Repair method and system for in-service steel box girder

Through the repair method of in-service steel box girders, cutting and magnetic suction equipment are used to cut and place sealing plates in the U ribs, increasing the length of the repair equipment, reducing the number of construction windows, and solving the damage to the bridge by welding repair in the prior art. and safety hazards extend the service life of the bridge and reduce costs.

CN119083337APending Publication Date: 2024-12-06WUHAN LIXIN AUTOMATION TECH CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411477231.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-22
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

In the existing welding and repair methods of in-service steel structure bridges, multiple facilities construction windows have led to damage and safety hazards that cannot be ignored during the bridge repair process, and the length of the repair equipment is limited, making it difficult to effectively repair cracks in different U-rib bridge units.

Method used

By cutting the seal plate along the U-rib extension direction on both sides of the construction window, forming a gap for the repair equipment to enter, using the cutting equipment and magnetic suction equipment to alternately use, increasing the maximum length of the repair equipment in a construction window, reducing the number of construction windows, and Power is supplied through the wire hole to reduce the weight effect of the equipment.

Benefits of technology

The number of construction windows on the entire bridge is reduced, the damage to the bridge is reduced by the repair process, the service life of the bridge is extended, the degree of manual participation and operation risks are reduced, and the costs are reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083337A_ABST
    Figure CN119083337A_ABST
Patent Text Reader

Abstract

The invention provides a method for repairing an in-service steel box girder, a U rib is provided with a construction window for repairing the steel box girder, and the method comprises the following steps: S1, cutting a sealing plate of the U rib along the extension direction of the U rib on two sides of the construction window; and S2, the repairing equipment walks in the extending direction of the U rib and conducts repairing operation on the to-be-repaired area of the U rib through the notch formed through cutting in the step S1. According to the repairing method provided by the invention, the sealing plate required to be opened by the U rib is cut, and the gaps formed after cutting enable the spaces in the U rib on the two sides of the sealing plate to be communicated with each other, so that the maximum length of repairing equipment for repairing operation in a construction window is increased, namely, the construction distance of a construction section is increased; and therefore, the number of construction windows formed in the full bridge is greatly reduced, damage to the in-service bridge caused by repairing is avoided when the in-service bridge is repaired, and the service life of the in-service bridge is prolonged.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of bridge engineering, and in particular relates to a method for repairing an in-service steel box girder. Background Art

[0002] At present, the main structural form of steel structure bridges in my country is longitudinal orthogonal steel structure, and U rib is an important part of traditional orthogonal steel structure bridges. Due to technical limitations, a large number of U rib steel structure bridges built in my country in the early days only welded the outside of the U rib plate unit on one side, and did not weld the inner corner of the U rib plate unit, which made the strength of the bridge insufficient, and cracks were easily generated after long-term use, causing major safety hazards and requiring timely maintenance.

[0003] Among the existing maintenance methods, there is a method for welding the inner corners of the U-ribs of in-service bridges. The inner corners of the in-service U-ribs are welded by the segmented method, and construction windows are opened on the U-ribs. Two construction windows are used as a welding construction section. By using welding equipment to weld inside the U-ribs, the geometric shape of the original single-sided welding between the U-ribs and the bridge top plate is fundamentally changed, stress concentration is reduced, and the hidden dangers caused by fatigue cracks are effectively eliminated. However, in this method, the beginning and end of each welding construction section are the two ends of a U-rib in a U-rib plate unit, so that the length of the welding equipment for welding repair inside the U-rib is limited by the length of the construction section. When cracks occur in different U-rib bridge units, construction windows need to be opened at both ends of each corresponding U-rib. A large number of construction windows will cause non-negligible repair damage to the in-service steel structure bridge. Therefore, while performing welding repairs on in-service bridges, it is imperative to reduce the damage caused to the in-service bridges by the welding repairs themselves as much as possible. Summary of the invention

[0004] To this end, the present invention provides a method for repairing an in-service steel box girder, which reduces the number of construction windows opened on the entire bridge, and reduces the damage to the in-service bridge caused by the repair itself when the in-service bridge is welded and repaired.

[0005] The technical solution adopted by the present invention is as follows:

[0006] In one aspect, the present invention provides a method for repairing an in-service steel box girder, wherein a U rib is provided with a construction window for repairing the steel box girder, and the method comprises the following steps:

[0007] S1. Cutting the sealing plates of the U ribs along the extending direction of the U ribs on both sides of the construction window;

[0008] S2. The repairing device moves along the extending direction of the U rib and passes through the notch formed by cutting in S1 to perform repair operations on the area to be repaired of the U rib.

[0009] Further, the S1 comprises the following steps:

[0010] S1-1, placing a cutting device for cutting the sealing plate to be opened in the U-rib on a lifting platform, wherein the lifting platform is arranged on the ground below the construction window;

[0011] S1-2, raising the lifting platform to a height that enables the cutting device to smoothly enter the interior of the U-rib;

[0012] S1-3, start the cutting device so that the cutting device cuts the sealing plate to be opened inside the U-rib along the extension direction of the U-rib.

[0013] Furthermore, in S1-3, when there are multiple sealing plates to be opened, all the sealing plates to be cut off have the same shape and size.

