Water conservancy project geology detection device
By setting up an expanding mechanism on the drill rod, the sleeve is left in the drilling hole, which solves the problem of mud blockage during the drilling process, improves the detection efficiency and accuracy, and reduces the detection cost.
Patent Information
- Application Number
- CN202310919409.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-07-25
- Publication Date
- 2024-12-06
AI Technical Summary
In the existing geological survey, clay particles in the mud adhere to the well pipe during drilling, causing blockage, and well washing is required to be sampled and tested. The process is cumbersome and is not conducive to improving the detection accuracy and quality. At the same time, multiple groups are required during geological survey. The inspection well has high engineering cost.
By setting up a cut-out mechanism on the drill bit of the drill rod, the drill rod can move through the sleeve and withdraw from the sleeve, leaving the sleeve in the drill hole, preventing clay particles from adhering in the mud, and directly conducting water detection, reducing The well washing steps were completed.
The layout efficiency of the detection well and the accuracy of the water body detection are improved, the well washing steps are avoided, and the detection cost is reduced.
Smart Images

Figure CN119083989A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of water conservancy engineering, and in particular relates to a geological detection device for water conservancy engineering. Background Art
[0002] Hydrogeological survey refers to the hydrogeological investigation and research work carried out to find out the hydrogeological conditions of a region. It aims to understand the causes, distribution and movement laws of groundwater and surface water. It provides a basis for the rational exploitation and utilization of water resources and the correct design and construction of foundation and piling projects. It includes two aspects: underground and above-ground hydrological survey. Underground hydrological survey mainly investigates and studies the changes in groundwater levels, flow directions, chemical composition, etc. at different times of the year, finds out the burial conditions and corrosiveness of groundwater, determines the changes and impacts that may occur in groundwater during the construction and use of buildings, and puts forward prevention and control suggestions.
[0003] Moreover, in the process of geological survey, the survey of groundwater level is particularly important. In the prior art, the detection of groundwater level in geology is mostly carried out by rotary drilling, and its steps include: well position measurement → drilling → well washing → well pipe production and installation → well pipe side wall filter material and clay ball backfill → well washing and test pumping → pressure water level observation → pipe pulling and hole sealing.
[0004] For example, the hydrogeological survey water source sampling and detection device disclosed in application number 202011564921.2 uses a drilling mechanism that utilizes the above-mentioned method for rotary drilling. However, in this method, a large amount of clay particles in the mud in the borehole adhere to the filter tube of the well pipe, causing blockage of the well pipe and distortion of the hydrological detection results. A series of operations such as well washing are required before sampling and detection can be performed. This process is not only cumbersome but also not conducive to improving the accuracy and quality of hydrological detection.
[0005] Therefore, the existing methods have the following defects:
[0006] At present, during geological surveys, when there are multiple confined aquifers on site and the confined water level needs to be observed, multiple sets of detection wells need to be made. The project cost is relatively high. How to reduce the manufacturing cost of the detection wells is a technical problem that needs to be solved.
[0007] The key point of geological survey process is well washing. The purpose of well washing is to reduce the clay particles in the mud adhering to the filter tube of the well pipe and clogging the well pipe. Once a large number of clay particles in the mud adhere to the filter tube of the well pipe, the well pipe is blocked and the water body detection results are distorted. Summary of the invention
[0008] In order to solve at least one technical problem existing in the above-mentioned background technology, the first aspect of the present invention provides a water conservancy engineering geological detection device, which adjusts the axial telescopic length of the expansion and cutting mechanism of the drill bit of the drill pipe so that the drill bit can move through the sleeve, releases the connection between the sleeve and the drill pipe, and pulls the drill pipe out of the sleeve. By lifting the drill pipe to the ground, the sleeve remains in the borehole, preventing clay particles in the mud from adhering to the filter tube of the well pipe in large quantities, and water body detection can be carried out without well washing.
