Construction method and construction system of foundation pit enclosing purlin
By using traction mechanism and triangular support in foundation pit construction, the problems of low efficiency and danger during the installation of steel purlins are solved, and efficient and safe installation of foundation pit purlins is achieved, reducing construction costs and manpower Waste of resources.
Patent Information
- Application Number
- CN202411330610.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-24
- Publication Date
- 2024-12-03
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In the existing foundation pit construction methods, the crane position needs to be frequently adjusted during the installation of steel purlins, resulting in low construction efficiency and high risk, and there is a risk of collision between the crown beam on the top of the foundation pit and the steel purlins during the lifting process, wasting manpower and material resources.
The traction mechanism is adopted, including lifting equipment, wire rope, fixed pulley and traction hook, and the purlin is supported by triangular support. The purlin is oriented and transversely installed by using wire rope and traction hook, reducing crane position adjustment, and improving construction safety and efficiency.
It improves construction efficiency, reduces the demand for labor and large-scale equipment, reduces construction costs, enhances construction safety, and avoids the damage to the steel support system.
Smart Images

Figure CN119061904A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of foundation pit construction, and in particular relates to a construction method and a construction system for a foundation pit perimeter purlin. Background Art
[0002] In the process of open-cut construction of existing large underground spaces such as tunnels, pipe galleries, and subways, in order to prevent the collapse of the deep foundation pit slope, the crown beam + steel purlin system is usually used to apply prestress to support the deep foundation pit. This type of construction method often requires the crane position to be constantly adjusted according to the installation position during the installation of the steel purlin, resulting in serious construction efficiency reduction; and due to the influence of the site space, there is a situation where the crane cannot stand during the installation of the steel purlin, and there is a risk of collision between the crown beam at the top of the foundation pit and the steel purlin during the hoisting process, which can easily cause damage to the steel support system. In order to prevent the steel purlin from being damaged during the hoisting process, multiple people are required to assist in the hoisting process, which wastes manpower and material resources, and the use of large machinery at the edge of the deep foundation pit is extremely dangerous.
[0003] Therefore, it is necessary to design a construction method for installing surrounding purlins in deep foundation pits. Summary of the invention
[0004] The invention provides a construction method and a construction system for a foundation pit perimeter purlin, which are used to solve the problems in the prior art that the position of a crane often needs to be constantly adjusted when installing the perimeter purlin, the construction efficiency is low, and the danger is high.
[0005] In one aspect, the present invention provides a method for constructing a foundation pit purlin, comprising the following steps: (1) Install a traction mechanism on the side of the retaining pile close to the foundation pit, and install two or more triangular supports at intervals on the first horizontal line of the retaining pile close to the foundation pit and at a vertical distance of 50 cm from the bottom; The traction mechanism includes a lifting device, a steel wire rope, a fixed pulley and a traction hook; the triangular support includes a bracket, a roller seat and a roller, the roller seat is fixedly installed above the bracket, and the roller is rotatably connected to the bracket through the roller seat; Install the fixed pulley above the triangular support at the edge of the first horizontal line, and install the lifting equipment on the side of the crown beam above the guard pile and at the same vertical position as the fixed pulley; one end of the wire rope is connected to the lifting equipment, and the other end of the wire rope connected to the traction hook passes over the fixed pulley and is placed above the triangular support roller on the first horizontal line; (2) Hoist and lower the purlin above the triangular support at the end farthest from the fixed pulley, and adjust the position of the purlin so that the ribs on both sides of the purlin are stuck into the pulley; (3) Hook the traction hook into the reserved hole of the purlin, adjust the position of the wire rope, and start the lifting equipment to move the purlin horizontally along the roller to the top of the triangular support close to the fixed pulley and fix it. At the same time, hoist and lower the next section of the purlin above the triangular support at the end far from the fixed pulley. Repeat step (3) until there is only enough space for lowering one purlin. The installation of the first purlin is completed.
[0006] Compared with the prior art, the present invention is beneficial in that: The purlins are installed through a traction mechanism, which has high construction efficiency, fast progress, high safety in the construction process, saves manpower, reduces labor intensity, reduces the cost of large machinery and equipment, and reduces construction costs.
[0007] Furthermore, after step (3), the method further includes: (4) continuing to excavate the foundation pit downwards, and installing two or more triangular supports at intervals on a second horizontal line 50 to 80 cm below the first perimeter purlin; transferring the fixed pulley to the top of the triangular support located at the outermost edge of the second horizontal line, connecting one end of the wire rope to the lifting equipment, and placing the other end of the wire rope connected to the traction hook over the fixed pulley and then placed above the triangular support roller on the second horizontal line; repeating steps (2) and (3), and the installation of the second perimeter purlin is completed.
