Anti-seepage construction method for underground space cast-in-place side wall structure
By using anti-seepage steel formwork device, telescopic steel pipe support device and pulling screw device in the cast-in-place side wall structure of the underground space of the pipe corridor, the problems of leakage and screw setting during construction are solved, and efficient prevention is achieved Infiltration construction and rapid formwork turnover have improved structural performance and construction efficiency.
Patent Information
- Application Number
- CN202411380645.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-30
- Publication Date
- 2024-12-03
AI Technical Summary
The cast-in-place side wall structures in existing underground spaces such as pipe corridors are prone to leakage problems during construction, and traditional pulling screws are difficult to set up, affecting the surface quality and structural performance of the concrete.
The screw-free support system is composed of anti-seepage steel formwork device, telescopic steel pipe support device and pull-out screw device. By standardizing the adjustment length of the steel mold side formwork and telescopic steel pipe, combined with the hoisting rack and stiffening plate, it can achieve rapid installation and Demolition to ensure the compactness and structural stability of the construction joints.
It effectively solves the problem of side wall leakage, improves the anti-seepage performance of the underground space structure, ensures one-time qualification of the concrete surface quality, and speeds up the turnover cycle of the formwork, simplifies the construction process.
Smart Images

Figure CN119061937A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of pipe gallery supports, and in particular relates to an anti-seepage construction method for a cast-in-situ side wall structure in an underground space. Background Art
[0002] Waterproofing is the lifeline of underground space construction such as pipeline corridors. In principle, waterproofing is based on self-waterproofing of the structure, supplemented by waterproofing measures to form a waterproofing system, with waterproofing of construction joints, deformation joints and other detailed structures as the key control points. At present, mainstream underground space structures such as pipeline corridors are mostly constructed with cast-in-place concrete. During the construction of cast-in-place concrete side wall structures, tie screws are generally used to fix the formwork. Although the tie screws are equipped with water stop plates to block the water flow path, considering the objective factors of the long structural construction line and the frequent overturning of the formwork, the tie screws will be damaged. The setting of the tie screws will cause holes on the concrete surface. Improper handling will cause rust and leakage, affecting the surface quality of the plain concrete and the performance of the structure.
[0003] The traditional steel formwork support system mostly uses water-stop screws to fix the side formwork during the use of the foundation pit. Underground space buildings such as pipe corridors have relatively high requirements for their own anti-seepage. Water-stop screws are prone to leakage problems, and the efficiency is slow during the formwork removal process, and the turnover cycle of the formwork is long. The traditional steel formwork part uses oblique support to reinforce the side formwork. Traditional oblique support mostly supports the support point on the ground and fixes it on the ground, while the two sides of the structure such as the pipe corridor are mostly (the outer edge of the foundation pit and the concrete box), and both sides are not suitable for oblique support settings. The traditional support steel pipe is difficult to install due to the length of the steel pipe and the support angle, and the space in underground spaces such as pipe corridors is not large, so it is not suitable for use.
[0004] The cast-in-place construction of the side wall concrete structure has certain advantages, such as low construction cost and fast formation. However, as the length of the underground space structure increases, the side wall is prone to leakage. The leakage at the location of the traditional tension screw occurs more frequently during construction. Summary of the invention
[0005] The purpose of the present invention is to overcome the shortcomings of the prior art and to provide an anti-seepage construction method for a cast-in-place side wall structure of an underground space, so as to solve the problem of side wall leakage during the cast-in-place construction of the underground space side wall structure and the problem of difficulty in supporting the side wall without screws.
[0006] The objective of the present invention is achieved through the following technical solution. The anti-seepage construction method of the cast-in-place side wall structure of the underground space comprises the following steps:
[0007] S1. Construction preparation: According to the standard design principle of "the width modulus is increased by 50mm, and when the width exceeds 600mm, it should be increased by 150mm; the length modulus is increased by 150mm, and when the length exceeds 90mm, it should be increased by 300mm", the steel mold side formwork is designed, and horizontal back ribs and vertical back ribs are fixed on the back of the steel mold side formwork by welding to form an anti-seepage steel formwork device; the adjustable length range size of the retractable steel pipe support device is selected according to the spacing between adjacent cast-in-place side walls;
[0008] S2. Construction joint treatment: The side wall reinforcement construction, anti-seepage steel formwork device installation and reinforcement are all performed on the side wall construction foundation. Before the anti-seepage steel formwork device is installed, the wall edge line and formwork control line are popped out with ink lines on the bottom plate beam of the side wall construction foundation, and the concrete surface is cut flush and the concrete of the bottom plate is roughened;
[0009] S3. Installation of side wall reinforcement: During the previous reinforcement construction of the bottom plate beam, the vertical reinforcement of the side wall and part of the longitudinal horizontal reinforcement are reserved and 40cm higher than the bottom plate surface. The reserved position and the length of the single-sided lap welding or binding meet the requirements. The longitudinal horizontal reinforcement of the side wall is installed. The reinforcement with a diameter greater than 20mm is welded by single-sided lap welding. The reinforcement with a diameter less than or equal to 16mm can be welded by single-sided lap welding or binding. The electric slag needs to be removed in time at the welding site; plum blossom-shaped concrete prefabricated pads are used every 2m at the intersection of the vertical reinforcement and the longitudinal horizontal reinforcement; the side wall reinforcement on both sides of the deformation joint is the focus of construction, and the binding construction of the side wall reinforcement at this location is strengthened according to the design drawings;
