Mountain city subway ventilation shaft construction method

By adopting non-blasting method and rock formation system segmentation method in the construction of Shancheng subway ventilation shaft, combined with the inverted well wall method and monitoring measures, the problems of low construction stability and efficiency are solved, and an efficient and safe construction of Shancheng subway ventilation shaft is achieved.

CN119021697APending Publication Date: 2024-11-26CHINA COMMUNICATIONS CONSTRUCTION +10
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411120185.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-15
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

In the construction of subway ventilation shafts in Shancheng area, complex terrain and geological conditions are faced, resulting in high construction risks, low efficiency, high cost, and the impact on existing buildings needs to be reduced.

Method used

The vertical shaft is divided into reinforced sections, standard sections and open sections by non-blasting method. The excavation method is selected according to the depth of the foundation pit and the geological conditions, and alternately with the shaft support during the excavation process, and the surface settlement monitoring points and levels are set. Convergence monitoring points are supported by rock strata system segmentation method and inverted well wall method, and downward construction is carried out layer by layer.

Benefits of technology

Effectively control excavation stability, improve construction efficiency, reduce construction period pressure, reduce project costs, and reduce the impact on existing buildings, and adapt to the construction needs of mountain city subway ventilation shafts in complex environments.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021697A_ABST
    Figure CN119021697A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method for a ventilation shaft of a mountain city subway. The construction method comprises the following steps: determining an excavation position on the ground; the vertical shaft is divided into a reinforcing section, a standard section and an opening section layer from top to bottom in the height direction from the excavation position and used for a non-blasting mode, different excavation methods are selected according to different foundation pit depths and geological conditions, the excavation construction process and vertical shaft supporting are circularly and alternately carried out, and layer-by-layer downward construction is carried out; horsehead construction is conducted on the opening section; and ground surface settlement monitoring points are arranged around the vertical shaft, and horizontal convergence monitoring points are arranged on the wall of the vertical shaft to monitor the vertical shaft. According to the construction method of the mountain city subway ventilation shaft, excavation stability can be effectively controlled, construction efficiency is improved, construction period pressure is relieved, engineering cost is reduced, influences on existing buildings are reduced, and therefore the construction requirements of the mountain city subway ventilation shaft in the complex environment are met.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of urban rail transit engineering construction, and in particular to a mountain city subway ventilation shaft construction method. Background Art

[0002] In the construction of urban subway systems, in order to maximize their service functions, ease ground traffic pressure, and enhance urban competitiveness, subway stations are often located in key areas with heavy traffic and dense population, such as near important public facilities and transportation hubs. These sites are usually developed after urban planning, so there are many challenges in the construction of subway facilities such as ventilation shafts, especially in mountainous areas with complex terrain.

[0003] First, the terrain in the mountain city area is undulating and the slope is steep, which not only increases the complexity of site selection and construction, but also the variability of the geological structure, including hard rock, fractured rock and unstable soil layers, also puts higher requirements on shaft excavation and support, increasing construction risks; secondly, the unique terrain and geological conditions of the mountain city require the use of special construction techniques and equipment, such as non-blasting mechanical excavation technology; in addition, considering that the mountain city area often has rich historical relics and dense residential areas, the impact on the lives of local residents and cultural relics must be minimized during construction. Summary of the invention

[0004] In view of the shortcomings of the prior art, the technical problem to be solved by the present invention is to provide a mountain city subway ventilation shaft construction method that can effectively control excavation stability, improve construction efficiency, alleviate construction period pressure, reduce project costs, and reduce the impact on existing buildings, thereby adapting to the needs of mountain city subway ventilation shaft construction in complex environments.

[0005] In order to achieve the above object, the present invention is implemented through the following technical scheme: a mountain city subway ventilation shaft construction method, comprising:

[0006] Determine the excavation location on the ground;

[0007] From the excavation position, the shaft is divided into reinforced section, standard section and opening section from top to bottom in height direction. For non-explosive methods, different excavation methods are selected according to different foundation pit depths and geological conditions. The excavation construction process is alternated with the shaft support cycle, and the construction is carried out layer by layer.

[0008] Carry out the construction of horse head door at the opening section;

[0009] Surface settlement monitoring points are set up around the shaft, and horizontal convergence monitoring points are arranged on the shaft wall to monitor the shaft.

