Simulation system, test system and test method

By using communication units and transmission circuits to automatically switch and transmit test signals in the simulation system, the problems of complexity and low efficiency of manual wiring in the prior art are solved, and an efficient and accurate test process is achieved, reducing operational risks and equipment complexity are achieved. sex.

CN119024744APending Publication Date: 2024-11-26CHINA TECHENERGY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411112967.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-14
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

When conducting regular tests, existing simulation systems need to manually disconnect the wiring from the field equipment, resulting in low test efficiency, long time, operating complexity and potential error risks, affecting the accuracy of the test results.

Method used

By introducing a communication unit into the simulation system, using communication methods and setting transmission circuits, the physical connection between the test equipment and the simulation system is reduced, automatic switching of test signals and data transmission is realized, and the need for manual wiring is reduced.

Benefits of technology

It shortens the test time, improves the test efficiency, reduces the complexity and error risk of manual operation, improves the accuracy of test results, and reduces the number of physical connections, simplifies the design of test equipment, and saves space and costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119024744A_ABST
    Figure CN119024744A_ABST
Patent Text Reader

Abstract

The invention provides a simulation system, a test system and a test method, in the simulation system, a communication mode of a communication unit and a set transmission circuit of an acquisition board card are used for reducing the number of physical connections between test equipment and the simulation system when data transmission is carried out between the test equipment and the simulation system, so that the test efficiency is improved. The number of manual wiring can be reduced, the overall test time is shortened, and the test efficiency is improved. Moreover, the complexity and potential error risk of manual operation can be reduced, and the accuracy of a test result is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of nuclear power plants, and in particular to a simulation system, a test system and a test method. Background Art

[0002] With the rapid advancement of computer technology, digital systems have penetrated deeply into many industries. As a key link, nuclear power plants are gradually transforming their instrumentation and control systems into full digital systems. However, given the extremely high safety and reliability requirements of nuclear power plants, analog systems continue to play an irreplaceable role in the diverse drive systems of nuclear power plants because they can effectively deal with common cause failures in software.

[0003] Among them, the simulation system is generally composed of a test interface board, an acquisition board, a computing board, and an output board. These boards work together to manually connect the test interface board to the field equipment of the nuclear power plant to achieve signal acquisition and transmission. The specific process is: the acquisition board is responsible for capturing the real-time signals of the field equipment, and then passing these signals to the computing board for necessary processing and analysis; after the computing board completes the calculation, it sends the results to the output board; finally, the output board uses the test interface board to feed back the processing results to other field equipment, so as to control and monitor the operating status of the nuclear power plant.

[0004] However, the current structural design of the simulation system restricts the convenience and efficiency of its regular testing to a certain extent. Specifically, when conducting a simulation system test, it is necessary to manually disconnect the wiring from the on-site equipment and connect it to the test device to collect the test signal for testing. This process is not only time-consuming and reduces the test efficiency, but the complexity of manual operation and the potential risk of error also increase the uncertainty of the test results. Summary of the invention

[0005] In order to solve the above technical problems, the embodiments of the present application provide a simulation system, a test system and a test method to achieve the purpose of improving the test efficiency and accuracy. The technical solutions are as follows:

[0006] On one hand, the present application provides a simulation system, comprising:

[0007] A communication unit, used to connect with the test equipment based on a communication mode, receive at least two signals of the test equipment, and send the at least two signals to different acquisition boards respectively; the at least two signals include at least one test switching signal and at least one test signal; the test signal is used to verify the performance of the nuclear power plant;

[0008] The acquisition board is used to obtain the test switching signal and the test signal based on the set transmission circuit, switch from the first path to the second path based on the test switching signal, and send the test signal to the operation board through the second path; the communication method and the set transmission circuit are used to reduce the number of physical connections between the test equipment and the simulation system when data is transmitted between the test equipment and the simulation system;

[0009] The operation board is used to perform operation processing in response to the test signal to obtain the operation processing result;

[0010] The output board is used to output the operation processing result to the communication unit based on the setting transmission circuit;

[0011] The communication unit is also used to send the calculation result to the test equipment.

