Rapid excavation construction method for rock foundation pit

By using the method of central drilling holes and weak blasting in the rock foundation pit excavation construction, combining digital electronic detonator and detonation cable, detonation segments are detonated and pre-cracked steel pipes and dense blast holes are blocked, the existing technology is solved The problem of large blasting vibration during rock foundation pit excavation has achieved more efficient construction results and lower environmental damage.

CN119063591APending Publication Date: 2024-12-03CHINA RAILWAY NO 5 ENGINEERING GROUP CO LTD +3
View PDF 9 Cites 0 Cited by

Patent Information

Application Number
CN202411250979.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-06
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

The existing rock foundation pit excavation construction method has poor blasting effect in granite with uneven weathering, resulting in large vibrations and causing damage to the surrounding environment, especially near residential functional areas and viewing platforms.

Method used

The central hollow hole and surrounding weak blasting method are adopted, combined with digital electronic detonator and detonator cable, and detonation cables are used to detonate one by one, and block the pre-cracked steel pipe and dense blast holes to control the destructive force of the explosive explosion to concentrate to the center, reducing the continuous wall The impact of

Benefits of technology

It effectively reduces vibration during blasting, reduces destructive power to the surrounding environment, improves the efficiency and effect of blasting construction, and avoids damage to continuous walls.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119063591A_ABST
    Figure CN119063591A_ABST
Patent Text Reader

Abstract

According to the rapid excavation construction method for the rock foundation pit, after the explosive explodes, destructive force can only be generated towards the center portion and cannot be generated backwards (the continuous wall portion), and therefore any damage cannot be generated to the continuous wall after the explosive explodes; by means of efficient and compact explosive charging, a smooth blasting method and dense shot hole blocking, vibration can be greatly reduced by means of section-by-section detonation, and the blasting construction effect is better achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of foundation pit excavation construction, and in particular to a rock foundation pit rapid excavation construction method. Background Art

[0002] During the excavation of granite weathering bodies formed by uneven weathering, due to its high strength and hard rock, and if there are residential functional areas and viewing platforms around, the existing excavation construction methods have poor blasting effects and are prone to large-scale vibrations, which are extremely destructive to the surrounding environment.

[0003] Application Contents

[0004] The purpose of this application is to provide a rock foundation pit rapid excavation construction method to solve the technical problems described in the background technology.

[0005] A rock foundation pit rapid excavation construction method, comprising the following steps:

[0006] S100: Blasting Preparation:

[0007] S110: Blasthole arrangement: Central part: First use the central drilling hole (aperture 600mm), and the holes are evenly arranged from the center to the outside; Peripheral parts: Use weak blasting (separated charge) to arrange peripheral holes. The impact range generated by the detonation of the peripheral holes is mainly the compression circle and crack circle generated by the explosion of the explosives. The calculation formula of the crack circle radius Rr is as follows: Rr = 8r (where r is the radius of the explosive bag) = 8 × (6 ÷ 2) = 24cm;

[0008] S200: Foundation pit blasting:

[0009] S210: Charge: First clean the area around the hole, use a long bamboo pole as a gun stick, and send the gunpowder rolls to the bottom of the hole one by one; Charge structure: Use continuous charge, and each gun hole is equipped with a digital electronic detonator;

[0010] S210: Select blasting materials: Explosives: Use No. 2 rock emulsion explosives, use standard explosive rolls Φ60mm; Detonators: Use digital electronic detonators in the hole (segment setting 0-25ms) (see attached Figure 4 ) Detonating cord: According to the geological surrounding rock conditions, the surrounding holes should adopt the smooth blasting method with detonating cord transmission;

[0011] S220: Blast hole plugging: plugging length: not less than 100cm, plugging material is taphole mud;

[0012] S230: Detonation using digital electronic detonator detonation network:

[0013] The detonation sequence is as follows: before blasting, a row of pre-cracked steel pipes are set at the stilt wall to ensure the protection of the rock mass to the bottom of the stilt wall. During blasting, the middle area is blasted first, and then pre-cracked steel pipes are driven along the ground wall (to protect the ground wall), and then the surrounding areas are blasted. Based on a large amount of experience and data collected from similar projects in the past, the designed sequence is followed, and a delay of 25ms each time can achieve better results. Detonating in stages can greatly reduce vibration, and a special detonator for digital electronic detonators is used for detonation, which is connected in parallel to the network.