[0010] S4. Installation and reinforcement of anti-seepage steel formwork device: The steel formwork side formwork is pre-assembled before use, and should be carried out on a flat ground in a panel matching manner. Before hanging, concrete pads are laid between the bottoms of adjacent steel formwork side formworks for temporary bearing to facilitate subsequent fixation, and a crane is used to hang the steel formwork side formwork. The steel formwork side formwork is provided with a plurality of blocks and arranged and connected in sequence along the length direction of the cast-in-place concrete structure, and adjacent steel formwork side formworks are connected and fixed by connecting units. The front of the steel formwork side formwork faces the cast-in-place concrete structure side, and the bottom of the steel formwork side formwork is connected to the steel formwork and the steel ribs are fastened with fastening bolts, and a temporary steel pipe is used on the back of the steel formwork side formwork for oblique support; a double-sided adhesive strip is pasted between the lower mouth of the steel formwork side formwork and the concrete surface to ensure that the gap is compacted, and the gap can also be filled with caulking materials or foaming agents, or extruded boards;
[0011] S5. Construction of the tension-free screw system: three retractable steel pipe support devices are arranged vertically between the back of the steel formwork side formwork and the enclosure structure, and the longitudinal arrangement spacing is 0.6-0.9m; two retractable steel pipe support devices are arranged horizontally between the backs of the two relatively distributed steel formwork side formworks, and the two retractable steel pipe support devices are respectively located on the top and bottom of the steel formwork side formworks, and the longitudinal spacing is 1m. The retractable steel pipe support device arranged in the form of scissors braces is provided in the middle position between the backs of the two relatively distributed steel formwork side formworks; if the height of the cast-in-place side wall is high, a tension screw device is used to tension and fix the top of the steel formwork side formwork;
[0012] S6. Concrete pouring of side walls: As the upper opening of the steel formwork side formwork is higher than the actual pouring completion surface of the side wall, it is necessary to measure the elevation with a level on the vertical reinforcement of the side wall to determine the actual pouring completion surface, and set a concrete control line, and use a truck pump for concrete pouring; commercial concrete is used, and concrete with a slump of 130mm-150mm is used for pouring the side wall; as the thickness of the side wall is relatively small, 30-50cm, and the reinforcement is relatively dense, during the concrete pouring process, it should be poured evenly from the low end to the high end continuously, first pouring the exterior wall, then pouring the middle partition wall, and vibrating the concrete with a vibrator in time after pumping to make it dense, and controlling the concrete pouring height during the concrete pouring process; during the pouring process, strengthen the observation of the formwork support system, and if there is a formwork runaway, make reinforcement and adjustment in time before pouring the concrete, and after pouring, finish and control the surface flatness; after the concrete pouring is completed, it needs to be maintained until it reaches final setting, and kept moist, and the support system can be dismantled after 7 days of maintenance;
[0013] S7. Dismantling of side wall formwork: The side formwork can be dismantled after the concrete strength reaches the design requirements. The anti-seepage steel formwork device and the retractable steel pipe support device are dismantled by crane and manual labor. First, the tension screw device on the top of the steel formwork side formwork is dismantled, and then the internal steel formwork side formwork and retractable steel pipe support device are dismantled. Finally, the steel formwork side formwork and retractable steel pipe support device on the enclosure structure are dismantled.
[0014] The beneficial effects of the present invention are as follows: a construction process combining a screw-free support system with a side wall cast-in-place construction technology is formed by adopting an anti-seepage steel formwork device, a retractable steel pipe support device and a tension screw device, which solves the bolt hole leakage of the measuring formwork structure from the root, avoids the leakage of the screws in the tension screw structure used in the cast-in-place construction process of the side wall formwork structure, thereby improving the leakage problem of the underground space structure. After the formwork support system is installed, concrete pouring and maintenance are carried out. After the pouring is completed, the clear water concrete surface is exposed (without modification), which can achieve qualified surface appearance quality at one time. The retractable steel pipe support device in the construction process of the side wall structure of the underground structure can be adjusted to achieve the purpose of rapid installation and removal, thereby accelerating the turnover cycle of the formwork.
[0015] Preferably, a plurality of horizontal back ribs are fixed to the back of the steel formwork side formwork, and the plurality of horizontal back ribs are arranged in sequence along the height direction of the steel formwork side formwork and are evenly spaced up and down, and a plurality of vertical back ribs are fixed to the plurality of horizontal back ribs, and the vertical back ribs are arranged in sequence along the length direction of the steel formwork side formwork and are evenly spaced left and right, and a lifting frame for lifting the anti-seepage steel formwork device is fixed to the vertical back ribs; the lifting frame is a support frame with an isosceles triangle cross-section, and the bottom of the lifting frame is fixed to the vertical back ribs by welding, and lifting holes are provided on both sides of the main body of the lifting frame; by arranging horizontal back ribs and vertical back ribs, the strength of the entire steel formwork side formwork is better, the horizontal back ribs can achieve a supporting effect with the retractable steel pipe support device, and the vertical back ribs can achieve the integrity of the steel formwork with the tension screw device, and at the same time, by arranging a lifting frame on the vertical back ribs, it is convenient to lift the formwork during use, and the stability during the lifting process can be guaranteed.