[0010] Furthermore, it also includes constructing a ground retaining structure at the excavation location, and setting an excavation contour line at the excavation location, and the vertical shaft extends vertically downward from the excavation contour line.

[0011] Furthermore, the construction of the ground retaining structure includes: foundation pit layout and excavation, pouring of secondary lining cast-in-place reinforced concrete layer, steel bar processing and binding, formwork production and installation of the ground retaining structure, concrete pouring and maintenance, and foundation pit backfilling.

[0012] Furthermore, the excavation contour line needs to reserve 50 mm of deformation for accurate layout.

[0013] Furthermore, the excavation method is specifically as follows:

[0014] Each cycle of footage is 1 to 2 steel frame spacings. In the artificial fill area of ​​0 to 5 meters deep, the soft rock or broken rock area over 5 meters deep needs to be broken and excavated; for the hard rock layer, the rock layer system segmentation method needs to be used to separate the hard rock;

[0015] Each layer is excavated in three steps. The left and right sides are excavated first and then the middle part is constructed. In the reinforced section, the advance per cycle is 1 steel frame spacing. Blasting or large-scale mechanical excavation cannot be used in this section. In the standard section, the advance per cycle is 2 steel frame spacings.

[0016] Furthermore, the rock system segmentation method is specifically as follows:

[0017] The rock layer is divided into 1.5m×1.2m sections. A water-jet drill is used to form core holes 2 at the corners of the foundation pit and within 0.8m on the inner side for rock sampling and pretreatment. In other accessible areas, a rock saw is used to cut along the predetermined line to achieve systematic segmentation of the rock layer. Subsequently, splitting holes are drilled in the rock along the dividing seams, and the rock is further crushed and split through the splitting holes.

[0018] Furthermore, the inverted shaft wall method is adopted to support the shaft in layers during the excavation process. The specific method is: the inverted shaft wall method includes anchor construction, initial shaft support steel frame, mesh installation, welding of connecting bars and shotcrete. The anchor is installed by drilling and grouting first and then the anchor is inserted. The horizontal incident inclination angle of the anchor is 15°, and the anchor is arranged in a plum blossom shape. The initial shaft support steel frame adopts I-beam steel frame, and the reinforced section is provided with triangular inner support. The steel frame spacing of the standard section and the opening section is twice that of the reinforced section.

[0019] Furthermore, the specific construction method at the horse head gate is:

[0020] When the vertical shaft is excavated in layers to the reinforced section, three steel frames are first connected, and then the advance support construction of the advance small guide tube is carried out. After the support is completed, the vertical shaft is continued to be excavated downward in layers. When the excavation reaches the upper step of the horizontal channel, the excavation is suspended. For the upper step of the horizontal channel, the core is taken longitudinally by a water-grinding drill and then the excavation is carried out in layers. The distance of each excavation is not more than 2 steel frames. After the excavation and support of the upper step of the horizontal channel is completed, the vertical shaft is continued downward until the bottom of the vertical shaft, and then the lower step of the horizontal channel is excavated in the same way, and the initial support is done.

[0021] Furthermore, the specific method for monitoring the shaft is:

[0022] Multiple surface settlement monitoring points are set up at intervals of 2 to 5 meters around the shaft, and horizontal convergence monitoring points are arranged on the shaft wall. The long side section is taken as a monitoring section with a horizontal interval of 5m to 10m. Each monitoring section should have monitoring points in the middle of the long and short sides of the shaft structure, and each monitoring section should have no less than two measuring lines.

[0023] Furthermore, the specific method for monitoring the shaft also includes:

[0024] The optimization layout principle of the horizontal convergence monitoring points of the vertical shaft is as follows: if the single side length of the vertical shaft is less than 10m, one group of measuring points is arranged; if the single side length of the vertical shaft is 10m to 20m, two groups of measuring points are arranged; if the single side length of the vertical shaft is greater than 20m, one group of measuring points is arranged every 10m.

