Preparation device and preparation method of ultra-high-concentration colloidal gold

By introducing heating time regulation and rinsing and drying mechanism into the colloidal gold preparation device, the problem of fixed heating time and cumbersome cleaning process in the prior art is solved, and flexible adjustment of heating time and simplified cleaning operations are achieved, which improves the universality of the device and productivity.

CN119075846APending Publication Date: 2024-12-06ZHENGZHOU LINGSI BIO-TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411428416.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-14
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

In the existing colloidal gold preparation device, the heating time of the reaction vessel is fixed and cannot be flexibly adjusted according to different types of reducing agents. The heating time limits the versatility and flexibility of the device; and the reaction vessel can only be cleaned after disassembly, which is time-consuming and labor-consuming.

Method used

A super high concentration colloidal gold preparation device is designed, including a heating time control mechanism, which can quickly switch heat exchange pipes of different lengths through a servo motor to achieve flexible adjustment of heating time, and without disassembly and assembly through flushing and drying mechanisms Clean and dry the heat pipes.

Benefits of technology

It realizes the flexibly adjusting the heating time of colloidal gold according to different reducing agent needs, improves the application scope and production efficiency of the device, simplifies the cleaning process, and reduces the preparation time and labor intensity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119075846A_ABST
    Figure CN119075846A_ABST
Patent Text Reader

Abstract

The invention discloses a preparation device and a preparation method of ultrahigh-concentration colloidal gold, and relates to the technical field of colloidal gold preparation. A plurality of heat exchange tubes with different lengths are arranged in the heating duration regulation and control mechanism, each heat exchange tube with different lengths corresponds to colloidal gold preparation heating duration with one duration, and the time of colloidal gold raw materials flowing through the heat exchange tubes can be changed by changing the heat exchange tubes with different lengths to working positions, so that the colloidal gold preparation efficiency is improved. Therefore, the purpose of controlling different time length heat exchange time of the colloidal gold raw material and the heat conduction oil is achieved, the heating time length requirements of different types of colloidal gold can be met, and the application range of the colloidal gold preparation device is widened. The positions of different heat exchange tubes are changed under the drive of the servo motor, the heat exchange tubes at different positions can be rapidly switched to the working positions, compared with a traditional mode that the heat exchange tubes are replaced through disassembly and assembly, the switching mode is faster, and the time for replacing the heat exchange tubes is greatly shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of colloidal gold preparation, in particular to a device for preparing ultra-high concentration colloidal gold and a preparation method thereof. Background Art

[0002] Colloidal gold is a stable, uniform, single-dispersed suspension of gold particles suspended in a liquid formed when gold salt is reduced to gold element. It is widely used in biomedical fields such as immunolabeling, detection technology and rapid diagnosis.

[0003] In the process of preparing colloidal gold, too short a reaction time may result in incomplete formation of gold particles, while too long a reaction time may result in the gold particles being too large or flocculating. In addition, the container for preparing colloidal gold must be absolutely clean. Any slight contamination may interfere with the formation of colloidal gold particles. Therefore, after the preparation of colloidal gold is completed, the preparation container needs to be carefully cleaned to ensure that the equipment is in a clean state.

[0004] Among them, the reducing agents commonly used in the preparation of colloidal gold include sodium citrate, tannic acid, ascorbic acid, white phosphorus, sodium borohydride, etc. Colloidal gold of different particle sizes can be prepared according to the type of reducing agent and the strength of the reducing effect. The use of different types of reducing agents requires targeted selection of heating times of different lengths to ensure that colloidal gold of the desired particle size is obtained.

[0005] A reaction device for continuously preparing colloidal gold disclosed in a patent application with reference publication number CN206445218U is provided, by connecting a raw material mixing container with a reaction container, and limiting the time for the mixed liquid to flow into the reaction container from the inlet end and flow out from the outlet end to match the set time, so that the mixed liquid starts to react immediately after entering the reaction container, until the reaction time required for the reaction is just reached when it flows out from the outlet end, and finally flows out to the colloidal gold collection container; the feeding, mixing, reaction and collection of colloidal gold of the entire reaction device are designed for continuous production, but its structure is simple, there is no complicated pipe spray device, the production time is short, and colloidal gold can be produced not only in large quantities but also on a small scale, and the amount of colloidal gold prepared can be adjusted by an opening and closing valve. Since different raw material bins can be independently controlled and the amount of raw material added can be arbitrarily adjusted, different raw materials can be added in any proportion, so that colloidal gold solutions of different particle sizes can be prepared according to demand.

[0006] A comprehensive analysis of the above patents reveals the following defects:

[0007] In the above patent, the time for the raw material to pass through the heating device is controlled by controlling the length of the reaction container in the heating device (the curved tube), thereby controlling the time for the raw material to be heated; however, after the reaction container is set, its length becomes an immutable parameter, thereby locking the time required for the raw material to pass through the container, so that the heating time can only be set to a fixed value. When different reducing agents are used to prepare colloidal gold, the heating time cannot be flexibly adjusted according to the type of reducing agent used, thereby greatly limiting the versatility and flexibility of the reaction device; secondly, the reaction container needs to be disassembled after each use to complete the cleaning operation, resulting in a time-consuming and labor-intensive cleaning process.

[0008] Therefore, the present invention proposes a preparation device and a preparation method of ultra-high concentration colloidal gold to solve the above problems. Summary of the invention

[0009] In view of the deficiencies in the prior art, the present invention provides a device for preparing ultra-high concentration colloidal gold and a method for preparing the same, which solves the problem that after the reaction container in the current colloidal gold preparation device is set, its length becomes an immutable parameter, thereby locking the time required for the raw material to pass through the container, resulting in the heating time being able to be set to a fixed value. When different types of reducing agents are used to prepare colloidal gold, the heating time cannot be flexibly adjusted according to the type of reducing agent used, thereby greatly limiting the versatility and flexibility of the reaction device; the reaction container needs to be disassembled after each use to complete the cleaning operation, resulting in the problem that the cleaning process is time-consuming and labor-intensive.