[0014] Further, in S1-3, when there are multiple sealing plates to be opened along an extension direction of the U rib, the sealing plates to be cut off are reduced in sequence according to the set shrinkage size a, and the height Hn of the sealing plate n and its order n close to the construction window satisfy the following formula:

[0015] Hn=H1-a×(n-1)

[0016] Among them, sealing plate n is the nth sealing plate that needs to be opened along the extension direction of the U rib on both sides of the construction window, n is a positive integer; a is the retracted size; H1 is the height of the first sealing plate part cut off; Hn is the height of the nth sealing plate part cut off; Hn is not less than the minimum height that the cutting equipment, magnetic suction equipment, and welding equipment can pass through.

[0017] Furthermore, the S1 also includes: S1-4, placing the sealing plate cut off in S1-3 at a designated position.

[0018] Further, the S1-4 comprises the following steps:

[0019] S1-4-1. Place the magnetic suction device used to remove the cut sealing plate in S1-3 on a lifting platform, wherein the lifting platform is arranged on the ground below the construction window;

[0020] S1-4-2, raising the lifting platform to a height that enables the magnetic attraction device to smoothly enter the interior of the U-rib;

[0021] S1-4-3, start the magnetic attraction device so that the magnetic attraction device magnetically attracts the sealing plate cut off in S1-3 along the extension direction of the U rib inside the U rib, and places the cut sealing plate at the designated position from the cut by extending and rotating the electromagnet device of the magnetic attraction device.

[0022] Furthermore, when there are multiple sealing plates to be opened, S1 is repeated until all the sealing plates to be opened are cut.

[0023] Further, the method further comprises the following steps:

[0024] S3, reinstall the sealing plate cut off in S1;

[0025] S4, restoring the sealing plate installed in S3.

[0026] The present invention further provides a repair system for an in-service steel box girder, comprising a repair device, the repair system being used to implement the repair method for an in-service steel box girder according to any one of claims 1 to 11, the repair system further comprising:

[0027] The cutting device cuts the sealing plate of the U rib along the extension direction of the U rib on both sides of the construction window.

[0028] Furthermore, the repair system further comprises:

[0029] A magnetic attraction device is used to magnetically attract the cut sealing plate inside the U-rib along the extension direction of the U-rib, and the cut sealing plate is placed at a designated position by extending and rotating the electromagnet device of the magnetic attraction device.

[0030] Furthermore, the repair system further comprises:

[0031] A lifting platform is arranged on the ground below the construction window, and the cutting device and / or the magnetic device are placed on the lifting platform;

[0032] The lifting platform is raised to a height that enables the cutting device and / or the magnetic attraction device to smoothly enter the interior of the U-rib.

[0033] Furthermore, the repair system further comprises:

[0034] A wire passing hole and a plug-in module, wherein the wire passing hole is opened at the bottom or side wall of the U-rib where the sealing plate to be opened is located, and the plug-in module constitutes the power receiving end of the cutting device and / or the magnetic device, and the output end of the power supply system is plugged into the plug-in module through the wire passing hole to supply power to the cutting device and / or the magnetic device.

[0035] Furthermore, the repair system further comprises:

[0036] A reinstallation device and a sealing device, wherein the reinstallation device installs the cut sealing plate back to the notch formed by the cutting;

[0037] The sealing device restores the seal of the cut sealing plate installed by the reinstalling device.

[0038] The present invention provides a repair method and system for an in-service steel box girder. According to the needs of actual construction, the sealing plates required to be opened in the U ribs are cut along the extension direction of the U ribs on both sides of the construction window. The gap formed after cutting makes the spaces inside the U ribs on both sides of the sealing plate connected to each other, and the repair equipment is moved along the extension direction of the U ribs and enters the connected internal space of the U ribs through the gap to perform repair operations on the area to be repaired in the space. The repair method provided by the present invention increases the maximum length of the repair equipment for repair operations in a construction window by cutting the sealing plates required to be opened on the U ribs, that is, increases the construction distance of a construction section, thereby greatly reducing the number of construction windows opened on the entire bridge, reducing the damage to the in-service bridge caused by the repair itself, and extending the service life of the in-service bridge. At the same time, the reduction in the number of construction windows also reduces the degree of manual participation in the bridge repair process, reduces the occurrence of operator casualties and other situations that may occur during the bridge repair process; reduces labor costs and ensures maximum economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] Figure 1 This is a schematic diagram of the U-rib plate unit structure of an in-service bridge of the present invention;

[0040] Figure 2 A schematic diagram of the construction window of the present invention is provided;

[0041] Figure 3 It is a schematic diagram of the cutting device of the present invention cutting a sealing plate in a U-rib;

[0042] Figure 4 This is a schematic diagram of manually cutting the first left sealing plate and the first right sealing plate in the present invention;

[0043] Figure 5 A schematic diagram of a first left U-rib plate unit including a cutting device working in the present invention;

[0044] Figure 6 A schematic diagram of the first left U-rib plate unit containing a magnetic attraction device working in the present invention;

[0045] Figure 7 Schematic diagram of continuous cutting operation of the cutting device of the present invention Figure 1 ;