[0009] In order to achieve the above-mentioned purpose, the present invention adopts the following technical scheme: a water conservancy engineering geological detection device, comprising: a base, an elevator, a turntable, a mounting plate, a drilling mechanism and a detection mechanism, the base is installed on the ground, the elevator is arranged at the center of the upper end surface of the base, a turntable is installed on the top of the elevator, a mounting plate is arranged on the turntable, and a drilling mechanism and a detection mechanism are installed on the mounting plate:
[0010] The drilling mechanism comprises a drill rod, an extension mechanism and a driving device, wherein the driving device is mounted on a mounting plate, and an output end of the driving device is connected to one end of the drill rod through the extension mechanism;
[0011] The extension mechanism comprises an extension shaft, an extension tube and a sleeve, wherein the extension shaft is installed in the extension tube, one end of the extension shaft is connected to the drill rod, and the other end is connected to the driving device, and the sleeve is sleeved outside the extension tube;
[0012] The drill rod includes a drill bit and an expansion and cutting mechanism. The expansion and cutting mechanism is sleeved on the outer side of the drill bit and fixedly connected to the drill bit. After the drill bit drills a hole, the expansion and cutting mechanism is used to expand the borehole so that the sleeve can be installed in the expanded borehole. When the drilling is completed, the expansion and cutting mechanism is used to detach from the sleeve and pull it out, leaving the sleeve in the borehole, and the detection mechanism is used to sample and detect the water in the sleeve.
[0013] Furthermore, guide rods are provided around the base, the guide rods are welded to the base, the mounting plate is slidably sleeved on the conductor rods, and the guide rods are used to guide the lifting movement of the mounting plate.
[0014] Furthermore, the mounting plate is provided with a plurality of guide holes, and the guide holes cooperate with the guide rods for guiding.
[0015] Furthermore, a mounting hole is provided at the center of the extension shaft, and the mounting hole is used for docking and mounting a drilling mechanism or a next extension mechanism.
[0016] Furthermore, the sleeve is clamped with the extension tube, and a docking hole is provided at one end of the sleeve, so that a plurality of sleeves can be docked and fixed by welding or fastener connection.
[0017] Furthermore, the drill bit includes a punching portion, a conical portion and a spiral portion which are arranged in sequence from bottom to top, and the punching portion, the conical portion and the spiral portion are coaxially arranged.
[0018] Furthermore, the top of the spiral portion has a mounting shaft or a mounting hole, and the mounting shaft or the mounting hole is used for docking and mounting the extension mechanism.
[0019] Furthermore, the expanding and cutting mechanism includes a barrel and an expanding and cutting knife. The barrel is coaxially arranged with the drill bit and fixedly connected with the spiral portion. The expanding and cutting knife is arranged along the radial direction of the barrel and can be extended and retracted along the axial direction of the barrel.
[0020] Furthermore, a radial groove is provided on the side of the cylinder, and the expander cutter is placed in the radial groove. The groove outlet has a buckle to prevent the expander cutter from escaping from the radial groove. A cavity is provided at the bottom of the radial groove, and a wedge-shaped pressure plate can be accommodated in the cavity. The wedge-shaped pressure plate is used to support the bottom of the expander cutter. When the expander cutter needs to be retracted, the expander cutter is retracted by pulling out the wedge-shaped pressure plate.
[0021] Furthermore, the detection mechanism includes a detection cylinder and several detection sensors. Several partitions are arranged from top to bottom in the detection cylinder, and the partitions divide the detection channel into multiple water storage tanks. The detection sensors are installed in the water storage tanks. Multiple water seepage holes are opened on the outside of the detection cylinder, and a filter membrane is arranged on the inside of the detection hole.
[0022] The beneficial effects of the present invention are:
[0023] 1. The drill rod of the present invention comprises a drill bit and an expansion and cutting mechanism. The expansion and cutting mechanism is sleeved on the outer side of the drill bit, and the expansion and cutting mechanism is fixedly connected to the drill bit. After the drill bit drills a hole, the expansion and cutting mechanism is used to expand the borehole so that the sleeve can be installed in the expanded borehole. When the drilling is completed, the expansion and cutting mechanism is used to detach and pull out from the sleeve, and the sleeve is left in the borehole. The detection mechanism is used to sample and detect the water in the sleeve. The sleeve is retained in the borehole to prevent a large amount of clay particles in the mud from adhering to the filter tube of the well pipe. Water body detection can be carried out without washing the well, which greatly improves the efficiency of the inspection well layout and can also improve the experimental accuracy of water body detection.
[0024] 2. The present invention uses a drilling mechanism to pass through the detection hole to drill holes on the ground. When the predetermined position is reached, the drilling mechanism is pulled out of the detection hole, the drilling mechanism is lifted by a lift, and the turntable is used to rotate a certain angle to deviate the drilling mechanism from the position of the detection hole, so that the detection mechanism is directly above the detection hole. The detection mechanism is used to pass through the detection hole to sample and detect the material in the detection well after drilling, which can conveniently and efficiently switch the drilling mechanism and the detection mechanism, effectively improving the detection efficiency.