[0008] Furthermore, after step (4), the method further includes: (5) after the excavation of the foundation pit is completed, the second perimeter purlin is installed in the remaining position, the towing hook is removed, and the first perimeter purlin is installed in the remaining position, thereby completing the installation of the perimeter purlin.
[0009] Furthermore, the purlin is made of steel, and includes two H-shaped steel plates and two side plates, and the side plates are fixed on both sides of the two H-shaped steel plates.
[0010] On the other hand, the present invention also provides a foundation pit purlin construction system for realizing the above-mentioned foundation pit purlin construction method, comprising: a retaining pile, a traction mechanism, two or more triangular supports, and two or more purlins; The traction mechanism is installed on the side of the retaining pile close to the foundation pit, and the triangular support is fixedly installed on the first horizontal line of the retaining pile close to the foundation pit and at a vertical distance of 50~80cm from the bottom; The traction mechanism includes a lifting device, a steel wire rope, a fixed pulley and a traction hook. The fixed pulley is installed above the triangular support located at the edge of the first horizontal line; the lifting device is installed on the side of the crown beam above the retaining pile and at the same vertical position as the fixed pulley; one end of the steel wire rope is connected to the lifting device, and the other end of the steel wire rope is connected to the traction hook; The triangular support is used to support the perimeter purlin. The triangular support includes a bracket, a roller seat and a roller. The roller seat is fixedly installed above the bracket, and the roller is rotatably connected to the bracket through the roller seat. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1This is a schematic diagram of the first purlin being hoisted into place in an embodiment of the present invention; Figure 2 1 is a schematic diagram of the transverse movement of the purlin according to an embodiment of the present invention; Figure 3 1 is a schematic diagram showing the first purlin having been installed in an embodiment of the present invention; Figure 4 This is a schematic diagram of the installation of a triangular support according to an embodiment of the present invention; Figure 5 Schematic diagram of a traction hook connected to a purlin according to an embodiment of the present invention; Figure 6 It is a schematic diagram showing the installation of the purlin according to an embodiment of the present invention.
[0012] Description of reference numerals: 1. Purlin; 11. Rib; 12. Reserved holes; 2. Traction mechanism; 21. Lifting equipment; 22. Wire rope; 23. Fixed pulley; 24. Traction hook; 3. Crown beam; 4. Triangular support; 41. Bracket; 42. Roller; 43. Expansion screw; 5. Foundation pit; 6. Guard pile. DETAILED DESCRIPTION
[0013] In order to make the purpose, technical solutions and advantages of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in combination with the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0014] See also Figure 1 to Figure 6 The present invention provides a construction method of a foundation pit purlin, comprising the following steps: (1) Install a traction mechanism 2 on the side of the retaining pile 6 close to the foundation pit 5, and install two or more triangular supports 4 at intervals on the first horizontal line of the retaining pile 6 close to the foundation pit 5 and at a vertical distance of 50 to 80 cm from the bottom; The traction mechanism 2 includes a lifting device 21, a wire rope 22, a fixed pulley 23 and a traction hook 24; the triangular support 4 includes a bracket 41, a roller 42 seat and a roller 42, the roller 42 seat is fixedly installed above the bracket 41, and the roller 42 is rotatably connected to the bracket 41 through the roller 42 seat; The fixed pulley 23 is installed above the triangular support 4 at the edge of the first horizontal line, and the lifting device 21 is installed on the side of the crown beam 3 above the retaining pile 6 and at the same vertical position as the fixed pulley 23; one end of the wire rope 22 is connected to the lifting device 21, and the other end of the wire rope 22 connected to the traction hook 24 passes over the fixed pulley 23 and is placed above the roller 42 of the triangular support 4 on the first horizontal line; (2) Hoist and lower the purlin 1 above the triangular support 4 at one end away from the fixed pulley 23, and adjust the position of the purlin 1 so that the ribs 11 on both sides of the purlin 1 are engaged with the pulley; (3) Hook the traction hook 24 into the reserved hole 12 of the purlin 1, adjust the position of the wire rope 22, and then start the lifting device 21 to make the purlin 1 move horizontally along the roller 42 to the top of the triangular support 4 close to the fixed pulley 23 and fix it. At the same time, hoist and lower the next section of the purlin 1 above the triangular support 4 at the end away from the fixed pulley 23. Repeat step (3) until there is only enough space for lowering one purlin 1. The installation of the first purlin 1 is completed.
[0015] Specifically, the construction section has completed the construction of the retaining piles 6 on both sides of the foundation pit 5, and installed a traction mechanism 2 on the side of the retaining piles 6 close to the foundation pit 5, wherein the traction mechanism 2 includes a lifting device 21, a wire rope 22, a fixed pulley 23 and a traction hook 24; and more than two triangular supports 4 are installed at intervals on the first horizontal line at a vertical distance of 50 to 80 cm from the bottom on the side of the retaining piles 6 close to the foundation pit 5, and the triangular supports 4 are arranged at intervals and horizontally on the first horizontal line.
