Spent fuel storage grillwork installation method
By setting up vertical track components and crane mechanisms in the auxiliary factory, the spent fuel storage tray is lifted into place after the fuel factory is topped off, solving the pollution and maintenance problems of equipment before the ceiling in the existing technology, and improving the equipment Cleaning and maintenance ease.
Patent Information
- Application Number
- CN202411175952.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-26
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2044-08-26
AI Technical Summary
The existing spent fuel storage rack installation method is hoisted before the fuel plant is topped off, resulting in long-term storage of equipment in a humid and polluted environment, prone to rust and foreign matter contamination, and difficulty in later maintenance.
Vertical track components and crane mechanisms are installed in the auxiliary factory, and the spent fuel storage lattice is transported to the bottom of the lifting port of the auxiliary factory through the transport vehicle and the overturning rack. It is placed on the ground by using the track components and crane mechanisms, and is then lifted through the lifting tool. Lift into a spent fuel pool at a designated location.
The lifting and introduction of spent fuel storage lattice after the top of the fuel plant is achieved, avoiding foreign body pollution and rust problems in the pre-top stage, and simplifying the later cleaning and maintenance process.
Smart Images

Figure CN119069152A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of spent fuel storage grid installation, and in particular to a spent fuel storage grid installation method. Background Art
[0002] The spent fuel storage rack is installed in the spent fuel pool of the fuel plant. It is an important equipment in the fuel operation and storage system of the pressurized water reactor nuclear power plant. The fuel plant is equipped with spent fuel pool, container cleaning pool, auxiliary plant and operation room and other areas.
[0003] The existing CAP1400 reactor-type spent fuel storage grids and AP1000 reactor-type spent fuel storage grids are installed by using the open-top method to lift and introduce them into the uncapped fuel building before the fuel building is capped. They are lifted and introduced by a 400t crawler crane and a 50t truck crane.
[0004] Since this method does not involve hoisting and introducing the spent fuel storage grids after the fuel building is capped, the spent fuel storage grids are in a humid and polluted environment for a long time before the fuel building is capped and during the commissioning and construction stage. The interior of each storage cell of the spent fuel storage grid is prone to rust and foreign objects falling into it, and it is difficult to clean and maintain it later. Summary of the invention
[0005] (I) The problem to be solved by the present invention is: how to introduce the spent fuel storage grid after the fuel plant is capped.
[0006] (II) Technical solution
[0007] The spent fuel storage grid installation method provided by the present invention comprises the following installation steps:
[0008] S1: installing a track assembly in the auxiliary plant, the track assembly comprising a first track and a second track arranged vertically, and installing a crane mechanism on the track assembly;
[0009] S2: Place the spent fuel storage grid on the tipping frame of the transport vehicle and transport it to the bottom of the lifting port of the auxiliary building by the transport vehicle;
[0010] S3: The spent fuel storage grid is placed on the ground through the cooperation of the crane mechanism on the track assembly and the crane under the lifting port of the auxiliary plant;
[0011] S4: connecting the crane mechanism hook to the spent fuel storage grid hoisting tool, then installing the spent fuel storage grid hoisting tool on the spent fuel storage grid, lifting the spent fuel storage grid by the crane mechanism and moving it along the track assembly to the top of the spent fuel pool at a designated position, and then lowering the spent fuel storage grid;
[0012] S5: Release the connection between the crane mechanism hook and the spent fuel storage grid lifting tool, dismantle the spent fuel storage grid lifting tool, and carry out the lifting and introduction of the next spent fuel storage grid.
[0013] According to one embodiment of the present invention, the crane mechanism in step S1 includes a spent fuel container crane, a fuel grabber and a hand-operated double-beam trolley, the spent fuel container crane and the fuel grabber are arranged in sequence along the length direction of the first track, the fuel grabber is provided with a movable track, the hand-operated double-beam trolley is arranged on the movable track, and the length direction of the movable track is perpendicular to the length direction of the first track.
[0014] According to one embodiment of the present invention, the step of installing the crane mechanism on the track assembly in step S1 comprises the following steps:
[0015] S11: Set up hanging points on the roof of the auxiliary plant;
[0016] S12: Connect the lifting sling to the hand-operated double-beam trolley, lift the hand-operated double-beam trolley to the moving track on the fuel grabbing machine through the lifting point, and connect it to the fuel grabbing machine through the anti-turnover hook.