[0046] Figure 8 Schematic diagram of continuous cutting operation of the cutting device of the present invention Figure 2 ;

[0047] Fig. 9 It is a schematic diagram of the welding repair work of the welding equipment of the present invention;

[0048] Fig.10 This is a schematic diagram of the magnetic attraction device of the present invention reinstalling the sealing plate;

[0049] Fig.11 This is a schematic diagram of the construction window reinstallation work of the present invention;

[0050] Fig.12 A schematic diagram illustrating a wire hole of the present invention;

[0051] Fig.13 This is a schematic diagram for explaining the size of the cutting notch of the sealing plate of the present invention;

[0052] In the accompanying drawings, the components represented by the reference numerals are listed as follows:

[0053] 11. First left U rib unit; 12. Second left U rib unit; 21. First right U rib unit; 22. Second right U rib unit; 31. First left sealing plate; 32. Second left sealing plate; 33. Third left sealing plate; 34. Fourth left sealing plate; 35. Fifth left sealing plate; 41. First right sealing plate; 42. Second right sealing plate; 43. Third right sealing plate; 44. Fourth right sealing plate; 45. Fifth right sealing plate; 5. Steel liner; 6. Construction window; 7. Power supply system; 81. Cutting equipment; 82. Magnetic suction equipment; 821. Electromagnet device; 83. Welding equipment; 9. Plug-in module; 100. Wire hole.

[0054] It should be understood that the drawings are not necessarily drawn to scale, presenting somewhat simplified representations of various features illustrating the basic principles of the present disclosure. Specific design features of the present invention as disclosed herein, including, for example, specific size, orientation, position, and shape, will be determined in part by the particular intended application and use environment. In the drawings, throughout the several figures of the drawings, reference numerals refer to the same or equivalent parts of the present invention. DETAILED DESCRIPTION

[0055] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0056] Throughout this article, unless otherwise specified, Figure 1As shown in the figure, the U rib mentioned in this article can usually be used in orthogonal steel structure bridges and is a component of the steel box girder. Of course, in some specific cases, it can also be used in other systems that require U ribs as standard fixings. The U rib mentioned in this article has been welded to the U rib plate unit by external corner welding during construction. Specifically, each two adjacent U-rib plate units (for example, the second left U-rib plate unit 12 and the first left U-rib plate unit 11, the first left U-rib plate unit 11 and the first right U-rib plate unit 21, the first right U-rib plate unit 21 and the second right U-rib plate unit 22, etc.) have a butt weld due to the welding connection. Similarly, each two connected U ribs (for example, the left U rib 2 and the left U rib 1, the left U rib 1 and the right U rib 1, the right U rib 1 and the right U rib 2, etc.) also have a weld due to the welding connection. In most of the existing in-service steel structure bridges containing U ribs, each U rib has a sealing plate at both ends. With the construction window 6 as the center and along the extension direction of the left U rib to be repaired, The first left U rib plate unit 11 has a first left sealing plate 31 and a second left sealing plate 32; the second left U rib plate unit 12 has a third left sealing plate 33 and a fourth left sealing plate 34; the third left U rib plate unit has a fifth left sealing plate 35 and a sixth left sealing plate… the nth left U rib plate unit has a 2n-1th left sealing plate and a 2nth left sealing plate; along the extension direction of the right U rib to be repaired, the first right U rib plate unit 21 has a first right sealing plate 41 and a second right sealing plate 42; the second right U rib plate unit 22 has a third right sealing plate 43 and a fourth right sealing plate 44; the third right U rib plate unit has a fifth right sealing plate 45 and a sixth right sealing plate… the nth right U rib plate unit has a 2n-1th right sealing plate and a 2nth right sealing plate. A steel liner 5 (such as Figure 1 As shown), when welding the U rib (welding the U rib plate unit instead of welding the inner and outer corners of the U rib), in the case where a steel liner 5 is provided, it is necessary to weld the metal pad first to fix the U rib plate unit.

[0057] In addition, "in service" referred to in this article, unless otherwise specified, means that the bridge has been built, has been used, is in use or is about to be used, that is, the U-rib is in a bridge or other system structure in use.

[0058] According to the first aspect of the present invention, a method for repairing an in-service steel box girder is provided. The method provided by the present application is particularly suitable for internal welding repair of the U rib of an in-service steel structure bridge. The repair form of a cutting device 81, a magnetic device 82 and a welding device 83 is used to make full use of the construction window 6 that has been opened. The cutting device 81 and the magnetic device 82 are used alternately to cut and place the sealing plate that needs to be opened in the U rib. The so-called placement can be to take the sealing plate out of the construction window 6 from the inside of the U rib, or to place the sealing plate in a suitable designated position in the internal space of the U rib, as long as the sealing plate that is cut off can be placed without affecting the gap formed by the subsequent equipment through cutting. It can greatly reduce the number of construction windows 6 opened on the entire bridge, increase the maximum length that can be repaired by the welding device 83 in each opened construction window 6, and reduce the damage to the in-service bridge caused by the welding repair itself when the in-service bridge is welded.