[0012] In a possible implementation, the communication unit includes:

[0013] Communication interface, used for wired or wireless connection with test equipment;

[0014] A main processor, configured to receive at least one test switching signal and at least one test signal of the test device through the communication interface, and send the at least one test switching signal and the at least one test signal to a test control circuit;

[0015] A test control circuit, used for sending the at least one test switching signal and the at least one test signal to different acquisition boards respectively;

[0016] The main processor is also used to receive the calculation processing result and send the calculation processing result to the test equipment through the communication interface.

[0017] In a possible implementation, the acquisition board is further used to send the test result of the acquisition board to the communication unit based on the set transmission circuit; the test result of the acquisition board includes the at least two signals acquired by the acquisition board;

[0018] The communication unit is also used to send the test results of the acquisition board to the test equipment.

[0019] In a possible implementation, the computing board is further used to send the computing result to the communication unit based on the setting transmission circuit;

[0020] The communication unit is also used to send the calculation results of the calculation board to the test equipment.

[0021] In a possible implementation, the setting transmission circuit includes: a serial-to-parallel conversion circuit.

[0022] In a possible implementation, the acquisition board, the computing board, and the output board further include:

[0023] Signal isolation circuit.

[0024] Another aspect of the present application provides a test system, comprising:

[0025] A test device, used for running the test software to simulate and generate at least two signals, wherein the at least two signals include at least one test switching signal and at least one test signal;

[0026] Simulation system, including:

[0027] A communication unit, used to connect with the test equipment based on the communication mode, receive at least two signals of the test equipment, and send the at least two signals to different acquisition boards respectively; the at least two signals include at least one test switching signal and at least one test signal; the communication mode and the set transmission circuit are used to reduce the number of physical connections between the test equipment and the simulation system when data is transmitted between the test equipment and the simulation system; the test signal is used to verify the performance of the nuclear power plant;

[0028] The acquisition board is used to obtain the test switching signal and the test signal based on the set transmission circuit, switch from the first path to the second path based on the test switching signal, and send the test signal to the operation board through the second path;

[0029] The operation board is used to perform operation processing in response to the test signal to obtain the operation processing result;

[0030] The output board is used to output the operation processing result to the communication unit based on the setting transmission circuit;

[0031] The communication unit is also used to send the calculation result to the test equipment.

[0032] The third aspect of the present application provides a test method, comprising:

[0033] The communication unit receives at least two signals from the test equipment and sends the at least two signals to different acquisition boards respectively; the at least two signals include at least one test switching signal and at least one test signal; the test signal is used to verify the performance of the nuclear power plant;

[0034] The acquisition board obtains the test switching signal and the test signal based on the set transmission circuit, switches from the first path to the second path based on the test switching signal, and sends the test signal to the operation board through the second path; the communication method and the set transmission circuit are used to reduce the number of physical connections between the test device and the simulation system when data is transmitted between the test device and the simulation system;

[0035] The computing board performs computing processing in response to the test signal to obtain a computing processing result;

[0036] The output card outputs the calculation result to the communication unit based on the setting transmission circuit;

[0037] The communication unit sends the calculation result to the test equipment.

[0038] In a possible implementation, the test method further includes at least one of the following:

[0039] The acquisition board sends the test result of the acquisition board to the communication unit based on the set transmission circuit; the test result of the acquisition board includes the at least two signals acquired by the acquisition board;

[0040] The communication unit sends the test result of the acquisition board to the test equipment;

[0041] The computing board sends the computing result to the communication unit based on the setting transmission circuit;

[0042] The communication unit sends the calculation result of the calculation board to the test equipment.

[0043] In a possible implementation, the test method further includes at least one of the following:

[0044] The acquisition board electrically isolates the test result of the acquisition board and the at least one test signal based on the signal isolation circuit;

[0045] The computing board performs electrical isolation on the computing result based on a signal isolation circuit;

[0046] The output card electrically isolates the operation processing result to be output by the output card based on the signal isolation circuit.