[0017] According to one embodiment of the present invention, the step S2 of placing the spent fuel storage grid on the tipping frame of the transport vehicle and transporting it to the bottom of the auxiliary plant lifting port by the transport vehicle comprises the following steps:
[0018] S21: After removing the outer packaging box of the spent fuel storage grid and hoisting the tipping frame onto the transport vehicle, the spent fuel storage grid is positioned onto the tipping frame;
[0019] S22: Fix the spent fuel storage grid and the transport vehicle by the first vehicle sealing belt, fix the spent fuel storage grid and the tipping frame by the second vehicle sealing belt, transport the transport vehicle to the bottom of the auxiliary plant lifting port, and release the first vehicle sealing belt.
[0020] According to one embodiment of the present invention, in the step S3, the spent fuel storage grid is placed on the ground by cooperating with the crane mechanism on the track assembly and the crane below the auxiliary plant hoisting port, including the following steps:
[0021] S31: four counterweights are arranged below the lifting port of the auxiliary plant, and a first hand chain hoist is connected to each counterweight;
[0022] S32: After the spent fuel storage grid is flipped from horizontal to vertical, the spent fuel storage grid is turned over by connecting the spent fuel container crane hook and the MH crane hook below the auxiliary building hoisting port to the first lifting point and the second lifting point in the tilting frame respectively, and then each first hand chain hoist is connected to the lifting lug plate on the tilting frame;
[0023] S33: Place the overturned vertical spent fuel storage grid on the ground, and adjust the first hand chain hoist to tighten the tipping frame.
[0024] According to one embodiment of the present invention, between steps S2 and S3, the following steps are also included:
[0025] Two sets of scaffolding were set up in the container cleaning pool on one side of the spent fuel pool, and the spent fuel storage grid lifting tools were assembled.
[0026] According to one embodiment of the present invention, in the step S4, the crane mechanism hook is connected to the spent fuel storage grid hoisting tool, then the spent fuel storage grid hoisting tool is installed on the spent fuel storage grid, the spent fuel storage grid is lifted by the crane mechanism and moved along the track assembly to above the spent fuel pool at a designated position, and then the spent fuel storage grid is lowered, which includes the following steps:
[0027] Connect the spent fuel container crane hook with the spent fuel storage grid lifting tool, lift the spent fuel storage grid lifting tool to the spent fuel storage grid by the spent fuel container crane, connect the spent fuel storage grid lifting tool to the spent fuel storage grid, release the second vehicle sealing belt, lift the spent fuel storage grid by the spent fuel container crane, move it along the track assembly to the top of the spent fuel pool at the designated position, and then lower the spent fuel storage grid.
[0028] According to one embodiment of the present invention, in step S4, the crane mechanism hook is connected to the spent fuel storage grid hoisting tool, then the spent fuel storage grid hoisting tool is installed on the spent fuel storage grid, the spent fuel storage grid is lifted by the crane mechanism and moved along the track assembly to above the spent fuel pool at a designated position, and then the spent fuel storage grid is lowered, which includes:
[0029] S41: connecting the spent fuel container crane hook to the spent fuel storage grid lifting tool, lifting the spent fuel storage grid lifting tool to the spent fuel storage grid by the spent fuel container crane, connecting the spent fuel storage grid lifting tool to the spent fuel storage grid, releasing the second vehicle sealing belt, lifting the spent fuel storage grid by the spent fuel container crane, and moving it along the track assembly to a position close to the fuel grabber, and removing the spent fuel container crane hook;
[0030] S42: Connect the special lifting tool for the fuel storage grid to the lifting sling of the hand-operated double-beam trolley, drive the hand-operated double-beam trolley to move along the track assembly through the fuel grabbing machine, and move the hand-operated double-beam trolley along the moving track on the fuel grabbing machine to move the spent fuel storage grid to the top of the spent fuel pool at the designated position, and then lower the spent fuel storage grid.
[0031] According to one embodiment of the present invention, in step S5, releasing the connection between the crane mechanism hook and the spent fuel storage grid lifting tool, and dismantling the spent fuel storage grid lifting tool comprises:
[0032] Remove the spent fuel storage grid lifting tool and the installed spent fuel storage grid, put the spent fuel storage grid lifting tool back onto the scaffolding via the spent fuel container crane, and remove the spent fuel container crane hook and the spent fuel storage grid lifting tool.
[0033] According to one embodiment of the present invention, in step S5, releasing the connection between the crane mechanism hook and the spent fuel storage grid lifting tool, and dismantling the spent fuel storage grid lifting tool comprises:
[0034] Remove the spent fuel storage grid lifting tool and the installed spent fuel storage grid, move the spent fuel storage grid lifting tool to the scaffolding by the lifting sling on the hand-cranked double-beam trolley, and disconnect the lifting sling on the hand-cranked double-beam trolley from the spent fuel storage grid lifting tool.