[0016] Preferably, transverse support plates are provided at the upper and lower ends of the steel mold side template, the transverse support plates are distributed vertically with the steel mold side template, and the width of the transverse support plates is equal to the width of the horizontal back ribs, both ends of the vertical back ribs extend out of the upper and lower ends of the steel mold side template, and the vertical back ribs are fixed to the transverse support plates and the horizontal back ribs by welding; stiffening plates are fixed between the transverse support plates and the horizontal back ribs by welding, and the stiffening plates are sequentially arranged along the length direction of the steel mold side template and are distributed at equal intervals on the left and right; by arranging the transverse support plates, the fixation between the steel mold side template and the vertical back ribs is more stable, thereby making the stability of the steel mold side template better during use; because the stress at the upper and lower ends of the steel mold side template is relatively weak, and in actual applications, the upper and lower ends of the steel mold side template have higher strength requirements, and the transverse support plates and the steel mold side template are fixed and formed by welding, therefore, by arranging the stiffening plates, the strength is greatly improved to increase the overall stability between the templates.
[0017] Preferably, the vertical back rib is composed of two symmetrically distributed channel steels, and a gap space for the insertion of tension screws is reserved between the two channel steels. A steel plate is fixed to one side of the end of the vertical back rib extending from the upper and lower ends of the steel mold side template. The steel plate is provided with insertion holes for the insertion of tension screws, and the hole core of the insertion hole is aligned with the center of the gap space; a tension screw device is provided between the front faces of the two relatively distributed steel mold side templates, and the tension screw device is located at the upper end of the steel mold side template and inserted into the steel plate. The tension screw device includes a tension screw, a screw A cap and a clamping block, the clamping block is provided with a through hole and fixed on one end face of the nut, the tension screw is inserted through the insertion hole of the steel plate, and is tightened and fixed by the nut; a tension screw device is adopted at the top of the steel formwork side formwork, especially when the cast-in-place concrete structure is in an ultra-high pouring state, it can effectively ensure the integrity of the steel formwork and avoid deformation of the top steel formwork side formwork. The tension screw is arranged in the steel formwork side formwork, which can well ensure the construction quality of the concrete surface and prevent leakage of the tension screw in the traditional process. Compared with the formwork with bundled screws, it is more convenient during installation and removal.
[0018] Preferably, the connecting unit is arranged on the left and right ends of the steel mold side formwork, and the connecting unit includes a connecting plate and bolts. The connecting plate is fixed on the left and right ends of the steel mold side formwork, and bolt holes are provided on the connecting plate. Adjacent steel mold side formworks are connected and fixed with the bolts through the bolt holes on the connecting plate. Through the arrangement of the above structure, the connection between adjacent steel mold side formworks is more convenient, the structural stability after installation is better, and disassembly and assembly are more convenient.
[0019] Preferably, the telescopic steel pipe supporting device comprises a supporting top bracket and a steel pipe, wherein the supporting top bracket and the steel pipe are each provided with two, a threaded supporting rod is fixed to the back of the supporting top bracket, one end of the steel pipe is sleeved on the threaded supporting rod, and a knob buckle is installed between the threaded supporting rod and the steel pipe, the knob buckle is screwed on the threaded supporting rod, and the length of the steel pipe supporting device is adjusted by rotating the knob buckle clockwise or counterclockwise; the other ends of the two steel pipes are connected to an adjusting mechanism through a connecting assembly, and the driving position of the adjusting mechanism is adjusted by the driving position of the adjusting mechanism. The length of the steel pipe support device can be adjusted by shifting after the template is pre-pressed; the centers of the support top bracket, the threaded support rod, the steel pipe and the adjustment mechanism are all on the same straight line; a threaded support rod and a knob buckle are added to the support top bracket, and the steel pipe is sleeved on the threaded support rod, so that the telescopic steel pipe support device can be adjusted in a wide range of length, and an adjustment mechanism is installed between the two steel pipes, so that the telescopic steel pipe support device can be fine-tuned in length after the template is pre-pressed; the support top bracket, steel pipe and adjustment mechanism can be disassembled and reused to save costs, promote green construction and improve construction efficiency.
[0020] Preferably, the supporting jack is a steel "C"-shaped member. The opening of the supporting jack faces the horizontal back ribs on the side formwork of the steel formwork, and the opening is engaged with the horizontal back ribs. The threaded support rod is located at the center of the back of the supporting jack. The adjustable supporting jack can quickly adjust the length of the supporting steel pipe, and the supporting jack arranged by the above structure can expand the contact surface, better transfer the side wall stress of the formwork during the pouring process of the side wall structure, make the supporting stability of the supporting jack for the formwork better, and the clamping is more convenient during the supporting process.
[0021] Preferably, the knob buckle includes a knob and a nut. The nut is fixed at the center position of the knob. The knob buckle is screwed to the threaded support rod through the nut. One side of the nut is flush with one side of the knob, and a bayonet is formed between the other side of the nut and the circumferential inner wall of the knob. The bayonet abuts against one end of the steel pipe. Through the setting of the above structure, the forming of the knob buckle is simpler and more convenient in actual application, and the length adjustment of the steel pipe support device is realized by rotating the knob buckle clockwise and counterclockwise.
[0022] Preferably, the connecting component includes four flange plates. Two of the flange plates are respectively fixed on the end faces of the other ends of the two steel pipes, and the other two flange plates are respectively fixed on the bottom end and the top end of the adjusting mechanism. The adjacent flange plates are fixedly connected by bolts. Through the setting of the above structure, the disassembly and assembly between the two steel pipes and the adjusting mechanism are more convenient, which brings convenience to the construction, and the stability is better after using the flange plates for connection. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 is a flow chart of the anti-seepage construction method of the present invention.
