Ancient building ridge purlin dismounting and replacing method

By adopting the method of replacing the ridge purlins without removing the regular ridge in ancient buildings in southern Fujian, the problem of ridge purlin decay caused by roof slippage and tile fragmentation is solved, and the replacement of ridge purlins does not damage the integrity and historical information. Reserved and suitable for the renovation of ancient buildings of all sizes and environments.

CN119041739APending Publication Date: 2024-11-29SHANGHAI JIANWEI CULTURAL HERITAGE CONSERVATION TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411271360.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-11
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

Due to the large slope of the roof of ancient buildings in southern Fujian, the roof is prone to slipping and tiles breaking after long-term use, resulting in rotating ridges. Traditional repair methods require the removal of the main ridge, which damages the integrity of the building and makes it difficult to retain historical information.

Method used

The method of replacing the ridge purlins without removing the main ridge is used to make new ridge purlins, and the old ridge purlins are removed using the roof cantilever auxiliary tools, forming holes and penetrating the new ridge purlins, repairing the gables to fix the new ridge purlins, and retaining the building's Cultural values ​​and integrity.

Benefits of technology

The replacement of ridge purlins does not require the removal of the main ridge, which retains the characteristics of the building to the maximum extent, extends the life of the building, is easy to operate, is suitable for the repair of ancient buildings of all sizes and environments, with few equipment and materials, no electricity required, and is suitable for mountainous areas. Restoration of cultural relics and buildings.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041739A_ABST
    Figure CN119041739A_ABST
Patent Text Reader

Abstract

The invention provides an ancient building ridge purlin replacing method which comprises the following steps: manufacturing a new ridge purlin to be replaced according to an old ridge purlin on an ancient building; a ridge of the ancient building is overhung through a lever, and stress of an old ridge purlin is removed; releasing the fixation between the old ridge purlin and an upper rafter of the ancient building; corresponding to the old ridge purlin position, a gable brick masonry of the historic building is dismantled, and a hole is formed; the old ridge purlin is dismantled, and a new ridge purlin penetrates through the hole; and the hole in the gable is repaired, and the new ridge purlin is fixed. According to the scheme, the integrity and historical information of the main ridge of the ancient building are reserved, the cultural value of the main ridge of the ancient building is completely reserved, the operation method is simple and convenient, operation is easy, and the method is suitable for ancient building repairing projects of various scales and various environments and particularly suitable for Lingnan and Fujian ancient buildings with graceful ridges and with requirements for roofs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of ancient building restoration, and in particular relates to a method for dismantling and replacing a ridge purlin of an ancient building. Background Art

[0002] Southern Fujian has a rich cultural heritage and unique architectural style, among which ridge decoration is one of the important features of Southern Fujian architecture. Ancient buildings in Southern Fujian have unique sloping roofs. Due to the large slope of the roof, the roof often slides down and tiles break during long-term use, resulting in ridge leakage, which makes the ridge purlin of ancient buildings easy to decay. The traditional ridge purlin repair method often requires the removal of the ridge, which not only destroys the integrity of the building, but also makes it difficult to preserve historical information. Summary of the invention

[0003] In view of the above-mentioned shortcomings of the prior art, an object of the present invention is to provide a method for dismantling and replacing the ridge purlin of an ancient building, so as to solve the above-mentioned problems.

[0004] To achieve the above-mentioned and other related purposes, the present invention provides a method for dismantling and replacing a ridge purlin of an ancient building, comprising:

[0005] According to the old ridge purlin on the ancient building, make the new ridge purlin to be replaced;

[0006] The roof of the ancient building is cantilevered to relieve the stress of the old ridge purlin;

[0007] Remove the fixation between the old ridge purlin and the upper rafters of the ancient building;

[0008] Corresponding to the location of the old ridge purlin, the brickwork of the gable of the ancient building was removed to form an opening;

[0009] Remove the old ridge purlin and insert the new ridge purlin through the opening;

[0010] Repair the opening in the gable and secure the new ridge purlin.

[0011] Optionally, after manufacturing the new ridge purlin to be replaced, the method further comprises:

[0012] Remove the tiles outside the preset range of the main ridge of the ancient building roof to form a working surface;

[0013] Determine the fixed points of the ridge cantilever auxiliary tools, and remove the remaining tiles on the roof of the ancient building according to the fixed points;

[0014] Install the ridge cantilever auxiliary tools.