[0025] Advantages of additional aspects of the present invention will be given in part in the following description, and in part will become obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] The accompanying drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.
[0027] Figure 1 2. It is a front view of the water conservancy engineering geological detection device of the embodiment;
[0028] Figure 2 is a stereoscopic diagram of a water conservancy engineering geological detection device of an embodiment;
[0029] Figure 3 is a schematic structural diagram of a drilling mechanism of an embodiment;
[0030] Figure 4 is a schematic structural diagram of an extension mechanism of an embodiment;
[0031] Figure 5 It is a structural schematic diagram of a drill rod of an embodiment;
[0032] Among them: 1. Mounting plate; 2. Guide rod; 3. Detection mechanism; 4. Drive device; 5. Drilling mechanism; 6. Turntable; 7. Lifter; 8. Detection hole; 9. Base; 10. Guide hole; 51. Extension mechanism; 52. Drill rod; 501. Extension shaft; 502. Extension tube; 503. Sleeve; 504. Punching part; 505. Conical part; 506. Cylinder; 507. Expander; 508. Radial groove; 509. Spiral part. DETAILED DESCRIPTION
[0033] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0034] It should be noted that the following detailed descriptions are all illustrative and intended to provide further explanation of the present invention. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present invention belongs.
[0035] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit exemplary embodiments according to the present invention. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprising" and / or "including" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.
[0036] In the present invention, terms such as "upper", "lower", "left", "right", "front", "back", "vertical", "horizontal", "side", "bottom", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings. They are relational words determined only for the convenience of describing the structural relationships of the various parts or elements of the present invention, and do not specifically refer to any part or element in the present invention and should not be understood as limitations on the present invention.
[0037] In the present invention, terms such as "fixed connection", "connected", "connection", etc. should be understood in a broad sense, indicating that it can be fixedly connected, integrally connected or detachably connected; it can be directly connected or indirectly connected through an intermediate medium. Relevant scientific research or technical personnel in this field can determine the specific meanings of the above terms in the present invention according to specific circumstances, and they should not be understood as limiting the present invention.
[0038] Example
[0039] like Figure 1 As shown, this embodiment provides a water conservancy engineering geological detection device, including: a base 9, a lift 7, a turntable 6, a mounting plate 1, a drilling mechanism 5 and a detection mechanism 3; the base 9 is installed on the ground, and the lift 7 is arranged at the center of the upper end surface of the base 9, and the turntable 6 is installed on the top of the lift 7. The mounting plate 1 is arranged on the turntable 6, and the drilling mechanism 5 and the detection mechanism 3 are installed on the mounting plate 1. The base 9 is also provided with a detection hole 8. The drilling mechanism 5 passes through the detection hole 8 to drill the ground. When the predetermined position is reached, the drilling mechanism 5 is pulled out of the detection hole 8, the drilling mechanism 5 is lifted by the lift 7, and the turntable 6 is rotated by a certain angle to deviate the drilling mechanism 5 from the position of the detection hole 8, so that the detection mechanism 3 is directly above the detection hole 8, and the detection mechanism 3 passes through the detection hole 8 to sample and detect the material in the detection well after drilling.
[0040] As an implementation mode, a plurality of guide holes 10 are provided on the mounting plate 1 , and the guide holes 10 cooperate with the guide rods 2 for guiding.
[0041] As an implementation mode, the mounting plate 1 and the base 9 are both semicircular structures, and the lift 7 is installed at the center of the semicircular structure.
[0042] As an implementation method, the detection mechanism 3 includes a detection cylinder and several detection sensors. Several partitions are arranged from top to bottom in the detection cylinder, and the partitions divide the detection passage into multiple water storage tanks. The detection sensors are installed in the water storage tanks. Multiple water seepage holes are opened on the outside of the detection cylinder, and a filter membrane is arranged on the inside of the detection cylinder. The detection sensor is a water quality detection sensor, and the detection sensor is electrically connected to the controller.
[0043] As an implementation mode, guide rods 2 are further provided around the base 9 , the guide rods 2 are welded to the base 9 , the mounting plate 1 is slidably sleeved on the conductor rods, and the guide rods 2 are used to guide the lifting movement of the mounting plate 1 .
