Material distribution method and device, electronic equipment and medium

By obtaining material demand orders and calculating the total distribution value of the material collection, and using the split backpack algorithm to optimize material distribution, the problems of disorderly consumption of material batches and poor distribution routes caused by manual judgment in the existing technology are solved, and material distribution is realized automation and efficiency improvement.

CN119067574APending Publication Date: 2024-12-03GREE ELECTRIC APPLIANCE INC OF ZHUHAI +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410960981.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-17
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

Relying on manual judgment during the distribution of existing materials is prone to errors, resulting in disorderly consumption of material batches and poor distribution routes, increasing production costs and reducing production efficiency.

Method used

By obtaining material demand orders, determining the material collection based on the material identification, and determining the target material collection from multiple warehouses based on the total distribution value, optimizing the distribution route, calculating the material batch value and path value using the split backpack algorithm, and automatically adjusting the distribution equipment loading and route.

Benefits of technology

The material distribution process is optimized, manual errors are reduced, production costs are reduced, production efficiency is improved, and the orderly consumption of material batches and the optimization of distribution routes is ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119067574A_ABST
    Figure CN119067574A_ABST
Patent Text Reader

Abstract

The embodiment of the invention provides a material delivery method and device, electronic equipment and a medium, and the method comprises the steps: obtaining a material demand order, and determining one or more material sets according to a material identifier carried by the material demand order; according to the total distribution value of the one or more material sets, one or more target material sets are determined from the one or more storage locations in sequence, and a material set list is obtained; and sending a distribution instruction to a distribution device to control the distribution device to sequentially acquire corresponding materials from the storage locations corresponding to the target material set in the material set list, and performing distribution. According to the embodiment of the invention, the optimization of the material delivery process is realized, the materials to be delivered are preferably selected according to the delivery values of different batches of materials, the material batches are consumed in order, the delivery route of the delivery equipment is optimized, the manual errors are reduced, the production cost is reduced, and the production efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of material distribution, and in particular to a material distribution method, device, electronic equipment and medium. Background Art

[0002] In the process of factory production and manufacturing, it is usually necessary to deliver materials from the material warehouse to the production station. With the continuous expansion of the material warehouse, the types of materials are increasing, and the same type of materials have different production batches. In the existing material distribution process, the selection of material batches is usually manually intervened, which relies too much on manual judgment and is prone to errors, resulting in the material batches not being consumed in an orderly manner and the distribution routes of the distribution equipment are not good, which increases production costs and reduces production efficiency. Summary of the invention

[0003] In view of the above problems, a material distribution method, device, electronic device and medium are proposed to overcome the above problems or at least partially solve the above problems, including:

[0004] A material distribution method, the method comprising:

[0005] Obtain a material demand order, and determine one or more material sets according to the material identifier carried in the material demand order; wherein the same material identifier has one or more batches of materials in the warehouse, and the same batch of materials corresponding to the same material identifier in the same storage location is a material set;

[0006] According to the total delivery value of the one or more material sets, one or more target material sets are determined from the one or more storage locations in turn to obtain a material set list; wherein the sum of the material quantities of the target material sets corresponding to the same material identifier is greater than or equal to the quantity required by the material demand order;

[0007] A delivery instruction is sent to the delivery device to control the delivery device to sequentially obtain corresponding materials from the storage locations corresponding to the target material set in the material set list and deliver them.

[0008] Optionally, determining one or more target material sets from the one or more storage locations in sequence according to the total delivery value of the one or more material sets to obtain a material set list includes:

[0009] Determine a material batch value of the one or more material sets, and determine a total delivery value of the one or more material sets based on the material batch value;

[0010] According to the total delivery value, a first material set is determined as a target material set from the one or more material sets, and is added to the material set list.

[0011] Optionally, determining the material batch value of the one or more material sets includes:

[0012] Determine the product value based on the product attributes corresponding to each material set;

[0013] Determine the quantity value based on the quantity of materials corresponding to each material set;

[0014] A material batch value is determined based on the product value and the quantity value.

[0015] Optionally, determining the material batch value according to the product value and the quantity value includes:

[0016] Determine the destination path value based on the distance between the storage location of each material collection and the delivery destination location;

[0017] A material batch value is determined based on the product value, the quantity value, and the destination path value.

[0018] Optionally, the product attribute is the product time of a material batch corresponding to the material set.

[0019] Optionally, after determining the first material set as the target material set from the one or more material sets according to the total delivery value and adding the first material set to the material set list, the method further includes:

[0020] Determine the inter-location path value between the location where the other material collections are located and the location where the target material collection that was most recently added to the material collection list is located;

[0021] Update the total delivery value according to the path value between the storage locations and the material batch value;

[0022] According to the updated total delivery value, the second material set is determined as the target material set from the other material sets, and is added to the material set list.

[0023] Optionally, determining the inter-stock location path value between the stock location where the other material sets are located and the stock location where the target material set that was most recently added to the material set list is located includes:

[0024] Determine the path value between storage locations based on the distance between the storage locations of other material collections and the storage location of the target material collection that was most recently added to the material collection list.

[0025] Optionally, updating the total delivery value according to the path value between storage locations and the material batch value includes:

[0026] The total delivery value is updated according to the path value between storage locations and the corresponding first proportional coefficient, the material batch value and the corresponding second proportional coefficient.

[0027] Optionally, it also includes:

[0028] In response to a user operation, the first proportionality factor and / or the second proportionality factor is adjusted.

[0029] Optionally, the distribution device sends a distribution instruction to control the distribution device to sequentially obtain corresponding materials from storage locations corresponding to the target material set in the material set list, including:

[0030] Acquire capacity information of the distribution equipment, and determine the materials that the distribution equipment can accommodate from the target material set in the material set list in turn according to the capacity information;

[0031] A distribution instruction is sent to the distribution device to control the distribution device to sequentially obtain the materials that the distribution device can accommodate from the storage locations corresponding to the target material set in the material set list.

