Ultra-large type suction pile machining and manufacturing method
By adopting vertical and horizontal production methods on the upper connecting section and lower cylinder of the suction pile, and using the crawler crane for overall flipping and welding, the problem of difficulty in manufacturing super-large suction piles is solved, achieving high quality and rapid production .
Patent Information
- Application Number
- CN202411009505.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-26
- Publication Date
- 2024-12-03
AI Technical Summary
As the size of the suction pile increases, conventional lifting and production methods cannot meet the high quality, high reliability and short construction period requirements of super-large suction piles, and the manufacturing difficulty increases, and new processing and production methods are urgently needed.
The upper connecting section is vertical and the lower cylinder horizontal. The auxiliary components are prefabricated at different stations simultaneously. The prefabricated auxiliary components are welded to the upper connecting section. The track suspender flip group is used to carry out the overall sanding and paint , reduce the number of high-altitude operations and welding times, and improve welding quality control.
It shortens the production cycle, reduces the time and number of dangerous high-altitude operations, improves welding quality control, and achieves the rapid and reliable production of super-large suction piles.
Smart Images

Figure CN119057288A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of offshore wind power foundation manufacturing, and in particular to a method for processing and manufacturing super-large suction piles. Background Art
[0002] Offshore wind power is an important area of renewable energy development and an important part of strategic emerging industries. At present, my country's offshore wind power industry is also developing rapidly. With the development and progress of technology, the capacity of units is increasing, and the size of wind power mainframes and foundations is also increasing. At present, the suction pile type jacket foundation structure has been widely used in my country. With the development of products towards large capacity and large scale, the size of suction piles in wind power foundations is also increasing, and the difficulty of manufacturing is increasing.
[0003] As the outer diameter of the suction pile increases, the length of the cylinder section increases, and the weight of the product increases, conventional lifting and manufacturing methods can no longer meet the development needs of high quality, high reliability and short construction period for ultra-large suction piles. A new processing and manufacturing method for ultra-large suction piles is urgently needed. Summary of the invention
[0004] In view of the defects of the prior art, the present invention provides a method for processing and manufacturing super-large suction piles.
[0005] In order to achieve the above object, the technical solution adopted by the present invention is: A method for processing and manufacturing a super-large suction pile, wherein the suction pile is mainly composed of an upper connecting section, a lower cylinder and auxiliary components, and the auxiliary components mainly include a grouting pipeline and a suction pump interface; the basic process of processing and manufacturing is as follows: the upper connecting section is vertically manufactured, the lower cylinder is horizontally manufactured, and the auxiliary components are prefabricated simultaneously at different workstations; the prefabricated auxiliary components are welded to the upper connecting section; two main turning over ears and two auxiliary lifting ears are welded on the upper connecting section, and two tail lifting ears are welded on the lower cylinder; the upper connecting section is turned over 90 degrees from a vertical state by a crawler crane and then assembled with the horizontal lower cylinder; the suction pile is sanded and painted in a horizontal state; the super-large suction pile is turned over from a horizontal state to an upright state by a crawler crane, and finally an inspection and acceptance is carried out.
[0006] Furthermore, the specific steps for making the upper connecting section are as follows: taking the bottom plate as a reference, installing the support columns on the bottom plate and welding them, and at the same time, assembling and connecting the web plate and the cover plate at different workstations, and then welding the assembled web plate and the cover plate to the bottom plate around the support columns; and then sequentially welding the top plate, the side plate and the rib plate, wherein the top plate is located above the support columns, the side plates are located on both sides of the web plate, and the rib plate is located on the bottom plate between the web plates.
[0007] Furthermore, the lower cylinder body is assembled by horizontally welding a plurality of cylinder segments on a special welding roller frame. During the manufacturing process, the plurality of cylinder segments are firstly positioned and spot welded, and then a plurality of circumferential seams are synchronously welded.
[0008] Furthermore, the tail lifting lug is arranged on the second cylinder section at the bottom of the lower cylinder.
[0009] Furthermore, before the multiple cylinder segments of the lower cylinder are assembled and welded, supporting fixtures need to be welded inside the cylinder segments to improve the rigidity of the cylinder segments.
[0010] Furthermore, when the suction pile is turned over to an upright state, it is necessary to remove the tail lifting lug welded to the outside of the lower cylinder and the supporting tooling welded to the inside of each cylinder section of the lower cylinder.
