthermore, the embedded support is manufactured by the following steps:
[0011] According to the dimensions of the drawings, as well as the loads of mechanical equipment and steel structures, the original embedded parts are modified by welding channel steel behind the steel plate, or directly using finished steel sections, with the length, width and height dimensions remaining unchanged.
[0012] Furthermore, the embedded supports are directly welded to the steel beams on the roof of the warehouse by arranging the installation positions according to drawings.
[0013] Furthermore, the stud welding is performed simultaneously with the installation of the embedded support, or the stud welding is performed after the mechanical equipment and the steel structure are installed.
[0014] Furthermore, the mechanical equipment and steel structure are installed on the embedded support by means of a large crane mechanical equipment and steel structure for hoisting the main beam of the warehouse roof.
[0015] Furthermore, the embedded support is in the form of a steel plate and a steel section or a finished steel section.
[0016] Furthermore, the mechanical equipment includes dust collectors and fans as well as other process production equipment designed in drawings and steel structure installation.
[0017] Compared with the prior art, the present invention has the following beneficial effects:
[0018] 1. A method for installing equipment and steel structure on the roof of a concrete composite floor greatly shortens the overall construction period of the roof. Mechanical equipment and steel structure installation are carried out in advance. Stud welding and steel bar laying can be carried out simultaneously, or after the equipment and steel structure installation are completed. The installation construction team does not need to wait for the civil construction team to complete the work, and the cleaning of embedded parts and foundation safety procedures are reduced.
[0019] 2. A method for installing equipment and steel structures on the roof of a concrete composite floor slab improves the positioning accuracy of the equipment and steel structure installation, which is conducive to ensuring the overall installation quality and reduces the later rectification items. The equipment and steel structure are fixed in place in advance, and the position displacement and elevation change of the equipment and steel structure will not be caused during concrete pouring;
[0020] 3. A method for installing and constructing equipment and steel structures on the roof of a concrete composite floor, which saves construction costs. Large cranes used for lifting mechanical equipment and steel structures and lifting the main beams on the roof are used in a concentrated and continuous manner, saving crane shift costs and secondary site costs, especially for multi-storage projects, which can further reduce crane costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 The present invention is a flow chart of a method for installing and constructing equipment and steel structure on top of a concrete composite floor slab. DETAILED DESCRIPTION
[0022] It should be noted that relational terms such as "first" and "second" are used only to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0023] The features and performance of the present invention are further described in detail below in conjunction with the embodiments.
[0024] The installation of mechanical equipment and steel structure on the roof of the composite floor is usually carried out after the overall construction of the composite floor is completed, and then the mechanical equipment and steel structure are installed, and finally the waterproof layer is constructed. The specific construction process is as follows:
[0025] Laying of steel beams and corrugated steel plates on the roof; laying of steel bars and arrangement of embedded parts; pouring of concrete; concrete maintenance; cleaning of embedded parts and foundation installation; installation of roof equipment and steel structures; and construction of waterproof layers.
[0026] Years of on-site construction practice have found that the existing construction methods have the following deficiencies:
[0027] 1. The overall construction period is long. The construction process is carried out step by step. Since the welding of bolts, the arrangement of embedded parts, and the curing of concrete require a long construction time, the installation of equipment and steel structures must wait until the concrete strength meets the requirements before construction can begin. The waterproof layer construction can also be carried out after all mechanical equipment and steel structures are installed, otherwise it will affect the overall waterproof quality. The installation construction team and the civil construction team cannot work continuously.
[0028] 2. There is a risk of inaccurate installation and positioning of equipment and steel structures or an increase in the risk of subsequent rectification matters. During the concrete pouring process, it is very easy to cause the position of embedded parts to shift, the elevation to change or tilt. The equipment and steel structures cannot be positioned and installed according to the drawings, which will affect the entire production process and require rectification of embedded steel plates or equipment and steel structures, increasing additional workload.
[0029] 3. High construction cost. The height of the concrete storage tank is generally more than 40 meters. The installation of the top equipment and steel structure is limited by the location and height. A large crane is required, but it cannot be used together with the combined floor slab main beam crane, which increases the extra crane shift cost. At the same time, due to the offset of the position of the embedded steel plate, the elevation change or tilt, the additional rectification workload is increased, and the labor and material costs are increased.
[0030] To sum up, this application improves the traditional construction technology and adopts the method of installing mechanical equipment and steel structures during the construction of composite floor slabs, ultimately achieving the goal of shortening the construction period, saving construction costs, and increasing the accuracy of equipment and steel structure installation positioning.
[0031] See also Figure 1 , a concrete composite floor slab roof equipment and steel structure installation construction method, comprising the following steps:
[0032] Installation of steel beams on the roof of the warehouse and laying of corrugated steel plates;
[0033] Install mechanical equipment and embedded steel structure supports according to the process layout drawing and fix them to the steel beams on the roof by welding;
[0034] Install mechanical equipment and steel structures, and perform stud welding at the same time;
[0035] Rebar laying, concrete pouring and maintenance, and waterproofing layer construction.