[0025] Beneficial effects of the present invention:

[0026] 1. During the entire excavation process, non-explosive methods are used to reduce the impact on existing buildings, thus meeting the needs of mountain city subway ventilation shaft construction in complex environments;

[0027] 2. Since the shaft is divided into reinforced section, standard section and opening section from top to bottom along the height direction, it is used for non-explosive methods. Different excavation methods are selected according to different foundation pit depths and geological conditions, which can effectively control the ground pressure balance during the construction process, reduce the disturbance to the surrounding strata, and significantly improve the safety and efficiency of the excavation operation; in addition, it can make the construction method more precise and easier to control the disturbance during the construction of the ultra-deep shaft in Shancheng, thereby improving the stability of the entire construction.

[0028] 3. During the construction process, the excavation construction process and the shaft support cycle are carried out alternately, which can improve the construction efficiency, reduce the pressure of the construction period, reduce the project cost, and reduce the impact on existing buildings, thus adapting to the construction needs of the ventilation shaft of the mountain city subway in a complex environment. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] In order to more clearly illustrate the specific implementation of the present invention, the following will briefly introduce the drawings required for use in the specific implementation. In all the drawings, each element or part is not necessarily drawn according to the actual scale.

[0030] Figure 1 It is a schematic diagram of the rock segmentation method of the mountain city subway ventilation shaft of the present invention;

[0031] Figure 2 It is a schematic diagram of the construction of the ventilation shaft of the mountain city subway of the present invention;

[0032] Figure 3 It is a schematic diagram of the lining design of the reinforced section of the mountain city subway ventilation shaft of the present invention;

[0033] Figure 4 This is a schematic diagram of the steel frame design of the reinforced section of the ventilation shaft of a mountain city subway according to the present invention;

[0034] Figure 5 It is a schematic diagram of the monitoring and measurement plane of the ventilation shaft of a mountain city subway according to the present invention;

[0035] Figure 6 It is a schematic cross-sectional diagram of monitoring and measuring of ventilation shaft of mountain city subway of the present invention;

[0036] Reference numerals:

[0037] 1. Splitting hole; 2. Coring hole; 3. Longitudinal slit; 4. Horizontal slit; 5. Rock block; 6. Locking ring beam; 7. Intercepting ditch; 8. Anchor rod; 9. Existing tunnel; 10. Temporary steel support; 11. Shaft reinforcement section; 12. Shaft standard section; 13. Shaft opening section; 14. Sprayed concrete layer; 15. I-beam; 16. Waterproof layer; 17. Secondary lining cast-in-place reinforced concrete; 18. Three connected steel frames; 19. Advance small guide tube; 20. Horizontal passage; 21. Upper step of the horizontal passage; 22. Lower step of the horizontal passage; 23. Horizontal convergence monitoring point; 24. Surface settlement monitoring point; 25. Support axial force monitoring point. DETAILED DESCRIPTION

[0038] The following embodiments of the technical solution of the present invention are described in detail in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the present invention, and are therefore only used as examples, and cannot be used to limit the protection scope of the present invention.

[0039] See also Figures 1 to 6 The present invention provides a method for constructing a ventilation shaft for a mountain city subway, comprising the following steps:

[0040] S110, determining an excavation position on the ground;

[0041] Specifically, as a preferred embodiment, after the excavation position is determined, the ground enclosure structure can be constructed at the excavation position, and an excavation contour line is set at the excavation position, and the shaft extends vertically downward from the excavation contour line. The specific construction of the ground enclosure structure includes: foundation pit lofting and excavation, pouring of the secondary lining molded reinforced concrete layer 17, steel bar processing and binding, template production and installation of the ground enclosure structure, concrete pouring and curing, and foundation pit backfilling.

[0042] Specifically, at the beginning of construction, the excavation edge line is firstly set out with the total station instrument, and then the trench is dug to construct the concrete locking ring beam 6 and its upper retaining wall, and the intercepting ditch 7 is set up to ensure the stability of the subsequent excavation work. In addition, the excavation contour line needs to reserve 50 mm of deformation for accurate setting out.

[0043] S120, from the excavation position, the shaft is divided into a reinforced section, a standard section and an open section from top to bottom in the height direction, and used for non-blasting methods. Different excavation methods are selected according to different foundation pit depths and geological conditions, and the excavation construction process is alternately carried out with the shaft support cycle, and the construction is carried out layer by layer;

[0044] S130, construct the horse head door at the opening section;

[0045] S140, setting up surface settlement monitoring points 24 around the vertical shaft, arranging horizontal convergence monitoring points 23 on the shaft wall, and monitoring the vertical shaft.