[0011] Furthermore, the turning process of the upper connecting section is as follows: one crawler crane hangs two main turning ears through two shackles, and the other crawler crane hangs two auxiliary ears through two shackles; the two crawler cranes lift the upper connecting section at the same lifting speed and lift the upper connecting section to a safe position for turning over; the crawler crane hanging the main turning ears remains stationary, and the crawler crane hanging the auxiliary ears continues to lift until the upper connecting section changes from a horizontal state to a vertical state, and adjusts the misalignment between the upper connecting section and the lower cylinder. After the misalignment is adjusted to within 3mm, positioning welding is performed.
[0012] Furthermore, after the suction pile is manufactured horizontally, it is sandblasted and painted as a whole in a horizontal state. The sandblasting and painting range is mainly the upper connecting section and the lower cylinder within 2m below the mud surface.
[0013] Furthermore, the specific process of flipping the super-large suction pile from a horizontal state to an upright state is as follows: two crawler cranes hang the two main turning lifting ears on the upper connecting section through the shackles respectively, and the other crawler crane hangs the two tail lifting ears on the lower cylinder through the shackles; the three crawler cranes lift the horizontal suction pile steadily at the same lifting speed to the height required for turning; the crawler crane hanging the tail lifting ears stops lifting, and the two crawler cranes hanging the main turning lifting ears lift synchronously until the suction pile is flipped to an upright state.
[0014] Furthermore, the inspection and acceptance of suction piles mainly involves checking the size, tolerance and paint quality of the suction piles. The inspection items include straightness, axis vector, cylinder roundness, suction pile height, magnetic particle inspection of polished surface and paint film quality.
[0015] Beneficial effects: The present invention divides the production of large suction piles into an upper connecting section, a lower cylinder, and various auxiliary components. During the processing and manufacturing process, the various parts are prefabricated simultaneously at different workstations; after the prefabrication is completed, the auxiliary components are first welded to the upper connecting section in a horizontal state, and then hoisted and turned over as a whole to a horizontal state to be welded and assembled with the horizontally manufactured cylinder; after the assembly is completed, the suction pile is hoisted and turned over as a whole. For the overall production and manufacturing process of the suction pile, the present invention can greatly shorten the production cycle, reduce the time and number of dangerous high-altitude operations, and in addition, compared with other methods in the prior art, the present invention has less vertical welding and overhead welding and more flat welding, which is more conducive to the welding quality control of the suction pile. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a three-dimensional schematic diagram of the entire super-large suction pile; Figure 2 It is a schematic diagram of the manufacturing process of the upper connecting section; Figure 3 It is a schematic diagram of the manufacturing process of the lower cylinder; Figure 4 is a schematic diagram of the arrangement of lifting lugs on the upper connecting section; Figure 5 It is a schematic diagram of the arrangement of the lifting lugs on the lower cylinder; Figure 6 This is a schematic diagram of the position of the upper connecting section and the lower cylinder after prefabrication Figure 7 It is a schematic diagram of the turning-over process of the upper connecting section and the attached components; Figure 8 This is a schematic diagram of the upper connecting section being welded and connected to the lower cylinder after turning over; Fig. 9 It is a schematic diagram of the overall lifting and turning of the suction pile.
[0017] Markings in the figure: 1. Upper connecting section; 101. Bottom plate; 102. Support column; 103. Web plate; 104. Top plate; 105. Side plate; 106. Cover plate; 107. Rib plate; 2. Lower cylinder; 201. Cylinder section; 202. Support tooling; 3. Grouting pipeline; 4. Suction pump interface; 5. Main turning lifting eye; 6. Auxiliary lifting eye; 7. Tail lifting eye. DETAILED DESCRIPTION
[0018] The present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.
[0019] As attached Figure 1As shown in the figure, the suction pile mainly includes an upper connecting section 1, a lower cylinder 2 and related auxiliary components, wherein the auxiliary components are mainly a grouting pipeline 3 and a suction pump interface 4, and the grouting pipeline 3 and the suction pump interface 4 are installed on the upper connecting section 1. In addition, in order to meet the production needs, two main lifting ears 5 and two auxiliary lifting ears 6 are welded on the upper connecting section 1, and two tail lifting ears 7 are welded on the lower cylinder 2. In order to improve the rigidity of the lower cylinder 2, a temporary support tooling 202 is welded inside it.