[0024] Figure 2 is a schematic structural diagram of the anti-seepage steel formwork screw-free support system of the present invention.
[0025] Figure 3 is a schematic front view structural diagram of the anti-seepage steel formwork device of the present invention.
[0026] Figure 4 is a schematic side view structural diagram of the anti-seepage steel formwork device of the present invention.
[0027] Figure 5 is a schematic structural diagram of the splicing structure of the side formwork of the steel formwork of the present invention.
[0028] Figure 6 is a schematic structural diagram of the telescopic steel pipe support device of the present invention.
[0029] Figure 7 It is a schematic diagram of the structure between the supporting jack and the steel pipe of the present invention.
[0030] Figure 8 It is a schematic diagram of the structure between the steel pipe and the adjusting mechanism of the present invention.
[0031] Fig. 9 It is a structural schematic diagram of the tension screw device of the present invention.
[0032] The reference numerals in the attached drawings are: 100, steel mold side formwork; 101, connecting unit; 102, horizontal back rib; 103, vertical back rib; 104, hanging frame; 105, horizontal support plate; 106, stiffening plate; 107, channel steel; 108, steel plate; 109, insertion hole; 110, connecting plate; 111, bolt hole; 112, bolt; 113, hanging hole; 200, supporting top bracket; 201, Steel pipe; 202, threaded support rod; 203, knob buckle; 204, adjustment mechanism; 205, knob; 206, nut; 207, bayonet; 208, flange; 300, tension screw; 301, nut; 302, clamping block; 400, anti-seepage steel formwork device; 500, retractable steel pipe support device; 600, side wall construction foundation; 700, bottom plate beam; 800, concrete pad stone. DETAILED DESCRIPTION
[0033] The present invention will be described in detail below with reference to the accompanying drawings: Figure 1 , 2 As shown, the anti-seepage construction method of the present invention comprises the following steps:
[0034] S1. Construction preparation: According to the standard design principle of "the width modulus is increased by 50mm, and when the width exceeds 600mm, it should be increased by 150mm; the length modulus is increased by 150mm, and when the length exceeds 90mm, it should be increased by 300mm", the steel mold side formwork 100 is designed, and the horizontal back ribs 102 and the vertical back ribs 103 are fixed on the back of the steel mold side formwork 100 by welding to form an anti-seepage steel formwork device 400; the adjustable length range size of the telescopic steel pipe support device 500 is selected according to the spacing between adjacent cast-in-place side walls;
[0035] S2. Construction joint treatment: The side wall reinforcement construction, installation and reinforcement of the anti-seepage steel formwork device 400 are all performed on the side wall construction foundation 600. Before the installation of the anti-seepage steel formwork device 400, the wall edge line and formwork control line are popped out with ink lines on the bottom plate beam 700 of the side wall construction foundation 600, and the concrete surface is cut flush and the concrete of the bottom plate is roughened;
[0036] S3, side wall reinforcement installation: During the previous reinforcement construction of the bottom plate beam 700, the vertical reinforcement of the side wall and part of the longitudinal horizontal reinforcement are reserved and 40cm higher than the bottom plate surface. The reserved position and the length of the single-sided lap welding or binding meet the requirements. The longitudinal horizontal reinforcement of the side wall is installed. The reinforcement with a diameter greater than 20mm is welded by single-sided lap welding, and the reinforcement with a diameter less than or equal to 16mm can be welded by single-sided lap welding or binding. The electric slag needs to be removed in time at the welding site; to ensure the thickness of the reinforcement protective layer, plum blossom-shaped concrete prefabricated pads are used every 2m at the intersection of the vertical reinforcement and the longitudinal horizontal reinforcement; the side wall reinforcement on both sides of the deformation joint is the focus of construction, and the binding construction of the side wall reinforcement at this location is strengthened according to the design drawings;
[0037] S4. Installation and reinforcement of anti-seepage steel formwork device: The steel formwork side formwork 100 shall be pre-assembled before use. It shall be done on a flat ground in the formwork matching manner. A channel steel shall be laid flat about 20 cm below the horizontal construction joint of the side wall as a temporary support point for the temporary installation of the steel formwork. Steel pipes shall be used to reinforce the channel steel firmly and keep it level. Before hanging, concrete pads 800 shall be laid between the bottoms of adjacent steel formwork side formworks 100 for temporary bearing to facilitate subsequent fixation. A 25t crane shall be used to hang the steel formwork side formwork 100 through the hanging hole 113. The steel formwork side formwork 100 is provided with several blocks and arranged and connected in sequence along the length direction of the cast-in-place concrete structure, and the adjacent steel formwork side formworks 1 00 are connected and fixed by connecting units 101, the front of the steel mold side template 100 faces the cast-in-place concrete structure side, the bottom of the steel mold side template 100 is connected to the steel mold and the steel ribs are fastened with fastening bolts, and a temporary steel pipe is used on the back of the steel mold side template 100 for oblique support; due to the large rigidity of the steel template, the lower end of the steel template used after the concrete bottom plate is poured may not be able to be close to the concrete surface, which may easily cause leakage and breakage of slurry in the later stage. A double-sided adhesive strip is pasted between the lower end of the steel mold side template 100 and the concrete surface to ensure that the gap is compacted, so that the wall panel joints do not leak slurry or break slurry, and the joints are ensured to be tight. Caulking materials or foaming agents, extruded boards can also be used to fill the gaps;