[0015] Optionally, after installing the roof ridge cantilever auxiliary tool, the method further comprises:

[0016] A weight bag will be set at the position where the roof ridge cantilever auxiliary tool and the upper purlin of the ancient building are fixed to balance the force;

[0017] Remove the remaining tiles on the roof of the ancient building.

[0018] Optionally, remove the old ridge purlin, including:

[0019] Dismantle the old ridge purlin in sections;

[0020] Remove the old ridge purlin from the ancient building.

[0021] Optionally, insert a new ridge purlin through the opening, including:

[0022] From the opening of the gable on one side, insert the new purlins of the main room;

[0023] Insert thick support plates into the areas where the new purlins touch the columns of the ancient buildings;

[0024] Insert the new secondary purlins from the upper part of the opening respectively;

[0025] Fix the joint position between the new secondary purlin and the new main purlin.

[0026] Optionally, repair the opening in the gable wall and secure the new ridge purlin, including:

[0027] At the opening, build a lining gable to fix the position of the new ridge purlin;

[0028] The outer gables were closed and repaired.

[0029] Optionally, after repairing the hole on the gable and fixing the new ridge purlin, the method further comprises:

[0030] In ancient buildings, supports are set between the ridge and rafters to support both sides of the ridge;

[0031] Auxiliary tools for removing roof ridge overhangs;

[0032] Fix the ridge purlin to the upper rafters of the ancient building; restore the tiles on the roof of the ancient building and remove the supporting parts.

[0033] Optionally, install the ridge overhang auxiliary tool, including:

[0034] Correspondingly, long metal pieces are set at the rafters of the ancient building, with the top of the long metal piece lifting the roof ridge, and the bottom of the long metal piece extending between the roof ridge and the purlin, and are distributed at intervals on the front slope and the back slope of the ancient building, and the long metal pieces between the front slope and the back slope are staggered;

[0035] Wedge the long metal piece between the ridge and secure it to the purlin.

[0036] Optionally, wedging the long metal piece against the roof ridge includes:

[0037] Use triangular wooden wedges to squeeze the long metal piece and the ridge tightly;

[0038] Fix each part of the triangular wooden wedge to the long metal piece respectively.

[0039] Optionally, before dismantling the old ridge purlin in sections, the method further comprises:

[0040] Measure the elevation and center line of the old ridge purlin, and place it in the relative position to the gable.

[0041] As described above, the method for dismantling and replacing the ridge purlin of an ancient building of the present invention has the following beneficial effects:

[0042] It should be noted that the ancient buildings in southern Fujian have high cultural relic value and have beautifully shaped roof ridges. At present, when replacing the ridge purlin, the ridge purlin needs to be removed. In order to implement the principle of minimum intervention in ancient buildings and maximum preservation of historical information, this method uses the method of replacing the ridge purlin without removing the ridge purlin, which preserves the original characteristics of the building to the greatest extent and prolongs the service life of the building.

[0043] This solution preserves the integrity and historical information of the ridge of the ancient building, and relatively completely preserves its cultural value. The operation method is simple and easy to operate, and it is suitable for ancient building repair projects of various scales and environments. The overall use of equipment and materials is small, and the operation does not require a large operating surface, which is suitable for the restoration of various cultural relics. No electricity is required, and it is suitable for various regions and mountainous areas. The requirements for personnel are low, and conventional carpenters and plasterers can operate and implement it. It is especially suitable for ancient buildings with beautiful ridges that have roof requirements of Lingnan and Fujian schools. BRIEF DESCRIPTION OF THE DRAWINGS

[0044] Figure 1 Schematic diagram of the distribution of long metal pieces in an embodiment of the present invention.

[0045] Figure 2 It is a schematic diagram of the restoration status of an ancient building in an embodiment of the present invention.

[0046] Figure 3 This is a schematic diagram of the location of the opening of the hole according to an embodiment of the present invention. DETAILED DESCRIPTION

[0047] The reference numerals in the drawings of the specification include: purlin 1, ridge purlin 101, rafter 2, long metal piece 3, ridge 4, support member 5, weight bag 7, column 8, tile 9, opening 10.

[0048] The following is a description of the implementation of the present invention by means of specific embodiments. Those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification.

[0049] It should be emphasized that in the present application, the ridge purlin 101 is the purlin 1 located at the highest point of the roof.

[0050] Reference Figure 1 To Attachment Figure 3 As shown, the present application provides a method for dismantling and replacing a ridge purlin of an ancient building, comprising:

[0051] Step S110, making a new ridge purlin to be replaced based on the old ridge purlin 101 on the ancient building.