[0014] Compared with the prior art, the advantages and positive effects of the present invention are: the rock foundation pit rapid excavation construction method involved in the present invention, after the explosion of the explosives, will only produce destructive force to the central part but not to the rear (continuous wall part), so no damage will be caused to the continuous wall after the blasting; through efficient and tight charging, combined with the smooth blasting method, dense blasthole blocking, and step-by-step detonation, the vibration can be greatly reduced, thereby achieving a better blasting construction effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] In order to more clearly illustrate the technical solution of the present invention, the following briefly introduces the drawings used in the description of the embodiments of the present invention. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative work:

[0016] Figure 1 The present invention is a schematic diagram of the arrangement of blastholes in a working well of an embodiment of a rapid excavation construction method for a rock foundation pit.

[0017] Figure 2 The present invention is a schematic diagram of the charging structure of the working well of an embodiment of a rapid excavation construction method for a rock foundation pit.

[0018] Figure 3 The present invention is a schematic diagram of the charging structure of the working well of an embodiment of a rapid excavation construction method for a rock foundation pit.

[0019] Figure 4 The present invention is a schematic diagram of a detonation system for an embodiment of a method for rapid excavation of a rock foundation pit.

[0020] Figure 5 The present invention is a schematic diagram of a detonation network for an embodiment of a method for rapid excavation of a rock foundation pit.

[0021] Figure 6 This is a large-scale drawing of a hanging foot pre-cracked steel pipe in one embodiment of a rock foundation pit rapid excavation construction method.

[0022] Figure 7 The present invention is a plan view of the support structure of the working pit in one embodiment of a rapid excavation construction method for a rock foundation pit.

[0023] Figure 8 The present invention is a working well section division diagram of an embodiment of a rock foundation pit rapid excavation construction method.

[0024] Fig. 9 The AA cross-sectional view of the working shaft of an embodiment of a rock foundation pit rapid excavation construction method is shown.

[0025] Fig.10 The present invention is a cross-sectional view of working shaft BB of an embodiment of a method for rapid excavation of a rock foundation pit.

[0026] Fig.11 The present invention is a flowchart of blasting vibration monitoring in an embodiment of a method for rapid excavation of a rock foundation pit.

[0027] Fig.12 The present invention is a schematic diagram of the safety protection of the working pit of an embodiment of a rapid excavation construction method for a rock foundation pit. DETAILED DESCRIPTION

[0028] Example embodiments will now be described more fully with reference to the accompanying drawings. However, example embodiments can be implemented in many forms and should not be construed as limited to the embodiments set forth herein; rather, these embodiments are provided so that this application will be comprehensive and complete and will fully convey the concepts of the example embodiments to those skilled in the art. The same reference numerals in the figures represent the same or similar parts, and thus their repeated description will be omitted.

[0029] The described features, structures or characteristics may be combined in one or more embodiments in any suitable manner. In the following description, many specific details are provided to provide a full understanding of the embodiments of the present disclosure. However, those skilled in the art will appreciate that the technical solutions of the present disclosure may be practiced without one or more of these specific details, or other modes, components, materials, devices, etc. may be adopted. In these cases, known structures, methods, devices, implementations, materials or operations will not be shown or described in detail.

[0030] In addition, the terms "include" and "have" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but may optionally include steps or units that are not listed, or may optionally include other steps or units that are inherent to these processes, methods, products or devices.

[0031] The terms "first", "second" and the like in the specification and claims of this application and the above drawings are used to distinguish different objects rather than to describe a specific order.