[0010] To achieve the above objectives, the present invention is implemented by the following technical scheme: a preparation device for ultra-high concentration colloidal gold, comprising:

[0011] An operating table, wherein a partition is fixedly arranged inside the cavity, and two sides of the partition respectively form an installation chamber and a heating chamber;

[0012] A raw material supply mechanism, which is arranged inside the installation chamber and is used to provide raw materials for preparing ultra-high concentration colloidal gold;

[0013] A heating time regulating mechanism is arranged inside the heating chamber, and is used to provide conveying channels with different lengths according to the heating time requirements for the preparation of ultra-high concentration colloidal gold, so as to ensure that the time for the ultra-high concentration colloidal gold raw material to flow through the conveying pipeline is equal to the required heating time. A servo motor for driving the heating time regulating mechanism to rotate is also fixedly arranged on the inner wall of the installation chamber;

[0014] A flushing mechanism, used for flushing the heating time control mechanism that has completed the ultra-high concentration colloidal gold preparation work;

[0015] The drying mechanism is used to dry the heating time regulating mechanism after the rinsing is completed.

[0016] Furthermore, heat transfer oil is arranged inside the heating chamber, and an electric heating plate for heating the heat transfer oil is fixedly arranged at the bottom thereof, and a control panel is fixedly arranged on the outer wall of the operating table for controlling the operation of all electrical equipment in the ultra-high concentration colloidal gold preparation device.

[0017] Furthermore, the raw material supply mechanism includes a raw material tank 1 and a raw material tank 2 fixedly arranged on the left and right sides of the top of the operating table, and the bottom of the raw material tank 1 and the raw material tank 2 are fixedly provided with a raw material output pipe, and the inside of each of the raw material output pipes is fixedly provided with a quantitative control unit for controlling the release amount of ultra-high concentration colloidal gold preparation raw materials, and the bottom ends of the two raw material output pipes are jointly provided with a mixing unit for mixing ultra-high concentration colloidal gold raw materials, and the output port at the bottom of the mixing unit is fixedly provided with a joint sleeve assembly 1 through a pipeline.

[0018] Furthermore, the mixing unit comprises a mixing cylinder and a stirring shaft rotatably arranged inside the mixing cylinder through a bracket, and an impeller and a stirring blade are fixedly arranged at the top and bottom ends of the stirring shaft respectively.

[0019] Furthermore, the connector sleeve assembly 1 includes a slide seat, a slide groove is provided on the side wall of the slide seat, slopes are provided on both sides of the slide groove, a through hole is provided in the middle position of the slide groove side wall, and the through hole is connected to the output end of the mixing unit through a pipeline.

[0020] Furthermore, the heating time regulating mechanism comprises two annular frames arranged opposite to each other on the left and right sides and a transmission shaft fixedly arranged inside the two annular frames. The spiral heat exchange tube 1, the spiral heat exchange tube 2, the spiral heat exchange tube 3 and the straight heat exchange tube are equidistantly and detachably arranged on the opposite side walls of the two annular frames in sequence. The pitches of the spiral heat exchange tube 1, the spiral heat exchange tube 2 and the spiral heat exchange tube 3 increase proportionally in sequence. A joint assembly is arranged on the side walls of the two annular frames and at positions corresponding to the two ends of the spiral heat exchange tube 1, the spiral heat exchange tube 2, the spiral heat exchange tube 3 and the straight heat exchange tube, respectively. Each of the joint assemblies is connected to the interior of the spiral heat exchange tube 1, the spiral heat exchange tube 2, the spiral heat exchange tube 3 and the straight heat exchange tube at the corresponding position, and an isolation assembly is arranged on one side of the two annular frames.

[0021] The isolation assembly comprises a vertical plate fixedly arranged inside the heating chamber, a through hole three is opened inside the vertical plate, and a circular plate is sealed and rotatably arranged inside the through hole three.

[0022] Further, the joint assembly includes an inner cylinder assembly, an outer cylinder assembly and a plurality of reset assemblies arranged between the inner cylinder assembly and the outer cylinder assembly, the inner cylinder assembly includes a pipe fitting 1 fixedly arranged on the outer wall of the annular frame, a pipe fitting 2 is fixedly arranged inside the pipe fitting 1, a plurality of through holes 1 are evenly opened on the outer wall of the pipe fitting 2, and a gap 1 for liquid flow is formed between the outer wall of the pipe fitting 2 and the inner wall of the pipe fitting 1;

[0023] The outer cylinder assembly comprises a pipe fitting 3 slidably sleeved on the outer wall of the pipe fitting 1, a pipe fitting 4 sealingly and slidably arranged inside the pipe fitting 2 is fixedly arranged on the inner wall of the pipe fitting 3, a gap 2 is formed between the pipe fitting 4 and the inner wall of the pipe fitting 3, and through holes 2 corresponding to the positions of the through holes 1 are evenly opened on the outer wall of the pipe fitting 4;

[0024] The reset assembly includes a guide rod fixedly arranged on the inner wall of the second gap, the guide rod slides through the second pipe and extends to the inside of the first gap, and a spring is slidably sleeved on the outer wall of the guide rod and located between the second pipe and the second gap.

[0025] Further, the flushing mechanism includes a discharge assembly, a clean water pump assembly, a clean water tank and a waste liquid discharge assembly, the clean water pump assembly includes a water pump fixedly arranged on the side wall of the partition and a clean water input pipe and a clean water output pipe fixedly arranged at the input end and output end of the water pump, one end of the clean water output pipe is fixedly arranged with a joint sleeve assembly 3, and the end of the clean water input pipe away from the water pump is connected to the clean water tank;

[0026] The discharge assembly comprises a valve fixedly arranged on the outer wall of the operating table, and a second joint sleeve assembly is fixedly arranged on the input end of the valve;

[0027] The waste liquid discharge assembly includes a liquid discharge pipe fixedly arranged on the outer wall of the operating table, one end of the liquid discharge pipe passes through the operating table and is fixedly provided with a joint sleeve assembly four.

[0028] Further, the drying mechanism includes a drying component, an air purifier and an exhaust gas exhaust component, the drying component includes a hot air blower fixedly arranged on the side wall of the partition, an air inlet pipe and an exhaust pipe are fixedly arranged on the input end and the output end of the hot air blower respectively, a joint sleeve component 5 is fixedly arranged on one end of the exhaust pipe, and the end of the air inlet pipe away from the hot air blower is connected to the air purifier;

[0029] The exhaust gas discharge assembly includes an air supply pipe fixedly arranged on the outer wall of the operating table, one end of the air supply pipe passes through the operating table and is fixedly provided with a joint sleeve assembly 6.