[0032] A material distribution device, comprising:

[0033] A material set determination module is used to obtain a material demand order and determine one or more material sets according to the material identification carried in the material demand order; wherein the same material identification has one or more batches of materials in the warehouse, and the same batch of materials corresponding to the same material identification in the same storage location is a material set;

[0034] A material set list generating module is used to determine one or more target material sets from the one or more storage locations in turn according to the total delivery value of the one or more material sets, and obtain a material set list; wherein the sum of the material quantities of the target material sets corresponding to the same material identifier is greater than or equal to the quantity required by the material demand order;

[0035] The delivery instruction sending module is used to send a delivery instruction to the delivery device to control the delivery device to sequentially obtain corresponding materials from the storage locations corresponding to the target material set in the material set list and deliver them.

[0036] An electronic device comprises a processor, a memory and a computer program stored in the memory and capable of running on the processor, wherein the computer program implements the material distribution method as described above when executed by the processor.

[0037] A computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the material distribution method described above is implemented.

[0038] The embodiments of the present invention have the following advantages:

[0039] In an embodiment of the present invention, by obtaining a material demand order and determining one or more material sets according to the material identification carried in the material demand order, the same material identification has one or more batches of materials in the warehouse, and the same batch of materials corresponding to the same material identification in the same storage location is a material set. According to the total delivery value of one or more material sets, one or more target material sets are determined from one or more storage locations in turn to obtain a material set list, and then a delivery instruction is sent to the delivery equipment to control the delivery equipment to obtain the corresponding materials from the storage locations corresponding to the target material sets in the material set list in turn and deliver them, thereby optimizing the material delivery process. By selecting the materials to be delivered according to the delivery values ​​of different batches of materials, and then consuming the material batches in an orderly manner and optimizing the delivery routes of the delivery equipment, manual errors are reduced, production costs are reduced, and production efficiency is improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0040] In order to more clearly illustrate the technical solution of the present invention, the accompanying drawings required for use in the description of the present invention will be briefly introduced below. Obviously, the accompanying drawings in the following description are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative labor.

[0041] Figure 1 is a schematic diagram of a system architecture provided by an embodiment of the present invention;

[0042] Figure 2 It is a flow chart of the steps of a material distribution method provided by one embodiment of the present invention;

[0043] Figure 3 is a flow chart of steps of another material distribution method provided by one embodiment of the present invention;

[0044] Figure 4 is a flow chart of steps of another material distribution method provided by one embodiment of the present invention;

[0045] Figure 5 It is a schematic diagram of the structure of a material distribution device provided in some embodiments of the present invention. DETAILED DESCRIPTION

[0046] In order to make the above-mentioned purposes, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. Obviously, the described embodiments are part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0047] In the related art, there are two solutions for material distribution:

[0048] In the first material distribution plan, the workshop that can be used as the distribution center is determined based on the factory layout. After it is used as the distribution center, the transportation distance from other workshops to each distribution center is determined according to the material transportation route, and a corresponding distribution center is allocated to each workshop based on the transportation distance. For each workshop, a periodic cyclic distribution mode is determined based on the workstation coordinates, material demand and material demand time of each workstation to carry out material distribution.

[0049] In the second material distribution plan, the model of the material box is selected according to the size of the material box, and standard material boxes and standard transport vehicles are set up respectively, and the number of standard material boxes fully loaded on the standard transport vehicle is calculated; the material box loading coefficient of various models of material boxes is calculated when they are transferred using standard transport vehicles based on standard material boxes; the total time of all material picking routes is calculated based on the material box loading coefficient and transfer influencing parameters to obtain the optimal material picking route.

[0050] In the above two material distribution solutions, although the first solution can reduce the transportation time of materials, it does not solve the problem of multiple material locations. For example, a certain material has surplus in one or more locations according to different material batches. When there are many material batches and a single material batch is not enough to meet the order, manual intervention is required in the selection of material batches and material locations, and the material batches and corresponding material locations are reselected for the materials in the order; and although the second solution calculates the maximum capacity of the material box and the path calculation, it does not consider the situation where the material box transports multiple materials. For small materials, it is common and time-consuming to transport multiple materials for one order.

[0051] In the embodiment of the present invention, the split backpack algorithm is used to optimize the material distribution process. The smart car calculates the value weight of each batch of materials and the maximum capacity of the backpack according to the split backpack algorithm to obtain the optimal batch distribution, and transports the required parts according to the order manufacturing situation, making full use of the automatic navigation and transportation of the smart car, thereby reducing production costs, improving production efficiency, reducing manual errors, realizing automatic distribution, and saving manufacturing costs. Specifically, through the split backpack algorithm, the distribution value of the material batch itself and the path distribution value between different storage locations are comprehensively calculated, and the maximum value of materials that the material car can accommodate in a single distribution can be obtained, which not only reduces the steps of manual batch selection, but also improves the transportation efficiency of the material car, and reduces transportation costs to a greater extent.

[0052] like Figure 1 In the embodiment of the present invention, the material pulling system includes: system management, equipment management, transportation rule management, basic data management, order management, login and personal center; in equipment management, the power, operating status and location of the conveyor can be monitored in real time; in transportation rule management, the distribution value calculation rules of the materials are stored; in basic data management, the basic information such as the code, name, storage location, and distribution destination of all materials are recorded; in order management, order placement, order process selection, order progress, etc. are included; in the personal center, the basic information of the logged-in user can be modified.

[0053] In the daily factory manufacturing process, the material batch quantity is that each machine will produce a batch of materials in one production process. After production, a printed material batch information will be attached to this batch of materials. Different machines are located in different locations, and the produced materials will also be recorded in different warehouses according to the location of the machines. Users can use the material pull system to pre-set the material distribution value calculation rules according to the material batch information in the basic data management, such as the material code, name, type (self-produced or purchased), material batch quantity and the location from the material storage location to the distribution destination, and obtain the material batch value of each material collection, and store it in the material pull system for subsequent use.