[0059] Specifically, the previous steps may be:

[0060] Open construction window 6 (such as Figure 2 As shown in the figure): a construction window 6 for welding repair is opened on the in-service U-rib, and the opening position of the construction window 6 is located between two partitions on both sides of the welding seam of the U-rib, and is also located on both sides of the butt weld of the U-rib plate unit corresponding to the U-rib;

[0061] Cut and remove the sealing plates on both sides of the construction window 6 (such as Figure 4 As shown): manually cutting the first left sealing plate 31 and the first right sealing plate 41 on both sides of the construction window 6 and taking out the cut first left sealing plate 31 and the first right sealing plate 41;

[0062] Grinding: Grinding the first left sealing plate 31, the first right sealing plate 41 and the cutting edges of the U ribs;

[0063] Cleaning: Clean the inside of the U rib.

[0064] After the above steps, the method provided by the present invention comprises the following steps:

[0065] S1, along the extension direction of the U ribs on both sides of the construction window 6, cut the sealing plate to be opened in the U rib (such as Figure 3 shown);

[0066] Taking the opened construction window 6 as the center, the first left sealing plate 31 of the left U rib 1 and the first right sealing plate 41 of the right U rib 1 located on both sides of the construction window 6 inside the U rib have been cut and taken out. The specific position of the U rib to be repaired determines the trajectory of the welding equipment 83 in the U rib, so it is necessary to open the sealing plate in the U rib that hinders the welding equipment 83 from repairing. In other words, once the specific position of the U rib to be repaired is clarified, the sealing plate that needs to be cut and placed in the U rib is clarified.

[0067] Specifically, the following steps can be taken:

[0068] S1-1, placing a cutting device 81 for cutting the sealing plate to be opened in the U-rib on a lifting platform, the lifting platform being arranged on the ground below a construction window 6;

[0069] S1-2, raising the lifting platform to a height that enables the cutting device 81 to smoothly enter the interior of the U-rib;

[0070] S1-3, start the cutting device 81, so that the cutting device 81 cuts the sealing plate to be opened along the extension direction of the U rib inside the U rib (such as Figure 5 As shown), if step S1 is used multiple times, the second left sealing plate 32, the third left sealing plate 33, ..., the nth left sealing plate (as shown) can be obtained from the left side of the construction window 6 in sequence. Figure 7 From the right side of the construction window 6, the second right sealing plate 42, the third right sealing plate 43, ..., the nth right sealing plate can be obtained in sequence. After the cutting is completed, the cutting device 81 is moved to the lifting platform again, and the lifting platform is lowered to the initial height, and the cutting device 81 is taken out.

[0071] Here, when the cut sealing plate is placed in the designated position, the specific method is to take the cut sealing plate out from the inside of the U rib. After the cutting device 81 completes cutting of a sealing plate in the U rib, it needs to return to the initial position of the cutting device 81 at the construction window 6 in the U rib. After the cut sealing plate is placed in the designated position, the sealing plate that needs to be opened in the same direction can be cut as needed. In order to improve the efficiency of cutting sealing plates, the cutting device 81 can be taken out after cutting a sealing plate in the extension direction of both sides of the U rib with the construction window 6 as the center.

[0072] The cutting program can be pre-set for the cutting device 81 so that the cutting device 81 cuts the sealing plate with the required shape and size. When multiple sealing plates need to be cut, the shapes and sizes of the sealing plates cut by the cutting device 81 can be the same or different, or even change in a certain regular pattern (such as Fig.13As shown). Although there is no fixed requirement for the shape and size of the sealing plate to be cut off, because the sealing plate to be cut off in the same direction of the U-rib extension needs to be taken out through the gap left by the sealing plate to be cut off previously, the sealing plate to be cut off in the same direction of the U-rib extension is smaller than the sealing plate to be cut off previously (for example, the gap left by cutting the first left sealing plate 31 can allow the second left sealing plate 32 to pass through, and the gap left by cutting the second left sealing plate 32 can allow the third left sealing plate 33 to pass through, and so on). Moreover, the sealing plates to be cut off need to pass through the steel liner 5 located at the butt weld between the U-rib plate units to be taken out of the U-rib, so the size of all the sealing plates to be cut off is also limited by the size and shape of the gap in the steel liner 5; the gap left by the sealing plates to be cut off needs to pass through the welding equipment 83, so the size of all the sealing plates to be cut off is also limited by the size and shape of the welding equipment 83.

[0073] As a cutting and sealing solution, in S1-3, when there are multiple sealing plates to be opened along one extension direction of the U rib, the sealing plates to be cut off are reduced in sequence according to the set shrinkage size a, and the height Hn of the sealing plate n and its order n close to the construction window 6 satisfy the following formula:

[0074] Hn=H1-a×(n-1)

[0075] Among them, sealing plate n is the nth sealing plate that needs to be opened along the extension direction of the U ribs on both sides of the construction window 6, n is a positive integer; a is the retracted size; H1 is the height of the first sealing plate part cut off; Hn is the height of the nth sealing plate part cut off; Hn is not less than the minimum height that the cutting equipment 81, the magnetic suction equipment 82, and the welding equipment 83 can pass through.