[0052] Specifically, investigate the damage status, shape characteristics, and type of wood used for the old ridge purlin 101 (including old secondary purlins and old main purlins), and issue a material list based on the shape, method, and size. Select the same wood as the old ridge purlin 101, and use the original process to process and manufacture the new ridge purlin (including new secondary purlins and new main purlins) according to the size and shape of the old ridge purlin 101, and do a good job of anti-corrosion and anti-insect treatment.

[0053] Exemplary anti-corrosion and anti-insect treatment includes: applying asphalt to the new ridge purlin where it enters the wall, and soaking the new ridge purlin in a diboron solution pool for 24 hours to prevent termites. Since the two ends of the new main purlin and the new secondary purlin are connected by dovetail joints, they cannot be installed and replaced. For ease of installation, the heads of the new main purlin are not made of dovetail joints.

[0054] In this embodiment, before making a new ridge purlin, the disease and damage degree of the old ridge purlin 101 need to be determined to determine whether the old ridge purlin needs to be replaced. The purpose of preparing the new ridge purlin to be replaced in advance is to avoid the deformation of the roof ridge due to the long placement time after the old ridge purlin 101 is removed, and to effectively ensure a reasonable production period.

[0055] Step S120, removing the tiles 9 near the main ridge 4 of the ancient building roof to form a working surface.

[0056] Specifically, the tiles are exposed and the rafters are not removed within a preset range near the roof ridge 4, so as to form a support effect of an oblique triangle at both ends of the ridge 4, thereby reducing the possibility of outward deformation of the roof ridge 4. The formation of the working surface facilitates the subsequent installation of the long metal parts 3 and ensures that the roof tiles are not crushed.

[0057] Step S130, determining the fixed point position of the roof ridge cantilever auxiliary tool, and removing the remaining tiles 9 on the roof of the ancient building at a fixed point according to the fixed point position.

[0058] In this embodiment, the roof ridge cantilever auxiliary tools include long metal pieces, counterweight bags, etc.

[0059] Specifically, the tile 9 is removed at a fixed point to facilitate the installation of the long metal piece 3 described later.

[0060] Step S140, installing the roof ridge cantilever auxiliary tool.

[0061] Specifically, long metal pieces 3 are respectively arranged at the rafter positions where the tile pieces 9 are removed. The upper part of the long metal piece 3 lifts up the bottom of the roof ridge, and the bottom penetrates into the ancient building, is located between the rafters 2, is parallel to the rafters, and is located on the two slopes of the ancient building. The positions where the two slopes pass through are staggered. The first long metal piece 3 is placed at both ends of the gable on the front slope, and the long metal piece 3 on the gable on the rear slope is staggered with the front slope by a rafter spacing. A triangular wooden wedge is used to squeeze the long metal piece 3 and the roof ridge, and each part of the wooden wedge is fixed to the ancient building by screws to prevent the wooden wedge from sliding down. The rafter body of the long metal piece 3 is fixed to the purlin 1 with self-tapping screws, with no less than two screws at each position.

[0062] In this embodiment, the long metal piece 3 is used to form a cantilever lever to cantilever the roof ridge. The wooden wedge is used to fill the gap between the long metal piece 3 and the roof ridge to balance the force; in order to prevent the triangular wooden wedge from sliding down, it is fixed with screws.

[0063] Exemplarily, the long metal piece 3 is made of steel, and is a rectangular steel tube.

[0064] Step S150, a weight bag 7 is arranged at a position where the roof ridge cantilever auxiliary tool is fixed to the upper purlin 1 of the ancient building.

[0065] Specifically, in order to prevent the rafter 2 from tilting, three weight bags 7 (or sand bags) are stacked at the position where the long metal piece 3 and the purlin 1 are fixed with screws to increase the weight.

[0066] It is worth noting that the stacked weight bags 7 play a role of counterweight to prevent the tail of the long metal piece 3 from being overstressed and tilted up.

[0067] Step S160, removing the remaining tiles 9 on the roof of the ancient building.

[0068] In this embodiment, all tiles 9 are removed to prepare for the subsequent separation of the rafters 2 from the ridge purlin 101 .

[0069] Step S170, releasing the fixation between the old ridge purlin 101 and the upper rafter 2 of the ancient building.

[0070] Exemplarily, a hacksaw is used to cut off the nails connecting the rafter 2 and the old ridge purlin 101 .

[0071] It is worth noting that, since the rafters 2 and the old ridge purlin 101 are connected and fixed with nails, if the rafters 2 are separated from the old ridge purlin 101 and the old ridge purlin 101 is taken out, the nails must be cut off.