[0030] The present invention also discloses a method for preparing a device for preparing ultra-high concentration colloidal gold, which is used for preparing a device for preparing ultra-high concentration colloidal gold. The method comprises the following steps:

[0031] Step 1: First, adjust the amount of different raw materials in the raw material supply mechanism according to the required preparation amount of high-concentration colloidal gold, and ensure that the amount of different types of raw materials is the correct ratio;

[0032] Step 2: adjusting the position of the heating time regulating mechanism according to the heating time required for the high-concentration colloidal gold preparation process, starting the servo motor to drive the heating time regulating mechanism to rotate intermittently, each time the heating time regulating mechanism rotates by a preset angle value, and turning off the servo motor after the heating time regulating mechanism rotates to the required position;

[0033] Step 3: After the preparation of high-concentration colloidal gold has been completed, the servo motor is started again to drive the heating time adjustment mechanism to rotate intermittently until the part of the heating time adjustment mechanism that participates in the preparation of high-concentration colloidal gold is connected to the flushing mechanism, and the flushing mechanism draws clean water to flush the part of the heating time adjustment mechanism that participates in the preparation of high-concentration colloidal gold;

[0034] Step 4: Start the servo motor again to drive the heating time adjustment mechanism to rotate intermittently until the part of the heating time adjustment mechanism that participates in the preparation of high-concentration colloidal gold and has completed the flushing rotates to complete the connection with the drying mechanism, and the hot air blown out by the drying mechanism dries the flushed part of the heating time adjustment mechanism.

[0035] The present invention provides a device and method for preparing ultra-high concentration colloidal gold. Compared with the prior art, the device has the following beneficial effects:

[0036] 1. A preparation device and preparation method of ultra-high concentration colloidal gold. A heating time control mechanism is provided, wherein a plurality of heat exchange tubes of different lengths are arranged inside the device. Each length of the heat exchange tube corresponds to a heating time for the preparation of colloidal gold. By switching the heat exchange tubes of different lengths to the working position, the time for the colloidal gold raw material to flow through the heat exchange tube can be changed, thereby achieving the purpose of controlling the heat exchange time of the colloidal gold raw material and the heat transfer oil for different lengths, and then being applicable to the heating time requirements of different types of colloidal gold, thereby broadening the application scope of the colloidal gold preparation device. Secondly, by using a servo motor to drive the switching of the positions of different heat exchange tubes, the heat exchange tubes at different positions can be quickly switched to the working position, making the switching process simple and quick. Compared with the traditional method of replacing the heat exchange tube by disassembly and assembly, the switching method of the present invention is faster, greatly shortening the time for replacing the heat exchange tube, and avoiding the process of replacing the heat exchange tube to delay more preparation time.

[0037] 2. A preparation device for ultra-high concentration colloidal gold and a preparation method thereof. By setting a flushing mechanism, after the spiral heat exchange tube or straight tube completes the work of preparing colloidal gold, it can quickly switch from the position of preparing colloidal gold to the position where the flushing mechanism is assembled. The flushing mechanism can use clean water to flush the spiral heat exchange tube or straight tube without disassembling the heat exchange tube, which simplifies the cleaning operation steps of the spiral heat exchange tube or straight tube, making the cleaning process of the colloidal gold preparation device simpler and more convenient.

[0038] 3. A preparation device and preparation method of ultra-high concentration colloidal gold. By setting a drying mechanism, after the spiral heat exchange tube or straight tube is flushed, it can switch from the position of the flushing mechanism to the position of the drying mechanism. There is still no need to disassemble the spiral heat exchange tube or straight tube. The inside of the spiral heat exchange tube or straight tube can be dried by hot air, so that the inside is in a dry and clean state, which is convenient for reuse next time, greatly reducing the difficulty of removing residual water stains inside the spiral heat exchange tube or straight tube. Secondly, the spiral heat exchange tube or straight tube can achieve the purpose of flushing and drying in the process of alternating switching positions. The process of selecting the heat exchange tube, flushing and drying in the preparation of colloidal gold are all achieved by using the same servo motor to drive the position of the switching heating time control mechanism. The three processes cooperate with each other to complete the entire process of colloidal gold preparation, making the structure of the preparation device more compact and the preparation process of colloidal gold simpler and more convenient. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] Figure 1 It is a schematic diagram of the overall three-dimensional structure of the present invention;

[0040] Figure 2 It is a schematic diagram of the internal structure of the present invention;

[0041] Figure 3 This is a schematic diagram of the structure of the raw material supply mechanism of the present invention;

[0042] Figure 4 It is a structural schematic diagram of the joint sleeve component 1 and the joint component in the assembled state of the present invention;

[0043] Figure 5 It is a schematic diagram of the cross-sectional structure of the mixing unit of the present invention;

[0044] Figure 6 This is a schematic diagram of the structure of the heating time regulating mechanism of the present invention in a decomposed state;

[0045] Figure 7 For the present invention Figure 6 A schematic diagram of the enlarged structure of part A;

[0046] Figure 8 This is a schematic diagram of the overall structure of the heating time regulating mechanism of the present invention;

[0047] Fig. 9This is a first structural schematic diagram of the heating time regulating mechanism and the discharge assembly, the joint sleeve assembly IV, and the exhaust gas discharge assembly in the assembly state of the present invention;

[0048] Fig.10 This is a second structural schematic diagram of the heating time regulating mechanism and the discharge assembly, the joint sleeve assembly 4, and the exhaust gas discharge assembly in the assembly state of the present invention;

[0049] Fig.11 It is a schematic diagram of a first cross-sectional structure of a joint assembly of the present invention;

[0050] Fig.12 For the present invention Fig.11 A schematic diagram of the enlarged structure of part B in FIG.

[0051] Fig.13 It is a second cross-sectional structural schematic diagram of the connector assembly of the present invention;

[0052] Fig.14 For the present invention Fig.13 A schematic diagram of the enlarged structure of part C in FIG.

[0053] Fig.15 It is a schematic diagram of the three-section structure of the pipe fitting of the present invention;

[0054] Fig.16 It is a cross-sectional structural schematic diagram of a pipe fitting of the present invention;

[0055] Fig.17 It is a schematic diagram of the structure of the clean water pump assembly of the present invention;

[0056] Fig.18 It is a schematic diagram of the structure of the drying component of the present invention.