[0044] The drilling mechanism 5 includes a drill rod 52 , an extension mechanism 51 and a driving device 4 . The driving device 4 is mounted on the mounting plate 1 . The output end of the driving device 4 is connected to one end of the drill rod 52 through the extension mechanism 51 .
[0045] As an embodiment, a plurality of extension mechanisms 51 are provided, which can be connected in sequence to extend the length between the drill rod 52 and the driving device 4. The extension mechanisms 51 are connected in a detachable manner. The extension mechanism 51 includes an extension shaft 501, an extension tube 502 and a sleeve 503. The extension shaft 501 is installed in the extension tube 502. A mounting hole is provided in the center of the extension shaft 501. The mounting hole can be used to dock and install with the drill rod mechanism or the next extension mechanism 51. One end of the extension shaft 501 is connected to the drill rod 52, and the other end is connected to the driving device 4. A sleeve 503 is sleeved on the outside of the extension tube 502. The sleeve 503 is clamped with the extension tube 502. A docking hole is provided at one end of the sleeve 503. Multiple sleeves 503 can be docked and fixed by welding or fastener connection. After the drill bit of the drill rod 52 drills a hole, a space for the sleeve 503 is reserved so that the sleeve 503 is set close to the outer wall of the borehole. After the drill rod 52 has finished drilling the hole, the extension tube 502 is separated from the sleeve 503 so that the extension tube 502 can be removed from the sleeve 503. By shrinking the drill bit of the drill rod 52 to a certain size, the extension tube 502 drives the drill rod 52 to rise to the ground, and the sleeve 503 is left at the borehole for protective support, so that the borehole meets the detection environment, which not only effectively avoids the slipping of the well body soil formed after drilling and affects the well, but also saves the steps of well washing, well pipe production and installation, and well pipe side wall filter material and clay ball backfilling; the driving device 4 can be a motor; the sleeve 503 can be made of corrosion-resistant material, such as PVC plastic or alloy metal.
[0046] The drill rod 52 includes a drill bit and an expansion and cutting mechanism. The expansion and cutting mechanism is sleeved on the outer side of the drill bit and fixedly connected to the drill bit. After the drill bit drills a hole, the expansion and cutting mechanism is used to expand the borehole so that the sleeve 503 can be installed in the expanded borehole. When the drilling is completed, the expansion and cutting mechanism can be used to detach from the sleeve 503 and withdrawn, leaving the sleeve 503 in the borehole for further sampling and testing.
[0047] The drill bit includes a drilling portion 504, a conical portion 505 and a spiral portion 509 which are arranged in sequence from bottom to top. The drilling portion 504, the conical portion 505 and the spiral portion 509 are coaxially arranged. The spiral portion 509 is arranged on the top of the conical portion 505. The size of the spiral portion 509 is larger than that of the conical portion 505. The drilling portion 504 is arranged below the conical portion 505. The drilling portion 504 is used to drill holes in the ground surface in contact with it, and then the drill hole is expanded to a conical transition hole through the conical portion 505, and the ground surface is further loosened through the spiral portion 509; the top of the spiral portion 509 has an installation shaft or an installation hole, and the installation shaft or the installation hole is used for docking and installing the extension mechanism 51; the setting area of the spiral portion 509 is also provided with a connecting rod, and the spiral portion 509 is connected to the cylinder 506 of the expansion and cutting mechanism through the connecting rod.
[0048] The expanding and cutting mechanism includes a cylinder 506 and an expanding and cutting knife 507. The cylinder 506 is coaxially arranged with the drill bit and fixedly connected with the spiral portion 509. The expanding and cutting knife 507 is radially arranged along the cylinder 506. The expanding and cutting knife 507 can be extended and retracted along the axial direction of the cylinder 506. The blade of the expanding and cutting knife 507 has an inclination angle. The blade of the expanding and cutting knife 507 is radially arranged, and the bottom end of the expanding and cutting knife 507 has a cutter head. The cutter head extends out of the cylinder 506, and the cutter head at the bottom of the expanding and cutting knife 507 faces inward.