[0076] S1-4. Place the sealing plate cut off in S1-3 at the designated location:

[0077] Step S1-4 and step S1-3 are two related steps and the number of steps of step S1-4 and step S1-3 is the same. Whenever a sealing plate is cut in step S1-3 and the sealing plate is taken out from the U rib in step S1-4, the space connection in the U rib on both sides of the sealing plate is completed, which increases the maximum construction length of the construction window 6, thereby reducing the number of construction windows 6 opened and reducing the damage to the bridge in service caused by the welding repair process. Of course, it is not necessary to take out the cut sealing plate from the inside of the U rib through the construction window 6. The sealing plate can also be placed in a suitable designated position in the internal space of the U rib, as long as the gap formed by the subsequent equipment through cutting can be formed after the cut sealing plate is put back.

[0078] Specifically, Figure 6As shown, the following steps can be taken:

[0079] S1-4-1, placing the magnetic suction device 82 used to remove the sealing plate that is cut off in S1-3 and needs to be opened on a lifting platform, and the lifting platform is set on the ground below the construction window 6;

[0080] S1-4-2, raising the lifting platform to a height that enables the magnetic attraction device 82 to smoothly enter the interior of the U-rib;

[0081] S1-4-3, start the magnetic attraction device 82, so that the magnetic attraction device 82 magnetically attracts the sealing plate that is cut off in S1 along the extension direction of the U rib inside the U rib, and removes the sealing plate that is cut off from the cut by extending and rotating the electromagnet device 821 of the magnetic attraction device 82;

[0082] S1-4-4, after the magnetic attraction is completed, the magnetic attraction device 82 adsorbing the sealing plate cut off in S1-3 and requiring to be opened is moved to the lifting platform again, and the lifting platform is lowered to the initial height, and the magnetic attraction device 82 is taken out.

[0083] As a specific solution for cutting and placing the sealing plate, the cutting function of the above-mentioned cutting device 81 and the adsorption function of the magnetic device 82 can be combined on the same device. The specific method can be to install the electromagnet device 821 on the magnetic device 82 that can perform operations such as extension and rotation on the cutting device 81. When using the cutting device 81 equipped with the electromagnet device 821, the electromagnet device 821 can be started immediately after each cutting off of the sealing plate that needs to pass through to adsorb the sealing plate. When the return procedure of the cutting device 81 equipped with the electromagnet device 821 is started, the sealing plate adsorbed on the electromagnet device 821 will be brought back together. This design omits the procedure of separately starting the magnetic device 82 to adsorb and bring back the sealing plate, which greatly reduces the construction time and further improves the overall work efficiency.

[0084] When there are multiple sealing plates to be opened, the method further comprises the following steps:

[0085] Repeat step S1 until all the sealing plates to be opened are cut.

[0086] As the sealing plates that need to be opened previously are taken out one by one, the sealing plates that need to be opened later are farther and farther away from the construction window 6. When the cutting device 81 and the magnetic device 82 are started to operate the sealing plates that need to be opened later, the tail needs to drag the long-distance transmission line in the U rib. The long-distance transmission line has a considerable weight, which will affect the normal use of the cutting device 81, the magnetic device 82 and other equipment functions.

[0087] like Figure 8 , Fig. 9, Fig.10 As shown, in order to solve the above problems, the present invention provides a solution, which sets the power receiving end of the cutting device 81, the magnetic device 82 and other devices as the plug-in module 9. Specifically, the plug-in module 9 can be set in the middle of the side wall of the cutting device 81, the magnetic device 82 and other devices. Fig.12 As shown, a wire hole 100 is provided at the bottom or side wall of the U-rib where the sealing plate to be opened is located, and the output end of the power supply system 7 is connected to the plug-in module 9 through the wire hole 100 to supply power to the cutting device 81, the magnetic suction device 82 and other equipment.

[0088] The shape of the wire hole 100 is not particularly limited, and can be a circular through hole, a square through hole, or a long strip through hole. The number of wire holes 100 can be multiple as needed and distributed along the extension direction of the U rib. The main function of the wire hole 100 is to allow the transmission lines of cutting equipment 81, magnetic suction equipment 82 and other equipment to pass through. Combined with the actual application scenario, the size of the wire hole 100 opened on the U rib can be more than ten centimeters or even several centimeters. Compared with the opening of the construction window 6, the damage caused by the opening of the wire hole 100 to the in-service bridge is almost negligible.

[0089] like Fig. 9 As shown, S2, the repair equipment moves along the extension direction of the U rib and passes through the notch formed by the cutting in S1 to perform repair operations on the U rib area to be repaired. The repair equipment can be a welding equipment 83.

[0090] Grinding: Grind the excess height of the butt weld of the U-rib plate unit and the steel liner 5; Grind the area to be repaired inside the U-rib.

[0091] Cleaning: After cutting and placing the cover plates, clean the inside of the U-ribs where the spaces are interconnected.

[0092] Welding repair: The welding equipment 83 is sent to the interior of the U-ribs which are interconnected in space to perform welding repair on the area to be repaired.

[0093] This step is a prior art and will not be described in detail here.