[0038] S5. Construction of the tension-free screw system: Three retractable steel pipe support devices 500 are arranged vertically between the back of the steel mold side formwork 100 and the enclosure structure, and the longitudinal arrangement spacing is 0.6-0.9m; two retractable steel pipe support devices 500 are arranged horizontally between the backs of the two relatively distributed steel mold side formworks 100, and the two retractable steel pipe support devices 500 are respectively located on the top and bottom of the steel mold side formworks 100, and the longitudinal spacing is 1m. A retractable steel pipe support device arranged in the form of a scissors brace is provided in the middle position between the backs of the two relatively distributed steel mold side formworks 100; if there is a cast-in-place side wall The height is high, and the top of the steel mold side template 100 is fixed with a tension screw device; specifically: the external support system of the side wall templates on both sides is installed: the support top bracket 200 is used to expand the supported working surface, and the retractable steel pipe support device 500 is initially positioned. The middle part is assembled with steel pipe 201 and adjustment mechanism 204, and the connection form is bolted; the enclosure structure is used as the counter-support point, φ48×3.5mm steel pipe 201 is used as the counter-support material, and the steel pipe material slightly larger than the working surface width of 5cm is cut. The support top bracket 200 is added to the end of one side to act on the outer template board, and the end of one side directly acts on the enclosure structure. The adjustment mechanism 204 is used between the steel pipes. The longitudinal arrangement spacing is 0.6-0.9m for arrangement; the vertical arrangement spacing is 1m, with a total of 3. The knob buckles 203 on both sides and the adjustment mechanism 204 in the middle can be adjusted to make the steel pipe support the template and stably support it on the enclosure structure. Installation of steel pipes of horizontal support system: The horizontal support steel pipe system adopts support top support 200 to expand the supported working surface, and performs preliminary positioning of the retractable steel pipe support device 500. The middle part adopts steel pipe 201 and adjustment mechanism 204 for assembly. The connection form is connected by bolts. The upper and lower parts are arranged horizontally, with one on the top and bottom plates, and one on each 1m in the longitudinal spacing. The supporting top brackets 200 on both sides both support and act on the horizontal back ribs 102 of the steel mold side formwork 100. The horizontal back ribs 102 are made of channel steel. Square wood pads are added to the upper part of the channel steel plate to expand the force-bearing area, and together with the support system, form a counter-support surface; the installation of the diagonal support system adopts a scissors support form, and the supporting top brackets 200 are used to expand the supported working surface, and the retractable steel pipe support device 500 is initially positioned. The middle part is assembled with steel pipes 201 and adjustment mechanisms 204, and the connection form is bolted. One end is against the horizontal back rib 102 on the upper part of the steel mold side formwork 100, and the other end is against the horizontal back rib 102 on the lower part of the steel mold side formwork 100. If necessary, square wood pads can be set with the same width as the channel steel to form a counter-support surface together.
[0039] S6. Concrete pouring of side walls: As the upper end of the steel formwork side template 100 is higher than the actual pouring surface of the side wall, it is necessary to measure the elevation on the vertical reinforcement of the side wall with a level to determine the actual pouring surface, and set a concrete control line. Use a truck pump to pour concrete. Commercial concrete is used, and concrete with a slump of 130mm-150mm is used for pouring the side wall. As the thickness of the side wall is relatively small, 30-50cm, and the reinforcement is relatively dense, the concrete should be poured evenly from the low end to the high end during the pouring process. The exterior wall should be poured first, and then the partition wall should be poured. For walls, during the concrete pouring process, pay attention to making the concrete enter the mold evenly, avoid a large amount of concentrated concrete pouring, and use a vibrator to vibrate and compact the concrete in time after pumping. When pouring concrete, control the concrete pouring height to reduce leakage and concrete segregation; during the pouring process, strengthen the observation of the formwork support system. If there is a formwork leak, make reinforcement and adjustment in time before pouring concrete. After pouring, polish and control the surface flatness; after the concrete pouring is completed, it needs to be maintained until it reaches final setting and kept moist. The support system can be dismantled after 7 days of maintenance;
[0040] S7. Dismantling of side wall formwork: the side formwork can be dismantled after the concrete strength reaches the design requirement. The anti-seepage steel formwork device 400 and the retractable steel pipe support device 500 are dismantled by a crane in cooperation with manual labor. First, the tension screw device on the top of the steel formwork side formwork 100 is dismantled, and then the internal steel formwork side formwork 100 and the retractable steel pipe support device are dismantled, and finally the steel formwork side formwork 100 and the retractable steel pipe support device on the enclosure structure are dismantled; specifically, first dismantle the internal formwork support system: use the hydraulic telescopic device of the supporting steel pipe to retract the steel pipe, dismantle the horizontal support and the oblique support, use a car crane to lift the formwork through the reserved holes, release the top tension screw device before dismantling, and finally dismantle the side wall outer formwork and the supporting steel pipe on the enclosure structure. The construction method is the same as above. After pouring, the plain concrete surface is exposed (without modification), which can achieve a one-time qualified surface appearance quality.