[0035] Beneficial effects of the present invention:
[0036] By installing a track assembly having a first track and a second track that are perpendicular to each other in the auxiliary building, and installing a crane mechanism on the track assembly, after the spent fuel storage grid is transported to the bottom of the auxiliary building hoisting port by the tipping frame of the transport vehicle, the spent fuel storage grid can be put on the ground by the cooperation of the crane mechanism and the crane under the auxiliary building hoisting port, the hook of the crane mechanism is connected with the spent fuel storage grid hoisting tool, and then the spent fuel storage grid is connected with the spent fuel storage grid by the spent fuel storage grid hoisting tool, and then the crane mechanism can hoist the spent fuel storage grid into a spent fuel pool at a designated position and then lower it. In this way, the spent fuel storage grid can be hoisted and introduced after the fuel building is capped, and foreign objects generated in the pre-capping stage and the commissioning construction stage of the fuel building and external foreign objects falling into the spent fuel storage grid will not occur, and since the fuel building is capped, the environment is good and rust is not easy to occur.
[0037] Since the spent fuel storage grids are hoisted and introduced after the fuel building is capped, the time from the use of the spent fuel storage grids is short after the storage cells of the spent fuel storage grids are pickled and passivated before they are hoisted and introduced. After the spent fuel storage grids are hoisted into place, they are easier to clean and maintain later. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0039] Figure 1 A flow chart of a spent fuel storage grid installation method provided by an embodiment of the present invention;
[0040] Figure 2 Provides a schematic diagram of the installation of a transport vehicle, a spent fuel storage grid and a tipping frame for an embodiment of the present invention;
[0041] Figure 3 A schematic diagram of the overturning of a tilting frame provided in an embodiment of the present invention;
[0042] Figure 4 A schematic diagram of a tilting frame and a spent fuel storage grid provided in an embodiment of the present invention after being erected;
[0043] Figure 5 A schematic diagram of a spent fuel container crane provided in an embodiment of the present invention lifting a spent fuel storage grid to a spent fuel pool;
[0044] Figure 6 A schematic diagram of a spent fuel storage grid being hoisted by a sling provided in an embodiment of the present invention;
[0045] Figure 7 A schematic diagram of the area distribution in the auxiliary plant and the moving range of the fuel grabber and the spent fuel container crane provided in an embodiment of the present invention.
[0046] Icons: 1. Spent fuel container crane; 2. Fuel grabber; 3. Hand-cranked double-beam trolley; 4. Lifting sling; 401. Second hand chain hoist; 402. First lifting belt; 403. Second lifting belt; 404. Third lifting belt; 405. Protective rope; 5. Auxiliary plant lifting port; 6. Spent fuel pool; 7. Transport vehicle; 8. Tipping frame; 801. First lifting point; 802. Second lifting point; 9. Counterweight; 10. Spent fuel storage grid; 11. Lifting lug plate; 12. First hand chain hoist; 13. Container cleaning pool. DETAILED DESCRIPTION
[0047] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0048] like Figure 1 - Figure 7 As shown, one embodiment of the present invention provides a spent fuel storage grid installation method, comprising the following installation steps:
[0049] S1: installing a track assembly in the auxiliary plant, the track assembly comprising a first track and a second track arranged vertically, and installing a crane mechanism on the track assembly;
[0050] S2: placing the spent fuel storage grid 10 on the tipping frame 8 of the transport vehicle 7, and transporting it to the bottom of the auxiliary plant lifting port 5 by the transport vehicle 7;
[0051] S3: The spent fuel storage grid 10 is placed on the ground through the cooperation of the crane mechanism on the track assembly and the crane under the auxiliary plant lifting port 5;
[0052] S4: connecting the crane hook to the spent fuel storage grid hoisting tool, then installing the spent fuel storage grid hoisting tool on the spent fuel storage grid 10, lifting the spent fuel storage grid 10 by the crane mechanism and moving it along the track assembly to the top of the spent fuel pool 6 at a designated position, and then lowering the spent fuel storage grid 10;
[0053] S5: disconnecting the crane mechanism hook from the spent fuel storage grid hoisting tool, dismantling the spent fuel storage grid hoisting tool, and hoisting and introducing the next spent fuel storage grid 10.
[0054] By installing a track assembly having a first track and a second track that are perpendicular to each other in the auxiliary building, and installing a crane mechanism on the track assembly, after the spent fuel storage grid 10 is transported to the bottom of the auxiliary building hoisting port 5 by the tipping frame 8 of the transport vehicle 7, the spent fuel storage grid 10 can be placed on the ground by the cooperation of the crane mechanism and the crane under the auxiliary building hoisting port 5, the hook of the crane mechanism is connected to the spent fuel storage grid hoisting tool, and then the spent fuel storage grid hoisting tool is connected to the spent fuel storage grid 10, and then the crane mechanism can hoist the spent fuel storage grid 10 into the spent fuel pool 6 at a designated position and then lower it. This method can realize the hoisting and introduction of the spent fuel storage grid 10 after the fuel building is capped, and thus the situation that foreign matter generated in the pre-capping stage and the commissioning construction stage of the fuel building falls into the spent fuel storage grid 10 and the situation that external foreign matter falls into the spent fuel storage grid 10 will not occur, and because the fuel building has been capped, the environment is good and it is not easy to rust.