[0049] As an implementation method, a radial groove 508 is provided on the side of the cylinder 506, and the radial groove 508 contains the expansion cutter 507. The groove outlet has a buckle to prevent the expansion cutter 507 from being separated from the radial groove 508. A cavity is provided at the bottom of the radial groove 508, and a wedge-shaped pressure plate can be accommodated in the cavity. The wedge-shaped pressure plate is used to support the bottom of the expansion cutter 507. When the expansion cutter 507 needs to be retracted, the expansion cutter 507 is retracted by pulling out the wedge-shaped pressure plate. The top of the wedge-shaped pressure plate is set in a wedge shape so that the expansion cutter 507 can be retracted after retraction. When the expansion cutter 507 is supported, the wedge-shaped head of the wedge-shaped pressure plate can be conveniently inserted into the bottom of the expansion cutter 507 to support the expansion cutter 507; further, an elastic sheet is installed at the bottom of the expansion cutter 507, one end of the elastic sheet is connected to the bottom of the radial groove 508, and the other end is connected to the expansion cutter 507. A through groove is set in the center of the wedge-shaped pressure plate. When the wedge-shaped pressure plate supports the expansion cutter 507, the elastic sheet is in the through groove. When the wedge-shaped pressure plate is pulled out, the expansion cutter 507 is contracted by the pre-tightening force of the elastic sheet. One end of the wedge-shaped pressure plate is connected to a steel rope, which extends to the ground. The wedge-shaped pressure plate is pulled out by pulling the steel rope. The wedge-shaped pressure plate is made of metal.
[0050] A groove is also provided on the cylinder 506 along the radial direction of the cylinder 506, an elastic member is installed at the bottom of the groove, and an expander 507 is installed in the groove. The bottom end of the expander 507 is connected to the elastic member, and the elastic member is used to provide a pre-tightening force for the expander 507. When the wedge-shaped pressure plate is pulled out, the expander 507 shrinks along the groove. After the expander 507 is retracted, the drill rod 52 can smoothly pass through the sleeve 503 and return to the ground.
[0051] The extension mechanism includes a plurality of extension mechanisms 51, and the extension mechanisms 51 are detachably connected to each other. The uppermost extension mechanism 51 is detachably connected to the output shaft of the driving motor, and the lowermost extension mechanism 51 is detachably connected to the earth-breaking mechanism. The extension mechanism 51 includes a hollow support pipe and an auger rod 52 located inside the hollow support pipe and fixedly connected to the hollow support rod.
[0052] The working process of the water conservancy engineering geological detection device is:
[0053] First, the bottom surface of the area requiring geological inspection is leveled, and then the base 9 is fixedly mounted on the flat bottom surface by fasteners;
[0054] The levelness of the base 9 is tested by a level meter and a multimeter. According to the test results of the instruments, the levelness of the lifter 7 and the guide rod 2 is adjusted so that the mounting plate 1 is in a horizontal state and the lifting movement of the mounting plate 1 is perpendicular to the ground.
[0055] Use geological testing methods such as static penetration to conduct geological testing on the borehole depth at the measurement location to confirm the soil layer structure in the borehole depth direction.
[0056] Assemble the drill rod 52 and install it on the drive motor. According to the soil layer structure in the drilling depth direction, adjust the speed of the drive motor. The harder the soil layer, the lower the speed of the drive motor. As the drill rod 52 goes down, the number of extension mechanisms 51 is continuously increased until the drill rod 52 reaches the specified depth.
[0057] By adjusting the axial extension length of the expansion and cutting mechanism of the drill bit of the drill rod 52, the drill bit can move through the sleeve 503, the connection between the sleeve 503 and the drill rod 52 is released, the drill rod 52 is pulled out of the sleeve 503, and the sleeve 503 is retained in the borehole by lifting the drill rod 52 to the ground, so as to prevent a large amount of clay particles in the mud from adhering to the filter tube of the well pipe, and water body detection can be carried out without washing the well;
[0058] When the predetermined position is reached, the drilling mechanism 5 is pulled out from the detection hole 8, the drilling mechanism 5 is lifted by the lift 7, and the turntable 6 is used to rotate it at a certain angle to deviate the drilling mechanism 5 from the position of the detection hole 8, so that the detection mechanism 3 is directly above the detection hole 8, and the detection mechanism 3 is used to pass through the detection hole 8 to sample and test the material in the detection well after drilling.