[0016] The triangular support 4 includes a bracket 41 with a triangular cross-section, a roller seat and a roller 42. The bracket 41 is installed on the guardrail pile 6 through an expansion screw 43, and the roller seat is fixed on the top of the bracket 41 by welding. The roller 42 is rotatably connected to the bracket 41 through the roller seat; the triangular support 4 is used to support the surrounding purlin 1; the surrounding purlin 1 is made of steel, including two H-shaped steel plates and two side plates, and the side plates are welded on both sides of the two H-shaped steel plates.
[0017] The fixed pulley 23 is installed above the triangular support 4 located at the outermost edge of the first horizontal line, and the lifting equipment 21 is installed on the side of the crown beam 3 above the guard pile 6 and at the same vertical position as the fixed pulley 23; one end of the wire rope 22 is connected to the lifting equipment 21, and the other end of the wire rope 22 is connected to the traction hook 24 and then passed around the fixed pulley 23 and placed above the roller 42 of the triangular support 4 on the first horizontal line.
[0018] At the end of the foundation pit 5 away from the fixed pulley 23, the assembled purlin 1 is hoisted to a position about 10 cm above the triangular support 4, and the hoisting and lowering is stopped. The position of the purlin 1 is adjusted to align the ribs 11 on both sides of the purlin 1 with the rollers 42, and then the purlin 1 is continued to be lowered to clamp the ribs 11 on both sides of the purlin 1 into the rollers 42.
[0019] The traction hook 24 is hung in the reserved hole 12 of the purlin 1, the wire rope 22 is positioned correctly, and the lifting device 21 is started to move the purlin 1 along the roller 42 to the other end of the foundation pit 5 and fix it. Figure 2As shown, during the transverse movement of the purlin 1, the next steel purlin 1 is hoisted into place, the lifting equipment 21 is closed, and the traction hook 24 is hung to the reserved hole 12 of the next purlin 1 to move it transversely to the specified position until the first steel purlin 1 is completely installed, a space for the purlin 1 is reserved, and the installation of the first purlin is completed.
[0020] In a specific embodiment, after the first steel purlin 1 is installed, a foundation pit 5 is excavated to 50-80 cm below the second purlin 1, and two or more triangular supports 4 are installed at intervals on a second horizontal line 50-80 cm below the first purlin 1; the position of the fixed pulley 23 is adjusted to be above the triangular support 4 at the edge of the second horizontal line, and the above steps are repeated to hoist the purlin 1 and start the lifting equipment 21 to install each section of the purlin 1 in place in turn; the installation of the second purlin 1 is completed.
[0021] In a specific embodiment, after the excavation of the foundation pit 5 is completed, the second purlin 1 is installed in the vacant position, the traction hook 24 is removed, and the first purlin 1 is installed in the vacant position to complete the installation of the purlin 1.
[0022] In one embodiment, the purlin 1 is made of steel, and includes two H-shaped steel plates and two side plates, and the side plates are welded to both sides of the two H-shaped steel plates.
[0023] Optionally, the lifting device 21 is an electric hoist.
[0024] The present invention does not limit the specific number of sections and the number of rows of the surrounding purlin 1 , and it can be adaptively adjusted according to the length and depth of the foundation pit 5 .
[0025] The present invention also provides a construction system for a foundation pit 5 surrounding purlin 1, which is used to implement the above-mentioned construction method for the foundation pit 5 surrounding purlin 1, comprising: a retaining pile 6, a traction mechanism 2, two or more triangular supports 4, and two or more surrounding purlins 1; The traction mechanism 2 is installed on the side of the retaining pile 6 close to the foundation pit 5, and the triangular support 4 is fixedly installed on the first horizontal line of the retaining pile 6 close to the foundation pit 5 and at a vertical distance of 50 to 80 cm from the bottom; The traction mechanism 2 includes a lifting device 21, a steel wire rope 22, a fixed pulley 23 and a traction hook 24. The fixed pulley 23 is installed above the triangular support 4 at the edge of the first horizontal line. The lifting device 21 is installed on the side of the crown beam 3 above the retaining pile 6 and at the same vertical position as the fixed pulley 23. One end of the steel wire rope 22 is connected to the lifting device 21, and the other end of the steel wire rope 22 is connected to the traction hook 24. The triangular support 4 is used to support the surrounding purlin 1. The triangular support 4 includes a bracket 41, a roller 42 seat and a roller 42. The roller 42 seat is fixedly installed above the bracket 41, and the roller 42 is rotatably connected to the bracket 41 through the roller 42 seat.
