Construction method applied to split type bent cap and capable of automatically adjusting reverse tensioning

By combining the embedded anchor rod and temporary pull rod with the independent pressure stabilization and adjustment system, the problem of loose tension of the piece-type cover beam is solved, stable tension during the construction process is achieved, and safety and construction efficiency are improved.

CN119083316APending Publication Date: 2024-12-06THE THIRD CONSTR OF CHINA CONSTR EIGHTH ENG BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411278835.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-12
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

In the construction of prefabricated bridges, the reverse tension of the segmented cover beam is prone to slack and instability during assembly, resulting in safety accidents and low construction efficiency.

Method used

The embedded anchor rod and temporary pull rod are combined with the autonomous pressure stabilization and adjustment system, and the tension is performed through the penetrating jack to ensure that the tension force remains stable during the construction process, and automatic adjustment is achieved using the hydraulic system and PLC control module.

Benefits of technology

It effectively avoids instability accidents caused by tension and slack, improves construction safety and efficiency, and ensures the stability and construction quality of the cover beam.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083316A_ABST
    Figure CN119083316A_ABST
Patent Text Reader

Abstract

The invention provides a construction method applied to the reverse tensioning of a fragmented cover beam and capable of automatically adjusting, and relates to the technical field of assembly type bridge construction, and the construction method comprises the steps of installing an embedded component, installing the cover beam, connecting the cover beam with the embedded component, adjusting tension and the like. The construction safety and stability of the split type bent cap can be improved, and smooth proceeding of the construction process is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of prefabricated bridge construction, and in particular to a construction method for reverse tensioning of a segmented cap beam that can be adjusted autonomously. Background Art

[0002] Prefabricated bridge engineering is a modern bridge construction method that uses prefabricated components for bridge construction. These prefabricated components include piers, cap beams, box beams, etc., among which the segmented cap beam is one of them. The segmented cap beam is one of the bridge superstructure components prefabricated in the factory or on site. It is one of the main load-bearing components in the bridge, bearing the lateral forces between the piers and transmitting these forces to the piers. In prefabricated bridge engineering, the production and hoisting of the segmented cap beam is an important link, which embodies the principles of efficiency, environmental protection and sustainability of prefabricated bridge engineering. By adopting the segmented cap beam, construction efficiency can be improved, environmental impact can be reduced, resources and costs can be saved, and project quality can be improved.

[0003] The reverse tension method can be used to temporarily fix the two cap beam segments after assembling them on the columns, and then cast the middle wet joint to close the cap beam. However, the effect of on-site application is not good at present. After the prestressed threaded steel is tensioned, tension relaxation will occur, and safety accidents caused by instability have occurred.

[0004] Therefore, maintaining the reverse tension of the segmented cap beam is a key issue in construction and a necessary means to improve operating experience and work efficiency. Summary of the invention

[0005] In view of the above-mentioned prior art, the present invention proposes a construction method for self-adjusting reverse tensioning of a segmented cap beam.

[0006] The present invention provides a construction method for self-adjusting reverse tension of a segmented cap beam, comprising the following steps: S1. Install embedded components: Before pouring the cap and prefabricating the cap beam, embed several embedded anchor rods on the cap and embed several embedded steel pipes on the cap beam; S2. Install the cap beam: install the cap beam on the upper end of the column; S3, connecting the cap beam and the embedded components: a number of temporary tie rods are arranged on each side of the segmented cap beam segment, the lower ends of the temporary tie rods are connected to the embedded anchor rods, the upper ends of the temporary tie rods pass through the cap beam through the embedded steel pipes and are anchored on the top surface of the cap beam, a through-type jack is installed on the top of the temporary tie rod, and tensioning is performed by the through-type jack to achieve the tension stress value required by the temporary tie rod; S4. Adjust the tension: During the tensioning process, continuously control the tensioning stress value of the through-type jack.

