Correction method for eliminating deviation size of steel structure
The correction method addresses inaccuracies in steel structure measurements by accounting for earth curvature, improving accuracy and reducing calculation time through site elevation adjustments and earth curvature corrections.
Patent Information
- Application Number
- CN202411091986.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2024-12-06
AI Technical Summary
Existing methods for controlling the dimensions of large-scale steel structures in marine construction fail to account for the earth's curvature, leading to inaccuracies in measurement due to the use of non-horizontal leveling surfaces, which exceed established technical requirements.
A correction method that involves arranging elevation sites around the steel structure, calculating station elevations, determining plane distances, applying earth curvature corrections using a lookup table or formula, and adjusting elevations to ensure measurements are in the same plane, using trigonometric methods and earth curvature formulas.
This method improves the accuracy and matching of site elevations, ensuring measurements are in the same plane and reduces calculation time, thereby enhancing the precision of assembly and process control.
Smart Images

Figure CN119089539A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of marine engineering construction, and in particular relates to a correction method for eliminating deviation dimensions of a steel structure. Background Art
[0002] In the process of assembly and construction, in order to avoid the error accumulation problem caused by local size control, the coordinate control network is generally used to perform three-dimensional control on the overall size of the controlled steel structure. This technology has been widely used in the size control of large-scale jackets in China. Among them, the elevation data of the control network points are mostly obtained by closed leveling routes.
[0003] Large deep-water steel structures are mostly built horizontally. From a design perspective, the plane in contact with the ground is a horizontal plane, so that the jacket remains a plane after being straightened in the seawater; from a construction perspective, if the traditional leveling method is used, that is, the station is moved, and the elevation of each node on the surface is measured in turn, this horizontal plane is not a plane. The reason is that the position of the instrument is different each time the measurement is made, and the level surface used is the earth's level surface here. Different level surfaces are not strictly horizontal, and if the size span of each station is large. In the early stage, due to the influence of construction experience and mathematical models, the impact of the earth's curvature on the elevation has not received enough attention. In reality, this error has exceeded the established technical requirements, and the impact at this time can no longer be ignored.
[0004] Therefore, it is urgent to design a correction method for eliminating the deviation size of steel structures to solve the above-mentioned problems. Summary of the invention
[0005] The purpose of the present invention is to provide a correction method for eliminating deviation dimensions of a steel structure, which has the advantages of improving the accuracy of assembly dimension positioning and process control and solves the problems mentioned in the background technology.
[0006] To achieve the above purpose, the specific technical solution of a correction method for eliminating deviation size of a steel structure of the present invention is as follows: A correction method for eliminating deviation dimensions of a steel structure comprises the following steps: S1. Arrange reasonable elevation sites around the constructed steel structure; S2, calculate the elevation of each station; S3. Calculate the plane distance from all leveling points to this point; S4. Calculate the elevation correction of each station according to the distance between each station and the center of the steel structure; S5. Add the elevation correction amount to the elevation of each station in turn to complete the elevation correction.
[0007] Furthermore, in S2, the elevation of each station is calculated by adjusting the closure error.
[0008] Furthermore, the basic elevation of the site was obtained using a closed leveling route.
[0009] Furthermore, the basic elevation of the site is obtained by using trigonometric height measurement.
[0010] Furthermore, in S3, the plane distances from all leveling points to the center point of the steel structure are calculated by taking the center point of the circle as the center.
[0011] Furthermore, the plane to be reduced is the earth's horizontal plane where the center of the controlled structure is located.
[0012] Furthermore, in S4, the elevation correction is obtained using an earth curvature correction lookup table.
[0013] Furthermore, in S4, the elevation correction is obtained using the earth curvature elevation correction formula.
[0014] Furthermore, the correction formula for the earth curvature elevation is ∆h=D 2 / 2R; Among them, ∆h is the elevation correction, D is the plane distance between the center point of the rigid structure and the site, and R is the radius of the earth.
[0015] Furthermore, the steel structure is a large steel structure.
[0016] The present invention has the following advantages: it can eliminate the phenomenon that the final measurement results are not in the same plane due to different selected horizontal planes, shorten the calculation time, and improve the accuracy and matching degree of the site elevation. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 A schematic diagram of the earth curvature correction of the present invention; Figure 2 A schematic diagram of the earth curvature correction lookup table of the present invention; Explanation of the markings in the figure: 1. Elevation correction; 2. Plane distance between the center point of the steel structure and the site; 3. Earth radius; 4. Center point of the steel structure; 5. Site; 6. Location of the Earth's center of mass. DETAILED DESCRIPTION
[0018] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.
[0019] Those skilled in the art will appreciate that, although some embodiments herein include certain features included in other embodiments but not other features, the combination of features of different embodiments is meant to be within the scope of the present invention and form different embodiments. For example, in the claims, any one of the claimed embodiments may be used in any combination.
[0020] Please refer to the attached Figure 1 To Attachment Figure 2 The invention describes a correction method for eliminating deviation dimensions of a steel structure.