[0026] In one embodiment, the traction hook 24 is hung in the reserved hole 12 of the purlin 1 to pull the purlin 1 so that the purlin 1 moves laterally along the roller 42 in a directional manner.
[0027] In a specific embodiment, the purlin 1 is made of steel, and includes two H-shaped steel plates and two side plates, and the side plates are fixed on both sides of the two H-shaped steel plates.
[0028] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the above embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the above embodiments, or replace some or all of the technical features therein by equivalents. If these modifications and variations fall within the scope of the claims of the present invention and their equivalent technologies, they should be considered to be within the protection scope of the present invention.
Claims
1. A construction method for foundation pit purlins, characterized in that: The following steps are involved: (1) Install a traction mechanism on the side of the retaining pile close to the foundation pit, and install two or more triangular supports at intervals on the first horizontal line of the retaining pile close to the foundation pit and at a vertical distance of 50 to 80 cm from the bottom; The traction mechanism includes a lifting device, a steel wire rope, a fixed pulley and a traction hook; the triangular support includes a bracket, a roller seat and a roller, the roller seat is fixedly installed above the bracket, and the roller is rotatably connected to the bracket through the roller seat; Install the fixed pulley above the triangular support at the edge of the first horizontal line, and install the lifting equipment on the side of the crown beam above the guard pile and at the same vertical position as the fixed pulley; one end of the wire rope is connected to the lifting equipment, and the other end of the wire rope connected to the traction hook passes over the fixed pulley and is placed above the triangular support roller on the first horizontal line; (2) Hoist and lower the purlin above the triangular support at the end farthest from the fixed pulley, and adjust the position of the purlin so that the ribs on both sides of the purlin are stuck into the pulley; (3) Hook the traction hook into the reserved hole of the purlin, adjust the position of the wire rope, and start the lifting equipment to move the purlin horizontally along the roller to the top of the triangular support close to the fixed pulley and fix it. At the same time, hoist and lower the next section of the purlin above the triangular support at the end far from the fixed pulley. Repeat step (3) until there is only enough space for lowering one purlin. The installation of the first purlin is completed.
2. The construction method of foundation pit purlin according to claim 1, characterized in that: After step (3), the following steps are also included: (4) Continue to dig the foundation pit downwards, and install two or more triangular supports at intervals on the second horizontal line 50 to 80 cm below the first perimeter purlin; move the fixed pulley to the top of the triangular support at the edge of the second horizontal line, connect one end of the wire rope to the lifting equipment, and the other end of the wire rope connected to the traction hook passes over the fixed pulley and is placed above the triangular support roller on the second horizontal line; repeat steps (2) and (3) to complete the installation of the second perimeter purlin.
3. The construction method of foundation pit purlin according to claim 2, characterized in that: After step (4), the method further includes: (5) After the excavation of the foundation pit is completed, install the remaining position of the second purlin, remove the towing hook, install the remaining position of the first purlin, and complete the installation of the purlin.
4. The construction method of foundation pit purlin according to any one of claims 1 to 3, characterized in that: The purlin is made of steel, including two H-shaped steel plates and two side plates, and the side plates are fixed on both sides of the two H-shaped steel plates.
5. A construction system for foundation pit purlins, used to implement the construction method for foundation pit purlins according to any one of claims 1 to 4, characterized in that: include: Guard piles, traction mechanism, two or more triangular braces, two or more enclosure purlins; The traction mechanism is installed on the side of the retaining pile close to the foundation pit, and the triangular support is fixedly installed on the first horizontal line of the retaining pile close to the foundation pit and at a vertical distance of 50~80cm from the bottom; The traction mechanism includes a lifting device, a steel wire rope, a fixed pulley and a traction hook. The fixed pulley is installed above the triangular support located at the edge of the first horizontal line; the lifting device is installed on the side of the crown beam above the retaining pile and at the same vertical position as the fixed pulley; one end of the steel wire rope is connected to the lifting device, and the other end of the steel wire rope is connected to the traction hook; The triangular support is used to support the perimeter purlin. The triangular support includes a bracket, a roller seat and a roller. The roller seat is fixedly installed above the bracket, and the roller is rotatably connected to the bracket through the roller seat.
Citation Information
Patent Citations
Foundation ditch construction method in water for supporting circuit purlin
CN101289862A
Installation system and installation method for steel support inside foundation pit
CN108396749A
Method for constructing foundation pit with circulating steel supports
CN111074903A
Construction process for installing steel purlins and steel supports on water
CN111236253A
Disassembly-free quick mounting construction method for supporting structure of deep foundation pit of open cut tunnel
CN118461618A