[0055] In addition, since the spent fuel storage grid 10 is hoisted and introduced after the fuel plant is capped, before the spent fuel storage grid 10 is hoisted and introduced, each storage chamber of the spent fuel storage grid 10 is pickled and passivated, and the time from the use of the spent fuel storage grid 10 is short. After the spent fuel storage grid 10 is hoisted in place, it is easier to clean and maintain.
[0056] It should be noted that the track assembly, the spent fuel container crane 1 and the fuel grabber 2 in the fuel plant are all indispensable equipment for construction in the fuel plant. The spent fuel container crane 1 and the fuel grabber 2 are hoisted onto the track assembly before the fuel plant is capped to carry out other construction work in the fuel plant. After the fuel plant is capped, the installation of the spent fuel storage grid 10 begins.
[0057] like Figure 5 As shown, further, the crane mechanism in step S1 includes a spent fuel container crane 1, a fuel grabber 2 and a hand-operated double-beam trolley 3, the spent fuel container crane 1 and the fuel grabber 2 are arranged in sequence along the length direction of the first track, the fuel grabber 2 is provided with a movable track, the hand-operated double-beam trolley 3 is arranged on the movable track, and the length direction of the movable track is perpendicular to the length direction of the first track.
[0058] The length direction of the first track is Figure 7 The east-west direction is the same. The first track, the second track and the moving track are all parallel to the horizontal plane.
[0059] Specifically, the installation of the crane mechanism on the track assembly in step S1 includes the following steps:
[0060] S11: Set up hanging points on the roof of the auxiliary plant;
[0061] S12: Connect the lifting sling 4 to the hand-operated double-beam trolley 3, lift the hand-operated double-beam trolley 3 to the moving track on the fuel grabbing machine 2 through the lifting point, and connect it to the fuel grabbing machine 2 through the anti-turnover hook.
[0062] Since the fuel grabber 2 has a rated lifting capacity of 2t, the main hook of the spent fuel container crane 1 has a rated lifting capacity of 140t, and the auxiliary hook has a rated lifting capacity of 10t, the fuel grabber 2 and the spent fuel container crane 1 share the same track, are both located on the first track, and span the entire auxiliary plant. The crane on the ground below the auxiliary plant hoisting port 5 uses an MH14 crane with a rated lifting capacity of 10t. Therefore, the fuel grabber 2 cannot lift the spent fuel storage grid 10 alone, so a hand-operated double-beam trolley 3 is installed on the track of the fuel grabber 2, and a lifting sling 4 is installed on the hand-operated double-beam trolley 3, and the spent fuel storage grid 10 is lifted by the lifting sling 4. Compared with the traditional method of lifting and introducing the spent fuel storage grid by a 400t crawler crane and a 50t truck crane, the mechanical cost of the spent fuel container crane 1, the fuel grabber 2, and the hand-operated double-beam trolley 3 currently used are lower and more cost-effective.
[0063] In addition, in order to prevent the hand-operated double-beam trolley 3 from tipping over from the fuel grabbing machine 2, the hand-operated double-beam trolley 3 and the fuel grabbing machine 2 are connected by installing an anti-tip hook to ensure safety.
[0064] Among them, when arranging the sling 4, it should be satisfied that the operator standing on the two-person bridge of the fuel grabber can easily pull the second hand winch 401 in the sling 4, such as Figure 6 As shown, the sling 4 is composed of a second hand chain hoist 401 of 20t×6m, a protective rope 405 of 20t×6m, a first sling 402 of 20t×5m, a second sling 403 of 20t×10m and two third slings 404 of 10t×1.5m. The top of the first sling 402 is connected to the hand-cranked double-beam trolley 3 through a 25t shackle, the top of the second hand chain hoist 401 is connected to the bottom end of the first sling 402, and its bottom end is connected to the top of the second sling 403, the two third slings 404 are connected to the bottom end of the second sling 403 through a 25t shackle, and the two third slings 404 are used to lift the spent fuel storage grid lifting tool.