[0032] The following is a clear and complete description of the technical solution of the present application in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present application.

[0033] As the instruction manual Figure 1-12 As shown:

[0034] A rock foundation pit rapid excavation construction method, comprising the following steps:

[0035] S100: Blasting Preparation:

[0036] S110: Blasthole arrangement:

[0037] Center: First, use the center to drill a hole (aperture 600mm), and then arrange the holes evenly from the center to the outside;

[0038] Surrounding parts: Use weak blasting (separated charge) to arrange peripheral holes. The impact range generated by the detonation of the peripheral holes is mainly the compression circle and crack circle generated by the explosion of the explosives. The calculation formula of the crack circle radius Rr is as follows: Rr = 8r (where r is the radius of the explosive bag) = 8 × (6 ÷ 2) = 24cm

[0039] The peripheral holes are set at a distance of 150 cm (six times the radius of the crack circle) from the contour line, and the holes are slightly inclined to the outside. In addition, weak blasting is used for the peripheral holes. After the explosion of the explosives, destructive force will only be generated towards the center and not towards the back (the continuous wall part), so there will be no damage to the continuous wall after the blast.

[0040] Blast hole arrangement: Arrange blast holes in a plum blossom shape; timely adjust different hole depth operation methods according to different operation areas and different step operation heights on site;

[0041] S200: Foundation pit blasting:

[0042] S210: Charge: First clean the area around the hole, use a long bamboo pole as a gun stick, and send the gunpowder rolls to the bottom of the hole one by one; Charge structure: Use continuous charge, and each gun hole is equipped with a digital electronic detonator;

[0043] When delivering the explosive roll to the bottom of the hole, there must be no blockage in the middle and it must be installed to the bottom of the hole. Otherwise, it will directly affect the blastholes that are detonated later, causing a large number of bottom roots, rock steps, etc., and the blasting effect is poor.

[0044] S210: Select blasting materials: Explosives: Use No. 2 rock emulsion explosives, use standard explosive rolls Φ60mm; Detonators: Use digital electronic detonators in the hole (segment setting 0-25ms) (see attached Figure 4) Detonating cord: According to the geological and surrounding rock conditions, the surrounding holes should be blasted using the smooth surface blasting method with detonating cord.

[0045] S220: Blast hole plugging: plugging length: not less than 100cm, plugging material is gun mud.

[0046] The quality of the plugging must be dense, without gaps and discontinuities. The plugging effect allows the explosive to produce sufficient explosion stress under constrained conditions to improve energy utilization.

[0047] S230: Detonation using digital electronic detonator detonation network:

[0048] The detonation sequence is: before blasting, a row of pre-cracked steel pipes are set at the foot wall to ensure the protection of the bottom of the foot wall by the rock mass. During blasting, the middle area is blasted first, and then pre-cracked steel pipes are drilled along the ground wall (to protect the ground wall), and then the surrounding areas are blasted. Based on the experience and data collected from similar projects in the past, according to the designed sequence, each delay of 25ms can achieve better results; the use of staged detonation can greatly reduce vibration, and the use of digital electronic detonator special detonator is used for detonation, and the network is connected in parallel. The detonation network is as shown in the attached Figure 5 .

[0049] In this embodiment, the peripheral holes are set at 150 cm (six times the radius of the crack circle) away from the contour line, and the holes are slightly inclined to the outside. In addition, weak blasting is used for the peripheral holes. After the explosion of the explosives, destructive force will only be generated toward the center and not toward the back (the continuous wall part), so no damage will be caused to the continuous wall after the blast. Through efficient and tight charging, combined with the smooth blasting method, dense hole blocking, and step-by-step detonation, the vibration can be greatly reduced, thereby achieving a better blasting construction effect.