[0054] Through the split backpack algorithm, multiple material batch values ​​of the required materials are obtained, the warehouse location with the highest total distribution value is found, and one or more material batch sets are determined from one or more warehouse locations in turn to obtain a material batch set list, which is sorted according to actual conditions. The distribution equipment is simulated to load materials based on the sorted material batch set list to determine the maximum loading value that the distribution equipment can load materials.

[0055] Reference Figure 2, showing a step flow chart of a material distribution method provided by an embodiment of the present invention. The method can be applied to a material pulling system. The material pulling system can be installed on a PC (personal computer) or a mobile terminal. The management personnel can log in to the material pulling system on the PC terminal, manually add or batch import task information, and the task information includes order information, delivery time, progress, etc. The task information is sent to the message queue through the message middleware. The warehouse operator on the user side can determine whether to accept the task based on the task information in the message queue. If accepted, a material demand order is submitted to the delivery person.

[0056] Specifically, the following steps may be included:

[0057] Step 201, obtain a material demand order, and determine one or more material sets according to the material identification carried in the material demand order; wherein the same material identification has one or more batches of materials in the warehouse, and the same batch of materials corresponding to the same material identification in the same storage location is a material set.

[0058] As some examples, a material requirement order includes the material ID and quantity of the required material. The material ID can be a unique name, model, character string, etc. of the material. For example, the material requirement order includes material 1, 200 pieces; material 2, 300 pieces.

[0059] In the specific implementation, the delivery staff can accept the material demand order issued by the warehouse operator through the user terminal, and according to the required material identification and quantity in the material demand order, the material pull system can find one or more storage locations that store the required materials according to the material batch information in the basic data management, such as the material code, name, and type (self-produced parts or purchased parts), so as to determine one or more material sets in which to store the material.

[0060] When materials enter the warehouse, they will be placed in the corresponding storage location according to their material batch information. Materials of the same type will be placed in the same storage location or different storage locations in the warehouse due to different batches and storage location capacity; that is to say, for storage locations, the same storage location may store multiple materials and may store multiple batches of the same material. For materials, the same material has one or more batches of materials in the warehouse, and the one or more batches of materials may be stored in the same storage location or in different storage locations.

[0061] In order to consume material batches in an orderly manner and optimize the distribution routes of distribution equipment, the same batch of materials corresponding to the same material identification (that is, the same kind of material) in the same storage location can be regarded as a material set, and materials in different storage locations belong to different material sets (different storage locations do not need to consider the type and batch of materials). For the same storage location, different types of materials contained therein are different material sets, and different batches of the same kind of material are different material sets.

[0062] For example, in Example 1, the material required in the material demand order is A. The delivery staff inquires from the material pull system that the storage locations for the material are 001, 002, and 003. Storage location 001 stores two batches of material A (1-A-1 and 1-A-2), which means there are two material sets. Storage location 002 stores one batch of material A (2-A-1), which means there is one material set. Storage location 003 stores one batch of material A (3-A-1), which means there are one material set. That is, there are 4 material sets for material A in the warehouse locations.

[0063] Step 202, based on the total delivery value of the one or more material sets, determine one or more target material sets from the one or more storage locations in turn to obtain a material set list; wherein the sum of the material quantities of the target material sets corresponding to the same material identifier is greater than or equal to the quantity required by the material demand order.

[0064] In the process of a single material delivery, the delivery staff receives the material demand order issued by the warehouse operator based on the user end, and after determining one or more material sets storing the material in the storage location, the total delivery value of the one or more material sets can be calculated; for example, the total delivery value of one or more material sets storing the material in the storage location can be calculated based on the transportation rules in the material pull system, and one or more target material sets can be determined from one or more storage locations in turn according to the total delivery value to obtain a material set list.

[0065] As in Example 1, after determining that material A has 4 material sets in the warehouse location, the total distribution value of the four material batch sets (1-A-1)(1-A-2)(2-A-1)(3-A-1) can be calculated according to the transportation rules. Based on the total distribution value, (1-A-1)(1-A-2)(3-A-1) is determined as the target material set, and a material set list is established, which includes (1-A-1)(1-A-2)(3-A-1).

[0066] As in Example 2, the material required in the material demand order is A, and the required quantity is 100 pieces. The delivery staff inquires from the material pull system that the storage locations where the material is stored are 001, 002, and 003 respectively; storage location 001 has two batches of material A (1-A-1, quantity 25, 1-A-2, quantity 20), which is two material sets; storage location 002 has one batch of material A (2-A-1, quantity 10), which is one material set; storage location 003 has one batch of material A (3-A-1, quantity 60), which is one material set; that is, there are 4 material sets for this material in the warehouse locations.

[0067] After determining that material A has 4 material sets in the warehouse location, the total distribution value of the four material batch sets (1-A-1)(1-A-2)(2-A-1)(3-A-1) can be calculated according to the transportation rules. According to the total distribution value and quantity, (1-A-1, quantity 25)(1-A-2, quantity 20)(3-A-1, quantity 60) are determined as the target material sets, and a material set list is established, which includes (1-A-1, quantity 25)(1-A-2, quantity 20)(3-A-1, quantity 60).

[0068] In actual applications, such as Example 2, the sum of the material quantities of the target material set (1-A-1, quantity 25) (1-A-2, quantity 20) (3-A-1, quantity 60) corresponding to the same material identifier A needs to be greater than or equal to the required quantity of material A in the material demand order, 100 pieces.

[0069] In some embodiments of the present invention, determining one or more target material sets from the one or more storage locations in sequence according to the total delivery value of the one or more material sets to obtain a material set list includes:

[0070] Sub-step 11, determining the material batch value of the one or more material sets, and determining the total distribution value of the one or more material sets based on the material batch value.

[0071] In actual applications, the material batch value is calculated based on the material's production batch (time), quantity, and the distance from the storage location where the material collection is stored to the delivery destination.

[0072] As some examples, batchValue (material batch value) = productValue (product value) + numValue (quantity value) + destinationValue (destination path value).