[0057] In the figure: 1. operating table; 2. partition; 3. installation chamber; 4. heating chamber; 5. raw material supply mechanism; 51. raw material tank 1; 52. raw material tank 2; 53. raw material output pipe; 54. quantitative control unit; 55. mixing unit; 551. mixing barrel; 552. stirring shaft; 553. impeller; 554. stirring blade; 56. joint sleeve assembly 1; 561. slide seat; 562. slide groove; 563. slope; 6. heating time adjustment mechanism; 61. annular frame; 62. transmission shaft; 63. spiral heat exchange tube 1; 64. spiral heat exchange tube 2; 65. spiral heat exchange tube 3; 66. straight heat exchange tube; 67. joint assembly; 671. pipe fitting 1; 672. pipe fitting 2; 673. through hole 1; 674. pipe fitting three; 675, pipe fitting four; 676, through hole two; 677, guide rod; 678, spring; 68, isolation assembly; 681, vertical plate; 682, through hole three; 683, circular plate; 7, discharge assembly; 71, valve; 72, joint sleeve assembly two; 8, clean water pump assembly; 81, water pump; 82, clean water inlet pipe; 83, clean water outlet pipe; 84, joint sleeve assembly three; 9, clean water tank; 10, waste liquid discharge assembly; 101, discharge pipe; 102, joint sleeve assembly four; 11, drying assembly; 111, hot air blower; 112, air inlet pipe; 113, air supply pipe; 114, joint sleeve assembly five; 12, air purifier; 13, waste gas discharge assembly; 131, exhaust pipe; 132, joint sleeve assembly six. DETAILED DESCRIPTION

[0058] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0059] like Figures 1 to 18 The present invention provides three technical solutions: a device for preparing ultra-high concentration colloidal gold, specifically including the following embodiments:

[0060] Embodiment 1: A device for preparing ultra-high concentration colloidal gold, comprising:

[0061] An operating table 1, wherein a partition 2 is fixedly arranged inside the cavity, and a mounting chamber 3 and a heating chamber 4 are formed on both sides of the partition 2;

[0062] A raw material supply mechanism 5, which is arranged inside the installation chamber 3 and is used to provide raw materials for preparing ultra-high concentration colloidal gold;

[0063] The heating time regulating mechanism 6 is arranged inside the heating chamber 4 and is used to provide conveying channels with different lengths according to the heating time requirements for the preparation of ultra-high concentration colloidal gold, so as to ensure that the time for the ultra-high concentration colloidal gold raw material to flow through the conveying pipeline is equal to the required heating time. A servo motor for driving the heating time regulating mechanism 6 to rotate is also fixedly arranged on the inner wall of the installation chamber 3;

[0064] A flushing mechanism, used for flushing the heating time control mechanism 6 that has completed the ultra-high concentration colloidal gold preparation work;

[0065] The drying mechanism is used to dry the heating time adjustment mechanism 6 after the rinsing is completed.

[0066] The heating chamber 4 is provided with heat transfer oil inside, and an electric heating plate for heating the heat transfer oil is fixedly provided at the bottom thereof, and a control panel is fixedly provided on the outer wall of the operating table 1 for controlling the operation of all electrical equipment in the ultra-high concentration colloidal gold preparation device. The electric heating plate adjusts the heating temperature value that can be achieved through the control panel, thereby controlling the temperature value of the heat transfer oil; a heat transfer oil addition amount marking line is provided on the inner wall of the heating chamber 4, and the oil level of the heat transfer oil should be consistent with the marking line, allowing the heat transfer oil liquid level to be within an error range of two centimeters above and below the marking line; after the heat transfer oil is added as required, only one of the spiral heat exchange tube 1 63, spiral heat exchange tube 2 64, spiral heat exchange tube 3 65, or straight heat exchange tube 66 located at the bottom is immersed in the heat transfer oil each time, ensuring that only one of the spiral heat exchange tube 1 63, spiral heat exchange tube 2 64, spiral heat exchange tube 3 65, or straight heat exchange tube 66 is heated each time. The flushing mechanism includes a discharge assembly 7, a clean water pump assembly 8, a clean water tank 9 and a waste liquid discharge assembly 10. The clean water pump assembly 8 includes a water pump 81 fixedly arranged on the side wall of the partition 2 and a clean water input pipe 82 and a clean water output pipe 83 fixedly arranged at the input end and output end of the water pump 81. One end of the clean water output pipe 83 is fixedly provided with a joint sleeve assembly 3 84, and the end of the clean water input pipe 82 away from the water pump 81 is connected to the clean water tank 9; the discharge assembly 7 includes a valve 71 fixedly arranged on the outer wall of the operating table 1, and the input end of the valve 71 is fixedly provided with a joint sleeve assembly 2 72; the waste liquid discharge assembly 10 includes a discharge pipe 101 fixedly arranged on the outer wall of the operating table 1, one end of the discharge pipe 101 passes through the operating table 1 and is fixedly provided with a joint sleeve assembly 4 102; the joint sleeve assembly 4 102 and the joint sleeve assembly Three 84 are located at a relative position on the same horizontal line, and are used for connecting the joint assemblies 67 at both ends of the spiral heat exchange tube one 63 or the spiral heat exchange tube two 64 or the spiral heat exchange tube three 65 or the straight heat exchange tube 66 to the joint sleeve assembly three 84 and the joint sleeve assembly four 102 respectively during the rotation of the spiral heat exchange tube one 63 or the spiral heat exchange tube two 64 or the spiral heat exchange tube three 65 or the straight heat exchange tube 66, so as to ensure that clean water can enter the spiral heat exchange tube one 63 or the spiral heat exchange tube two 64 or the spiral heat exchange tube three 65 or the straight heat exchange tube 66 through the joint sleeve assembly three 84 and the joint assembly 67, and enter the joint sleeve assembly four 102 through the joint assembly 67 at the other end of the spiral heat exchange tube one 63 or the spiral heat exchange tube two 64 or the spiral heat exchange tube three 65 or the straight heat exchange tube 66, and finally be discharged through the drain pipe 101.The drying mechanism includes a drying component 11, an air purifier 12 and an exhaust gas exhaust component 13. The drying component 11 includes a hot air blower 111 fixedly arranged on the side wall of the partition 2. An air inlet pipe 112 and an exhaust pipe 113 are fixedly arranged on the input end and the output end of the hot air blower 111 respectively. A joint sleeve component 5 114 is fixedly arranged at one end of the exhaust pipe 113. The end of the air inlet pipe 112 away from the hot air blower 111 is connected to the air purifier 12; the exhaust gas exhaust component 13 includes an air supply pipe 131 fixedly arranged on the outer wall of the operating table 1. One end of the air supply pipe 131 passes through the operating table 1 and is fixedly provided with a joint sleeve component 6 132. The joint sleeve assembly six 132 and the joint sleeve assembly five 114 are in relative positions on the same horizontal line, and are used for connecting the joint assemblies 67 located at both ends of the spiral heat exchange tube one 63 or the spiral heat exchange tube two 64 or the spiral heat exchange tube three 65 or the straight heat exchange tube 66 to the joint sleeve assembly five 114 and the joint sleeve assembly six 132 respectively during the rotation of the spiral heat exchange tube one 63 or the spiral heat exchange tube two 64 or the spiral heat exchange tube three 65 or the straight heat exchange tube 66, so as to ensure that the air can enter the spiral heat exchange tube one 63 or the spiral heat exchange tube two 64 or the spiral heat exchange tube three 65 or the straight heat exchange tube 66 through the joint sleeve assembly five 114 and the joint assembly 67, and enter the joint sleeve assembly six 132 through the joint assembly 67 at the other end of the spiral heat exchange tube one 63 or the spiral heat exchange tube two 64 or the spiral heat exchange tube three 65 or the straight heat exchange tube 66, and finally be discharged through the air supply pipe 131.