[0050] Specifically, a rock foundation pit rapid excavation construction method, S100 blasting preparation step also includes:

[0051] S105: Setting up foundation pit retaining structure:

[0052] The foundation pit excavation adopts underground continuous wall vertical support, and the inner lining wall adopts reverse construction method; the specific foundation pit support structure design is as follows: the underground continuous wall is 1.0m thick, with a total of 18 continuous walls, 9 sections of sequence I trench sections, and 9 sections of sequence II trench sections. The underground continuous wall joints are connected by milling joints. The trench depth of the underground continuous wall is 30.3m, the length of the ground-connected wall is 27.6m, and the trench verticality requirement is 1 / 300; the reverse construction method lining wall is 1.0m thick, and the inner diameter after lining is 21.6m; the foundation pit adopts ground-connected wall water stopping, and φ600 single-tube high-pressure rotary jet piles are used for anti-seepage reinforcement treatment of the trench section connection parts.

[0053] S108: Set the free surface:

[0054] After completing the foundation pit retaining structure, drill holes in the middle area of ​​blasting. Holes are taken from the ground and drilled to the base (i.e. the bottom plate of blasting) using a rotary drill. The hole diameter is 1 meter. The number of holes drilled on the air surface is at least 3 (depending on the blasting area, it can also be set to 4, 5, or 7).

[0055] In this embodiment, the foundation pit retaining structure is constructed by reverse construction and lining wall construction. The circular lining wall is a self-contained system and does not require internal support. The structural depth of the rock layer fluctuates. After several blastings, the rock layer is basically flat. At this time, the foundation pit retaining structure cooperates with the air surface to form a blasting space, reduce blasting vibration, thereby saving explosives and improving blasting efficiency.

[0056] Specifically, a rock foundation pit rapid excavation construction method also includes:

[0057] S120: Single hole dosage calculation: Single hole dosage calculation: Q = q·a·b·H

[0058] According to the surrounding environment of the site and the rock structure, φ60 emulsion explosive was selected, and the unit explosive consumption q: 0.6kg / m 3 (Center) and 0.5kg / m 3 (surrounding parts); a-hole spacing; b-row spacing; H-single blasting depth.

[0059] S122: Center blasting parameter selection:

[0060] Blasting method: digital electronic detonator blasting network; explosive type: Φ = 60mm cylindrical emulsion explosive; single cycle footage: actual footage of each blasting cycle is 2.8m;

[0061] Blast hole parameter arrangement:

[0062] Hole depth: L = 2.8m-3.0m; Rock foundation pit rapid excavation construction method Aperture: Φ = 76mm; Rock foundation pit rapid excavation construction method Hole spacing: a = 1.2m-2.0m; Rock foundation pit rapid excavation construction method Row spacing: b = 1.5m; Rock foundation pit rapid excavation construction method Inclination: β = 900 Rock foundation pit rapid excavation construction method Charge amount:

[0063] Single blasting charge: Q single = Kn * V

[0064] Where: Kn is the average explosive consumption per unit, which is 0.6kg / m3; V is the volume of blasted rock, which is calculated based on the actual penetration of 2.8m per cycle, V = (9 / 2)^2*3.14*2.8 = 177m3;

[0065] Then: Q single time = V*Kn = 105kg.

[0066] Table 1 Central part blasting parameters

[0067]

[0068] In this embodiment, the central blasting parameters are combined with the settings of specific structures such as pre-splitting steel pipes, foundation pit retaining structures, and free surfaces, so that the rock foundation pit rapid excavation construction method can more accurately control the scope and direction of blasting, reduce the impact of flying rocks and vibration on the surrounding environment, and minimize secondary disasters caused by blasting, such as landslides and collapses.

[0069] Specifically, S122: Selection of blasting parameters for the surrounding area:

[0070] Blasting method: digital electronic detonator blasting network; explosive type: Φ = 60mm cylindrical emulsion explosive; single cycle footage: actual footage of each blasting cycle is 2.8m;

[0071] Blast hole parameter arrangement:

[0072] Hole depth: L = 2.8m; hole diameter: Φ = 76mm; hole spacing: a = 2.0m; row spacing: b = 1.5m;

[0073] Charge quantity:

[0074] Single blasting charge: Q single = Kn * V

[0075] Where: Kn is the average explosive consumption per unit, which is 0.5kg / m3; V is the volume of blasted rock, which is calculated based on the actual footage of each cycle being 2.6m, V=373.6*2.6≈971.4m3;

[0076] Then: Q single time = V*Kn≈486kg.