[0073] As some examples, the value of a material batch can be calculated after the materials are put into storage and stored in the material pull system; it can also be obtained by the delivery staff through querying and calculating through the material pull system after obtaining the material demand order, and the present invention is not limited to this.

[0074] As some examples, value (total distribution value of a collection of materials) = batchRatio (first proportional coefficient) * batchValue (material batch value) + routeRatio (second proportional coefficient) * routeValue (path value between storage locations)

[0075] In actual applications, because materials are different, some are produced in-house and some are purchased and put into storage. For the factory, if the purchased parts need to give priority to the materials purchased earlier, then the first proportional coefficient will be increased; if the self-produced parts need to give priority to the materials transported over short distances, then the second proportional coefficient will be increased. By adjusting the first and second proportional coefficients, the consumption of each material can be flexibly controlled to achieve the principle of reasonable material consumption.

[0076] In a specific implementation, the delivery staff can determine the material batch value of one or more material collections, and based on the material batch value and the transportation rules in the material pull system (such as giving priority to consuming material batches with earlier production dates, or giving priority to short-distance transportation), calculate the total delivery value of one or more material collections stored in the warehouse location.

[0077] Sub-step 12: determining a first material set as a target material set from the one or more material sets according to the total delivery value, and adding the first material set to the material set list.

[0078] In practical applications, after determining the total distribution value of one or more material collections storing the material, a material collection list is established, and a material collection with the highest total distribution value is taken as the first material collection and added to the material collection list.

[0079] If the total distribution values ​​of the three material sets corresponding to material A are: Q set total distribution value 2, W set total distribution value 5, E set total distribution value 7; then we can determine E set as the first material set from the three sets based on the total distribution value, and add E set as the target material set to the material set list.

[0080] In some embodiments of the present invention, determining the material batch value of the one or more material sets includes:

[0081] The product value is determined according to the product attributes corresponding to each material set; the quantity value is determined according to the material quantity corresponding to each material set; and the material batch value is determined according to the product value and the quantity value.

[0082] When materials enter the warehouse, they will be placed in the corresponding storage location according to their material batch information. Materials of the same type will be placed in the same storage location or different storage locations in the warehouse according to the storage location capacity due to different batches. Therefore, the same material and the same batch in a storage location are considered as a material collection, and the same material and different batches are considered as multiple material collections.

[0083] In actual applications, the product attributes corresponding to the material set are the material's production batch, product time, model, etc. For example, for material A, the product time is 2024.03.05; the material quantity corresponding to the material set is the batch quantity corresponding to the material set, such as material A, the production batch is 2024.03.05, and the quantity is 30.

[0084] As some examples, the value of a material batch can be calculated after the materials are put into storage and stored in the material pull system; it can also be calculated by the delivery staff by querying the material collection through the material pull system after obtaining the material demand order. The present invention does not limit this.

[0085] In some embodiments of the present invention, determining the material batch value according to the product value and the quantity value includes:

[0086] Sub-step 21, determining the destination path value according to the distance between the storage location of each material collection and the delivery destination location.

[0087] In actual applications, since the basic data management in the material pulling system records the basic information of all materials, such as the code, name, storage location, and delivery destination, the terminal path value can be calculated based on the distance between the storage location of the material collection and the delivery destination.

[0088] Sub-step 22, determining the material batch value based on the product value, the quantity value, and the terminal path value.

[0089] As some examples, batchValue (material batch value) = productValue (product value) + numValue (quantity value) + destinationValue (destination path value).

[0090] In actual applications, the delivery person can calculate the material batch value of the material collection based on the product value, quantity value, and destination path value of the material collection.

[0091] As some examples, the value of a material batch can be calculated after the material is put into storage and saved in the material pull system; it can also be calculated by the delivery staff when querying the material collection through the material pull system after obtaining the material demand order. The present invention does not limit this.

[0092] In some embodiments of the present invention, the product attribute is the product time of the material batch corresponding to the material set.

[0093] In actual applications, the product attributes corresponding to the material set are the product time and model of the material's production batch. For example, for material A, the product time is 2024.03.05.

[0094] In some embodiments of the present invention, after determining the first material set as the target material set from the one or more material sets according to the total delivery value and adding the first material set to the material set list, the method further includes:

[0095] Sub-step 31, determining the inter-location path value between the location where the other material collections are located and the location where the target material collection that was most recently added to the material collection list is located.

[0096] As some examples, when selecting the material set with the highest total delivery value as the first material set among multiple material sets, it is necessary to determine whether the quantity of the first material set can meet the quantity required by the materials in the material demand order. If so, there is no need to calculate the path value between storage locations. If the quantity of the first material set cannot meet the quantity required by the materials in the material demand order, it is necessary to determine other material sets from the multiple material sets again, determine the distance between the storage locations where the other material sets are located and the storage location where the target material set that was most recently added to the material set list is located, and calculate the path value between the storage locations.

[0097] For example, if the required quantity of material A in the material demand order is 100 pieces, and the first material set with the highest total delivery value is 70 pieces, then the quantity of the first material set cannot meet the required quantity of the material in the material demand order. It is necessary to determine the other material sets corresponding to the material from multiple material sets again to ensure that the required quantity of the material in the material demand order is met during delivery; then determine the distance between the storage location where the other material sets are located and the storage location where the target material set that was most recently added to the material set list is located, and calculate the path value between the storage locations.

[0098] As some examples, first, a delivery task is generated when an order is placed, and the backpack algorithm is split according to each material required for the task. For a single-material order, the material in each storage location will have its own delivery value based on the quantity and production date. If the value batchRatio*batchValue of a certain storage location is the highest, and if the quantity of materials in this storage location meets the order, the material in this storage location can be delivered directly; if the quantity of materials in this storage location is insufficient, the path value batchRatio*batchValue+routeRatio*routeValue must be additionally calculated when calculating the material value of subsequent storage location materials. By calculating the path value from different storage locations to this storage location, plus the material value of the storage location itself, the storage location with the highest delivery value is taken for multi-location delivery until the quantity meets the order requirements.