[0021] Large deep-water steel structures are mostly built horizontally. From a design perspective, the plane in contact with the ground is a horizontal plane, so that the jacket remains a plane after being straightened in the seawater; from a construction perspective, if the traditional leveling method is used, that is, the station is moved, and the elevation of each node on the surface is measured in turn, this horizontal plane is not a plane. The reason is that the position of the instrument is different each time the measurement is made, and the level surface used is the earth's level surface here. Different level surfaces are not strictly horizontal, and if the size span of each station is large. In the early stage, due to the influence of construction experience and mathematical models, the impact of the earth's curvature on the elevation has not received enough attention. In reality, this error has exceeded the established technical requirements, and the impact at this time can no longer be ignored.
[0022] Therefore, the correction method for eliminating the deviation size of the steel structure includes the following steps: S1. Arrange reasonable elevation sites around the constructed steel structure; S2, calculate the elevation of each station; By adjusting the closure error, the elevation of each station is calculated.
[0023] Preferably, the basic elevation of the station is obtained by using a closed leveling route. In other embodiments of the present invention, the basic elevation of the station can also be obtained by using a trigonometric elevation measurement method, as long as the elevation of each station can be calculated by adjusting the closing error.
[0024] S3. Calculate the plane distance from all leveling points to this point; Specifically, by taking the center point of the steel structure as the center of the circle, the plane distances from all leveling points to this point are calculated.
[0025] Furthermore, the plane to be reduced is the earth's horizontal plane where the center of the controlled structure is located.
[0026] S4. Calculate the elevation correction of each station according to the distance between each station and the center of the steel structure; Preferably, the elevation correction is obtained using an earth curvature correction lookup table, such as Figure 2 As shown, when the elevation correction exceeds the range of the earth curvature correction table, the elevation correction is obtained using the earth curvature elevation correction formula.
[0027] Specifically, the formula for correction of the earth curvature elevation is ∆h=D2 / 2R; Among them, ∆h is the elevation correction, D is the plane distance between the center point of the steel structure and the site, and R is the radius of the earth.
[0028] S5. Add the elevation correction amount to the elevation of each station in turn to complete the elevation correction.
[0029] Construction steps: S11. First, determine the positions of the center point A4 of the steel structure and the site C5, mark them using plane coordinates X and Y, and calculate the plane distance D2 between the center point A4 of the steel structure and the site C5.
[0030] Step 2: If Figure 2 The earth curvature correction query table shows that the height correction ∆h 1 is calculated; Step 3: If it exceeds the range of the earth curvature correction query table, use the earth curvature elevation correction formula to calculate the elevation correction ∆h 1; Step 4: Add the C5 elevation of each station in turn with its own elevation correction ∆h 1 to obtain the final elevation; The present invention can eliminate the phenomenon that the final measurement results are not in the same plane due to different selected horizontal planes, shorten the calculation time, and improve the accuracy and matching degree of the site elevation.
[0031] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the embodiments here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the claims of the present invention.
Claims
1. A method for correcting the deviation size of a steel structure, characterized in that: The following steps are involved: S1. Arrange reasonable elevation sites around the constructed steel structure; S2, calculate the elevation of each station; S3. Calculate the plane distance from all leveling points to this point; S4. Calculate the elevation correction of each station according to the distance between each station and the center of the steel structure; S5. Add the elevation correction amount to the elevation of each station in turn to complete the elevation correction.
2. The method for correcting the deviation size of a steel structure according to claim 1, characterized in that: In S2, the elevation of each station is calculated by adjusting the closure error.
3. The method for correcting the deviation size of a steel structure according to claim 2, characterized in that: The basic elevation of the site is obtained using a closed leveling route.
4. The method for correcting the deviation size of a steel structure according to claim 2, characterized in that: The basic elevation of the site is obtained by trigonometric height measurement.
5. The method for correcting the steel structure to eliminate deviation dimensions according to claim 1, characterized in that: In S3, the plane distances from all leveling points to the center point of the steel structure are calculated by taking the center point of the circle as the center.
6. The method for correcting the steel structure to eliminate deviation dimensions according to claim 5, characterized in that: The plane to be calculated is the earth's level surface where the center of the controlled structure is located.
7. The method for correcting the steel structure to eliminate deviation dimensions according to claim 1, characterized in that: In S4, the elevation correction is obtained using the earth curvature correction lookup table.
8. The method for correcting the steel structure to eliminate deviation dimensions according to claim 1, characterized in that: In S4, the elevation correction is obtained using the earth curvature elevation correction formula.
9. The method for correcting the steel structure to eliminate deviation dimensions according to claim 8, characterized in that: The formula for correction of the height due to the curvature of the earth is ∆h=D 2 / 2R; Among them, ∆h is the elevation correction, D is the plane distance between the center point of the rigid structure and the site, and R is the radius of the earth.
10. The method for correcting the steel structure to eliminate deviation dimensions according to claim 1, characterized in that: The steel structure is a large steel structure.