[0077] Table 2 Parameters of blasting around the perimeter

[0078]

[0079] In this embodiment, the setting of the blasting parameters of the surrounding parts can guide the paths of the explosion shock wave and stress transmission, improve the crushing and shearing effects of the rocks, and enhance the overall blasting effect.

[0080] Specifically, a rock foundation pit rapid excavation construction method also includes:

[0081] S300: Blasting safety control: Safety control of harmful effects such as vibration, air shock waves, toxic gases, dust, noise, flying rocks, etc. during the blasting process.

[0082] Specifically, S310: Blasting vibration safety control:

[0083] S313: Blasting vibration verification: The impact of the vibration generated by the blasting on the surrounding area is measured by the vertical vibration velocity of the particle. The maximum amount of explosive in a single stage is calculated according to the following formula:

[0084] V=K(Q1 / 3 / R)a

[0085] In the formula: Q is the maximum amount of explosive in a single stage, the maximum for this project is 34kg; V is the vertical vibration speed of the particle; K, a are parameters related to topographical and geological factors and blasting conditions, for this project K=120, a=1.5; R~ is the horizontal distance from the protected object to the center of the explosion source.

[0086] Table 4-1-1 Blasting vibration safety allowable standards

[0087]

[0088] S316: Blasting vibration control:

[0089] Use millisecond blasting, strictly control the maximum single-stage explosive quantity, and reasonably arrange the detonation interval; Monitoring measures: Arrange multiple measuring points according to the actual working environment of the construction site and the characteristics of the building, analyze the data of each measuring point, and immediately stop the blasting operation when the data exceeds the safe vibration speed specification, and adjust the relevant operating methods; Setting of vibration monitoring points: Blasting vibration monitoring is mainly set according to the structural characteristics of the building and the distance from the blasting area. The vibration monitoring points of the working well construction are arranged on the viewing platform, slope retaining wall, steel trestle, etc. near the wellhead.

[0090] Blasting vibration monitoring process: Before implementing the alert, all instruments should be installed and the sensors should be fixed to the ground; then the vibration meter should be turned on 20 minutes before the blasting; 15 minutes after the blasting, enter the site to collect the instruments.

[0091] In this embodiment, blasting vibration is safely controlled to improve the flatness and smoothness of the excavation contour surface of the rock foundation pit rapid excavation construction method, improve excavation accuracy, ensure that the blasting vibration is within the tolerable range of surrounding buildings, reduce noise generation to a certain extent, and meet environmental protection requirements.

[0092] Specifically, S320: Blasting rock control: press sandbags at the hole mouth, and cover the sandbags with a layer of covering material, including thickened steel plates or thickened tire plastic (see attached Fig.12 ).

[0093] In this embodiment, blasting flying rock control can reduce the generation of pollutants such as noise and dust, and reduce the cost of subsequent cleaning and treatment of flying rocks.

[0094] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0095] While the embodiments of the present invention have been shown and described, it will be apparent to those skilled in the art that various changes, modifications, substitutions and variations can be made to the embodiments without departing from the principles and spirit of the present invention.

[0096] The present invention and its implementation methods are described above, but such description is not restrictive. The drawings show only one implementation method of the present invention, and the actual steps are not limited thereto. In short, if ordinary technicians in the field are inspired by it and design structural methods and embodiments similar to the technical solution without creativity without departing from the purpose of the invention, they should all fall within the protection scope of the present invention.