[0047] Compared with the prior art, the beneficial effects of this application are:

[0048] In the present application, the communication unit in the simulation system can be connected to the test equipment based on the communication mode, receive at least two signals from the test equipment, and the acquisition board is used to obtain the test switching signal and the test signal based on the set transmission circuit, and switch from the first path to the second path based on the test switching signal, and send the test signal to the operation board through the second path. Among them, the communication mode and the set transmission circuit are used to reduce the number of physical connections between the test equipment and the simulation system when transmitting data between the test equipment and the simulation system. The simulation system of the above structure can reduce the number of manual wiring, shorten the overall test time, and improve the efficiency of the test. In addition, it can reduce the complexity and potential error risks of manual operations and improve the accuracy of test results. BRIEF DESCRIPTION OF THE DRAWINGS

[0049] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0050] Figure 1 is a structural schematic diagram of a simulation system provided in Example 1 of the present application;

[0051] Figure 2 is a structural schematic diagram of a communication unit provided in Example 2 of the present application;

[0052] Figure 3 is an interactive schematic diagram of a communication unit provided in Example 2 of the present application;

[0053] Figure 4 is a structural schematic diagram of a simulation system provided in Example 6 of the present application;

[0054] Figure 5 It is a structural schematic diagram of a test system provided in this application. DETAILED DESCRIPTION

[0055] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0056] In order to make the above-mentioned objects, features and advantages of the present application more obvious and easy to understand, the present application is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.

[0057] Reference Figure 1 , is a schematic diagram of the structure of a simulation system provided in Example 1 of the present application, such as Figure 1 As shown, the simulation system may include: a communication unit 100 , an acquisition board 200 , a computing board 300 and an output board 400 .

[0058] The communication unit 100 is used to connect with the test equipment based on a communication method, receive at least two signals from the test equipment, and send the at least two signals to different acquisition boards 200 respectively.

[0059] The at least two signals may include at least one test switching signal and at least one test signal. The test signal may be used to verify the performance of the nuclear power plant, such as verifying the logic operation function of the simulation system of the nuclear power plant.

[0060] In this embodiment, the test device may send a test switching signal corresponding to a plurality of acquisition boards 200 or send a test switching signal corresponding to each acquisition board 200 .

[0061] Corresponding to the implementation method in which the test equipment sends a test switching signal to multiple acquisition boards 200, the communication unit 100 can receive the test switching signal sent by the test equipment based on the communication method and the connection with the test equipment, and send the test switching signal to different acquisition boards 200 respectively.

[0062] Corresponding to the implementation method in which the test equipment sends a test switching signal to each acquisition board 200 respectively, the communication unit 100 can receive multiple test switching signals sent by the test equipment based on the communication method and the test equipment connection, and send each test switching signal to the corresponding acquisition board 200 respectively.

[0063] The test equipment can send test signals to each acquisition board 200. Accordingly, the communication unit 100 can receive multiple test signals sent by the test equipment based on the communication mode and the connection with the test equipment, and send each test signal to the corresponding acquisition board 200.

[0064] At least two signals may be generated based on a simulation of the test equipment running the test software.

[0065] The acquisition board 200 is used to obtain a test switching signal and a test signal based on a set transmission circuit, switch from a first path to a second path based on the test switching signal, and send the test signal to the operation board 300 through the second path.

[0066] The communication method and the setting transmission circuit can be used to reduce the number of physical connections between the test equipment and the simulation system when data is transmitted between the test equipment and the simulation system.

[0067] It can be understood that the first path can be used to inject the actual generated field signal, and the second path can be used to inject the test signal of the test equipment.

[0068] The operation board 300 is used to perform operation processing in response to the test signal, obtain the operation processing result, and send the operation processing result to the output board 400.

[0069] The output board 400 is used to output the operation processing result to the field device and the communication unit 100 based on the set transmission circuit.

[0070] The communication unit 100 is also used to send the calculation results to the test equipment.

[0071] The test equipment can verify whether the performance of the nuclear power plant meets the expected standard by comparing the operation processing results and the expected response values ​​corresponding to the test signals. This comparison process can not only confirm whether the response of the nuclear power plant meets expectations, but also indirectly reflect the integrity of the operation processing results. Furthermore, if the operation processing results can accurately match the expected response values, then to a certain extent it can be shown that the output board 400 maintains a good working state in the process of outputting the operation processing results to the communication unit 100, thereby verifying its performance in this link.