[0046] In this embodiment, the shaft excavation adopts non-explosive excavation construction. Different excavation methods are selected according to different foundation pit depths and geological conditions. Each cycle of advance is 1 to 2 steel frame spacings. In the artificial fill area with a depth of 0 to 5 meters, an excavator is directly used for excavation and manual trimming; in the soft rock or broken rock area with a depth of more than 5 meters, a pneumatic pick is used for comprehensive crushing and excavation. For hard rock formations, the rock formation system segmentation method is used to separate the hard rock.

[0047] In addition, each layer is excavated in three steps, with the left and right sides excavated first and then the middle part constructed. In the reinforced section, the advance per cycle is 1 steel frame spacing. Blasting or large-scale machinery excavation cannot be used in this section. In the standard section, the advance per cycle is 2 steel frame spacings.

[0048] In addition, the section near the existing tunnel 9 or the section with relatively broken rock formation is the shaft reinforcement section 11, and the footage per cycle is 1 steel frame spacing; the section from the end of the shaft reinforcement section 11 to 1.5 to 2.0 m above the arch of the cross passage 20 is the shaft standard section 12, and the footage per cycle of this section is 2 steel frame spacings; the remaining section is the shaft opening section 13. It should be noted that this section cannot be excavated by blasting or large-scale machinery, and can only be excavated by static excavation equipment with low disturbance, such as water-grinding drills, circular saws, splitting bars, etc.

[0049] In specific implementation, the rock formation system segmentation method is specifically as follows:

[0050] For different areas, the rock formation is divided by water-grinding core drilling or rock saw cutting technology. The rock formation is divided into 1.5m×1.2m. At the corners of the foundation pit and within 0.8 meters inside, due to space limitations, a water-grinding drill is used to form a core hole 2 for rock sampling and pretreatment. In other accessible areas, a rock saw is used to cut along the predetermined line to achieve systematic segmentation of the rock formation. It should be noted that when performing water-grinding core drilling and rock saw cutting operations, it is necessary to ensure that the working areas do not intersect. Subsequently, a splitting hole 1 is drilled in the rock along the dividing seam, and then a blasting hammer is used to further crush and split the rock through the splitting hole 1, and then it is vertically lifted to a temporary storage yard, and a blasting hammer is used to further crush large rock blocks, and then loaded and transported at night.

[0051] In this application, the inverted shaft wall method is used to support the shaft in layers during the excavation process. The specific method is as follows:

[0052] Among them, the inverted shaft wall method includes the construction of anchor rods 8, the initial support steel frame of the shaft, the installation of mesh, the welding of connecting bars and the sprayed concrete layer 14. Specifically, the anchor rods 8 are installed by drilling and driving, and the construction process of grouting first and then inserting the anchor rods 8 is adopted. The horizontal incident inclination angle of the anchor rods 8 is 15°, and the anchor rods 8 are arranged in a plum blossom shape. The length and vertical spacing of the anchor rods 8 are determined according to the actual construction situation; the initial support steel frame of the shaft adopts an I-shaped steel frame 15, and the reinforced section is provided with a triangular inner support. The steel frame spacing of the standard section and the opening section is twice that of the reinforced section. In the specific implementation, a waterproof layer 16 should also be set between the sprayed concrete layer 14 and the secondary lining molded reinforced concrete layer 17.

[0053] In the shaft reinforcement section 11, the vertical spacing of anchor rods 8 is the same as the spacing of one steel frame. No anchor rods 8 are installed on the side near the existing tunnel 9, but anchor rods 8 of about 0.5m long are installed to effectively connect with the steel frame. The excavation progress of the shaft part (reinforced section) near the existing tunnel 9 is controlled by one steel frame spacing per cycle, and the initial support and temporary triangular steel inner support 10 also need to be followed up in time. At the same time, the steel frame should be erected in a plane perpendicular to the shaft axis, and the allowable deviation of the installation position is: the support distance from the center line position is not more than 30mm, the verticality is 0.5%, the spacing between the front and rear frames is ±50mm, and the elevation accumulation is ±50mm.