[0007] Preferably, in S1, the distance error from the center of the embedded anchor rod to the edge of the column is ±2mm, the embedded anchor rod is set vertically, and the accuracy error is controlled within 2mm. The embedded anchor rod adopts a diameter of 50mm, a PSB strength of not less than 1080Mpa, and a length of 2400mm. It is fixed by an anchor plate and a nut. The size of the anchor plate is 300*300*20mm, and the nut is a matching product; the embedded depth of the embedded anchor rod is 2100mm, 300mm is reserved for the top of the pedestal, the lateral spacing between the center of the embedded anchor rod and the inner surface of the column is 320mm, and the lateral spacing of the embedded anchor rod along the bridge direction is 800mm; the diameter of the embedded steel pipe is 80mm and the thickness is 3mm.

[0008] Preferably, in S2, the installation of the cap beam is specifically as follows: the transport vehicle is parked on the side walkway of the column, two cranes respectively use the lifting wire rope to vertically fasten the two lifting points at both ends of the cap beam, and the cap beam is slowly lifted synchronously, and the transport vehicle is withdrawn; one crane moves backward while rotating, and the other crane cooperates with the rotation, and slowly lifts the cap beam above the height of the column. After the entire cap beam rotates 90 degrees, it is slowly lowered toward the column; when the embedded steel bars of the column are all inserted into the embedded sleeves of the cap beam, the force is unloaded in stages; when the cap beam is in place, each crane reserves 20t of lifting force to adjust the coordinate position of the cap beam.

[0009] Preferably, in S3, the temporary tie rod is made of high-quality rolled threaded steel with a diameter of 50 mm and a PSB strength of not less than 930 MPa. The temporary tie rod is 330 mm away from the inner edge of the cap beam and 320 mm away from the edge of the column.

[0010] Preferably, in S4, an autonomous pressure-stabilizing and regulating system is used to continuously control the tensile stress value of the through-type jack; the autonomous pressure-stabilizing and regulating system includes a main system oil circuit, one side of the main system oil circuit is connected to the oil chamber and cavity of the hydraulic jack, the other side of the main system oil circuit is connected to the motor and the hydraulic oil pump in sequence, the oil outlet end of the hydraulic oil pump is connected to the two-position three-way hydraulically controlled reversing valve, the oil outlet ends of the two-position three-way hydraulically controlled reversing valve are respectively connected to the cavity of the hydraulic jack and the hydraulic oil tank, a one-way valve 3 is arranged between the two-position three-way hydraulically controlled reversing valve and the cavity of the hydraulic jack, a sequence valve is arranged between the hydraulic control end of the two-position three-way hydraulically controlled reversing valve and the cavity of the hydraulic jack, an overflow valve is arranged between the hydraulic oil pump and the hydraulic oil tank, and the pressure value of the overflow valve is the pressure maintaining value of the system.

[0011] Preferably, during voltage stabilization, when the oil pressure monitoring module monitors that the oil pressure of the hydraulic system drops to the oil replenishment starting pressure value, the signal is fed back to the PLC control module, and the PLC control module again sends an instruction to start the hydraulic oil pump to replenish the oil pressure; when the oil pressure monitoring module monitors that the oil pressure of the hydraulic system rises to the oil replenishment stop pressure value, the signal is fed back to the PLC control module, and the PLC control module controls the hydraulic oil pump to stop running.

[0012] Compared with the prior art, the beneficial effects of the present invention are as follows: the present invention proposes a self-adjustable construction method for reverse tensioning of a segmented cap beam, which can solve the tension relaxation and instability problems of prestressed threaded steel bars caused by the reverse tensioning method in the prior art when assembling the cap beam segments. By adopting this method, after the cap beam segments are assembled on the columns, they can be temporarily fixed by the reverse tensioning method, and the stability and reliability of the tensioning force can be ensured by the self-adjusting mechanism. This can not only improve the safety during the construction process and avoid instability safety accidents caused by tension relaxation, but also help to improve the overall construction quality and efficiency of the cap beam. The present invention can improve the safety and stability of the construction of segmented cap beams and ensure the smooth progress of the construction process. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a construction schematic diagram of the self-adjustable reverse tensioning of the segmented cap beam in an embodiment of the present invention.

[0014] Figure 2 Schematic diagram of the structure of the autonomous voltage stabilization and regulation system in an embodiment of the present invention.