[0072] An example is now given to illustrate the interaction between the communication unit 100, the acquisition board 200, the computing board 300 and the output board 400. For example, the test equipment running the test software can simulate the generation of a water level signal (i.e., an implementation of the test signal). The communication unit 100 is connected to the test equipment based on the communication mode, can receive the water level signal of the test equipment, send the water level signal to the acquisition board 200, the acquisition board 200 sends the water level signal to the computing board 300, the computing board 300 responds to the water level signal, determines whether the water level is less than the set water level threshold, and if so, generates a water level control instruction, outputs the water level control instruction to the field equipment (such as a pump) through the output board 400, and at the same time, the water level control instruction is sent to the communication unit 100, the communication unit 100 sends the water level control instruction to the test equipment, and the test equipment can determine whether the water level control instruction is consistent with the expected value, thereby achieving the purpose of verification.

[0073] In this embodiment, the communication unit in the simulation system can be connected to the test equipment based on the communication mode, receive at least two signals from the test equipment, and the acquisition board is used to obtain the test switching signal and the test signal based on the set transmission circuit, and switch from the first path to the second path based on the test switching signal, and send the test signal to the operation board through the second path. Among them, the communication mode and the set transmission circuit are used to reduce the number of physical connections between the test equipment and the simulation system when transmitting data between the test equipment and the simulation system. The simulation system with the above structure can reduce the number of manual wiring, shorten the overall test time, and improve the efficiency of the test. In addition, it can reduce the complexity and potential error risks of manual operations and improve the accuracy of test results.

[0074] Furthermore, since too many cables are no longer needed, the test equipment no longer needs to store too many cables, and the size of the test equipment can be reduced, saving space.

[0075] Furthermore, at least two signals can be generated based on the simulation of the test software running on the test equipment. The test equipment has higher flexibility in generating test switching signals or test signals without the need for additional hardware equipment, thereby saving costs.

[0076] As another optional embodiment of the present application, refer to Figure 2 , is a schematic diagram of the structure of a communication unit provided in Example 2 of the present application. This embodiment is mainly an implementation method of the communication unit 100 in the above-mentioned Example 1, such as Figure 2 As shown, the communication unit 100 includes: a communication interface 1001 , a main processor 1002 and a test control circuit 1003 .

[0077] The communication interface 1001 is used for wired or wireless connection with the test equipment.

[0078] The main processor 1002 is used to obtain at least one test switching signal and at least one test signal of the test equipment through the communication interface 1001, and send the at least one test switching signal and the at least one test signal to the test control circuit 1003.

[0079] The test control circuit 1003 is used to send at least one test switching signal and at least one test signal to different acquisition boards 200 respectively.

[0080] During the period when no regular test is performed, the test control circuit 1003 may be in a power-off state, that is, the test control function is not effective. Figure 3As shown, when periodic testing is required, power can be controlled to be powered on. After powering on, the communication unit 100 can receive the test switching signal sent by the test equipment. The communication unit 100 sends the test switching signal to the acquisition board 200. The acquisition board 200 can switch from the first path to the second path based on the test switching signal. The communication unit 100 can perform test switching readback. If it is determined that the acquisition board 200 switches from the first path to the second path, a signal indicating the switching completion can be fed back to the test equipment. Accordingly, the test equipment sends a test signal, and the communication unit 100 can send the test signal to the acquisition board 200. The acquisition board 200 sends the test signal to the operation board 300 based on the set transmission circuit.

[0081] The main processor 1002 is also used to receive the calculation processing results and send the calculation processing results to the test equipment through the communication interface 1001.

[0082] In this embodiment, the communication interface 1001 is used to connect to the test equipment by wire or wirelessly. Before the test, the communication unit 100 can be connected to the test equipment by a communication line, or, before the test, no connection is required. Therefore, the simulation system is provided with the communication unit 100, which can shorten the overall test time and improve the test efficiency.

[0083] As another optional embodiment of the present application, an acquisition board 200 and a communication unit 100 provided in Embodiment 3 of the present application are mainly introduced. In this embodiment, the acquisition board 200 can also be used to send the test results of the acquisition board 200 to the communication unit based on the set transmission circuit.

[0084] The test result of the acquisition board 200 may include the at least two signals acquired by the acquisition board 200 .

[0085] The communication unit 100 can also be used to send the test results of the acquisition board 200 to the test equipment.