[0020] The basic process of suction pile production is: the upper connecting section 1 is produced vertically; the lower cylinder 2 is produced horizontally; the grouting pipeline 3 and the suction pump interface 4 are produced simultaneously at other workstations, and then installed on the upper connecting section 1 after production is completed; two main lifting ears 5 and two tail lifting ears 6 are welded on the upper connecting section 1, and two tail lifting ears 6 are welded on the lower cylinder 2; the upper connecting section 1 is turned over 90° and assembled horizontally with the lower cylinder 2; the suction pile is turned over as a whole to an upright state; the two tail lifting ears 6 and the supporting tooling welded inside the lower cylinder 2 are removed; the appearance and paint quality of the suction pile are inspected and accepted.
[0021] The specific process steps for processing and manufacturing the super-large suction piles described in the present invention are as follows: Step a, vertical production of the upper connecting section 1: The upper connecting section is mainly composed of a bottom plate 101, a support column 102, a web 103, a top plate 104, a side plate 105, a cover plate 106 and a rib plate 107; the production process of the upper connecting section 1 is as shown in the attached figure. Figure 2 As shown, during the production, the base plate 101 is used as a reference, and the support column 102 is positioned and installed on it, and the web plate 103 and the cover plate 106 are welded and connected at different stations, and then the two parts that have been assembled are welded and connected, that is, the connected web plate 103 and the cover plate 106 are welded to the base plate 101 equipped with the support column 102; and then the top plate 104, the side plate 105 and the rib plate 107 are welded in sequence. The advantage of the vertical production of the upper connecting section 1 is accurate positioning, and the overhead welding and horizontal welding in the welding process are changed to flat welding, which ensures the welding quality and speeds up the production efficiency, with less overhead welding and vertical welding and more flat welding, and the welding quality is easier to control.
[0022] Step b, horizontal production of the lower cylinder 2: The lower cylinder 2 is composed of a plurality of cylinder sections 201 of different plate thicknesses which are horizontally welded on a special welding roller frame. The production process includes: steel plate blanking, splicing, rolling, longitudinal seam welding, correction, welding assembly and the like. During the production process, a plurality of cylinder sections 201 can be firstly positioned and spot welded, and then a plurality of circumferential seams can be simultaneously welded to improve work efficiency. Among them, before the plurality of cylinder sections 201 are assembled and welded, a supporting tool 202 needs to be welded inside the cylinder section 201, in order to improve the rigidity of the cylinder section 201, so as to improve the production accuracy of the lower cylinder 2. The production process of the lower cylinder 2 is as follows: Figure 3 shown.
[0023] Step c: welding the main lifting lug 5 and the auxiliary lifting lug 6: Figure 4 As shown, according to the production process requirements, four lifting ears are arranged on the upper connecting section 1 after prefabrication, which are used for turning over the upper connecting section 1, two of which are main turning over lifting ears 5, and two are auxiliary lifting ears 6. The four lifting ears are arranged on different web edges respectively. Figure 4 The vertical planes shown are symmetrical, wherein Figure 4 (b) Figure 4 (a) Top view.
[0024] Step d, welding of tail lifting lug 7: Figure 5 As shown ( Figure 5 (a) and Figure 5 (b) is a schematic diagram of the lower cylinder at different angles. Two tail lifting ears 7 are arranged on the lower cylinder 2. The arrangement position is on the second cylinder section 201 at the bottom of the lower cylinder 2. The two tail lifting ears 7 are located on the same side of the lower cylinder 2 and cooperate with the main turning lifting ears 5 on the upper connecting section 1 to perform the overall turning of the suction pile. The two tail lifting ears 7 are symmetrical about the vertical center plane of the lower cylinder 2. Among them, the main turning lifting ears 5 on the upper connecting section 1 are of a common design and can be used in both hoisting and turning processes, but they have different functions. For details, see steps f and h.
[0025] Step e: Production and installation of auxiliary components: Figure 6 As shown, the auxiliary components on the suction pile mainly include a grouting pipeline 3 and a suction pump interface 4. The prefabrication of the grouting pipeline 3 and the suction pump interface 4 can be synchronized with the upper connecting section 1 and the lower cylinder 2 at different stations. This manufacturing method can improve the manufacturing efficiency; the prefabricated grouting pipeline 3 and the suction pump interface 4 are welded to the upper connecting section 1 according to the dimensions on the drawing, and the auxiliary components are installed before the upper connecting section 1 is turned over, which can avoid high-altitude operations and improve work efficiency.