[0099] As some examples, when there are multiple materials and multiple storage locations in a material demand order, it is necessary to calculate the path value between the storage locations. The path value between the storage locations is calculated by determining the distance between the storage location where other material collections are located and the storage location where the target material collection that was most recently added to the material collection list is located.

[0100] For example, in the material demand order, there are materials A, B, and C that need to be distributed; there are multiple material sets containing material A, namely A001, A002, and A003; there are multiple material sets containing material B, namely B020 and B021; there are multiple material sets containing material C, namely B050 and B056; there are 7 material sets in total, and the total distribution value of the 7 material sets is calculated; through calculation, it is determined that A002 is the material set with the highest total distribution value for material A, B020 is the material set with the highest total distribution value for material B, and B056 is the material set with the highest total distribution value for material C. If the total distribution value of the A002 material set>the total distribution value of the B056 material set>the total distribution value of the B020 material set; take the A002 material set as the first material set, add it to the material set list, determine the distance between the location of the B056 material set and the location of the A002 material set, and calculate the path value between the locations.

[0101] Sub-step 31, updating the total delivery value according to the path value between the storage locations and the material batch value.

[0102] In actual applications, after determining the distance between the storage location of other material collections and the storage location of the target material collection that was most recently added to the material collection list, and calculating the path value between the storage locations, it is necessary to update the total distribution value of other material collections based on the path value between the storage locations and the material batch value of other material collections.

[0103] As in Example 4, after adding the A002 material set as the first material set to the material set list, although B020 is the material set with the highest total distribution value for material B, in the case of multiple materials, in order to improve transportation efficiency, it is necessary to additionally calculate the path value between storage locations. In this case, it is necessary to recalculate the multiple material sets B020 and B021 containing material B, and calculate the distance between B020 and the storage location where the A002 material set is located, and the distance between B021 and the storage location where the A002 material set is located, respectively. Based on the material batch values ​​of the B020 material set and the B021 material set, update the total distribution value of the B020 and B021 material sets.

[0104] Sub-step 32, according to the updated total delivery value, determine the second material set as the target material set from the other material sets, and add it to the material set list.

[0105] In actual applications, after the total delivery value of other material sets is updated, the second material set with the highest total delivery value is determined from other material sets as the target material set according to the updated total delivery value, and is added to the material set list.

[0106] As shown in Example 4, although the total distribution value of material set B020 is the highest in Example 3, in order to improve transportation efficiency, the path value between storage locations is additionally calculated, and the total distribution value of material sets B020 and B021 is updated. The updated total distribution value of material set B021 is greater than the total distribution value of material set B020. Therefore, material set B021 can be used as the second material set and added to the material set list.

[0107] In some embodiments of the present invention, determining the inter-stock location path value between the stock location where the other material collections are located and the stock location where the target material collection that was most recently added to the material collection list is located includes:

[0108] Determine the path value between storage locations based on the distance between the storage locations of other material collections and the storage location of the target material collection that was most recently added to the material collection list.

[0109] As in Example 4, after adding the A002 material set as the first material set to the material set list, although B020 is the material set with the highest total distribution value of material B, in the case of multiple materials, in order to improve transportation efficiency, it is necessary to additionally calculate the path value between storage locations. In this case, it is necessary to recalculate the multiple material sets B020 and B021 containing material B, calculate the distance between B020 and the storage location where the A002 material set is located, and the distance between B021 and the storage location where the A002 material set is located, and determine the storage location path value between B020 and A002, and between B021 and A002.

[0110] In some embodiments of the present invention, updating the total delivery value according to the path value between storage locations and the material batch value includes:

[0111] The total delivery value is updated according to the path value between storage locations and the corresponding first proportional coefficient, the material batch value and the corresponding second proportional coefficient.

[0112] As some examples, value (total distribution value of a collection of materials) = batchRatio (first proportional coefficient) * batchValue (material batch value) + routeRatio (second proportional coefficient) * routeValue (path value between storage locations)

[0113] In actual applications, because materials are different, some are produced in-house and some are purchased and put into storage. For the factory, if the purchased parts need to give priority to the materials purchased earlier, then the first proportional coefficient will be increased; if the self-produced parts need to give priority to the materials transported over short distances, then the second proportional coefficient will be increased. By adjusting the first and second proportional coefficients, the consumption of each material can be flexibly controlled to achieve the principle of reasonable material consumption.

[0114] In some embodiments of the present invention, the method further includes: adjusting the first proportional coefficient and / or the second proportional coefficient in response to a user operation.

[0115] In actual applications, the value of a material batch can be calculated after the material is put into storage and saved in the material pull system; it can also be obtained by the delivery staff through query and calculation through the material pull system after obtaining the material demand order; if the delivery staff has modification requirements, the material pull system can respond to the delivery staff's operation and adjust the first proportional coefficient and / or the second proportional coefficient to give priority to consuming a certain material batch or give priority to consuming materials that can be transported over short distances.

[0116] As some examples, for orders with multiple materials, since the storage locations for multiple materials are scattered and stored in multiple places, the routeRatio size, that is, the path value ratio between the storage locations (the second proportional coefficient), can be increased accordingly. By reducing the path consumption between different storage locations for different materials, the maximum distribution value of multiple materials can be achieved.

[0117] Step 203: Send a delivery instruction to the delivery device to control the delivery device to sequentially obtain corresponding materials from the storage locations corresponding to the target material set in the material set list and deliver them.

[0118] In actual applications, after obtaining the material collection list, the delivery personnel can send delivery instructions to the delivery equipment through the material pulling system according to the material collection list. The delivery instructions include the warehouse location, material identification, and quantity. The delivery equipment obtains the corresponding materials according to the warehouse location corresponding to the target material collection in the material collection list.

[0119] For example, if the material set list is: the first material set (material A, coordinate 1.0.1, quantity 30), the second material set (material B, coordinate 2.0.1, quantity 50), the distribution equipment reaches the storage location corresponding to the first material set to obtain the corresponding materials, and then reaches the storage location corresponding to the second material set to obtain the corresponding materials for distribution.