[0067] Embodiment 2: The main difference between this embodiment and the first technical solution is: a device for preparing ultra-high concentration colloidal gold, the raw material supply mechanism 5 includes a raw material tank 1 51 and a raw material tank 2 52 fixedly arranged on the left and right sides of the top of the operating table 1, the bottom of the raw material tank 1 51 and the raw material tank 2 52 are fixedly provided with a raw material output pipe 53, and the inside of each raw material output pipe 53 is fixedly provided with a quantitative control unit 54 for controlling the release amount of raw materials for preparing ultra-high concentration colloidal gold, and the bottom ends of the two raw material output pipes 53 are jointly provided with a mixing unit 55 for mixing ultra-high concentration colloidal gold raw materials, and the output port at the bottom of the mixing unit 55 is fixedly provided with a joint sleeve assembly 1 56 through a pipeline. The quantitative control unit 54 includes a flow meter, a solenoid valve and a controller; the flow meter is used to measure and monitor the flow of the liquid in real time. The flow meter converts the flow signal into an electrical signal through a sensor and then transmits it to the controller; the controller compares the flow signal with the preset flow value after receiving the flow signal from the flow meter. When the actual flow reaches the preset value, the controller issues an instruction; the solenoid valve is an actuator. After receiving the instruction from the controller, the solenoid valve will quickly and accurately close the valve to cut off the flow of the liquid. The mixing unit 55 includes a mixing barrel 551 and a stirring shaft 552 that is rotatably arranged inside the mixing barrel through a bracket. The top and bottom of the stirring shaft 552 are fixedly provided with an impeller 553 and a stirring blade 554, respectively. The top and bottom of the mixing barrel 551 are respectively provided with a liquid inlet and a liquid outlet, and two raw material output pipes 53 are connected to the liquid inlet of the mixing barrel 551 at the same time. The joint sleeve assembly 1 56 includes a slide seat 561, a slide groove 562 is provided on the side wall of the slide seat 561, and slopes 563 are provided on both sides of the slide groove 562. A through hole is provided in the middle of the side wall of the slide groove 562, and the through hole is connected to the output end of the mixing unit 55 through a pipeline. The structures of the joint sleeve assembly 1 56, the joint sleeve assembly 2 72, the joint sleeve assembly 3 84, the joint sleeve assembly 4 102, the joint sleeve assembly 5 114, and the joint sleeve assembly 6 132 are all the same.

[0068] Embodiment 3: The main difference between this embodiment and the second technical solution is that: a preparation device for ultra-high concentration colloidal gold, the heating time regulating mechanism 6 includes two annular frames 61 arranged opposite to each other on the left and right and a transmission shaft 62 fixedly arranged inside the two annular frames 61, and the opposite side walls of the two annular frames 61 are equidistantly and detachably arranged with spiral heat exchange tube 1 63, spiral heat exchange tube 2 64, spiral heat exchange tube 3 65 and straight heat exchange tube 66, the pitch of spiral heat exchange tube 1 63, spiral heat exchange tube 2 64, spiral heat exchange tube 3 65 increases proportionally in sequence, and a joint assembly 67 is arranged on the side walls of the two annular frames 61 and at positions corresponding to the two ends of the spiral heat exchange tube 1 63, spiral heat exchange tube 2 64, spiral heat exchange tube 3 65 and straight heat exchange tube 66, each joint assembly 67 The head assembly 67 is respectively connected to the inside of the spiral heat exchange tube 1 63, the spiral heat exchange tube 2 64, the spiral heat exchange tube 3 65, and the straight heat exchange tube 66 at the corresponding positions, and an isolation assembly 68 is provided on one side of the two annular frames 61; the diameter and material of the spiral heat exchange tube 1 63, the spiral heat exchange tube 2 64, and the spiral heat exchange tube 3 65 are the same, and between the limited distance between the relative side walls of the two annular frames 61, since the pitches of the spiral heat exchange tube 1 63, the spiral heat exchange tube 2 64, and the spiral heat exchange tube 3 65 increase in proportion in sequence, the total length of the spiral heat exchange tube 1 63, the spiral heat exchange tube 2 64, and the spiral heat exchange tube 3 65 decreases in proportion in sequence, and the straight heat exchange tube 66 and the straight tube with the same diameter as the spiral heat exchange tube 1 63, the spiral heat exchange tube 2 64, and the spiral heat exchange tube 3 65 have the smallest length. The isolation assembly 68 includes a vertical plate 681 fixedly arranged inside the heating chamber 4, a through hole 3 682 is opened inside the vertical plate 681, and a circular plate 683 is sealed and rotatably arranged inside the through hole 3 682. The two ends of the transmission shaft 62 are respectively sealed and penetrate the circular plates 683 in the two isolation assemblies 68 and extend to the outside, and one end of the transmission shaft 62 is connected to the output shaft of the servo motor through a coupling, and the other end of the transmission shaft 62 is rotatably penetrated through the operating table 1 and extends to the outside, and the joint assembly 67 is sealed and penetrates the circular plate 683 near itself and extends to the outside; the heat transfer oil is located between the two isolation assemblies 68.The joint assembly 67 includes an inner cylinder assembly, an outer cylinder assembly, and a plurality of reset assemblies arranged between the inner cylinder assembly and the outer cylinder assembly. The inner cylinder assembly includes a pipe 671 fixedly arranged on the outer wall of the annular frame 61, a pipe 672 is fixedly arranged inside the pipe 671, a plurality of through holes 673 are evenly opened on the outer wall of the pipe 672, and a gap 673 for liquid flow is formed between the outer wall of the pipe 672 and the inner wall of the pipe 671; the outer cylinder assembly includes a sliding sleeve arranged on the pipe 671. The pipe fitting 3 674 is arranged on the outer wall of the pipe fitting 3 674, and the pipe fitting 4 675 is fixedly arranged on the inner wall of the pipe fitting 3 674, and the pipe fitting 4 675 is sealed and slidably arranged inside the pipe fitting 2 672. A gap 2 is formed between the pipe fitting 4 675 and the inner wall of the pipe fitting 3 674. The outer wall of the pipe fitting 4 675 is evenly provided with through holes 2 676 corresponding to the positions of the through holes 1 673. A sealing ring is fixedly arranged on the end of the pipe fitting 3 674, and is used to complete a sealed connection with the inner wall of the slide groove 562 when it meets the joint sleeve assembly 1 56. The reset assembly includes a guide rod 677 fixedly arranged on the inner wall of the gap 2, and the guide rod 677 slides through the pipe fitting 2 672 and extends to the inside of the gap 1. A spring 678 is slidably sleeved on the outer wall of the guide rod 677 and located between the pipe fitting 2 672 and the gap 2. A limit block is fixedly arranged on one end of the spring 678 located inside the gap 1, which is used to prevent the spring 678 from slipping out of the gap 1.