[0094] like Fig.10 As shown, S3, reinstalling the sealing plate cut off in step S1, may specifically include the following steps:

[0095] S3-1, placing the magnetic suction device 82 adsorbing the sealing plate cut off in S1 and requiring opening on a lifting platform, the lifting platform being arranged on the ground below the construction window 6;

[0096] S3-2, raising the lifting platform to a height that enables the magnetic attraction device 82 to smoothly enter the interior of the U-rib;

[0097] S3-3, start the magnetic attraction device 82, so that the magnetic attraction device 82 is sent inside the U rib along the extension direction of the U rib to the original cutting position of the sealing plate it adsorbs inside the U rib, and the electromagnet device 821 of the magnetic attraction device 82 is extended and rotated, and the sealing plate is installed back to the original cutting position;

[0098] S3-4, after the magnetic attraction is finished, the magnetic attraction device 82 is moved onto the lifting platform again, and the lifting platform is lowered to the initial height, and the magnetic attraction device 82 is taken out.

[0099] The main function of the U-rib inner sealing plate is to isolate the internal space formed by the U-rib and the corresponding U-rib plate unit from the external space, to prevent the air circulation inside the U-rib and external dust, leaves and other debris from entering the U-rib as much as possible, to slow down the oxidation rate inside the U-rib, and to extend the service life of the bridge in service. Therefore, after completing the welding and other repair work on the in-service steel structure bridge, it is necessary to reinstall and seal the cut and placed sealing plates.

[0100] S4, restoring the sealing plate that needs to be opened and installed in S3, which may specifically include the following steps:

[0101] S4-1, placing the welding equipment 83 used for welding and sealing the sealing plate installed back to its original position in step S3 on a lifting platform, which is set on the ground below the construction window 6;

[0102] S4-2, raising the lifting platform to a height that enables the welding equipment 83 to smoothly enter the interior of the U-rib;

[0103] S4-3, start welding, so that the welding device 83 is sent inside the U rib along the extension direction of the U rib to the sealing plate that was installed back to the original position in step S5, and welds and seals the sealing plate;

[0104] S4-4, after the welding and sealing is completed, the welding equipment 83 is moved onto the lifting platform again, and the lifting platform is lowered to the initial height, and the welding equipment 83 is taken out.

[0105] As a solution for reinstalling and sealing the sealing plate, the surface of the sealing plate that needs to be reinstalled can also be coated with a sticky material or a magnetic material, and the sealing plate and the cut can be sealed while the sealing plate is reinstalled using a magnetic vehicle. The purpose of the sealing plate is to isolate the internal space of the U rib from the outside world and prevent dust and other debris from entering the U rib to produce oxidation and other reactions, so there is no excessive requirement for the strength of the sealing plate after reinstallation. This design omits the procedure of separately starting the welding equipment 83 to seal the sealing plate, that is, omits step S4, greatly reduces the construction time, and further improves the overall work efficiency.

[0106] Repeat step S3 and step S4 until all the sealing plates that need to be opened are replaced and sealed.

[0107] Finally, the first left sealing plate 31 and the first right sealing plate 41 on both sides of the construction window 6 are reinstalled and sealed. Fig.11 As shown, the construction window 6 is sealed and welded, and the sealing window welding place is post-processed and the surface is painted. This is the existing technology, and a manual method can be used, so no more details are given here.

[0108] At this point, the repair of the steel box girders in the in-service bridge has been completed.

[0109] The practical application of the method of the present invention is exemplified below by Example 1.

[0110] Example 1

[0111] The U-rib upward position internal welding method was used to repair the steel box girder of an orthogonal steel structure bridge in service. The operation steps are as follows:

[0112] 1) After determining the length of the construction window 6 and the distance between the top of the construction window 6 and the top of the U-rib side plate, the U-rib is marked according to the size and position of the construction window 6. The plasma arc cutting method is used to cut along the marked line. The notch formed is the construction window 6. The cut U-rib part is taken out;

[0113] 2) The left and right sides of the construction window 6 are the left U rib 1 and the right U rib 1 connected to each other. The first left sealing plate 31 of the left U rib 1 close to the construction window 6 and the first right sealing plate 41 of the right U rib 1 close to the construction window 6 are manually cut in turn, and the cut first left sealing plate 31 and the first right sealing plate 41 are taken out in turn;

[0114] 3) Grind the removed U-rib part, the removed first left sealing plate 31 part that was cut off, and the removed first right sealing plate 41 part that was cut off; Grind the cut of the construction window 6; Grind the cut of the first left sealing plate 31 and the first right sealing plate 41 in the U-rib; Grind the excess height of the butt weld of the U-rib plate unit of the in-service bridge; Grind the steel liner 5 in the U-rib; Grind the area to be repaired in the U-rib: Use a tow truck to clean the inside of the U-rib;

[0115] 4) Place the cutting device 81 on the lifting platform, raise the lifting platform to a height that allows the cutting device 81 to smoothly enter the U-rib, start the cutting device 81, and make the cutting device 81 start from the construction window 6 and move along the extension direction of the U-rib to be repaired to the sealing plate to be opened, then start the cutting program, so that the cutting device 81 cuts the sealing plate until a preset incision shape is formed, and the cut part of the sealing plate falls into the U-rib. The fallen sealing plate has the same shape as the overall sealing plate and is large enough to pass through the gap of the steel liner 5. The cutting program ends, and the return program is started, so that the cutting device 81 returns to the original position of the construction window 6, and the cutting device 81 is moved onto the lifting platform again, and the lifting platform is lowered to the initial height, and the cutting device 81 is taken out;