[0120] In some embodiments of the present invention, the distribution device sends a distribution instruction to control the distribution device to sequentially obtain corresponding materials from the storage locations corresponding to the target material set in the material set list, including:

[0121] Sub-step 41, acquiring capacity information of the distribution equipment, and determining the materials that the distribution equipment can accommodate from the target material set in the material set list in turn according to the capacity information.

[0122] As an example, the capacity information of the delivery equipment is the maximum capacity that the transport vehicle can load.

[0123] In actual applications, before sending a delivery instruction to the delivery equipment, the capacity information of the delivery equipment can be obtained according to the equipment management interface in the material pulling system. According to the capacity information of the delivery equipment, the split backpack algorithm is used to simulate the loading, and the materials that the delivery equipment can accommodate are determined from the target material collection in the material collection list in turn.

[0124] like Figure 3 , obtain the capacity information of the distribution equipment according to the equipment management interface in the material pulling system, define the backpack capacity W of the distribution equipment and the material collection list (material list), calculate / obtain the unit value of each item (the total distribution value of the material collection added to the material collection list), sort the items in descending order according to the unit value (sort the material collection list in descending order), initialize the current weighing and distribution equipment loading value, traverse the sorted item list in sequence (traverse the target material collection in the material collection list in sequence), and determine whether it can be completely added to the backpack. If so, update the current weighing and distribution equipment loading value according to the weight recorded in the basic data management. If it cannot be completely added to the backpack, add the part that the backpack can accommodate, and update the distribution equipment loading value.

[0125] Sub-step 42, sending a delivery instruction to the delivery device to control the delivery device to sequentially obtain the materials that the delivery device can accommodate from the storage locations corresponding to the target material set in the material set list.

[0126] In practical applications, after performing split backpack algorithm simulation loading, the delivery personnel can obtain the transportation with the greatest value, so they can send delivery instructions to the delivery equipment to control the delivery equipment to obtain the materials that the delivery equipment can accommodate from the storage locations corresponding to the target material collection in the material collection list in turn.

[0127] In an embodiment of the present invention, by obtaining a material demand order and determining one or more material sets according to the material identification carried in the material demand order, the same material identification has one or more batches of materials in the warehouse, and the same batch of materials corresponding to the same material identification in the same storage location is a material set. According to the total delivery value of one or more material sets, one or more target material sets are determined from one or more storage locations in turn to obtain a material set list, and then a delivery instruction is sent to the delivery equipment to control the delivery equipment to obtain the corresponding materials from the storage locations corresponding to the target material sets in the material set list in turn and deliver them, thereby optimizing the material delivery process. By selecting the materials to be delivered according to the delivery values ​​of different batches of materials, and then consuming the material batches in an orderly manner and optimizing the delivery routes of the delivery equipment, manual errors are reduced, production costs are reduced, and production efficiency is improved.

[0128] Reference Figure 4 , shows a flow chart of another material distribution method provided by an embodiment of the present invention, which may specifically include the following steps:

[0129] Step 401, obtain a material demand order, and determine one or more material sets according to the material identification carried in the material demand order; wherein, the same material identification has one or more batches of materials in the warehouse, and the same batch of materials corresponding to the same material identification in the same storage location is a material set.

[0130] Step 402, determining a material batch value of the one or more material sets, and determining a total distribution value of the one or more material sets based on the material batch value.

[0131] Step 403: According to the total delivery value, determine the first material set from the one or more material sets as the target material set, and add it to the material set list.

[0132] Step 404, determine the inter-location path value between the location where the other material collections are located and the location where the target material collection that was most recently added to the material collection list is located.

[0133] Step 405: Update the total delivery value according to the path value between storage locations and the material batch value.

[0134] Step 406: According to the updated total delivery value, determine the second material set as the target material set from the other material sets, and add it to the material set list.

[0135] Step 407, acquiring capacity information of the distribution equipment, and determining the materials that the distribution equipment can accommodate from the target material set in the material set list in turn according to the capacity information.

[0136] Step 408: Send a delivery instruction to the delivery device to control the delivery device to sequentially obtain the materials that the delivery device can accommodate from the storage locations corresponding to the target material set in the material set list.

[0137] It should be noted that, for the sake of simplicity, the method embodiments are described as a series of action combinations, but those skilled in the art should be aware that the embodiments of the present invention are not limited by the order of the actions described, because according to the embodiments of the present invention, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions involved are not necessarily required by the embodiments of the present invention.

[0138] Reference Figure 5 , shows a schematic diagram of the structure of a material distribution device provided by some embodiments of the present invention, which may specifically include the following modules:

[0139] The material set determination module 501 is used to obtain a material demand order and determine one or more material sets according to the material identifier carried in the material demand order; wherein the same material identifier has one or more batches of materials in the warehouse, and the same batch of materials corresponding to the same material identifier in the same storage location is a material set;

[0140] The material set list generating module 502 is used to determine one or more target material sets from the one or more storage locations in turn according to the total delivery value of the one or more material sets, and obtain a material set list; wherein the sum of the material quantities of the target material sets corresponding to the same material identifier is greater than or equal to the quantity required by the material demand order;

[0141] The delivery instruction sending module 503 is used to send a delivery instruction to the delivery device to control the delivery device to sequentially obtain corresponding materials from the storage locations corresponding to the target material set in the material set list and deliver them.

[0142] In some embodiments of the present invention, the material set list generating module 502 includes:

[0143] A total distribution value determination submodule, used to determine the material batch value of the one or more material sets, and determine the total distribution value of the one or more material sets based on the material batch value;

[0144] The material set list adding submodule is used to determine the first material set as the target material set from the one or more material sets according to the total delivery value, and add it to the material set list.

[0145] In some embodiments of the present invention, the total delivery value determination submodule includes:

[0146] A product value determination unit, used to determine the product value according to the product attributes corresponding to each material set;

[0147] A quantity value determination unit, used to determine the quantity value according to the material quantity corresponding to each material set;

[0148] The material batch value determination unit is used to determine the material batch value according to the product value and the quantity value.