[0026] Step f, the upper connecting section 1 is turned 90 degrees and assembled horizontally with the lower cylinder 2. Figure 7 and Figure 8As shown, the equipment required for turning over the upper connection section 1 is: two crawler cranes, main turning lifting lugs 5, auxiliary lifting lugs 6, shackles and wire ropes. The main turning lifting lugs 5 play the role of tail lifting lugs in this process. The turning over process of the upper connection section 1 is as follows: one crawler crane hangs two main turning lifting lugs 5 through two shackles, and the other crawler crane hangs two auxiliary lifting lugs 6 through two shackles; the two crawler cranes lift the upper connection section 1 at the same lifting speed and lift the upper connection section 1 to a safe position for turning over; the crawler crane hanging the main turning lifting lugs 5 is stationary, and the crawler crane hanging the auxiliary lifting lugs 6 continues to lift until the upper connection section 1 changes from a horizontal state to a vertical state, and adjusts the misalignment between the upper connection section 1 and the lower cylinder 2. After the misalignment is adjusted within 3mm, positioning welding is performed.
[0027] Step g, sandblasting and painting of the suction pile as a whole: After the horizontal suction pile is manufactured, sandblasting and painting are performed as a whole. The sandblasting and painting range is mainly the upper connecting section 1 and the lower cylinder 2 within 2m below the mud surface.
[0028] Step h: Turn over the suction pile as a whole: Fig. 9 As shown in the figure, after the suction pile is manufactured horizontally, it needs to be turned over to an upright state. The equipment required for the overall turning over of the suction pile includes: three crawler cranes, two main turning over lifting eyes 5, two tail lifting eyes 7, shackles and wire ropes. The specific turning over process is as follows: two crawler cranes hang the two main turning over lifting eyes 5 on the upper connecting section through shackles, and another crawler crane hangs the two tail lifting eyes 7 on the cylinder through shackles; the three crawler cranes lift the horizontal suction pile steadily at the same lifting speed to the required height for turning over; the crawler crane hanging the tail lifting eyes 7 stops lifting, and the two crawler cranes hanging the main turning lifting eyes 5 are lifted synchronously until the suction pile is turned over to an upright state.
[0029] Step i, removal of the tail lifting lug 7 and the supporting tooling 202: When the suction pile is turned over to an upright state, the tail lifting lug 7 welded to the outside of the lower cylinder 2 and the supporting tooling welded to the inside of each cylinder section 201 of the lower cylinder 2 need to be removed; Step j, suction pile inspection and acceptance: After the tail lifting lug 7 and the supporting fixture 201 on the suction pile are removed, various inspections of the suction pile are started, including inspections of the suction pile size, tolerance and paint quality. The items to be inspected include straightness, axis vector, cylinder roundness, suction pile height, magnetic particle inspection of the polished surface and paint film quality.
[0030] Step a to step j are the overall production process of the super-large suction pile of the present invention, including the hoisting process.
[0031] Compared with the prior art, the present invention adopts a vertical method to manufacture the upper connecting section of the suction pile, which improves the assembly accuracy and work efficiency of the upper connecting section, and changes vertical welding and overhead welding to flat welding, which is more conducive to controlling the welding quality of the product and improving the welding efficiency; the auxiliary components are simultaneously prefabricated at different workstations with the upper connecting section and the lower cylinder, which shortens the production period of the product, and the upper connecting section and the lower cylinder are assembled horizontally and then turned upright, with a fast turning speed and easy control of the process, thereby reducing the number and time of high-altitude operations; the lower cylinder of the suction pile is manufactured horizontally with high manufacturing efficiency. Compared with the vertical manufacturing method, horizontal welding and vertical welding are changed to flat welding, with high welding quality, fast welding speed and small welding residual stress; the turning ears of the upper connecting section and the overall turning ears of the suction pile share a common design, thereby reducing the number of process ears.
[0032] The technical solutions and implementation methods listed in the present invention are not limiting, and solutions and methods that are equivalent to or have the same effects as the technical solutions and implementation methods listed in the present invention are all within the scope of protection of the present invention.