[0116] 5) Place the magnetic device 82 on the lifting platform, raise the lifting platform to a height that allows the magnetic device 82 to smoothly enter the U rib, start the magnetic device 82, and make it move along the extension direction of the U rib to be repaired to the sealing plate that fell into the U rib in step 4), then start the magnetic program, the electromagnet device 821 of the magnetic device 82 generates a magnetic attraction after being powered on, and the sealing plate that fell into the U rib is firmly adsorbed on the electromagnet device 821, and the sealing plate that fell into the U rib is taken out from the cut in an inclined manner by performing operations such as retracting and rotating the electromagnet device 821 with the sealing plate adsorbed, and start the return program, so that the magnetic device 82 returns to the original position to the initial position of the construction window 6, and the magnetic device 82 is moved to the lifting platform again, and the lifting platform is lowered to the initial height, and the magnetic device 82 is taken out;

[0117] 6) Repeat the above steps 4) and 5) in sequence, with the construction window 6 as the center, along the extension direction of the U rib to be repaired (which can be one side or both sides of the construction window 6), cut and remove the second left sealing plate 32, the third left sealing plate 33...the nth left sealing plate that needs to be opened in the left U rib 2, the left U rib 3...the left U rib n connected to the left U rib 1; cut and remove the second right sealing plate 42, the third right sealing plate 43...the nth right sealing plate that needs to be opened in the right U rib 2, the right U rib 3...the right U rib n connected to the right U rib 1, and the cut sealing plates are of the same size and shape, until all the sealing plates that need to be opened in the U rib are cut and removed;

[0118] 7) The power receiving ends of the cutting equipment 81, magnetic equipment 82, tow truck, welding equipment 83 and other equipment are all composed of plug-in modules 9. When the sealing plate to be cut is far enough from the construction window 6, the power cord connected to the cutting equipment 81, magnetic equipment 82 and other equipment in the U rib is too long, which will affect the maneuverability of the cutting equipment 81, magnetic equipment 82 and other equipment. At this time, a wire hole 100 is opened at the bottom or side wall of the U rib where the sealing plate to be cut is located, and the output end of the power supply system 7 is connected to the plug-in module 9 through the wire hole 100 to supply power to the cutting equipment 81, magnetic equipment 82, tow truck, welding equipment 83 and other equipment;

[0119] 8) Use the welding device 83 to perform overhead welding on the inside of the U-rib. The specific operation is as follows: first, use a tow truck to clean the inside of the connected U-rib and polish the area to be repaired, then place the welding device 83 on the lifting platform, raise the lifting platform to a height that allows the welding device 83 to smoothly enter the inside of the U-rib, start the welding device 83, and make the welding device 83 move along the extension direction of the U-rib to be repaired to the welding starting point, then start the welding program, so that the welding device 83, in the process of returning, welds the inner corner of the U-rib and the required repair position along the extension direction of the U-rib inside the U-rib. After the welding is completed, move the welding device 83 to the lifting platform again, and make the lifting platform descend to the initial height, and take out the welding device 83;

[0120] 9) Alternately use the magnetic suction device 82 and the welding device 83 to sequentially install and seal the cut and removed sealing plates. The step of using the magnetic suction device 82 to install the cut and removed sealing plates is the reverse process of the step of removing the sealing plates. The magnetic suction device 82 with the sealing plates adsorbed thereon is transported to the cut portion of the sealing plates in the U rib, and the electromagnet device 821 of the magnetic suction device 82 is manipulated to perform operations such as extension and rotation, and the sealing plates are installed back to the original cuts, and the return program is started, and finally the magnetic suction device 82 is taken out; the welding device 83 is transported to the original cut portion of the sealing plates in the U rib, and the welding device 83 is used to seal the sealing plates installed back to the original cuts, and the return program is started, and finally the welding device 83 is taken out; the order of sequentially installing and sealing the multiple sealing plates is opposite to the order of sequentially cutting and removing the sealing plates, which is the nth left sealing plate, the n-1th left sealing plate...the second left sealing plate 32; the nth right sealing plate, the n-1th right sealing plate...the second right sealing plate 42;

[0121] 10) Manually seal and weld the first left sealing plate 31 of the left U-rib 1 close to the construction window 6 and the first right sealing plate 41 of the right U-rib 1 close to the construction window 6, seal and weld the construction window 6 opened on the U-rib, and perform post-processing on the sealing welding part;

[0122] 11) Paint the exterior of the window sealing welding point of the construction window 6.

[0123] According to the second aspect of the present invention, the repair method of the in-service steel box girder cuts and repairs the U-rib cover plate through the repair system, and uses the cooperation of the lifting platform and the cutting equipment 81, the magnetic suction equipment 82 and the welding equipment 83, which reduces the degree of manual participation in the bridge repair process, reduces the cost of manual labor, ensures the maximization of economic benefits, and reduces the occurrence of operating personnel casualties during the bridge repair process.