Claims

1. A method for rapid excavation of a rock foundation pit, characterized in that the steps include: S100: Blasting Preparation: S110: Blasthole arrangement: Central part: First use the central drilling hole (aperture 600mm), and the holes are evenly arranged from the center to the outside; Peripheral parts: Use weak blasting (separated charge) to arrange peripheral holes. The impact range generated by the detonation of the peripheral holes is mainly the compression circle and crack circle generated by the explosion of the explosives. The calculation formula of the crack circle radius Rr is as follows: Rr = 8r (where r is the radius of the explosive bag) = 8 × (6 ÷ 2) = 24cm; S200: Foundation pit blasting: S210: Charge: First clean the area around the hole, use a long bamboo pole as a gun stick, and send the gunpowder rolls to the bottom of the hole one by one; Charge structure: Use continuous charge, and each gun hole is equipped with a digital electronic detonator; S210: Select blasting materials: Explosives: Use No. 2 rock emulsion explosives, with standard Φ60mm explosive rolls; Detonators: Use digital electronic detonators (set the number of stages to 0-25ms) in the hole (see Figure 4); Detonating cord: According to the geological surrounding rock conditions, the surrounding holes should adopt the smooth blasting method with detonating cord transmission; S220: Blast hole plugging: plugging length: not less than 100cm, plugging material is taphole mud; S230: Detonation using digital electronic detonator detonation network: The detonation sequence is as follows: before blasting, a row of pre-cracked steel pipes are set at the stilt wall to ensure the protection of the rock mass to the bottom of the stilt wall. During blasting, the middle area is blasted first, and then pre-cracked steel pipes are driven along the ground wall (to protect the ground wall), and then the surrounding areas are blasted. Based on a large amount of experience and data collected from similar projects in the past, the designed sequence is followed, and a delay of 25ms each time can achieve better results. Detonating in stages can greatly reduce vibration, and a special detonator for digital electronic detonators is used for detonation, which is connected in parallel to the network.

2. The rock foundation pit rapid excavation construction method according to claim 1, characterized in that: S100 blasting preparation steps also include: S105: Setting up foundation pit retaining structure: The foundation pit excavation adopts underground continuous wall vertical support, and the inner lining wall adopts reverse construction method; the specific foundation pit support structure design is as follows: the underground continuous wall is 1.0m thick, with a total of 18 continuous walls, 9 in the I sequence slot section and 9 in the II sequence slot section. The underground continuous wall joints are connected by milling joints. The underground continuous wall slot depth is 30.3m, the ground-connected wall is 27.6m long, and the slot verticality requirement is 1 / 300; the reverse construction inner lining wall is 1.0m thick, and the inner diameter after lining is 21.6m; the foundation pit adopts ground-connected wall water stop, and φ600 single-tube high-pressure rotary jet piles are used for anti-seepage reinforcement treatment of the slot section connection part; S108: Set the free surface: After completing the foundation pit retaining structure, drill holes in the middle area of ​​blasting. Holes are taken from the ground and drilled to the base (i.e. the bottom plate of blasting) using a rotary drill. The hole diameter is 1 meter. The number of holes drilled on the air surface is at least 3 (depending on the blasting area, it can also be set to 4, 5, or 7).

3. The rock foundation pit rapid excavation construction method according to claim 2 is characterized in that: Also includes: S120: Single hole charge calculation: Q = q·a·b·H According to the surrounding environment of the site and the rock structure, φ60 emulsion explosive is selected, and the explosive consumption per unit is q: 0.6kg / m 3 (Center) and 0.5kg / m 3 (surrounding parts); a-hole spacing; b-row spacing; H-single blasting depth.

4. The rock foundation pit rapid excavation construction method according to claim 3 is characterized in that: Also includes: S122: Center blasting parameter selection: Blasting method: using digital electronic detonator blasting network; Explosive type: Φ = 60mm cylindrical emulsion explosive; Single cycle footage: actual footage of each blasting cycle is 2.8m; Blast hole parameter arrangement: Hole depth: L = 2.8m-3.0m; Rock foundation pit rapid excavation construction method hole diameter: Φ = 76mm; Rock foundation pit rapid excavation construction method hole spacing: a = 1.2m-2.0m; Rock foundation pit rapid excavation construction method row spacing: b = 1.5m; Rock foundation pit rapid excavation construction method inclination: β = 900 Rock foundation pit rapid excavation construction method charge amount: Single blasting charge: Q single = Kn * V In the formula: Kn is the average unit consumption of explosives, which is 0.6kg / m3; V is the volume of blasted rock, based on the actual advance of 2.8m in each cycle, V = (9 / 2)^2*3.14*2.8 = 177m3; then: Q single time = V*Kn = 105kg.