[0041] As attached Figures 3 to 5 As shown, a plurality of horizontal back ribs 102 are fixed to the back of the steel formwork side formwork 100, and the plurality of horizontal back ribs 102 are sequentially arranged along the height direction of the steel formwork side formwork 100 and are evenly spaced up and down, and vertical back ribs 103 are fixed to the plurality of horizontal back ribs 102, and the vertical back ribs 103 are sequentially arranged along the length direction of the steel formwork side formwork 100 and are evenly spaced left and right, and a hoisting frame 104 for hoisting the anti-seepage steel formwork device is fixed to the vertical back ribs 103; the hoisting frame 104 is a support frame with an isosceles triangle cross section, and the bottom of the hoisting frame 104 is fixed to the vertical back ribs 103 by welding, and hoisting holes 113 are provided on both side bodies of the hoisting frame 104.
[0042] The upper and lower ends of the steel mold side template 100 are provided with transverse support plates 105, which are distributed vertically to the steel mold side template 100, and the width of the transverse support plate 105 is equal to the width of the horizontal back rib 102. Both ends of the vertical back rib 103 extend out of the upper and lower ends of the steel mold side template 100, and the vertical back rib 103 is fixed to the transverse support plate 105 and the horizontal back rib 102 by welding; a stiffening plate 106 is fixed between the transverse support plate 105 and the horizontal back rib 102 by welding, and the stiffening plates 106 are arranged in sequence along the length direction of the steel mold side template 100 and are distributed at equal intervals on the left and right.
[0043] The vertical back rib 103 is composed of two symmetrically distributed channel steels 107, and a gap space for the tension screw 300 to be inserted is reserved between the two channel steels 107. A steel plate 108 is fixed to one side of the end of the vertical back rib 103 extending from the upper and lower ends of the steel mold side template 100. The steel plate 108 is provided with an insertion hole 109 for the tension screw 300 to be inserted, and the hole core of the insertion hole 109 is aligned with the center of the gap space; a tension screw device is provided between the front faces of the two relatively distributed steel mold side templates 100. The tension screw device is located at the upper end of the steel mold side template 100 and inserted on the steel plate 108. Fig. 9 As shown, the tension screw device includes a tension screw 300, a nut 301 and a clamping block 302. The clamping block 302 is provided with a through hole and fixed on one end face of the nut 301. The tension screw 300 is inserted into the insertion hole 109 of the steel plate 108 and is tightened and fixed by the nut 301.
[0044] The connecting unit 101 is arranged on the left and right ends of the steel mold side template 100. The connecting unit 101 includes a connecting plate 110 and a bolt 112. The connecting plate 110 is fixed on the left and right ends of the steel mold side template 100. The connecting plate 110 is provided with a bolt hole 111. Adjacent steel mold side templates 100 are connected and fixed by the bolt holes 111 on the connecting plate 110 and the bolts 112.
[0045] As attached Figures 6 to 8As shown in the figure, the telescopic steel pipe support device includes a support jack 200 and steel pipes 201. There are two support jacks 200 and two steel pipes 201. A threaded support rod 202 is fixed on the back of the support jack 200. One end of the steel pipe 201 is sleeved on the threaded support rod 202, and a knob buckle 203 is installed between the threaded support rod 202 and the steel pipe 201. The knob buckle 203 is screwed onto the threaded support rod 202, and the length adjustment of the steel pipe support device is realized by rotating the knob buckle 203 clockwise or counterclockwise; the other ends of the two steel pipes 201 are both connected with an adjustment mechanism 204 through a connection component, and the length adjustment of the steel pipe support device after the formwork is pre-pressed is realized by the driving displacement of the adjustment mechanism 204; the centers of the support jack 200, the threaded support rod 202, the steel pipe 201 and the adjustment mechanism 204 are all on the same straight line. The adjustment mechanism 204 is a hydraulic jack, which is convenient for adjustment and control.
[0046] The support jack 200 is a steel "C" - shaped member. The opening of the support jack 200 faces the horizontal back rib 102 on the side formwork 100 of the steel form, and the opening is engaged with the horizontal back rib 102. The threaded support rod 202 is located at the center position on the back of the support jack 200.
[0047] The knob buckle 203 includes a knob 205 and a nut 206. The nut 206 is fixed at the center position of the knob 205. The knob buckle 203 is screwed and connected with the threaded support rod 202 through the nut 206. One side of the nut 206 is flush with one side of the knob 205, and a bayonet 207 is formed between the other side of the nut 206 and the circumferential inner wall of the knob 205. The bayonet 207 abuts against one end of the steel pipe 201.
[0048] The connection component includes four flange plates 208. Two of the flange plates 208 are respectively fixed on the end faces of the other ends of the two steel pipes 201, and the other two flange plates 208 are respectively fixed on the bottom end and the top end of the adjustment mechanism 204. The adjacent flange plates 208 are fixedly connected by bolts.
[0049] The above is only the specific implementation manner of the present application, but the protection scope of the present application is not limited thereto. Any change or replacement that can be easily thought of by those skilled in the technical field within the technical scope disclosed in the present application should be covered within the protection scope of the present application. Therefore, the protection scope of the present application should be subject to the protection scope of the claims.