[0069] The present invention also provides a method for preparing a device for preparing ultra-high concentration colloidal gold, which is used for preparing a device for preparing ultra-high concentration colloidal gold. The method comprises the following steps:

[0070] Step 1: First, adjust the amount of different raw materials in the raw material supply mechanism 5 according to the required preparation amount of high-concentration colloidal gold, and ensure that the amount of different types of raw materials added is the correct ratio; the specific process is: first, add the raw materials required for preparing colloidal gold into the raw material tank 1 51 and the raw material tank 2 52, and then adjust the quantitative control unit 54 according to the amount of different types of raw materials used, and use the controller in the quantitative control unit 54 to set the amount of raw materials output from the raw material tank 1 51 or the raw material tank 2 52 at a time.

[0071] Step 2: adjust the position of the heating time control mechanism 6 according to the heating time required for the high-concentration colloidal gold preparation process, start the servo motor to drive the heating time control mechanism 6 to rotate intermittently, and each time it rotates a preset angle value, and turn off the servo motor after the heating time control mechanism 6 rotates to the required position; the specific process is: since the total lengths of the spiral heat exchange tube 1 63, the spiral heat exchange tube 2 64, the spiral heat exchange tube 3 65, and the straight heat exchange tube 66 are successively reduced in proportion, the lengths of the spiral heat exchange tube 1 63, the spiral heat exchange tube 2 64, the spiral heat exchange tube 3 65, and the straight heat exchange tube 66 are all known values, and at each length, the high-concentration colloidal gold flows through the spiral heat exchange tube 1 63, the spiral heat exchange tube 2 64, the spiral heat exchange tube 3 65, and the straight heat exchange tube 66. The total time of the spiral heat exchange tube 1 64, the spiral heat exchange tube 3 65, and the straight heat exchange tube 66 is also a known value; at this time, the spiral heat exchange tube 1 63 or the spiral heat exchange tube 2 64 or the spiral heat exchange tube 3 65 or the straight heat exchange tube 66 is selected according to the heating time required for the high-concentration colloidal gold. It should be noted here that the heating time corresponding to the spiral heat exchange tube 1 63, the spiral heat exchange tube 2 64, the spiral heat exchange tube 3 65, and the straight heat exchange tube 66 is several commonly used colloidal gold processing time. When the spiral heat exchange tube 1 63, the spiral heat exchange tube 2 64, the spiral heat exchange tube 3 65, and the straight heat exchange tube 66 cannot meet the heating time requirement, the heat exchange tube with the corresponding time can be replaced; replace the spiral heat exchange tube 1 63, the spiral heat exchange tube 2 When one of the heat exchange tubes 64, 65, and 66 is rotated, the servo motor is programmed to rotate intermittently at a low speed, each time rotating 90 degrees. The output shaft of the servo motor drives the transmission shaft 62 to rotate intermittently. At the same time, the circular plate 683 rotates along the through hole 682, and the spiral heat exchange tube 1 63, the spiral heat exchange tube 2 64, the spiral heat exchange tube 3 65, and the straight heat exchange tube 66 continuously change positions alternately during the rotation process until the position of the spiral heat exchange tube 1 63, the spiral heat exchange tube 2 64, the spiral heat exchange tube 3 65, or the straight heat exchange tube 66 that meets the requirements is changed to the lowest position, that is, immersed in the heat transfer oil. When the heat exchange tube 1 63 or the spiral heat exchange tube 2 64 or the spiral heat exchange tube 3 65 or the straight heat exchange tube 66 rotates to the lowest position, the pipe fitting 3 674 in the joint assembly 67 at both ends of the spiral heat exchange tube 1 63 or the spiral heat exchange tube 2 64 or the spiral heat exchange tube 3 65 or the straight heat exchange tube 66 located at this position first contacts the slope 563, climbs along the slope 563 into the chute 562, and finally completes a sealed connection with the through hole located inside the chute 562, and the pipe fitting 3 674 is pushed by the slope 563 to slide along the outer wall of the pipe fitting 1 671 until the pipe fitting 3 674 climbs to the surface of the chute 562, and the positions of the through hole 1 673 and the through hole 2 676 coincide with each other;The joint assembly 67 and the joint sleeve assembly 2 72 on the other end of the spiral heat exchange tube 1 63 or the spiral heat exchange tube 2 64 or the spiral heat exchange tube 3 65 or the straight heat exchange tube 66 are connected. The connection process of the joint assembly 67 and the joint sleeve assembly 2 72 and the joint sleeve assembly 1 56 is the same and completed synchronously. The assembly process of the joint assembly 67 and the joint sleeve assembly 2 72 will not be repeated here; then turn off the servo motor. Since a locking mechanism is provided on the output shaft of the servo motor, the locking structure can lock the output shaft of the servo motor immediately after the servo motor is turned off, and can be unlocked immediately after the servo motor is started, thereby preventing the transmission shaft 62 from rotating freely; at this time, the heat transfer oil inside the heating chamber 4 has been heated in advance by the electric heating plate, and the heating temperature is the heating temperature value required by the colloidal gold; when the solenoid valve in the quantitative control unit 54 is opened, the flow The meter measures the amount of raw materials passing through in real time, and sends the metering data to the controller in real time. The liquid raw materials in the raw material tank 1 51 and the raw material tank 2 52 enter the mixing unit 55 through the raw material output pipes 53 below them respectively. The liquid raw materials impact on the surface of the impeller 553 under the action of gravity. The impeller 553 rotates under the impact of the liquid, and synchronously drives the stirring blade 554 to stir the raw materials at the bottom of the mixing barrel 551 cavity. When the amount of raw materials passing through reaches the preset value, the controller immediately sends a closing instruction to the solenoid valve, and the solenoid valve immediately cuts off the raw material passage; the heat transfer oil contacts the outer wall of the spiral heat exchange tube 1 63 or the spiral heat exchange tube 2 64 or the spiral heat exchange tube 3 65 or the straight heat exchange tube 66, and heat exchange is performed, thereby heating the colloidal gold raw material flowing through the spiral heat exchange tube 1 63 or the spiral heat exchange tube 2 64 or the spiral heat exchange tube 3 65 or the straight heat exchange tube 66;