[0086] In this embodiment, the test equipment can verify the working state of the acquisition board 200 in the process of acquiring the at least two signals by comparing the test result of the acquisition board 200 with whether the at least two signals sent by the test equipment are consistent.

[0087] In this embodiment, on the basis of the communication unit 100 sending the calculation and processing results to the test equipment, the acquisition board 200 sends the test results of the acquisition board 200 to the communication unit 100 based on the set transmission circuit; the communication unit 100 sends the test results of the acquisition board to the test equipment, so that the test equipment can verify the performance of the nuclear power plant based on the calculation and processing results, and can also verify the working status of the acquisition board 100 in the process of collecting at least two signals, so as to verify the performance of the nuclear power plant more comprehensively.

[0088] As another optional embodiment of the present application, a computing board 300 and a communication unit 100 provided in Embodiment 4 of the present application are mainly introduced. In this embodiment, the computing board 300 can also be used to send the computing processing result to the communication unit 100 based on the set transmission circuit.

[0089] The communication unit 100 can also be used to send the calculation results of the calculation board 300 to the test equipment.

[0090] In this embodiment, the test equipment can verify whether the performance of the nuclear power plant meets the expected standard by comparing whether the operation processing result output by the output board 400 is consistent with the expected response value corresponding to the test signal. This comparison process can not only confirm whether the response of the nuclear power plant meets expectations, but also indirectly reflect the integrity of the operation processing result. Further, if the operation processing result can accurately match the expected response value, then to a certain extent it can be shown that the output board 400 maintains a good working state in the process of outputting the operation processing result to the communication unit 100, thereby verifying its performance in this link.

[0091] In addition, the test equipment also has the ability to directly verify the logical operation function of the operation board 300. By comparing the operation processing results generated by the operation board 300 with the expected response value corresponding to the test signal, the accuracy and efficiency of the logical operation of the operation board 300 can be intuitively verified, ensuring that the operation board 300 can perform complex logical operations as expected when processing nuclear power plant related signals.

[0092] As another optional embodiment of the present application, a setting transmission circuit is provided in Embodiment 5 of the present application. This embodiment is mainly an implementation method of the setting transmission circuit. The setting transmission circuit may include but is not limited to:

[0093] Serial-to-parallel conversion circuit.

[0094] When the test signal output by the test equipment is presented in the form of serial data, the serial-to-parallel conversion circuit built into the acquisition board 200 can convert at least one test signal in the serial data stream into a parallel signal format. This conversion mechanism allows at least one test signal to be synchronously transmitted in a multi-bit parallel mode, which can enhance the efficiency and speed of data transmission and effectively shorten the delay of data transmission.

[0095] Accordingly, the computing board 300 can receive at least one converted parallel test signal in parallel to ensure data integrity and real-time performance. The computing board can execute different computing logics for the received diverse test signals to meet various test requirements.

[0096] What is particularly important is that by introducing the serial-to-parallel conversion circuit, not only can the number of physical connections between the test equipment and the simulation system be reduced, reducing the complexity and maintenance cost of the simulation system, but it is also suitable for application scenarios where the simulation system has high real-time requirements and needs to continuously process large amounts of data signals.

[0097] Through the serial-to-parallel conversion circuit, the acquisition board 200 can flexibly adapt to communication units with different interface standards without directly introducing complex digital processing elements (such as CPU, FPGA) into the analog system.

[0098] In addition, it should be noted that in several key data transmission scenarios, the serial-to-parallel conversion circuit is mainly used to convert parallel data into serial data format. Specifically, when the acquisition board 200 needs to send the collected test results to the communication unit 100, or the operation board 300 needs to send the operation processing results to the communication unit 100, and the output board 400 also needs to transmit the operation processing results to the communication unit 100, the serial-to-parallel conversion circuit integrated in these boards is mainly used to efficiently convert the parallel data processed internally into a serial data format. This conversion is to adapt to the characteristics of the communication unit usually receiving serial data streams, ensuring that the data can be accurately transmitted to the test equipment.

[0099] As another optional embodiment of the present application, a simulation system is provided in Embodiment 6 of the present application. In this embodiment, the acquisition board 200, the computing board 300 and the output board 400 may further include:

[0100] Signal isolation circuit.

[0101] The signal isolation circuit can be used to electrically isolate the signal.