Claims
1. A method for anti-seepage construction of a cast-in-place side wall structure in an underground space, characterized in that: The anti-seepage construction method comprises the following steps: S1. Construction preparation: According to the standard design principle of "the width modulus is increased by 50 mm, and when the width exceeds 600 mm, it should be increased by 150 mm; the length modulus is increased by 150 mm, and when the length exceeds 90 mm, it should be increased by 300 mm", a steel mold side formwork (100) is designed, and a horizontal back rib (102) and a vertical back rib (103) are fixed on the back of the steel mold side formwork (100) by welding to form an anti-seepage steel formwork device (400); the adjustable length range size of the telescopic steel pipe support device (500) is selected according to the spacing between adjacent cast-in-place side walls; S2, construction joint treatment: the side wall reinforcement construction, the installation and reinforcement of the anti-seepage steel formwork device (400) are all performed on the side wall construction foundation (600). Before the installation of the anti-seepage steel formwork device (400), the wall edge line and the formwork control line are popped out with ink lines on the bottom plate beam (700) of the side wall construction foundation (600), and the concrete surface is cut flush and the concrete of the bottom plate is roughened; S3, side wall reinforcement installation: During the previous reinforcement construction of the bottom plate beam (700), the vertical reinforcement of the side wall and part of the longitudinal horizontal reinforcement are reserved and 40 cm higher than the bottom plate surface. The reserved position and the length of the single-sided lap welding or binding meet the requirements. The longitudinal horizontal reinforcement of the side wall is installed. The reinforcement with a diameter greater than 20 mm is single-sided lap welding, and the reinforcement with a diameter less than or equal to 16 mm can be single-sided lap welding or binding. The electric slag needs to be removed in time at the electric welding site; plum blossom-shaped concrete prefabricated pads are used in advance every 2 m at the intersection of the vertical reinforcement and the longitudinal horizontal reinforcement; the side wall reinforcement on both sides of the deformation joint is the focus of construction, and the binding construction of the side wall reinforcement at this location is strengthened according to the design drawings; S4. Installation and reinforcement of anti-seepage steel formwork device: The steel formwork side formwork (100) is pre-assembled before use, and should be pre-assembled on a flat ground in a panel-matching manner. Before hanging, concrete pads (800) are laid between the bottoms of adjacent steel formwork side formworks (100) for temporary bearing to facilitate subsequent fixation, and a crane is used to hang the steel formwork side formwork (100). The steel formwork side formwork (100) is provided with a plurality of blocks and is sequentially arranged and connected along the length direction of the cast-in-place concrete structure, and the adjacent The steel mold side templates (100) are connected and fixed by connecting units (101), the front side of the steel mold side template (100) faces the cast-in-place concrete structure side, the bottom of the steel mold side template (100) is connected to the steel mold and the steel ribs are fastened by fastening bolts, and a temporary steel pipe is used on the back of the steel mold side template (100) for oblique support; a double-sided adhesive strip is pasted between the lower end of the steel mold side template (100) and the concrete surface to ensure that the gap is compacted, and the gap can also be filled with caulking materials or foaming agents, or extruded boards; S5. Construction of a tension-free screw system: three retractable steel pipe support devices (500) are arranged vertically between the back of the steel formwork side formwork (100) and the enclosure structure, and are arranged at a longitudinal spacing of 0.6-0.9m; two retractable steel pipe support devices (500) are arranged horizontally between the backs of two relatively distributed steel formwork side formworks (100), and the two retractable steel pipe support devices (500) are respectively located on the top and bottom of the steel formwork side formworks (100), and the longitudinal spacing is such that the retractable steel pipe support device is arranged every 1m, and the retractable steel pipe support device arranged in the form of scissors braces is provided in the middle position between the backs of the two relatively distributed steel formwork side formworks (100); if the height of the cast-in-place side wall is relatively high, a tension screw device is used at the top of the steel formwork side formwork (100) for tension and fixation; S6. Concrete pouring of side walls: Since the upper end of the steel formwork side formwork (100) is higher than the actual pouring completion surface of the side wall, it is necessary to measure the elevation on the vertical reinforcement of the side wall with a level to determine the actual pouring completion surface, and set a concrete control line. A truck pump is used for concrete pouring. Commercial concrete is used, and concrete with a slump of 130mm-150mm is used for pouring the side wall. Since the thickness of the side wall is relatively small, 30-50cm, and the reinforcement is relatively dense, the concrete should be poured evenly from the low end to the high end during the pouring process. The outer wall is poured first, and then the middle partition wall is poured. After the concrete is pumped, it is vibrated and compacted in time with a vibrator. When pouring concrete, the height of the concrete pouring should be controlled. During the pouring process, the formwork support system should be observed more closely. If there is a formwork runaway, reinforcement and adjustment should be made in time before the concrete pouring. After the pouring is completed, the surface flatness should be controlled by finishing. After the concrete pouring is completed, it should be maintained until it reaches final setting and kept moist. The support system can be dismantled after 7 days of maintenance. S7. Dismantling of side wall formwork: The side formwork can be dismantled after the concrete strength reaches the design requirements. The anti-seepage steel formwork device (400) and the retractable steel pipe support device (500) are dismantled by crane in cooperation with manual labor. First, the tension screw device on the top of the steel formwork side formwork (100) is dismantled, and then the internal steel formwork side formwork (100) and the retractable steel pipe support device are dismantled. Finally, the steel formwork side formwork (100) and the retractable steel pipe support device on the enclosure structure are dismantled.