[0072] Step 3: After the preparation of high-concentration colloidal gold has been completed, the servo motor is started again to drive the heating time control mechanism 6 to rotate intermittently until the part of the heating time control mechanism 6 that participates in the preparation of high-concentration colloidal gold is connected to the flushing mechanism, and the flushing mechanism draws clean water to flush the part of the heating time control mechanism 6 that participates in the preparation of high-concentration colloidal gold; the specific process is: the spiral heat exchange tube 1 63 or spiral heat exchange tube 2 64 or spiral heat exchange tube 3 65 or straight heat exchange tube 66 that has completed the preparation of colloidal gold needs to be cleaned immediately after use. At this time, the servo motor is started again to drive the transmission shaft 62 to rotate intermittently clockwise until it rotates to one hundred and eighty degrees, and the spiral heat exchange tube 1 63 or spiral heat exchange tube 2 64 or spiral heat exchange tube 3 65 or straight heat exchange tube 66 located at the bottom position rotates to the top position, that is, the two ends of the spiral heat exchange tube 1 63 or spiral heat exchange tube 2 64 or spiral heat exchange tube 3 65 or straight heat exchange tube 66 The joint assembly 67 on the top is respectively assembled and connected with the joint sleeve assembly four 102 and the joint sleeve assembly three 84. The connection process of the joint assembly 67 and the joint sleeve assembly three 84, the joint sleeve assembly four 102, and the joint sleeve assembly one 56 is the same, and the assembly process of the joint assembly 67 and the joint sleeve assembly three 84, the joint sleeve assembly four 102, will not be repeated here; then the water pump 81 draws the clean water in the clean water tank 9 into the inside through the clean water input pipe 82, and inputs it into the spiral heat exchange tube one 63 or the spiral heat exchange tube two 64 or the spiral heat exchange tube three 65 or the straight heat exchange tube 66 through the clean water output pipe 83 and the joint sleeve assembly three 84. When the high-speed flowing clean water passes through the spiral heat exchange tube one 63 or the spiral heat exchange tube two 64 or the spiral heat exchange tube three 65 or the straight heat exchange tube 66, the colloidal gold residue attached to the inner wall thereof can be removed, and the colloidal gold residue attached to the inner wall thereof can be discharged through the joint sleeve assembly four 102 and the drain pipe 101 along with the water flow. The flushing process lasts for two minutes and then the water pump 81 is turned off;

[0073] Step 4: Start the servo motor again to drive the heating time regulating mechanism 6 to rotate intermittently until the part of the heating time regulating mechanism 6 that participates in the high-concentration colloidal gold preparation and has completed the flushing is rotated to complete the connection with the drying mechanism, and the hot air blown out by the drying mechanism dries the flushed part of the heating time regulating mechanism 6; the specific process is: after the flushing is completed, start the servo motor again to rotate ninety degrees clockwise, and the position of the spiral heat exchange tube 1 63 or the spiral heat exchange tube 2 64 or the spiral heat exchange tube 3 65 or the straight heat exchange tube 66 after the flushing is changed from the highest point to the joint assemblies 67 at both ends thereof, respectively connected to the joint sleeve assembly 6 132, the joint sleeve component five 114 completes the sealed assembly connection, at this time, the hot air blower 111 draws the external air into the interior through the air purifier 12, and after heating, enters the spiral heat exchange tube one 63 or spiral heat exchange tube two 64 or spiral heat exchange tube three 65 or straight heat exchange tube 66 through the exhaust pipe 113, the joint sleeve component five 114 and the joint assembly 67, and the hot air can quickly heat the moisture remaining in the spiral heat exchange tube one 63 or spiral heat exchange tube two 64 or spiral heat exchange tube three 65 or straight heat exchange tube 66. After the moisture evaporates, it is discharged in the form of water vapor along with the air through the joint sleeve component six 132 and the air supply pipe 131.

[0074] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0075] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A device for preparing ultra-high concentration colloidal gold, characterized in that: include: An operating table, wherein a partition is fixedly arranged inside the cavity, and two sides of the partition respectively form an installation chamber and a heating chamber; A raw material supply mechanism, which is arranged inside the installation chamber and is used to provide raw materials for preparing ultra-high concentration colloidal gold; A heating time regulating mechanism is arranged inside the heating chamber, and is used to provide conveying channels with different lengths according to the heating time requirements for the preparation of ultra-high concentration colloidal gold, so as to ensure that the time for the ultra-high concentration colloidal gold raw material to flow through the conveying pipeline is equal to the required heating time. A servo motor for driving the heating time regulating mechanism to rotate is also fixedly arranged on the inner wall of the installation chamber; A flushing mechanism, used for flushing the heating time control mechanism that has completed the ultra-high concentration colloidal gold preparation work; The drying mechanism is used to dry the heating time regulating mechanism after the rinsing is completed.

2. The device for preparing ultra-high concentration colloidal gold according to claim 1, characterized in that: The interior of the heating chamber is provided with heat-conducting oil, and an electric heating plate for heating the heat-conducting oil is fixedly arranged at the bottom thereof; a control panel is fixedly arranged on the outer wall of the operating table for controlling the operation of all electrical equipment in the ultra-high concentration colloidal gold preparation device.

3. The device for preparing ultra-high concentration colloidal gold according to claim 1, characterized in that: The raw material supply mechanism includes a raw material tank 1 and a raw material tank 2 fixedly arranged on the left and right sides of the top of the operating table, and the bottom of the raw material tank 1 and the raw material tank 2 are fixedly provided with a raw material output pipe, and the inside of each of the raw material output pipes is fixedly provided with a quantitative control unit for controlling the release amount of ultra-high concentration colloidal gold preparation raw materials, and the bottom ends of the two raw material output pipes are jointly provided with a mixing unit for mixing ultra-high concentration colloidal gold raw materials, and the output port at the bottom of the mixing unit is fixedly provided with a joint sleeve component 1 through a pipeline.