[0065] like Figure 2 - Figure 4 As shown, according to one embodiment of the present invention, in step S2, placing the spent fuel storage grid 10 on the tipping frame 8 of the transport vehicle 7 and transporting it to the bottom of the auxiliary plant lifting port 5 by the transport vehicle 7 includes the following steps:
[0066] S21: After removing the outer packaging box of the spent fuel storage grid 10 and hoisting the tipping frame 8 onto the transport vehicle 7, the spent fuel storage grid 10 is positioned onto the tipping frame 8;
[0067] S22: The spent fuel storage grid 10 and the transport vehicle 7 are fixed by the first vehicle sealing belt, the spent fuel storage grid 10 and the tipping frame 8 are fixed by the second vehicle sealing belt, the transport vehicle 7 is transported to the bottom of the auxiliary plant lifting port 5, and the first vehicle sealing belt is released.
[0068] Since the height of the spent fuel storage grid 10 is relatively high, when the transport vehicle 7 transports the spent fuel storage grid 10, it is transported in a horizontal manner to improve the stability during transportation and prevent the spent fuel storage grid 10 from tipping over. In order to facilitate the subsequent operation of preventing the spent fuel storage grid 10 from falling to the ground, a tipping frame 8 is placed on the transport vehicle 7, and the tipping frame 8 is an L-shaped frame. The long side of the spent fuel storage grid 10 is on the long side of the L-shaped frame, which is convenient for lifting the spent fuel storage grid 10 and placing it on the ground. The first sealing belt can further ensure that the tipping frame 8 carrying the spent fuel storage grid 10 is not easy to tip over when the transport vehicle 7 transports it, and the second sealing belt can further ensure that the spent fuel storage grid 10 will not tip over on the tipping frame 8.
[0069] Of course, the spent fuel storage grid 10 can also be transported vertically. In this case, it is not necessary to turn it over by the cooperation of the MH14 crane and the spent fuel container crane 1, which saves work flow and improves construction efficiency.
[0070] like Figure 4 As shown, according to one embodiment of the present invention, in step S3, the spent fuel storage grid 10 is placed on the ground by the crane mechanism on the track assembly cooperating with the crane under the auxiliary plant hoisting port 5, including the following steps:
[0071] S31: four counterweights 9 are arranged below the auxiliary plant lifting port 5, and a first hand chain hoist 12 is connected to each counterweight 9;
[0072] S32: After the spent fuel storage grid 10 is flipped from the horizontal to the vertical, each first hand chain hoist 12 is connected to the lifting lug plate 11 on the tilting frame 8 by connecting the spent fuel container crane 1 hook and the MH14 crane hook under the auxiliary plant lifting port 5 to the first lifting point 801 and the second lifting point 802 in the tilting frame 8 respectively;
[0073] S33: placing the overturned vertical spent fuel storage grid 10 on the ground, and adjusting the first hand chain hoist 12 to tighten the tipping frame 8.
[0074] Specifically, the hook of the spent fuel container crane 1 is connected to the first lifting point 801 on the tilting frame 8, and the hook of the MH14 crane is connected to the second lifting point 802 on the tilting frame 8, and the tilting frame 8 carrying the spent fuel storage grid 10 is lifted, and the hook of the spent fuel container crane 1 is slowly lifted. Before the spent fuel storage grid 10 is flipped to a vertical state (about 30° with the vertical state), the lifting of the hook of the spent fuel container crane 1 is stopped, and the spent fuel container crane 1 and the MH14 crane synchronously cooperate to drop the hook. After the lowest end of the tilting frame 8 is close to the ground, the hook of the spent fuel container crane 1 is continued to be lifted, and the MH14 crane cooperates to complete the flipping and erection of the spent fuel storage grid 10. Since the spent fuel storage grid 10 is connected to the tilting frame 8 by multiple second sealing belts, it can prevent the spent fuel storage grid 10 from shaking during its flipping process.
[0075] The first hand chain hoist 12 can be used to tighten the vertical tilting frame 8 carrying the spent fuel storage grid 10 placed on the ground, so as to prevent the spent fuel storage grid 10 from becoming unstable and tipping over after being turned over and erected.
[0076] According to one embodiment of the present invention, between steps S2 and S3, the following steps are also included:
[0077] Two sets of scaffolding are set up in the container cleaning pool 13 on one side of the spent fuel pool 6, and the spent fuel storage grid hoisting tools are assembled.
[0078] Since the spent fuel storage grid hoisting tool is composed of a rectangular frame and four hanging chains connected around the rectangular frame, the spent fuel container crane 1 can easily lift the spent fuel storage grid hoisting tool by setting up a scaffold.