[0054] In this embodiment, the specific method of constructing the horse head door is as follows:

[0055] When the vertical shaft is excavated in layers to the reinforced section, three steel frames are first connected, and then the advance support construction of the advance small guide tube 19 is carried out. After the support is completed, the vertical shaft is continued to be excavated downward in layers, and the excavation is suspended when the excavation reaches the position of the upper step 21 of the horizontal channel. For the upper step 21 of the horizontal channel, the longitudinal core is taken by a water-grinding drill and then the excavation is carried out in layers. The distance of each excavation advance does not exceed 2 steel frames. After the excavation and support of the upper step 21 of the horizontal channel is completed, the vertical shaft excavation continues downward until the vertical shaft reaches the bottom, and then the lower step 22 of the horizontal channel is excavated in the same way, and the initial support is done to complete the construction of the horse head gate.

[0056] In this embodiment, the specific method for monitoring the shaft is:

[0057] A number of surface settlement monitoring points 24 are set up around the shaft at intervals of 2 to 5 meters, and measurements are carried out using a level, a level rod, and a steel ruler. At the same time, horizontal convergence monitoring points 23 are arranged on the shaft wall, and the long side section is set at a horizontal interval of 5m to 10m as a monitoring section. Each monitoring section should be equipped with monitoring points in the middle of the long and short sides of the shaft structure, and each monitoring section should have no less than 2 measuring lines, and a convergence meter should be used for monitoring.

[0058] In addition, stress gauges, strain gauges, and axial force gauges can be set at the support axial force points 25 to monitor the support axial force to ensure the safety and reliability of the shaft construction. Furthermore, the optimization layout principle of the shaft horizontal convergence monitoring point 23 is as follows: if the length of a single side (long side or short side) of the shaft is less than 10m, a group of measuring points (2) are arranged, such as a group of measuring points (2) are arranged for each long section of the safety entrance and exit, for a total of four measuring points; if the length of a single side of the shaft is 10m to 20m, 2 groups of measuring points (4) are arranged; if the length of a single side of the shaft is greater than 20m, a group of measuring points is arranged every 10m.

[0059] The beneficial effects of the present invention are:

[0060] 1. The present invention demonstrates its adaptability to complex geology and narrow space by using water-grinding drills to coring in spatially confined areas and rock saws to systematically segment rock formations in other areas, greatly improving construction accuracy and flexibility while reducing the impact on the surrounding environment. This method is not only suitable for complex geological conditions such as sandy mudstone and sandstone interlayers, but also provides an efficient technical solution for the construction of urban ancillary structures;

[0061] 2. The present invention adopts the inverted shaft wall method to excavate the main body of the shaft in layers, especially implements a three-step skipping excavation strategy during the excavation process. This method not only effectively controls the ground pressure balance during the construction process and reduces the disturbance to the surrounding strata, but also significantly improves the safety and efficiency of the excavation operation; in addition, the segmented excavation treatment of the shaft reinforcement section 11 and the standard section 12 is helpful to implement more precise engineering control under complex geological conditions, such as near the existing tunnel 9 or broken rock formations, and is easier to control the disturbance during the construction of the mountain city ultra-deep shaft.

[0062] 3. In the construction of the horse head gate, the present invention first excavates the shaft in layers to the reinforced section 11, and implements the advanced small guide tube 19 support after three steel frames 18 are connected. This technology significantly improves the foresight and safety of the construction. After the advanced support is completed, the vertical shaft excavation is continued downward in layers, and the water-grinding drill is used to coring at the upper step 21 and the lower step 22 of the horizontal channel 20 to carry out layered splitting excavation. This measure ensures the structural stability and construction safety of the horizontal channel 20.

[0063] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein by equivalents. These modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the present invention, and they should all be included in the scope of the claims and specification of the present invention.

Claims

1. A method for constructing a ventilation shaft for a mountain city subway, characterized in that: include: Determine the excavation location on the ground; From the excavation position, the shaft is divided into reinforced section, standard section and opening section from top to bottom in height direction. For non-explosive methods, different excavation methods are selected according to different foundation pit depths and geological conditions. The excavation construction process is alternated with the shaft support cycle, and the construction is carried out layer by layer. Carry out the construction of horse head door at the opening section; Surface settlement monitoring points are set up around the shaft, and horizontal convergence monitoring points are arranged on the shaft wall to monitor the shaft.