4. The device for preparing ultra-high concentration colloidal gold according to claim 3, characterized in that: The mixing unit comprises a mixing cylinder and a stirring shaft rotatably arranged inside the mixing cylinder through a bracket, and an impeller and a stirring blade are fixedly arranged at the top and bottom ends of the stirring shaft respectively.

5. The device for preparing ultra-high concentration colloidal gold according to claim 3, characterized in that: The connector sleeve assembly 1 includes a slide seat, a slide groove is provided on the side wall of the slide seat, slopes are provided on both sides of the slide groove, a through hole is provided in the middle position of the slide groove side wall, and the through hole is connected to the output end of the mixing unit through a pipeline.

6. The device for preparing ultra-high concentration colloidal gold according to claim 1, characterized in that: The heating time regulating mechanism comprises two annular frames arranged opposite to each other on the left and right sides and a transmission shaft fixedly arranged inside the two annular frames. The opposite side walls of the two annular frames are equidistantly and detachably arranged with spiral heat exchange tube 1, spiral heat exchange tube 2, spiral heat exchange tube 3 and straight heat exchange tube. The pitches of spiral heat exchange tube 1, spiral heat exchange tube 2 and spiral heat exchange tube 3 increase proportionally in sequence. A joint assembly is arranged on the side walls of the two annular frames and at positions corresponding to both ends of spiral heat exchange tube 1, spiral heat exchange tube 2, spiral heat exchange tube 3 and straight heat exchange tube. Each of the joint assemblies is respectively connected to the inside of spiral heat exchange tube 1, spiral heat exchange tube 2, spiral heat exchange tube 3 and straight heat exchange tube at the corresponding position. An isolation assembly is arranged on one side of the two annular frames. The isolation assembly comprises a vertical plate fixedly arranged inside the heating chamber, a through hole three is opened inside the vertical plate, and a circular plate is sealed and rotatably arranged inside the through hole three.

7. The device for preparing ultra-high concentration colloidal gold according to claim 6, characterized in that: The joint assembly comprises an inner cylinder assembly, an outer cylinder assembly and a plurality of reset assemblies arranged between the inner cylinder assembly and the outer cylinder assembly, the inner cylinder assembly comprises a pipe fitting 1 fixedly arranged on the outer wall of the annular frame, a pipe fitting 2 is fixedly arranged inside the pipe fitting 1, a plurality of through holes 1 are evenly opened on the outer wall of the pipe fitting 2, and a gap 1 for liquid flow is formed between the outer wall of the pipe fitting 2 and the inner wall of the pipe fitting 1; The outer cylinder assembly comprises a pipe fitting 3 slidably sleeved on the outer wall of the pipe fitting 1, a pipe fitting 4 sealingly and slidably arranged inside the pipe fitting 2 is fixedly arranged on the inner wall of the pipe fitting 3, a gap 2 is formed between the pipe fitting 4 and the inner wall of the pipe fitting 3, and through holes 2 corresponding to the positions of the through holes 1 are evenly opened on the outer wall of the pipe fitting 4; The reset assembly includes a guide rod fixedly arranged on the inner wall of the second gap, the guide rod slides through the second pipe and extends to the inside of the first gap, and a spring is slidably sleeved on the outer wall of the guide rod and located between the second pipe and the second gap.

8. The device for preparing ultra-high concentration colloidal gold according to claim 1, characterized in that: The flushing mechanism includes a discharge assembly, a clean water pump assembly, a clean water tank and a waste liquid discharge assembly. The clean water pump assembly includes a water pump fixedly arranged on the side wall of the partition and a clean water input pipe and a clean water output pipe fixedly arranged at the input end and the output end of the water pump. A joint sleeve assembly 3 is fixedly arranged at one end of the clean water output pipe. The end of the clean water input pipe away from the water pump is connected to the clean water tank. The discharge assembly comprises a valve fixedly arranged on the outer wall of the operating table, and a second joint sleeve assembly is fixedly arranged on the input end of the valve; The waste liquid discharge assembly includes a liquid discharge pipe fixedly arranged on the outer wall of the operating table, one end of the liquid discharge pipe passes through the operating table and is fixedly provided with a joint sleeve assembly four.

9. The device for preparing ultra-high concentration colloidal gold according to claim 1, characterized in that: The drying mechanism includes a drying component, an air purifier and an exhaust gas exhaust component. The drying component includes a hot air blower fixedly arranged on the side wall of the partition. An air inlet pipe and an exhaust pipe are fixedly arranged on the input end and the output end of the hot air blower respectively. A joint sleeve component 5 is fixedly arranged on one end of the exhaust pipe. The end of the air inlet pipe away from the hot air blower is connected to the air purifier. The exhaust gas discharge assembly includes an air supply pipe fixedly arranged on the outer wall of the operating table, one end of the air supply pipe passes through the operating table and is fixedly provided with a joint sleeve assembly 6.

10. A method for preparing a device for preparing ultra-high concentration colloidal gold, characterized in that: A device for preparing ultra-high concentration colloidal gold as claimed in any one of claims 1 to 9, the method comprising the following steps: Step 1: First, adjust the amount of different raw materials in the raw material supply mechanism according to the required preparation amount of high-concentration colloidal gold, and ensure that the amount of different types of raw materials is the correct ratio; Step 2: adjusting the position of the heating time regulating mechanism according to the heating time required for the high-concentration colloidal gold preparation process, starting the servo motor to drive the heating time regulating mechanism to rotate intermittently, each time the heating time regulating mechanism rotates by a preset angle value, and turning off the servo motor after the heating time regulating mechanism rotates to the required position; Step 3: After the preparation of high-concentration colloidal gold has been completed, the servo motor is started again to drive the heating time adjustment mechanism to rotate intermittently until the part of the heating time adjustment mechanism that participates in the preparation of high-concentration colloidal gold is connected to the flushing mechanism, and the flushing mechanism draws clean water to flush the part of the heating time adjustment mechanism that participates in the preparation of high-concentration colloidal gold; Step 4: Start the servo motor again to drive the heating time adjustment mechanism to rotate intermittently until the part of the heating time adjustment mechanism that participates in the preparation of high-concentration colloidal gold and has completed the flushing rotates to complete the connection with the drying mechanism, and the hot air blown out by the drying mechanism dries the flushed part of the heating time adjustment mechanism.