5. The rock foundation pit rapid excavation construction method according to claim 4 is characterized in that: Also includes: S122: Selection of blasting parameters for the surrounding area: Blasting method: using digital electronic detonator blasting network; Explosive type: Φ = 60mm cylindrical emulsion explosive; Single cycle footage: actual footage of each blasting cycle is 2.8m; Blast hole parameter arrangement: Hole depth: L = 2.8m; Aperture: Φ = 76mm; Hole spacing: a = 2.0m; row spacing: b = 1.5m; Charge quantity: Single blasting charge: Q single = Kn * V Where: Kn is the average unit explosive consumption, which is 0.5kg / m3; V is the volume of blasted rock, which is calculated based on the actual penetration of 2.6m per cycle, V = 373.6*2.6≈971.4m3; Then: Q single time = V*Kn≈486kg.

6. The rock foundation pit rapid excavation construction method according to claim 5, characterized in that: Also includes: S300: Blasting safety control: Safety control of harmful effects such as vibration, air shock waves, toxic gases, dust, noise, flying rocks, etc. during the blasting process; S310: Blasting Vibration Safety Control: S313: Blasting vibration verification: The impact of the vibration generated by the blasting on the surrounding area is measured by the vertical vibration velocity of the particle. The maximum amount of explosive in a single stage is calculated according to the following formula: V=K(Q1 / 3 / R)a In the formula: Q is the maximum amount of explosive in a single stage, the maximum for this project is 34kg; V is the vertical vibration speed of the particle; K, a are parameters related to topographical and geological factors and blasting conditions, for this project K=120, a=1.5; R~ is the horizontal distance from the protected object to the center of the explosion source.

7. The rock foundation pit rapid excavation construction method according to claim 6, characterized in that: Also includes: S316: Blasting Vibration Control: Use millisecond blasting, strictly control the maximum single-stage explosive quantity, and reasonably arrange the detonation interval time; Monitoring measures: Arrange multiple measuring points according to the actual working environment of the construction site and the characteristics of the building, analyze the data of each measuring point, and immediately stop the blasting operation when the data exceeds the safety vibration speed specification, and adjust the relevant working methods; Setting of vibration monitoring points: Blasting vibration monitoring is mainly set according to the structural characteristics of the building and the distance from the blasting area. The vibration monitoring points of the working well construction are arranged on the viewing platform, slope retaining wall, steel trestle, etc. near the wellhead.

8. The rock foundation pit rapid excavation construction method according to claim 7, characterized in that: Also includes: Blasting vibration monitoring process: Before implementing the alert, all instruments are installed and the sensors are fixed to the ground; then the vibration meter is turned on 20 minutes before the blasting; 15 minutes after the blast, we entered the scene to collect the instruments.

9. The rock foundation pit rapid excavation construction method according to claim 8, characterized in that: Also includes: S320: Blasting rock control: Sandbags are placed at the hole mouth and a layer of covering material is placed on top of the sandbags, including thickened steel plates or thickened tire plastic.

Citation Information

Patent Citations

  • Blasting method for bridge cylindrical pile foundation with pile foundation diameter of 1.1-1.3m

    CN108088338A

  • V-shaped cutting blasting method of foundation pit

    CN109029167A

  • Large-diameter offshore rock-socketed pile foundation pit excavation method

    CN111749612A

  • Construction method for dismantling diaphragm wall through low-vibration blasting

    CN113091541A

  • Single free face rock plug blasting parameter primary selection test method

    CN113916075A