[0149] In some embodiments of the present invention, the material batch value determination unit includes:

[0150] The terminal path value determination subunit is used to determine the terminal path value according to the distance between the storage location of each material collection and the distribution terminal location;

[0151] The material batch value determination subunit is used to determine the material batch value according to the product value, the quantity value, and the terminal path value.

[0152] In some embodiments of the present invention, the product attribute is the product time of the material batch corresponding to the material set.

[0153] In some embodiments of the present invention, the device further comprises:

[0154] The inter-location path value determination module is used to determine the inter-location path value between the location where other material sets are located and the location where the target material set that was most recently added to the material set list is located;

[0155] A total delivery value updating module, used for updating the total delivery value according to the path value between the storage locations and the material batch value;

[0156] The target material set determination module is used to determine the second material set as the target material set from the other material sets according to the updated total delivery value, and add it to the material set list.

[0157] In some embodiments of the present invention, the inter-location path value determination module includes:

[0158] The storage location distance determination module is used to determine the path value between storage locations based on the distance between the storage locations where other material collections are located and the storage location where the target material collection that was most recently added to the material collection list is located.

[0159] In some embodiments of the present invention, the total delivery value updating module includes:

[0160] The total distribution value updating submodule is used to update the total distribution value according to the path value between the storage locations and the corresponding first proportional coefficient, the material batch value and the corresponding second proportional coefficient.

[0161] In some embodiments of the present invention, the device further comprises:

[0162] The proportionality coefficient adjustment module is used to adjust the first proportionality coefficient and / or the second proportionality coefficient in response to a user operation.

[0163] In some embodiments of the present invention, the delivery instruction sending module 503 includes:

[0164] A distribution equipment capacity information acquisition submodule, used to acquire the capacity information of the distribution equipment, and determine the materials that the distribution equipment can accommodate from the target material set in the material set list in turn according to the capacity information;

[0165] The delivery instruction sending submodule is used to send a delivery instruction to the delivery device to control the delivery device to sequentially obtain the materials that the delivery device can accommodate from the storage locations corresponding to the target material set in the material set list.

[0166] In some embodiments of the present invention, determining one or more target material sets from the one or more storage locations in sequence according to the total delivery value of the one or more material sets to obtain a material set list includes:

[0167] Determine a material batch value of the one or more material sets, and determine a total delivery value of the one or more material sets based on the material batch value;

[0168] According to the total delivery value, a first material set is determined as a target material set from the one or more material sets, and is added to the material set list.

[0169] In some embodiments of the present invention, determining the material batch value of the one or more material sets includes:

[0170] Determine the product value based on the product attributes corresponding to each material set;

[0171] Determine the quantity value based on the quantity of materials corresponding to each material set;

[0172] A material batch value is determined based on the product value and the quantity value.

[0173] In some embodiments of the present invention, determining the material batch value according to the product value and the quantity value includes:

[0174] Determine the destination path value based on the distance between the storage location of each material collection and the delivery destination location;

[0175] A material batch value is determined based on the product value, the quantity value, and the destination path value.

[0176] In some embodiments of the present invention, the product attribute is the product time of the material batch corresponding to the material set.

[0177] In some embodiments of the present invention, after determining the first material set as the target material set from the one or more material sets according to the total delivery value and adding the first material set to the material set list, the method is further used to:

[0178] Determine the inter-location path value between the location where the other material collections are located and the location where the target material collection that was most recently added to the material collection list is located;

[0179] Update the total delivery value according to the path value between the storage locations and the material batch value;

[0180] According to the updated total delivery value, the second material set is determined as the target material set from the other material sets, and is added to the material set list.

[0181] In some embodiments of the present invention, determining the inter-stock location path value between the stock location where the other material collections are located and the stock location where the target material collection that was most recently added to the material collection list is located includes:

[0182] Determine the path value between storage locations based on the distance between the storage locations of other material collections and the storage location of the target material collection that was most recently added to the material collection list.

[0183] In some embodiments of the present invention, updating the total delivery value according to the path value between storage locations and the material batch value includes:

[0184] The total delivery value is updated according to the path value between storage locations and the corresponding first proportional coefficient, the material batch value and the corresponding second proportional coefficient.

[0185] In some embodiments of the present invention, it is also used for:

[0186] In response to a user operation, the first proportionality factor and / or the second proportionality factor is adjusted.

[0187] In some embodiments of the present invention, the distribution device sends a distribution instruction to control the distribution device to sequentially obtain corresponding materials from the storage locations corresponding to the target material set in the material set list, including:

[0188] Acquire capacity information of the distribution equipment, and determine the materials that the distribution equipment can accommodate from the target material set in the material set list in turn according to the capacity information;

[0189] A distribution instruction is sent to the distribution device to control the distribution device to sequentially obtain the materials that the distribution device can accommodate from the storage locations corresponding to the target material set in the material set list.

[0190] In an embodiment of the present invention, by obtaining a material demand order and determining one or more material sets according to the material identification carried in the material demand order, the same material identification has one or more batches of materials in the warehouse, and the same batch of materials corresponding to the same material identification in the same storage location is a material set. According to the total delivery value of one or more material sets, one or more target material sets are determined from one or more storage locations in turn to obtain a material set list, and then a delivery instruction is sent to the delivery equipment to control the delivery equipment to obtain the corresponding materials from the storage locations corresponding to the target material sets in the material set list in turn and deliver them, thereby optimizing the material delivery process. By selecting the materials to be delivered according to the delivery values ​​of different batches of materials, and then consuming the material batches in an orderly manner and optimizing the delivery routes of the delivery equipment, manual errors are reduced, production costs are reduced, and production efficiency is improved.

[0191] An embodiment of the present invention further provides an electronic device, which may include a processor, a memory, and a computer program stored in the memory and capable of running on the processor, and when the computer program is executed by the processor, the above-mentioned material distribution method is implemented.