[0015] In the figure, 1. oil chamber; 2. cavity; 3. one-way valve; 4. two-position three-way hydraulically controlled reversing valve; 5. overflow valve; 6. hydraulic oil pump; 7. electric motor; 8. main system oil circuit; 9. sequence valve; 10. pedestal; 11. embedded anchor rod; 12. cap beam; 13. embedded steel pipe; 14. column; 15. temporary pull rod; 16. connector; 17. jack bracket; 18. through-type jack. DETAILED DESCRIPTION

[0016] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific embodiments.

[0017] Example: Figure 1 , 2 As shown, a construction method for self-adjusting reverse tensioning of a segmented cap beam comprises the following steps: S1. Installation of embedded components: Before pouring the pedestal and prefabricating the cap beam, three embedded anchor rods 11 are embedded on each side of the pedestal 10, and three embedded steel pipes 13 are embedded on each side of the cap beam 12; the distance error between the center of the embedded anchor rod 11 and the edge of the column 14 is ±2mm, the embedded anchor rod 11 is set vertically, and the accuracy error is controlled within 2mm. The embedded anchor rod 11 adopts a diameter of 50mm, a PSB strength of not less than 1080Mpa, and a length of 2400mm. It is fixed by an anchor plate and a nut. The size of the anchor plate is 300*300*20mm, and the nut is a matching product; the embedded depth of the embedded anchor rod 11 is 2100mm, 300mm is reserved on the top of the pedestal, the lateral spacing between the center of the embedded anchor rod 11 and the inner surface of the column is 320mm, and the lateral spacing of the embedded anchor rod 11 along the bridge direction is 800mm; the diameter of the embedded steel pipe 13 is 80mm and the thickness is 3mm.

[0018] S2. Install the cap beam: install the cap beam 12 on the upper end of the column 14, specifically: park the transport vehicle on the side walkway of the column 14, and use two cranes to vertically fasten the two lifting points at both ends of the cap beam 12 with a lifting wire rope, and slowly lift the cap beam 12 synchronously, and remove the transport vehicle; one crane moves backward and rotates at the same time, and the other crane cooperates with the rotation to slowly lift the cap beam 12 above the height of the column 14. After the entire cap beam 12 rotates 90 degrees, it slowly begins to lower toward the column 14; when the embedded steel bars of the column 14 are all inserted into the embedded sleeves of the cap beam 12, the force is unloaded in stages; when the cap beam 12 is in place, each crane reserves 20t of lifting force to adjust the coordinate position of the cap beam 12.

[0019] S3. Connecting the cap beam and embedded components: three temporary tie rods 15 are arranged on each side of the segmented cap beam segment. The temporary tie rods 15 are made of high-quality rolled threaded steel with a diameter of 50 mm and a PSB strength of not less than 930 MPa. The temporary tie rods 15 are 330 mm away from the inner edge of the cap beam and 320 mm away from the edge of the column. The lower end of the temporary tie rod 15 is connected to the embedded anchor rod 11 through the connector 16. The upper end of the temporary tie rod 15 passes through the cap beam 12 through the embedded steel pipe 13 and is anchored to the top surface of the cap beam 12 with an anchor plate and a nut. A through-type jack 18 is installed on the top of the temporary tie rod 15 through a jack bracket 17. Tensioning is performed through the through-type jack 18 to achieve the required tension stress value of the temporary tie rod 15.