2. The anti-seepage construction method of the cast-in-situ side wall structure of the underground space according to claim 1 is characterized by: The front side of the steel formwork (100) faces the cast-in-place concrete structure side, and a plurality of horizontal back ribs (102) are fixed to the back side of the steel formwork (100), and the plurality of horizontal back ribs (102) are sequentially arranged along the height direction of the steel formwork (100) and are evenly spaced vertically, and a plurality of vertical back ribs (103) are fixed to each of the horizontal back ribs (102), and the vertical back ribs (103) are sequentially arranged along the length direction of the steel formwork (100) and are evenly spaced horizontally, and a hoisting frame (104) for hoisting an anti-seepage steel formwork device is fixed to the vertical back ribs (103); the hoisting frame (104) is a support frame with an isosceles triangle cross section, and the bottom of the hoisting frame (104) is fixed to the vertical back ribs (103) by welding, and hoisting holes (113) are provided on both sides of the main body of the hoisting frame (104).
3. The anti-seepage construction method of the cast-in-situ side wall structure of the underground space according to claim 2 is characterized by: The upper and lower ends of the steel mold side template (100) are both provided with transverse support plates (105), the transverse support plates (105) are vertically distributed with the steel mold side template (100), and the width of the transverse support plates (105) is equal to the width of the horizontal back ribs (102), both ends of the vertical back ribs (103) extend out of the upper and lower ends of the steel mold side template (100), and the vertical back ribs (103) are fixed to the transverse support plates (105) and the horizontal back ribs (102) by welding; a stiffening plate (106) is fixed between the transverse support plates (105) and the horizontal back ribs (102) by welding, and the stiffening plates (106) are sequentially arranged along the length direction of the steel mold side template (100) and are evenly spaced from left to right.
4. The anti-seepage construction method of the cast-in-situ side wall structure of the underground space according to claim 2 is characterized by: The vertical back rib (103) is composed of two symmetrically distributed channel steels (107), and a gap space for the tension screw (300) to be inserted is reserved between the two channel steels (107). A steel plate (108) is fixed to one side of the end of the vertical back rib (103) extending from the upper and lower ends of the steel mold side template (100). The steel plate (108) is provided with an insertion hole (109) for the tension screw (300) to be inserted, and the hole core of the insertion hole (109) is aligned with the center of the gap space; the two relatively distributed steel molds A tension screw device is provided between the front faces of the side formwork (100), the tension screw device is located at the upper end of the steel mold side formwork (100) and inserted into the steel plate (108), the tension screw device comprises a tension screw (300), a nut (301) and a clamping block (302), the clamping block (302) is provided with a through hole and is fixed on one end face of the nut (301), the tension screw (300) is inserted into the insertion hole (109) of the steel plate (108), and is tightened and fixed by the nut (301).
5. The anti-seepage construction method of the cast-in-situ side wall structure of underground space according to claim 1, characterized in that: The connecting unit (101) is arranged at the left and right ends of the steel formwork side form (100). The connecting unit (101) includes a connecting plate (110) and bolts (112). The connecting plate (110) is fixed to the left and right ends of the steel formwork side form (100). Bolt holes (111) are provided on the connecting plate (110). Adjacent steel formwork side forms (100) are connected and fixed through the bolt holes (111) on the connecting plate (110) and the bolts (112).
6. The anti-seepage construction method of the cast-in-situ side wall structure of the underground space according to claim 2, characterized in that: The telescopic steel pipe support device includes a support jack (200) and steel pipes (201). There are two support jacks (200) and two steel pipes (201). A threaded support rod (202) is fixed to the back of the support jack (200). One end of the steel pipe (201) is sleeved on the threaded support rod (202), and a knob buckle (203) is installed between the threaded support rod (202) and the steel pipe (201). The knob buckle (203) is screwed onto the threaded support rod (202), and the length of the steel pipe support device is adjusted by rotating the knob buckle (203) clockwise or counterclockwise; the other ends of the two steel pipes (201) are both connected to an adjusting mechanism (204) through a connecting component, and the length of the steel pipe support device after the formwork is pre-pressed is adjusted by the driving displacement of the adjusting mechanism (204); the centers of the support jack (200), the threaded support rod (202), the steel pipe (201), and the adjusting mechanism (204) are all on the same straight line.
7. The anti-seepage construction method of the cast-in-situ side wall structure of the underground space according to claim 6, characterized in that: The support jack (200) is a steel "C"-shaped member. The opening of the support jack (200) faces the horizontal back rib (102) on the steel formwork side form (100), and the opening is engaged with the horizontal back rib (102). The threaded support rod (202) is located at the center of the back of the support jack (200).
8. The anti-seepage construction method of the cast-in-situ side wall structure of the underground space according to claim 6, characterized in that: The knob buckle (203) includes a knob (205) and a nut (206). The nut (206) is fixed at the center position of the knob (205). The knob buckle (203) is screwed onto the threaded support rod (202) through the nut (206). One side of the nut (206) is flush with one side of the knob (205). A bayonet (207) is formed between the other side of the nut (206) and the circumferential inner wall of the knob (205). The bayonet (207) abuts against one end of the steel pipe (201).
9. The anti-seepage construction method of the cast-in-situ side wall structure of underground space according to claim 6, characterized in that: The connecting component includes four flange plates (208). Two of the flange plates (208) are respectively fixed on the end faces of the other ends of the two steel pipes (201), and the other two flange plates (208) are respectively fixed on the bottom end and the top end of the adjusting mechanism (204). Adjacent flange plates (208) are connected and fixed through bolts.