[0079] After the above preparation work of hoisting the spent fuel storage grid 10 to the ground below the auxiliary powerhouse hoisting port 5 is completed, Figure 5 and Figure 7 As shown, since the fuel grabber 2 and the spent fuel container crane 1 in the auxiliary plant area of the fuel plant share the same track and are both located on the first track, and the fuel grabber 2 will need to perform fuel grabbing operations later, it cannot be dismantled, and the spent fuel container crane 1 can only move in area B, and the range of movement is limited. Three rows of spent fuel storage grids 10 need to be installed from west to east in the spent fuel pool 6. Therefore, the spent fuel pool 6 is sequentially recorded as the first row installation area, the second row installation area, and the third row installation area from west to east. The spent fuel storage grids 10 installed in the first row installation area and the second row installation area cannot be directly hoisted into place by the spent fuel container crane 1. It is necessary to carry out secondary hoisting by the fuel grabber 2 that can move in area A and the hand-cranked double-beam trolley 3 to hoist the spent fuel storage grids 10 into place. Therefore, there will be two hoisting situations when the spent fuel storage grids 10 are hoisted into the spent fuel pool 6:
[0080] Case 1: When the area where the spent fuel storage grid 10 is placed is within the movement range of the spent fuel container crane 1 (i.e., the installed spent fuel storage grid 10 is located in the third row installation area), in step S4, the crane mechanism hook is connected to the spent fuel storage grid hoisting tool, and then the spent fuel storage grid hoisting tool is installed on the spent fuel storage grid 10, and the spent fuel storage grid 10 is lifted by the crane mechanism and moved along the track assembly to the top of the spent fuel pool 6 at the designated position, and then the spent fuel storage grid 10 is lowered, including the following steps:
[0081] The hook of the spent fuel container crane 1 is connected to the spent fuel storage grid lifting tool, the spent fuel storage grid lifting tool is lifted to the spent fuel storage grid 10 by the spent fuel container crane 1, the spent fuel storage grid lifting tool is connected to the spent fuel storage grid 10, the second vehicle sealing belt is released, the spent fuel storage grid 10 is lifted by the spent fuel container crane 1, and is moved along the track assembly to above the spent fuel pool 6 at the designated position, and then the spent fuel storage grid 10 is lowered.
[0082] In step S5, the connection between the crane mechanism hook and the spent fuel storage grid hoisting tool is released, and the spent fuel storage grid hoisting tool is removed, which includes:
[0083] The spent fuel storage grid hoisting tool and the installed spent fuel storage grid 10 are removed, the spent fuel storage grid hoisting tool is put back on the scaffolding by the spent fuel container crane 1, and the hook of the spent fuel container crane 1 and the spent fuel storage grid hoisting tool are released.
[0084] Case 2: When the area where the spent fuel storage grid 10 is placed is outside the movement range of the spent fuel container crane 1 (i.e., the installed spent fuel storage grid 10 is located in the first row installation area and the second row installation area), in step S4, the crane mechanism hook is connected to the spent fuel storage grid hoisting tool, and then the spent fuel storage grid hoisting tool is installed on the spent fuel storage grid 10, and the spent fuel storage grid 10 is lifted by the crane mechanism and moved along the track assembly to the top of the spent fuel pool 6 at the designated position, and then the spent fuel storage grid 10 is lowered, which includes:
[0085] S41: connecting the hook of the spent fuel container crane 1 to the spent fuel storage grid lifting tool, lifting the spent fuel storage grid lifting tool to the spent fuel storage grid 10 by the spent fuel container crane 1, connecting the spent fuel storage grid lifting tool to the spent fuel storage grid 10, releasing the second vehicle sealing belt, lifting the spent fuel storage grid 10 by the spent fuel container crane 1, and moving it along the track assembly to a position close to the fuel grabber 2, that is, lifting the spent fuel storage grid 10 to the third row installation area in the spent fuel pool 6, making its north-south distance from the pool as consistent as possible with the final position distance, and removing the hook of the spent fuel container crane 1;
[0086] S42: Connect the special lifting tool for the fuel storage grid to the lifting sling 4 of the hand-operated double-beam trolley 3, lift the spent fuel storage grid 10 to 50 mm from the bottom of the spent fuel pool 6 by the second hand chain hoist 401 in the lifting sling 4, drive the hand-operated double-beam trolley 3 to move along the track assembly by the fuel grabbing machine 2, and move the hand-operated double-beam trolley 3 along the moving track on the fuel grabbing machine 2 to move the spent fuel storage grid 10 to the top of the spent fuel pool 6 at the designated position, and then lower the spent fuel storage grid 10:
[0087] By making the distance from the north to south to the water pool consistent with the final position in step S41 as much as possible, the driving distance of the hand-operated double-beam trolley 3 on the fuel grabbing machine 2 on the moving track can be reduced.