[0020] S4. Adjusting tensioning: During the tensioning process, an autonomous pressure-stabilizing and regulating system is used to continuously control the tensioning stress value of the through-type jack 18 to ensure the safety of the construction process and minimize the risk; after the temporary pull rod 15 is tensioned to a predetermined value, the autonomous pressure-stabilizing and regulating system is installed on the upper side of the through-type jack 18 to achieve pressure stabilization and pressure maintenance; the autonomous pressure-stabilizing and regulating system includes a main system oil circuit 8, one side of the main system oil circuit 8 is connected to the oil chamber 1 and cavity 2 of the hydraulic jack, and the other side of the main system oil circuit 8 is connected to the motor 7 and the hydraulic oil pump 6 in sequence, and the oil outlet end of the hydraulic oil pump 6 is connected to the two-position three-way hydraulically controlled reversing valve 4, and the oil outlet ends of the two-position three-way hydraulically controlled reversing valve 4 are respectively connected to the cavity 2 of the hydraulic jack and the hydraulic oil tank They are connected, a one-way valve 3 is arranged between the two-position three-way hydraulically controlled reversing valve 4 and the cavity 2 of the hydraulic jack, a sequence valve 9 is arranged between the hydraulic control end of the two-position three-way hydraulically controlled reversing valve 4 and the cavity 2 of the hydraulic jack, and an overflow valve 5 is arranged between the hydraulic oil pump 6 and the hydraulic oil tank, and the pressure value of the overflow valve 5 is the pressure maintaining value of the system; during pressure stabilization, when the oil pressure monitoring module monitors that the oil pressure of the hydraulic system drops to the oil replenishment starting pressure value, the signal is fed back to the PLC control module, and the PLC control module sends an instruction to start the hydraulic oil pump 6 again to replenish the oil pressure; when the oil pressure monitoring module monitors that the oil pressure of the hydraulic system rises to the oil replenishment stop pressure value, the signal is fed back to the PLC control module, and the PLC control module controls the hydraulic oil pump 6 to stop running.

[0021] In the autonomous pressure-stabilizing and regulating system, the hydraulic oil pump 6, the motor 7 and the main system oil circuit 8 are rigidly connected. When the motor 7 rotates, the main system oil circuit 8 and the hydraulic oil pump 6 are driven to move simultaneously. The hydraulic oil pump 6 is connected to the cavity 2 of the hydraulic jack through the two-position three-way hydraulically controlled reversing valve 4. The hydraulic control end of the two-position three-way hydraulically controlled reversing valve 4 is connected to the cavity 2 through the sequence valve 9. Under the action of the sequence valve 9, the two-position three-way hydraulically controlled reversing valve 4 is determined to be reversed according to the pressure of the cavity 2, so that the hydraulic oil pump 6 provides the cavity 2 with pressure-maintaining pressure oil through the two-position three-way hydraulically controlled reversing valve 4. A relief valve 5 is also connected in parallel at the outlet of the hydraulic oil pump 6 to limit the outlet pressure of the hydraulic oil pump 6. The autonomous pressure-stabilizing and regulating system sets the pressure of the pressure-maintaining relief valve and the opening pressure value of the sequence valve, so that the sequence valve 9 is automatically opened during the pressure-maintaining process and the pressure is transmitted to the two-position three-way hydraulically controlled reversing valve 4, and the output pressure of the hydraulic oil pump 6 is transmitted to the actuator through the reversing valve.

[0022] This embodiment enables the cap beam segments to be temporarily fixed by reverse tensioning after being assembled on the columns 14. This method allows the tensioning force of the prestressed threaded steel bars to be adjusted autonomously during the construction process, ensuring that the tensioning force always remains stable, and avoiding the instability problem caused by tension relaxation. In this way, not only the safety of construction is improved, but also the stability and durability of the bridge structure are ensured, providing a more reliable technical solution for the construction of segmented cap beams.

[0023] The above are only implementation methods of the present invention, and do not limit the patent scope of the present invention. Any equivalent scheme made by using the contents of the present invention specification, directly or indirectly applied in other related technical fields, are also within the patent protection scope of the present invention.

Claims

1. A construction method for self-adjusting reverse tensioning of a segmented cap beam, characterized in that: The steps include: S1. Install embedded components: Before pouring the cap and prefabricating the cap beam, embed several embedded anchor rods on the cap and embed several embedded steel pipes on the cap beam; S2. Install the cap beam: install the cap beam on the upper end of the column; S3, connecting the cap beam and the embedded components: a number of temporary tie rods are arranged on each side of the segmented cap beam segment, the lower ends of the temporary tie rods are connected to the embedded anchor rods, the upper ends of the temporary tie rods pass through the cap beam through the embedded steel pipes and are anchored on the top surface of the cap beam, a through-type jack is installed on the top of the temporary tie rod, and tensioning is performed by the through-type jack to achieve the tension stress value required by the temporary tie rod; S4. Adjust the tension: During the tensioning process, continuously control the tensioning stress value of the through-type jack.