[0072] Step S180, measuring the elevation and marking the center line of the old ridge purlin 101, and placing it at a relative position to the gable.

[0073] It is worth mentioning that since the gable brick masonry at the old ridge purlin position 101 needs to be manually removed, relative lead line measurement is used at the two positions.

[0074] Specifically, the elevation and centerline of the old ridge purlin 101 are measured and marked, and the position relative to the gable is measured. This is to accurately locate the height, level and other spatial positions of the old ridge purlin 101 after the old ridge purlin 101 is accurately removed. After the old ridge purlin 101 is repaired, the position of the new ridge purlin is consistent with the old ridge purlin 101.

[0075] It should also be noted that when determining the position of the old ridge purlin 101, the position of the old secondary purlin and the old main purlin is also determined.

[0076] Step S190 , corresponding to the position of the old ridge purlin 101 , the gable brickwork of the ancient building is removed to form the opening 10 .

[0077] Specifically, taking the intersection of the old secondary purlin and the gable as the center line, 10 opening lines with a height of 300mm and a width of 400mm are laid out up and down and left and right along the wall, and popped out with ink lines.

[0078] It is worth mentioning that this step is to accurately determine the demolition location and achieve the goal of solving the problem with minimal changes.

[0079] For example, the bricks within the demolition range are manually numbered, sketched, and photographed to record the original brick positions, original craftsmanship, original masonry methods, wall shapes, etc., so that the walls can be restored to their original state later.

[0080] For example, in order to achieve minimum intervention and avoid vibrating the wall and causing adverse side effects to the main body, the bricks of the two gables within the angle steel reinforcement range are removed manually by static force to form the opening 10. The center line of the old ridge purlin 101 is used as the reference for laying out.

[0081] Step S200, removing the old ridge purlin 101.

[0082] Specifically, the old ridge purlin 101 is cut and dismantled in sections with an electric saw, and two old secondary purlins and old main purlins are taken out from the room. The column head position can be conveniently taken out by using a crowbar.

[0083] It is worth mentioning that the old ridge purlin 101 is relatively long, and it is easier to remove it by cutting it into sections.

[0084] Step S210 , inserting a new ridge purlin from the opening 10 .

[0085] Specifically, step S210 includes step S211 and step S212.

[0086] Step S211, insert the new purlin from the opening 10 of the gable on one side, and in order to facilitate the insertion of the new purlin, the diameter of the two ends of the new purlin is reduced by 20mm. After installation, the contact part between the column 8 and the new purlin is inserted into the bottom by the method of beating.

[0087] Exemplarily, the thick support plate is a 20 mm thick steel plate.

[0088] It should be noted that the head of the new purlin is made small to leave a gap for the column head position, which is convenient for the new purlin to penetrate. The thick steel plate is inserted to fill the gap between the column 8 and the new purlin to ensure reasonable force.

[0089] Step S212, insert the new secondary purlins from the upper cave entrance 10, and install the new secondary purlins at the height and position according to the positioning and laying position before removal. The joints of the new secondary purlins are fixed with a hook to prevent the new secondary purlins from rolling.

[0090] It should also be noted that the Pajuzi is similar to a staple structure.

[0091] Step S220, repair the opening 10 on the gable and fix the new ridge purlin.

[0092] Specifically, first, build the lining gable near the gable to fix the position of the new ridge purlin. Use the paving stones to fix the new secondary purlin and the new main purlin together to prevent them from moving. Secondly, close the outer gable and repair it.

[0093] Exemplarily, one end of the protruding beam is connected to the new secondary purlin, and the other end is connected to the new main purlin.

[0094] For example, clean up the old bricks, install the original shape according to the photos taken before demolition, number the demolished green bricks, and re-build according to the sketch of the brick arrangement before demolition. After the blocking is completed, clean the wall.

[0095] Step S230, a support member 5 is arranged between the roof of the ancient building and the rafter 2 to support both sides of the roof ridge.

[0096] Specifically, in order to prevent the supporting forces on both sides of the ridge from being suddenly withdrawn after the long metal piece 3 is removed, causing the ridge to collapse or shift, support members 5 (bracing rods) are temporarily arranged on both sides of the roof to play a supporting role.

[0097] Exemplarily, the support members 5 connect the ridge 4 and the rafters 2 .

[0098] Step S240, removing the roof ridge cantilever auxiliary tool.

[0099] Specifically, the weight bag 7 and the long metal piece 3 are removed, and the damage at the junction of the main ridge 4 and the rafter is repaired.