[0088] In step S5, the connection between the crane mechanism hook and the spent fuel storage grid hoisting tool is released, and the spent fuel storage grid hoisting tool is removed, which includes:
[0089] The spent fuel storage grid hoisting tool and the installed spent fuel storage grid 10 are removed, the spent fuel storage grid hoisting tool is driven to move to the scaffold by the sling 4 on the hand-cranked double-beam trolley 3, and the connection between the sling 4 on the hand-cranked double-beam trolley 3 and the spent fuel storage grid hoisting tool is disconnected.
[0090] According to one embodiment of the present invention, after all the spent fuel storage grids 10 are hoisted and introduced, the hand-operated double-beam trolley 3 is dismantled and removed using the hoisting points on the roof.
[0091] It should be noted that when installing the spent fuel storage racks 10, the spent fuel storage racks 10 in the first row of installation areas are installed first, then the spent fuel storage racks 10 in the second row of installation areas are installed, and finally the spent fuel storage racks 10 in the third row of installation areas are installed.
[0092] In the description of the present invention, it should be noted that the terms "upper", "lower", etc., indicating the orientation or positional relationship are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.
[0093] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a connection between the inside of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances. In addition, in the description of the present invention, unless otherwise specified, "plurality" means two or more.
[0094] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. Installation method of spent fuel storage grid, It is characterized in that The installation steps include: S1: installing a track assembly in the auxiliary plant, the track assembly comprising a first track and a second track arranged vertically, and installing a crane mechanism on the track assembly; S2: placing the spent fuel storage grid (10) on the tipping frame (8) of the transport vehicle (7), and transporting it to the bottom of the auxiliary plant lifting port (5) via the transport vehicle (7); S3: placing the spent fuel storage grid (10) on the ground through the cooperation of the crane mechanism on the track assembly and the crane below the auxiliary plant lifting port (5); S4: connecting the crane mechanism hook to the spent fuel storage grid hoisting tool, then installing the spent fuel storage grid hoisting tool on the spent fuel storage grid (10), lifting the spent fuel storage grid (10) by the crane mechanism and moving it along the track assembly to the top of the spent fuel pool (6) at a designated position, and then lowering the spent fuel storage grid (10); S5: disconnecting the crane mechanism hook from the spent fuel storage grid hoisting tool, dismantling the spent fuel storage grid hoisting tool, and hoisting and introducing the next spent fuel storage grid (10).
2. The spent fuel storage grid installation method according to claim 1, It is characterized in that The crane mechanism in step S1 comprises a spent fuel container crane (1), a fuel grabbing machine (2) and a hand-operated double-beam trolley (3); the spent fuel container crane (1) and the fuel grabbing machine (2) are arranged in sequence along the length direction of the first track; the fuel grabbing machine (2) is provided with a movable track; the hand-operated double-beam trolley (3) is arranged on the movable track; and the length direction of the movable track is perpendicular to the length direction of the first track.
3. The spent fuel storage grid installation method according to claim 2, It is characterized in that The step S1 of installing the crane mechanism on the track assembly comprises the following steps: S11: Set up hanging points on the roof of the auxiliary plant; S12: Connect the lifting sling (4) to the hand-operated double-beam trolley (3), lift the hand-operated double-beam trolley (3) onto the moving track on the fuel grabbing machine (2) through the lifting point, and connect it to the fuel grabbing machine (2) through the anti-turnover hook.
4. The method for installing a spent fuel storage grid according to claim 1, It is characterized in that In the step S2, the spent fuel storage grid (10) is placed on the tipping frame (8) of the transport vehicle (7), and transported to the bottom of the auxiliary plant lifting port (5) by the transport vehicle (7), which includes the following steps: S21: after removing the outer packaging box of the spent fuel storage grid (10) and hoisting the tipping frame (8) onto the transport vehicle (7), the spent fuel storage grid (10) is positioned onto the tipping frame (8); S22: The spent fuel storage grid (10) and the transport vehicle (7) are fixed by a first vehicle sealing belt, the spent fuel storage grid (10) and the tipping frame (8) are fixed by a second vehicle sealing belt, the transport vehicle (7) is transported to the lower side of the auxiliary plant lifting opening (5), and the first vehicle sealing belt is released.
5. The spent fuel storage grid installation method according to claim 1, It is characterized in that In the step S3, the spent fuel storage grid (10) is placed on the ground by the cooperation of the crane mechanism on the track assembly and the crane below the auxiliary plant lifting port (5), which includes the following steps: S31: four counterweights (9) are arranged below the auxiliary plant lifting port (5), and a first hand chain hoist (12) is connected to each counterweight (9); S32: connecting the spent fuel container crane (1) hook and the MH14 crane hook below the auxiliary plant lifting port (5) to the first lifting point (801) and the second lifting point (802) in the tilting frame (8) respectively, flipping the spent fuel storage grid (10) from the horizontal to the vertical, and then connecting each first hand chain hoist (12) to the lifting lug plate (11) on the tilting frame (8); S33: placing the overturned vertical spent fuel storage grid (10) on the ground, and adjusting the first hand chain hoist (12) to tighten the tipping frame (8).