2. The construction method for self-adjusting reverse tensioning of a segmented cap beam as claimed in claim 1 is characterized in that: In S1, the distance error from the center of the embedded anchor rod to the edge of the column is ±2mm. The embedded anchor rod is set vertically, and the accuracy error is controlled within 2mm. The embedded anchor rod adopts high-precision rolled threaded steel with a diameter of 50mm, a PSB strength of not less than 1080Mpa, and a length of 2400mm. It is fixed by anchor plates and nuts. The size of the anchor plate is 300*300*20mm, and the nut is a matching product. The embedded depth of the embedded anchor rod is 2100mm, and 300mm is reserved at the top of the pedestal. The lateral spacing between the center of the embedded anchor rod and the inner surface of the column is 320mm, and the lateral spacing of the embedded anchor rod along the bridge direction is 800mm. The diameter of the embedded steel pipe is 80mm and the thickness is 3mm.

3. The construction method for self-adjusting reverse tensioning of a segmented cap beam as claimed in claim 1 or 2, characterized in that: In S2, the installation of the cap beam is specifically as follows: the transport vehicle is parked on the side walkway of the column, two cranes respectively use the lifting wire rope to vertically fasten the two lifting points at both ends of the cap beam, and the cap beam is slowly lifted synchronously, and the transport vehicle is removed; one crane moves backward while rotating, and the other crane cooperates with the rotation, and slowly lifts the cap beam above the height of the column. After the entire cap beam rotates 90 degrees, it is slowly lowered towards the column; when the embedded steel bars of the column are all inserted into the embedded sleeves of the cap beam, the force is unloaded in stages; when the cap beam is in place, each crane reserves 20t of lifting force to adjust the coordinate position of the cap beam.

4. The construction method for self-adjusting reverse tensioning of a segmented cap beam as claimed in claim 1 or 2, characterized in that: In S3, the temporary tie rod is made of high-quality rolled threaded steel with a diameter of 50 mm and a PSB strength of not less than 930 MPa. The temporary tie rod is 330 mm away from the inner edge of the cap beam and 320 mm away from the edge of the column.

5. The construction method for self-adjusting reverse tensioning of a segmented cap beam as claimed in claim 1 or 2, characterized in that: In S4, an autonomous pressure-stabilizing and regulating system is used to continuously control the tensile stress value of the through-type jack; the autonomous pressure-stabilizing and regulating system includes a main system oil circuit, one side of the main system oil circuit is connected to the oil chamber and cavity of the hydraulic jack, the other side of the main system oil circuit is connected to the motor and the hydraulic oil pump in sequence, the oil outlet end of the hydraulic oil pump is connected to a two-position three-way hydraulically controlled reversing valve, the oil outlet ends of the two-position three-way hydraulically controlled reversing valve are respectively connected to the cavity of the hydraulic jack and the hydraulic oil tank, a one-way valve 3 is arranged between the two-position three-way hydraulically controlled reversing valve and the cavity of the hydraulic jack, a sequence valve is arranged between the hydraulic control end of the two-position three-way hydraulically controlled reversing valve and the cavity of the hydraulic jack, an overflow valve is arranged between the hydraulic oil pump and the hydraulic oil tank, and the pressure value of the overflow valve is the system pressure maintaining value.

6. The construction method for self-adjusting reverse tensioning of a segmented cap beam as claimed in claim 5 is characterized in that: During pressure stabilization, when the oil pressure monitoring module monitors that the oil pressure of the hydraulic system drops to the oil replenishment starting pressure value, the signal is fed back to the PLC control module, and the PLC control module sends an instruction to start the hydraulic oil pump again to replenish the oil pressure; when the oil pressure monitoring module monitors that the oil pressure of the hydraulic system rises to the oil replenishment stop pressure value, the signal is fed back to the PLC control module, and the PLC control module controls the hydraulic oil pump to stop running.