[0102] For example, Figure 4As shown, when periodic tests are required, the communication unit 100 can receive a test switching signal issued by the test equipment, and the test control circuit 1003 in the communication unit 100 sends the test switching signal to the acquisition board 200. The acquisition board 200 can switch from the first path to the second path based on the test switching signal. The communication unit 100 can perform test switching readback. If it is determined that the acquisition board 200 switches from the first path to the second path, a signal indicating the switching completion can be fed back to the test equipment. Accordingly, the test equipment sends a test signal in a serial data format, and the test control circuit in the communication unit 100 can send the test signal in a serial data format to the acquisition board 200. The acquisition board 200 converts the test signal in a serial data format into a parallel data format based on a serial-to-parallel conversion circuit. The acquisition board can electrically isolate the test signal in a parallel data format based on a signal isolation circuit and then output it to the operation board 300.

[0103] The operation circuit in the operation board 300 can perform operation processing based on the test signal in parallel data format to obtain the operation processing result. The signal isolation circuit in the operation board 300 can electrically isolate the operation processing result, output it to the output board 400, and output it to the main processor 1002 through the serial-to-parallel conversion circuit.

[0104] The signal isolation circuit in the output board 400 can electrically isolate the operation processing result output by the output circuit, and then output the operation processing result to the main processor 1002 through the serial-to-parallel conversion circuit.

[0105] In this embodiment, the signal is electrically isolated by the signal isolation circuit, which can reduce noise, current and other electromagnetic interference, ensure the quality of the signal, and ensure the accuracy of the test.

[0106] As another optional embodiment of the present application, refer to Figure 5 , is a schematic diagram of the structure of a test system provided in Example 7 of the present application, such as Figure 5 As shown, the test system includes: a test device 10 and a simulation system 20.

[0107] The test device 10 is used to run the test software to simulate and generate at least two signals, wherein the at least two signals include at least one test switching signal and at least one test signal.

[0108] In this embodiment, the test equipment 10 may include but is not limited to: a computer.

[0109] The test software has a good human-computer interaction interface. The operator can import, select, and execute test cases through the human-computer interface, and can automatically generate test result reports for test personnel to count the test status.

[0110] The test case can be used to cause the test equipment to generate test switching signals and test signals.

[0111] The composition of the simulation system 20 can refer to the simulation system introduced in Example 1, and will not be described in detail here.

[0112] As another optional embodiment of the present application, a test method is provided for Example 8 of the present application, which may include but is not limited to the following steps:

[0113] Step S101: a communication unit receives at least two signals from a test device, and sends the at least two signals to different acquisition boards respectively.

[0114] The at least two signals may include at least one test switching signal and at least one test signal.

[0115] The test signal can be used to verify the performance of the nuclear power plant.

[0116] Step S102: the acquisition board obtains the test switching signal and the test signal based on the set transmission circuit, switches from the first path to the second path based on the test switching signal, and sends the test signal to the computing board through the second path.

[0117] The communication method and the setting transmission circuit can be used to reduce the number of physical connections between the test equipment and the simulation system when data is transmitted between the test equipment and the simulation system.

[0118] Step S103: the computing board performs computing processing in response to the test signal to obtain a computing processing result.

[0119] Step S104: the output card outputs the calculation result to the communication unit based on the set transmission circuit.

[0120] Step S105: The communication unit sends the calculation result to the test equipment.

[0121] In this embodiment, the communication unit in the simulation system can be connected to the test equipment based on the communication mode, receive at least two signals from the test equipment, and the acquisition board is used to obtain the test switching signal and the test signal based on the set transmission circuit, and switch from the first path to the second path based on the test switching signal, and send the test signal to the operation board through the second path. Among them, the communication mode and the set transmission circuit are used to reduce the number of physical connections between the test equipment and the simulation system when transmitting data between the test equipment and the simulation system. Testing based on the simulation system with the above structure can reduce the number of manual wiring, shorten the overall test time, and improve the efficiency of the test. In addition, it can reduce the complexity and potential error risks of manual operations and improve the accuracy of test results.

[0122] As another optional embodiment of the present application, a test method is provided in Embodiment 9 of the present application. In this embodiment, the test method can further include at least one of the following on the basis of Embodiment 8:

[0123] Step S106: The acquisition board sends the test result of the acquisition board to the communication unit based on the set transmission circuit; the test result of the acquisition board includes at least two signals acquired by the acquisition board.