2. The mountain city subway ventilation shaft construction method according to claim 1 is characterized in that: It also includes the construction of a ground retaining structure at the excavation location, and setting an excavation contour line at the excavation location, with the shaft extending vertically downward from the excavation contour line.

3. The mountain city subway ventilation shaft construction method according to claim 2 is characterized in that: The construction of the ground retaining structure includes: foundation pit layout and excavation, pouring of secondary lining cast-in-place reinforced concrete layer, steel bar processing and binding, ground retaining structure formwork production and installation, concrete pouring and curing, and foundation pit backfilling.

4. The mountain city subway ventilation shaft construction method according to claim 2 is characterized in that: The excavation contour line needs to reserve 50 mm of deformation for accurate layout.

5. The mountain city subway ventilation shaft construction method according to claim 1 is characterized in that: The specific excavation methods are as follows: Each cycle of footage is 1 to 2 steel frame spacings. In the artificial fill area of ​​0 to 5 meters deep, the soft rock or broken rock area over 5 meters deep needs to be broken and excavated; for the hard rock layer, the rock layer system segmentation method needs to be used to separate the hard rock; Each layer is excavated in three steps. The left and right sides are excavated first and then the middle part is constructed. In the reinforced section, the advance per cycle is 1 steel frame spacing. Blasting or large-scale mechanical excavation cannot be used in this section. In the standard section, the advance per cycle is 2 steel frame spacings.

6. The mountain city subway ventilation shaft construction method according to claim 5 is characterized in that: The rock system segmentation method is as follows: The rock layer is divided into 1.5m×1.2m sections. A water-jet drill is used to form core holes 2 at the corners of the foundation pit and within 0.8m on the inner side for rock sampling and pretreatment. In other accessible areas, a rock saw is used to cut along the predetermined line to achieve systematic segmentation of the rock layer. Subsequently, splitting holes are drilled in the rock along the dividing seams, and the rock is further crushed and split through the splitting holes.

7. The mountain city subway ventilation shaft construction method according to claim 6 is characterized in that: The inverted shaft wall method is adopted to support the shaft in layers during the excavation process. The specific method is: the inverted shaft wall method includes anchor construction, initial shaft support steel frame, mesh installation, welding of connecting bars and shotcrete. The anchor is driven by drilling method, and grouting is performed before installing the anchor. The horizontal incident inclination angle of the anchor is 15°, and the anchor is arranged in a plum blossom shape. The initial shaft support steel frame adopts I-beam steel frame, and the reinforced section is provided with triangular inner support. The steel frame spacing of the standard section and the opening section is twice that of the reinforced section.

8. The mountain city subway ventilation shaft construction method according to claim 2 is characterized in that: The specific construction methods at the horse head gate are: When the vertical shaft is excavated in layers to the reinforced section, three steel frames are first connected, and then the advance support construction of the advance small guide tube is carried out. After the support is completed, the vertical shaft is continued to be excavated downward in layers. When the excavation reaches the upper step of the horizontal channel, the excavation is suspended. For the upper step of the horizontal channel, the core is taken longitudinally by a water-grinding drill and then the excavation is carried out in layers. The distance of each excavation is not more than 2 steel frames. After the excavation and support of the upper step of the horizontal channel is completed, the vertical shaft is continued downward until the bottom of the vertical shaft, and then the lower step of the horizontal channel is excavated in the same way, and the initial support is done.

9. The mountain city subway ventilation shaft construction method according to claim 1, characterized in that: The specific methods for monitoring the shaft are: Multiple surface settlement monitoring points are set up at intervals of 2 to 5 meters around the shaft, and horizontal convergence monitoring points are arranged on the shaft wall. The long side section is taken as a monitoring section with a horizontal interval of 5m to 10m. Each monitoring section should have monitoring points in the middle of the long and short sides of the shaft structure, and each monitoring section should have no less than two measuring lines.

10. The mountain city subway ventilation shaft construction method according to claim 9, characterized in that: Specific methods for monitoring shafts also include: The optimization layout principle of the horizontal convergence monitoring points of the vertical shaft is as follows: if the single side length of the vertical shaft is less than 10m, one group of measuring points is arranged; if the single side length of the vertical shaft is 10m to 20m, two groups of measuring points are arranged; if the single side length of the vertical shaft is greater than 20m, one group of measuring points is arranged every 10m.