6. The method for installing a spent fuel storage grid according to claim 1, It is characterized in that Between steps S2 and S3, the following steps are also included: Two sets of scaffolding are set up in a container cleaning pool (13) on one side of the spent fuel pool (6), and spent fuel storage grid hoisting tools are assembled.
7. The method for installing a spent fuel storage grid according to claim 6, It is characterized in that In the step S4, the crane mechanism hook is connected to the spent fuel storage grid hoisting tool, and then the spent fuel storage grid hoisting tool is installed on the spent fuel storage grid (10), the spent fuel storage grid (10) is lifted by the crane mechanism and moved along the track assembly to the top of the spent fuel pool (6) at a designated position, and then the spent fuel storage grid (10) is lowered, which includes the following steps: The hook of the spent fuel container crane (1) is connected to the spent fuel storage grid hoisting tool, the spent fuel storage grid hoisting tool is hoisted to the spent fuel storage grid (10) by the spent fuel container crane (1), the spent fuel storage grid hoisting tool is connected to the spent fuel storage grid (10), the second vehicle sealing belt is released, the spent fuel storage grid (10) is hoisted by the spent fuel container crane (1), and the spent fuel storage grid (10) is moved along the track assembly to the top of the spent fuel pool (6) at a designated position, and then the spent fuel storage grid (10) is lowered.
8. The method for installing a spent fuel storage grid according to claim 6, It is characterized in that In the step S4, the crane mechanism hook is connected to the spent fuel storage grid hoisting tool, and then the spent fuel storage grid hoisting tool is installed on the spent fuel storage grid (10), the spent fuel storage grid (10) is lifted by the crane mechanism and moved along the track assembly to the top of the spent fuel pool (6) at a designated position, and then the spent fuel storage grid (10) is lowered, which includes: S41: connecting the hook of the spent fuel container crane (1) to the spent fuel storage grid lifting tool, lifting the spent fuel storage grid lifting tool to the spent fuel storage grid (10) by the spent fuel container crane (1), connecting the spent fuel storage grid lifting tool to the spent fuel storage grid (10), releasing the second vehicle sealing belt, lifting the spent fuel storage grid (10) by the spent fuel container crane (1), and moving along the track assembly to a position close to the fuel grabber (2), and removing the hook of the spent fuel container crane (1); S42: Connect the special lifting tool for the fuel storage grid to the lifting sling (4) of the hand-operated double-beam trolley (3), drive the hand-operated double-beam trolley (3) to move along the track assembly through the fuel grabbing machine, and move the hand-operated double-beam trolley (3) along the moving track on the fuel grabbing machine (2) to move the spent fuel storage grid (10) to the top of the spent fuel pool (6) at the designated position, and then lower the spent fuel storage grid (10).
9. The method for installing a spent fuel storage grid according to claim 7, It is characterized in that In the step S5, the connection between the crane mechanism hook and the spent fuel storage grid hoisting tool is released, and the spent fuel storage grid hoisting tool is removed, which includes: The spent fuel storage grid hoisting tool and the installed spent fuel storage grid (10) are removed, the spent fuel storage grid hoisting tool is put back onto the scaffolding by the spent fuel container crane (1), and the spent fuel container crane (1) hook and the spent fuel storage grid hoisting tool are released.
10. The method for installing a spent fuel storage grid according to claim 8, It is characterized in that In the step S5, the connection between the crane mechanism hook and the spent fuel storage grid hoisting tool is released, and the spent fuel storage grid hoisting tool is removed, which includes: The spent fuel storage grid hoisting tool and the installed spent fuel storage grid (10) are removed, the spent fuel storage grid hoisting tool is driven to move onto the scaffolding by the sling (4) on the hand-cranked double-beam trolley (3), and the connection between the sling (4) on the hand-cranked double-beam trolley (3) and the spent fuel storage grid hoisting tool is disconnected.
Citation Information
Patent Citations
Double-crane common rail arrangement method for fuel workshop of PWR (pressurized water reactor) nuclear power plant
CN107342111A
Auxiliary lifting device of frameworks in spent fuel pool of 1000 MW nuclear power plant
CN108750906A
Lifting and conveying method for nuclear power station emergency diesel generator set
CN109368519A
Spent fuel storage grid rack transport and turnover device and installation method
CN111824938A
Automatic turnover system of spent fuel storage grillwork for nuclear island fuel plant
CN114582536A