Claims
1. A method for processing and manufacturing super-large suction piles, characterized in that: The suction pile is mainly composed of an upper connecting section, a lower cylinder and auxiliary components, and the auxiliary components mainly include a grouting pipeline and a suction pump interface; the basic processing and manufacturing process is: the upper connecting section is manufactured vertically, the lower cylinder is manufactured horizontally, and the auxiliary components are prefabricated simultaneously at different workstations; the prefabricated auxiliary components are welded to the upper connecting section; two main turning ears and two auxiliary lifting ears are welded on the upper connecting section, and two tail lifting ears are welded on the lower cylinder; the upper connecting section is turned 90° from a vertical state by a crawler crane and then assembled with the horizontal lower cylinder; the suction pile is sanded and painted in a horizontal state; the super-large suction pile is turned over from a horizontal state to an upright state by a crawler crane, and finally an inspection and acceptance is carried out.
2. The method for manufacturing a super-large suction pile according to claim 1, characterized in that: The specific steps for making the upper connecting section are: taking the bottom plate as a reference, installing the support columns on the bottom plate and welding them, at the same time, assembling and connecting the web plate and the cover plate at different workstations, and then welding the assembled web plate and the cover plate to the bottom plate around the support columns; then sequentially welding the top plate, the side plate and the rib plate, wherein the top plate is located above the support columns, the side plates are located on both sides of the web plate, and the rib plate is located on the bottom plate between the web plates.
3. The method for manufacturing a super-large suction pile according to claim 1, characterized in that: The lower cylinder is composed of multiple cylinder segments that are horizontally welded on a special welding roller frame. During the production process, multiple cylinder segments are first positioned and spot welded, and then multiple circumferential seams are welded synchronously.
4. The method for manufacturing a super-large suction pile according to claim 3 is characterized in that: The tail lifting lug is arranged on the second section of the bottom of the lower cylinder.
5. The method for manufacturing a super-large suction pile according to claim 3 is characterized in that: Before the multiple cylinder segments of the lower cylinder are assembled and welded, supporting fixtures need to be welded inside the cylinder segments to improve the rigidity of the cylinder segments.
6. The method for manufacturing a super-large suction pile according to claim 5, characterized in that: When the suction pile is turned over to an upright state, it is necessary to remove the tail lifting lug welded to the outside of the lower cylinder and the supporting tooling welded to the inside of each cylinder section of the lower cylinder.
7. The method for manufacturing a super-large suction pile according to claim 1, characterized in that: The turning process of the upper connecting section is as follows: one crawler crane hangs two main turning lifting ears through two shackles respectively, and the other crawler crane hangs two auxiliary lifting ears through two shackles respectively; the two crawler cranes lift the upper connecting section at the same lifting speed and lift the upper connecting section to a safe position for turning over; the crawler crane hanging the main turning lifting ears remains stationary, and the crawler crane hanging the auxiliary lifting ears continues to lift until the upper connecting section changes from a horizontal state to a vertical state, and adjusts the misalignment between the upper connecting section and the lower cylinder. After the misalignment is adjusted to within 3mm, positioning welding is performed.
8. The method for manufacturing a super-large suction pile according to claim 1, characterized in that: After the horizontal production of the suction pile is completed, the entire pile is sandblasted and painted in a horizontal state. The sandblasting and painting range is mainly the upper connecting section and the lower cylinder within 2m below the mud surface.
9. The method for manufacturing a super-large suction pile according to claim 1, characterized in that: The specific process of flipping the super-large suction pile from a horizontal state to an upright state is as follows: two crawler cranes hang the two main turning lifting ears on the upper connecting section through the shackles respectively, and the other crawler crane hangs the two tail lifting ears on the lower cylinder through the shackles; the three crawler cranes lift the horizontal suction pile steadily at the same lifting speed to the required height for turning; the crawler crane hanging the tail lifting ears stops lifting, and the two crawler cranes hanging the main turning lifting ears lift synchronously until the suction pile is flipped to an upright state.
10. The method for manufacturing a super-large suction pile according to claim 1, characterized in that: The inspection and acceptance of suction piles mainly involves checking the size, tolerance and paint quality of the suction piles. The inspection items include straightness, axis vector, cylinder roundness, suction pile height, magnetic particle inspection of polished surface and paint film quality.
Citation Information
Cited By
Split type suction pile for ultra-deepwater well drilling and lowering method of split type suction pile
CN120867668A