[0124] Step S107: The communication unit sends the test results of the acquisition board to the test equipment.

[0125] Step S108 , the computing board sends the computing result to the communication unit based on the set transmission circuit.

[0126] Step S109: The communication unit sends the calculation result of the calculation board to the test equipment.

[0127] In this embodiment, on the basis of the communication unit sending the calculation and processing results to the test equipment, the acquisition board sends the test results of the acquisition board to the communication unit based on the set transmission circuit; the communication unit sends the test results of the acquisition board to the test equipment, so that the test equipment can verify the performance of the nuclear power plant based on the calculation and processing results, and can also verify the working status of the acquisition board in the process of collecting at least two signals, so as to verify the performance of the nuclear power plant more comprehensively.

[0128] The test equipment can verify whether the performance of the nuclear power plant meets the expected standards by comparing the operation processing results output by the output board and the expected response value corresponding to the test signal. This comparison process can not only confirm whether the response of the nuclear power plant meets expectations, but also indirectly reflect the integrity of the operation processing results. Furthermore, if the operation processing results can accurately match the expected response value, then to a certain extent it can be shown that the output board maintains a good working condition in the process of outputting the operation processing results to the communication unit, thereby verifying its performance in this link.

[0129] In addition, the test equipment also has the ability to directly verify the logic operation function of the operation board. By comparing the operation processing results generated by the operation board with the expected response value corresponding to the test signal, the accuracy and efficiency of the logic operation of the operation board can be intuitively verified, ensuring that the operation board can perform complex logic operations as expected when processing nuclear power plant related signals.

[0130] As another optional embodiment of the present application, a test method is provided in Embodiment 10 of the present application. In this embodiment, the test method may further include at least one of the following on the basis of Embodiment 9:

[0131] Step S110: The acquisition board electrically isolates the test result of the acquisition board and at least one test signal based on the signal isolation circuit.

[0132] Step S111: The computing board performs electrical isolation on the computing result based on the signal isolation circuit.

[0133] Step S112: the output card electrically isolates the calculation processing result to be output by the output card based on the signal isolation circuit.

[0134] In this embodiment, the signal is electrically isolated by the signal isolation circuit, which can reduce noise, current and other electromagnetic interference, ensure the quality of the signal, and ensure the accuracy of the test.

[0135] It should be noted that each embodiment focuses on the differences from other embodiments, and the same or similar parts between the embodiments can be referred to each other. For the device embodiment, since it is basically similar to the method embodiment, the description is relatively simple, and the relevant parts can be referred to the partial description of the method embodiment.

[0136] Finally, it should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.

[0137] For the convenience of description, the above device is described in terms of functions divided into various modules. Of course, when implementing the present application, the functions of each module can be implemented in the same or multiple software and / or hardware.

[0138] It can be known from the description of the above implementation methods that those skilled in the art can clearly understand that the present application can be implemented by means of software plus a necessary general hardware platform. Based on such an understanding, the technical solution of the present application can be essentially or partly contributed to the prior art in the form of a software product, which can be stored in a storage medium such as ROM / RAM, a magnetic disk, an optical disk, etc., and includes several instructions for enabling a computer device (which can be a personal computer, a server, or a network device, etc.) to execute the methods described in the various embodiments of the present application or certain parts of the embodiments.

[0139] The above is a detailed introduction to a simulation system, a test system and a test method provided by the present application. Specific examples are used in this article to illustrate the principles and implementation methods of the present application. The description of the above embodiments is only used to help understand the method of the present application and its core idea. At the same time, for general technical personnel in this field, according to the idea of ​​the present application, there will be changes in the specific implementation method and application scope. In summary, the content of this specification should not be understood as a limitation on the present application.