[0100] Step S250, restore the roof tiles 9 of the ancient building and remove the support members 5.

[0101] Specifically, the manually disassembled roof tiles 9 are cleaned with clean water after the tiles are inspected and selected. The purpose of cleaning is to expose the essential features of the tiles 9, remove the mold on the surface of the tiles 9, and prevent subsequent grass and mold growth. During the installation of the tiles 9, the support members 5 are dismantled intermittently as the installation progresses.

[0102] The above embodiments are merely illustrative of the principles and effects of the present invention, and are not intended to limit the present invention. Anyone familiar with the art may modify or alter the above embodiments without departing from the spirit and scope of the present invention. Therefore, all equivalent modifications or alterations made by a person of ordinary skill in the art without departing from the spirit and technical concept disclosed by the present invention shall still be covered by the claims of the present invention.

Claims

1. A method for dismantling and replacing the ridge purlin of an ancient building, characterized in that: include: According to the old ridge purlin on the ancient building, make the new ridge purlin to be replaced; The roof of the ancient building is cantilevered to relieve the stress of the old ridge purlin; Remove the fixation between the old ridge purlin and the upper rafters of the ancient building; Corresponding to the location of the old ridge purlin, the brickwork of the gable of the ancient building was removed to form an opening; Remove the old ridge purlin and insert the new ridge purlin through the opening; Repair the opening in the gable and secure the new ridge purlin.

2. The method for dismantling and replacing the ridge purlin of an ancient building according to claim 1, characterized in that: After making the new ridge purlin to be replaced, the method further comprises: Remove the tiles outside the preset range of the main ridge of the ancient building roof to form a working surface; Determine the fixed points of the ridge cantilever auxiliary tools, and remove the remaining tiles on the roof of the ancient building according to the fixed points; Install the ridge cantilever auxiliary tools.

3. The method for replacing the ridge purlin of an ancient building according to claim 2, characterized in that: After installing the roof ridge cantilever auxiliary tool, the method further comprises: Counterweight bags are set at the positions where the roof ridge cantilever auxiliary tools and the purlins on the ancient building are fixed to balance the force; Remove the remaining tiles on the roof of the ancient building.

4. The method for dismantling and replacing the ridge purlin of an ancient building according to claim 1, characterized in that: Removal of old ridge purlin, including: Dismantle the old ridge purlin in sections; Remove the old ridge purlin from the ancient building.

5. The method for dismantling and replacing the ridge purlin of an ancient building according to claim 1, characterized in that: Insert the new ridge purlin through the opening, including: From the opening of the gable on one side, insert the new purlins of the main room; Insert thick support plates into the areas where the new purlins touch the columns of the ancient buildings; Insert the new secondary purlins from the upper part of the opening respectively; Fix the joint position between the new secondary purlin and the new main purlin.

6. The method for dismantling and replacing the ridge purlin of an ancient building according to claim 1, characterized in that: Repair the opening in the gable and fix the new ridge purlin, including: At the opening, build a lining gable to fix the position of the new ridge purlin; The outer gables were closed and repaired.

7. The method for replacing the ridge purlin of an ancient building according to claim 2, characterized in that: After repairing the opening on the gable and fixing the new ridge purlin, the method further comprises: In ancient buildings, supports are placed between the ridge and rafters to provide support on both sides of the ridge; Auxiliary tools for removing roof ridge overhangs; Fix the new ridge purlin to the upper rafters of the ancient building; Restore the tiles on the roof of the ancient building and remove the supporting parts.

8. The method for dismantling and replacing the ridge purlin of an ancient building according to claim 2, characterized in that: Install the ridge cantilever auxiliary tools, including: Correspondingly, long metal pieces are set at the rafters of the ancient building, with the top of the long metal piece lifting the roof ridge, and the bottom of the long metal piece extending between the roof ridge and the purlin, and are distributed at intervals on the front slope and the back slope of the ancient building, and the long metal pieces between the front slope and the back slope are staggered; Wedge the long metal piece between the ridge and secure it to the purlin.

9. The method for dismantling and replacing the ridge purlin of an ancient building according to claim 1, characterized in that: Wedging the long metal piece to the ridge includes: Use triangular wooden wedges to squeeze the long metal piece and the ridge tightly; Fix each part of the triangular wooden wedge to the long metal piece respectively.

10. The method for dismantling and replacing the ridge purlin of an ancient building according to claim 7, characterized in that: Before dismantling the old ridge purlin in sections, the method further comprises: Measure the elevation and center line of the old ridge purlin, and place it in the relative position to the gable.