[0124] Obviously, the above embodiments are merely examples for the purpose of clear explanation, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived therefrom are still within the scope of protection of the invention.

[0125] In the description of the present invention, it is necessary to understand that the terms "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "inside", "outside", etc., indicating directions or positional relationships, are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention.

[0126] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0127] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0128] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, unless they are contradictory.

[0129] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may change, modify, replace and vary the above embodiments within the scope of the present invention.

Claims

1. A method for repairing an in-service steel box girder, wherein a U rib is provided with a construction window for repairing the steel box girder, It is characterized in that The method comprises the following steps: S1. Cutting the sealing plates of the U ribs along the extending direction of the U ribs on both sides of the construction window; S2. The repairing device moves along the extending direction of the U rib and passes through the notch formed by cutting in S1 to perform repair operations on the area to be repaired of the U rib.

2. The method for repairing an in-service steel box girder according to claim 1, It is characterized in that The S1 comprises the following steps: S1-1, placing a cutting device for cutting the sealing plate to be opened in the U-rib on a lifting platform, wherein the lifting platform is arranged on the ground below the construction window; S1-2, raising the lifting platform to a height that enables the cutting device to smoothly enter the interior of the U-rib; S1-3, start the cutting device so that the cutting device cuts the sealing plate to be opened inside the U-rib along the extension direction of the U-rib.

3. The method for repairing an in-service steel box girder according to claim 2, It is characterized in that In S1-3, when there are multiple sealing plates to be opened, all the sealing plates to be cut off have the same shape and size.

4. The method for repairing an in-service steel box girder according to claim 2, It is characterized in that In S1-3, when there are multiple sealing plates to be opened along an extension direction of the U rib, the sealing plates to be cut off are reduced in sequence according to the set shrinkage size a, and the height Hn of the sealing plate n and its order n close to the construction window satisfy the following formula: Hn=H1-a×(n-1) Among them, sealing plate n is the nth sealing plate that needs to be opened along the extension direction of the U rib on both sides of the construction window, n is a positive integer; a is the retracted size; H1 is the height of the first sealing plate part cut off; Hn is the height of the nth sealing plate part cut off; Hn is not less than the minimum height that the cutting equipment, magnetic suction equipment, and welding equipment can pass through.

5. The method for repairing an in-service steel box girder according to claim 2, It is characterized in that The S1 further comprises: S1-4, placing the sealing plate cut off in S1-3 at a designated location.

6. The method for repairing an in-service steel box girder according to claim 5, It is characterized in that The S1-4 comprises the following steps: S1-4-1. Place the magnetic suction device used to remove the cut sealing plate in S1-3 on a lifting platform, wherein the lifting platform is arranged on the ground below the construction window; S1-4-2, raising the lifting platform to a height that enables the magnetic attraction device to smoothly enter the interior of the U-rib; S1-4-3, start the magnetic attraction device so that the magnetic attraction device magnetically attracts the sealing plate cut off in S1-3 along the extension direction of the U rib inside the U rib, and places the cut sealing plate at the designated position from the cut by extending and rotating the electromagnet device of the magnetic attraction device.

7. The method for repairing an in-service steel box girder according to claim 1, It is characterized in that When there are multiple sealing plates to be opened, S1 is repeated until all the sealing plates to be opened are cut.

8. The method for repairing an in-service steel box girder according to claim 1, It is characterized in that The following steps are also included: S3, reinstall the sealing plate cut off in S1; S4, restoring the sealing plate installed in S3.

9. A repair system for an in-service steel box girder, comprising a repair device, It is characterized in that The repair system is used to implement the repair method for an in-service steel box girder according to any one of claims 1 to 8, and the repair system further comprises: The cutting device cuts the sealing plate of the U rib along the extension direction of the U rib on both sides of the construction window.

10. The repair system for an in-service steel box girder according to claim 9, It is characterized in that The repair system also includes: A magnetic attraction device is used to magnetically attract the cut sealing plate inside the U-rib along the extension direction of the U-rib, and the cut sealing plate is placed at a designated position by extending and rotating the electromagnet device of the magnetic attraction device.

11. The repair system for an in-service steel box girder according to claim 9 or 10, It is characterized in that The repair system also includes: A lifting platform is arranged on the ground below the construction window, and the cutting device and / or the magnetic device are placed on the lifting platform; The lifting platform is raised to a height that enables the cutting device and / or the magnetic attraction device to smoothly enter the interior of the U-rib.

12. The repair system for an in-service steel box girder according to claim 9 or 10, It is characterized in that The repair system also includes: A wire passing hole and a plug-in module, wherein the wire passing hole is opened at the bottom or side wall of the U-rib where the sealing plate to be opened is located, and the plug-in module constitutes the power receiving end of the cutting device and / or the magnetic device, and the output end of the power supply system is plugged into the plug-in module through the wire passing hole to supply power to the cutting device and / or the magnetic device.

13. The repair system for an in-service steel box girder according to claim 9, It is characterized in that The repair system also includes: A reinstallation device and a sealing device, wherein the reinstallation device reinstalls the cut sealing plate back to the notch formed by the cutting; The sealing device restores the seal of the cut sealing plate installed by the reinstalling device.