[0192] An embodiment of the present invention further provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the above-mentioned material distribution method is implemented.

[0193] As for the device embodiment, since it is basically similar to the method embodiment, the description is relatively simple, and the relevant parts can be referred to the partial description of the method embodiment.

[0194] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.

[0195] Those skilled in the art will appreciate that the embodiments of the present invention may be provided as methods, devices, or computer program products. Therefore, the embodiments of the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the embodiments of the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program codes.

[0196] The embodiments of the present invention are described with reference to the flowcharts and / or block diagrams of the methods, terminal devices (systems), and computer program products according to the embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of the processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing terminal device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing terminal device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0197] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing terminal device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce a manufactured product including an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0198] These computer program instructions can also be loaded onto a computer or other programmable data processing terminal device so that a series of operating steps are executed on the computer or other programmable terminal device to produce a computer-implemented process, thereby providing instructions for executing on the computer or other programmable terminal device to implement the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0199] Although the preferred embodiments of the present invention have been described, those skilled in the art may make additional changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of the embodiments of the present invention.

[0200] Finally, it should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or terminal device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or terminal device. In the absence of further restrictions, the elements defined by the sentence "including one..." do not exclude the existence of other identical elements in the process, method, article or terminal device including the above elements.

[0201] The above is a detailed introduction to a material distribution method, device, electronic device and medium provided. Specific examples are used in this article to illustrate the principles and implementation methods of the present invention. The description of the above embodiments is only used to help understand the method of the present invention and its core idea; at the same time, for general technical personnel in this field, according to the idea of ​​the present invention, there will be changes in the specific implementation method and application scope. In summary, the content of this specification should not be understood as a limitation on the present invention.

Claims

1. A material distribution method, characterized in that: The method comprises: Obtain a material demand order, and determine one or more material sets according to the material identifier carried in the material demand order; wherein the same material identifier has one or more batches of materials in the warehouse, and the same batch of materials corresponding to the same material identifier in the same storage location is a material set; According to the total delivery value of the one or more material sets, one or more target material sets are determined from the one or more storage locations in turn to obtain a material set list; wherein the sum of the material quantities of the target material sets corresponding to the same material identifier is greater than or equal to the quantity required by the material demand order; A delivery instruction is sent to the delivery device to control the delivery device to sequentially obtain corresponding materials from the storage locations corresponding to the target material set in the material set list and deliver them.

2. The method according to claim 1, characterized in that: The step of determining one or more target material sets from the one or more storage locations in sequence according to the total distribution value of the one or more material sets to obtain a material set list includes: Determine a material batch value of the one or more material sets, and determine a total delivery value of the one or more material sets based on the material batch value; According to the total delivery value, a first material set is determined as a target material set from the one or more material sets, and is added to the material set list.

3. The method according to claim 2, characterized in that Determining the material batch value of the one or more material sets includes: Determine the product value based on the product attributes corresponding to each material set; Determine the quantity value based on the quantity of materials corresponding to each material set; A material batch value is determined based on the product value and the quantity value.

4. The method according to claim 3, characterized in that Determining the material batch value according to the product value and the quantity value includes: Determine the destination path value based on the distance between the storage location of each material collection and the delivery destination location; A material batch value is determined based on the product value, the quantity value, and the destination path value.

5. The method according to claim 3, characterized in that: The product attribute is the product time of the material batch corresponding to the material set.

6. The method according to any one of claims 2 to 5, characterized in that: After determining the first material set as the target material set from the one or more material sets according to the total delivery value and adding the first material set to the material set list, the method further includes: Determine the inter-location path value between the location where the other material collections are located and the location where the target material collection that was most recently added to the material collection list is located; Update the total delivery value according to the path value between the storage locations and the material batch value; According to the updated total delivery value, the second material set is determined as the target material set from the other material sets, and is added to the material set list.

7. The method according to claim 6, characterized in that The determining of the inter-location path value between the location where the other material collections are located and the location where the target material collection that was most recently added to the material collection list is located includes: Determine the path value between storage locations based on the distance between the storage locations of other material collections and the storage location of the target material collection that was most recently added to the material collection list.

8. The method according to claim 6, characterized in that The updating of the total delivery value according to the path value between the storage locations and the material batch value includes: The total delivery value is updated according to the path value between storage locations and the corresponding first proportional coefficient, the material batch value and the corresponding second proportional coefficient.

9. The method according to claim 8, characterized in that Also includes: In response to a user operation, the first proportionality factor and / or the second proportionality factor is adjusted.

10. The method according to claim 1, characterized in that The distribution device sends a distribution instruction to control the distribution device to sequentially obtain corresponding materials from the storage locations corresponding to the target material set in the material set list, including: Acquire capacity information of the distribution equipment, and determine the materials that the distribution equipment can accommodate from the target material set in the material set list in turn according to the capacity information; A distribution instruction is sent to the distribution device to control the distribution device to sequentially obtain the materials that the distribution device can accommodate from the storage locations corresponding to the target material set in the material set list.

11. A material distribution device, characterized in that: The device comprises: A material set determination module is used to obtain a material demand order and determine one or more material sets according to the material identification carried in the material demand order; wherein the same material identification has one or more batches of materials in the warehouse, and the same batch of materials corresponding to the same material identification in the same storage location is a material set; A material set list generating module is used to determine one or more target material sets from the one or more storage locations in turn according to the total delivery value of the one or more material sets, and obtain a material set list; wherein the sum of the material quantities of the target material sets corresponding to the same material identifier is greater than or equal to the quantity required by the material demand order; The delivery instruction sending module is used to send a delivery instruction to the delivery device to control the delivery device to sequentially obtain corresponding materials from the storage locations corresponding to the target material set in the material set list and deliver them.

12. An electronic device, characterized in that: The method comprises a processor, a memory, and a computer program stored in the memory and capable of running on the processor, wherein when the computer program is executed by the processor, the method for material distribution according to any one of claims 1 to 10 is implemented.

13. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the material distribution method according to any one of claims 1 to 10 is implemented.