Claims

1. A simulation system, It is characterized in that include: A communication unit, used to connect with the test equipment based on a communication mode, receive at least two signals of the test equipment, and send the at least two signals to different acquisition boards respectively; the at least two signals include at least one test switching signal and at least one test signal; the test signal is used to verify the performance of the nuclear power plant; The acquisition board is used to obtain the test switching signal and the test signal based on the set transmission circuit, switch from the first path to the second path based on the test switching signal, and send the test signal to the operation board through the second path; the communication method and the set transmission circuit are used to reduce the number of physical connections between the test equipment and the simulation system when data is transmitted between the test equipment and the simulation system; The operation board is used to perform operation processing in response to the test signal to obtain the operation processing result; The output board is used to output the operation processing result to the communication unit based on the setting transmission circuit; The communication unit is also used to send the calculation result to the test equipment.

2. The simulation system according to claim 1, It is characterized in that The communication unit comprises: Communication interface, used for wired or wireless connection with test equipment; A main processor, configured to receive at least one test switching signal and at least one test signal of the test device through the communication interface, and send the at least one test switching signal and the at least one test signal to a test control circuit; A test control circuit, used for sending the at least one test switching signal and the at least one test signal to different acquisition boards respectively; The main processor is also used to receive the calculation processing result and send the calculation processing result to the test equipment through the communication interface.

3. The simulation system according to claim 1, It is characterized in that The acquisition board is also used to send the test result of the acquisition board to the communication unit based on the set transmission circuit; the test result of the acquisition board includes the at least two signals acquired by the acquisition board; The communication unit is also used to send the test results of the acquisition board to the test equipment.

4. The simulation system according to claim 1, It is characterized in that The computing board is also used to send the computing result to the communication unit based on the setting transmission circuit; The communication unit is also used to send the calculation processing result of the calculation board to the test equipment.

5. A simulation system according to any one of claims 1 to 4, It is characterized in that The setting transmission circuit includes: a serial-to-parallel conversion circuit.

6. A simulation system according to any one of claims 1 to 4, It is characterized in that The acquisition board, the computing board and the output board also include: Signal isolation circuit.

7. A test system, It is characterized in that include: A test device, used for running the test software to simulate and generate at least two signals, wherein the at least two signals include at least one test switching signal and at least one test signal; Simulation system, including: A communication unit, used to connect with the test equipment based on the communication mode, receive at least two signals of the test equipment, and send the at least two signals to different acquisition boards respectively; the at least two signals include at least one test switching signal and at least one test signal; the communication mode and the set transmission circuit are used to reduce the number of physical connections between the test equipment and the simulation system when data is transmitted between the test equipment and the simulation system; the test signal is used to verify the performance of the nuclear power plant; The acquisition board is used to obtain the test switching signal and the test signal based on the set transmission circuit, switch from the first path to the second path based on the test switching signal, and send the test signal to the operation board through the second path; The operation board is used to perform operation processing in response to the test signal to obtain the operation processing result; The output board is used to output the operation processing result to the communication unit based on the setting transmission circuit; The communication unit is also used to send the calculation result to the test equipment.

8. A test method, It is characterized in that include: The communication unit receives at least two signals from the test equipment and sends the at least two signals to different acquisition boards respectively; the at least two signals include at least one test switching signal and at least one test signal; the test signal is used to verify the performance of the nuclear power plant; The acquisition board obtains the test switching signal and the test signal based on the set transmission circuit, switches from the first path to the second path based on the test switching signal, and sends the test signal to the operation board through the second path; the communication method and the set transmission circuit are used to reduce the number of physical connections between the test device and the simulation system when data is transmitted between the test device and the simulation system; The computing board performs computing processing in response to the test signal to obtain a computing processing result; The output card outputs the calculation result to the communication unit based on the setting transmission circuit; The communication unit sends the calculation result to the test equipment.

9. The test method according to claim 8, It is characterized in that The test method also includes at least one of the following: The acquisition board sends the test result of the acquisition board to the communication unit based on the set transmission circuit; the test result of the acquisition board includes the at least two signals acquired by the acquisition board; The communication unit sends the test result of the acquisition board to the test equipment; The computing board sends the computing result to the communication unit based on the setting transmission circuit; The communication unit sends the calculation result of the calculation board to the test equipment.

10. The test method according to claim 9, It is characterized in that The test method also includes at least one of the following: The acquisition board electrically isolates the test result of the acquisition board and the at least one test signal based on the signal isolation circuit; The computing board performs electrical isolation on the computing result based on a signal isolation circuit; The output card electrically isolates the operation processing result to be output by the output card based on the signal isolation circuit.