[0059] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A water conservancy engineering geological detection device, comprising: A base (9), an elevator (7), a turntable (6), a mounting plate (1), a drilling mechanism (5) and a detection mechanism (3), characterized in that the elevator (7) is arranged at the center of the upper end surface of the base (9), a turntable (6) is installed on the top of the elevator (7), a mounting plate (1) is arranged on the turntable (6), and the drilling mechanism (5) and the detection mechanism (3) are installed on the mounting plate (1): The drilling mechanism (5) comprises a drilling rod (52), an extension mechanism (51) and a driving device (4); the driving device (4) is mounted on the mounting plate (1); and the output end of the driving device (4) is connected to one end of the drilling rod (52) via the extension mechanism (51); The extension mechanism (51) comprises an extension shaft (501), an extension tube (502) and a sleeve (503); the extension shaft (501) is installed in the extension tube (502); one end of the extension shaft (501) is connected to the drill rod (52), and the other end is connected to the driving device (4); the sleeve (503) is sleeved on the outside of the extension tube (502); The drill rod (52) comprises a drill bit and an expansion and cutting mechanism. The expansion and cutting mechanism is sleeved on the outer side of the drill bit and is fixedly connected to the drill bit. After the drill bit drills a hole, the expansion and cutting mechanism is used to expand the hole so that the sleeve (503) can be installed in the expanded hole. When the hole is drilled, the expansion and cutting mechanism is used to detach from the sleeve (503) by using its elasticity, and the sleeve (503) is left in the hole. The water in the sleeve (503) is sampled and tested by using the detection mechanism (3).
2. The water conservancy engineering geological detection device according to claim 1, characterized in that: The base (9) is also provided with guide rods (2) around it. The guide rods (2) are welded to the base (9). The mounting plate (1) is slidably sleeved on the conductor rods. The guide rods (2) are used to guide the lifting movement of the mounting plate (1).
3. The water conservancy engineering geological detection device according to claim 2, characterized in that: A plurality of guide holes (10) are provided on the mounting plate (1), and the guide holes (10) cooperate with the guide rods (2) for guiding.
4. The water conservancy engineering geological detection device according to claim 1, characterized in that: The center of the extension shaft (501) is provided with a mounting hole, and the mounting hole is used for docking and mounting the drilling mechanism (5) or the next extension mechanism (51).
5. The water conservancy engineering geological detection device according to claim 1, characterized in that: The sleeve (503) is clamped with the extension tube (502), and a butt hole is provided at one end of the sleeve (503), so that a plurality of sleeves (503) can be butt-jointed and fixed by welding or fastener connection.
6. The water conservancy engineering geological detection device according to claim 1, characterized in that: The drill bit comprises a punching portion (504), a conical portion (505) and a spiral portion (509) which are arranged in sequence from bottom to top, and the punching portion (504), the conical portion (505) and the spiral portion (509) are coaxially arranged.
7. The water conservancy engineering geological detection device according to claim 1, characterized in that: The top of the spiral portion (509) is provided with a mounting shaft or a mounting hole, and the mounting shaft or the mounting hole is used for docking and mounting the extension mechanism (51).
8. The water conservancy engineering geological detection device according to claim 1, characterized in that: The expansion and cutting mechanism comprises a cylinder (506) and an expansion and cutting knife (507). The cylinder (506) is coaxially arranged with the drill bit and fixedly connected with the spiral part (509). The expansion and cutting knife (507) is radially arranged along the cylinder (506) and can be extended and retracted along the axial direction of the cylinder (506).
9. The water conservancy engineering geological detection device according to claim 8, characterized in that: The side of the cylinder (506) is provided with a radial groove (508), and the expansion cutter (507) is accommodated in the radial groove (508). The groove outlet has a buckle to prevent the expansion cutter (507) from escaping from the radial groove (508). A cavity is arranged at the bottom of the radial groove (508), and a wedge-shaped pressure plate can be accommodated in the cavity. The wedge-shaped pressure plate is used to form a support for the bottom of the expansion cutter (507). When the expansion cutter (507) needs to be retracted, the expansion cutter (507) is retracted by pulling out the wedge-shaped pressure plate.
10. The water conservancy engineering geological detection device according to claim 1, characterized in that: The detection mechanism (3) comprises a detection tube and a plurality of detection sensors. A plurality of partitions are arranged from top to bottom in the detection tube, and the partitions divide the detection channel into a plurality of water storage tanks. The detection sensors are installed in the water storage tanks. A plurality of water seepage holes are opened on the outside of the detection tube, and a filter membrane is arranged inside the detection hole (8).
Citation Information
Patent Citations
Hydrogeological survey water source sampling detection device
CN112761520A