[0036] The embedded support is made through the following steps:
[0037] According to the dimensions of the drawings, as well as the loads of mechanical equipment and steel structures, the original embedded parts are modified by welding channel steel behind the steel plate, or directly using finished steel sections, with the length, width and height dimensions remaining unchanged.
[0038] The embedded supports are high in strength, and the process equipment can be directly placed and fixed on the supports. The installation work can be carried out in advance without waiting for concrete pouring. The embedded parts are usually steel plates and anchor steel bars, and they can reach the required strength only after concrete pouring. The embedded supports have been welded to the steel beams of the composite floor slabs, and pouring concrete will not cause positional and elevation offsets, thereby not affecting the positioning of the process equipment. The cleaning of embedded parts and foundation safety work are reduced.
[0039] The embedded supports are installed at the positions arranged according to the drawings and are directly welded to the steel beams on the roof.
[0040] The stud welding is carried out simultaneously with the installation of the embedded supports, or the stud welding is carried out after the installation of mechanical equipment and steel structures.
[0041] The mechanical equipment and steel structure are installed on the embedded supports by a large crane that lifts the main beam of the warehouse roof.
[0042] The embedded supports are in the form of steel plates and steel sections or finished steel sections.
[0043] Mechanical equipment includes dust collectors and fans as well as other process production equipment designed in drawings, and steel structure installation.
[0044] In another specific embodiment of the present application, in order to further understand the content, characteristics and effects of the present invention, a cement warehouse workshop of a certain project is taken as an example. The workshop has a total of 4 cement storage tanks, with a height of 48m and a diameter of 20m. The roof of the warehouse is a composite floor of corrugated steel plate and reinforced concrete. Dust collectors, fans, steel structures, etc. need to be installed on the composite floor.
[0045] 1. After the slipform of the cement storage tank wall is completed, the main beam on the top of the tank is installed and the corrugated steel plate is laid according to the traditional construction method.
[0046] 2. Fabrication of embedded supports. According to the dimensions of the design drawings, as well as the loads of the mechanical equipment and steel structures, the original embedded parts (steel plates + anchor steel bars) are modified, and channel steel is directly welded behind the steel plates, with the length, width and height dimensions remaining unchanged.
[0047] 3. Installation of embedded supports. Arrange embedded supports according to the drawings and weld them firmly to the steel beams.
[0048] 4. Installation of mechanical equipment and steel structure. Use the large crane that hoisted the main beam on the roof of the warehouse to continue hoisting the dust collector, fan and steel structure, and install and weld them to the corresponding embedded supports.
[0049] 5. Stud welding and steel bar laying. It can be carried out simultaneously with the installation of embedded supports, or after the installation of mechanical equipment and steel structure.
[0050] 6. Concrete pouring. The pouring method is consistent with the traditional construction method. After the pouring is completed, there is no displacement of mechanical equipment and steel structure.
[0051] 7. Subsequent concrete maintenance and waterproofing layer construction are consistent with traditional construction methods.
[0052] The above-mentioned embodiments only express the specific implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the protection scope of the present application. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the technical solution concept of the present application, and these all belong to the protection scope of the present application.
Claims
1. A concrete composite floor slab roof equipment and steel structure installation construction method, characterized in that: The following steps are involved: Installation of steel beams on the roof of the warehouse and laying of corrugated steel plates; Install mechanical equipment and embedded steel structure supports according to the process layout drawing and fix them to the steel beams on the roof by welding; Install mechanical equipment and steel structures, and perform stud welding at the same time; Rebar laying, concrete pouring and maintenance, and waterproofing layer construction.
2. A method for installing and constructing a concrete composite floor roof equipment and steel structure according to claim 1, characterized in that: The embedded support is manufactured by the following steps: According to the dimensions of the drawings, as well as the loads of mechanical equipment and steel structures, the original embedded parts are modified by welding channel steel behind the steel plate, or directly using finished steel sections, with the length, width and height dimensions remaining unchanged.
3. A concrete composite floor slab roof equipment and steel structure installation construction method according to claim 1 or 2, characterized in that: The embedded supports are installed at the positions arranged according to drawings and are directly welded to the steel beams on the roof of the warehouse.
4. A concrete composite floor slab roof equipment and steel structure installation construction method according to claim 3, characterized in that: The stud welding is carried out simultaneously with the installation of the embedded support, or the stud welding is carried out after the mechanical equipment and the steel structure are installed.
5. The method for installing and constructing concrete composite floor roof equipment and steel structure according to claim 1, characterized in that: The mechanical equipment and steel structure are installed on the embedded support by a large crane mechanical equipment and steel structure that hoist the main beam of the warehouse roof.
6. A concrete composite floor slab roof equipment and steel structure installation construction method according to claim 1, characterized in that: The embedded support is in the form of a steel plate and a steel section or a finished steel section.
7. A concrete composite floor slab roof equipment and steel structure installation construction method according to claim 1, characterized in that: The mechanical equipment includes dust collectors and fans as well as other process production equipment designed in drawings and steel structure installation.