BIM (Building Information Modeling)-based steel bar construction positioning method
Through the BIM-based reinforcement construction positioning method, the problem of low measurement accuracy of steel bar position is solved, efficient and accurate positioning of steel bar construction is achieved, cost reduction and structural safety and durability are improved.
Patent Information
- Application Number
- CN202411286518.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-13
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2044-09-13
AI Technical Summary
In house construction, the position measurement accuracy of the steel bar is low, resulting in large construction errors, which cannot achieve accurate positioning of the steel bars, affecting the structural strength and subsequent installation projects, and the impact of position deviation on costs cannot be predicted.
Using the BIM-based reinforcement construction positioning method, by establishing a three-dimensional BIM model, calculating and correcting the location of the connection points in the reinforcement mesh, ensuring the rationality and accuracy of the steel bar layout, using strain constraints to optimize the layout of the reinforcement mesh, and output accurate construction drawing.
It realizes efficient and precise positioning of steel bar construction, reduces rework and correction time, reduces material and labor costs, and improves structural safety and durability.
Smart Images

Figure CN119089557A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of building construction design, and in particular to a reinforcement construction positioning method based on BIM. Background Art
[0002] In the field of housing construction, due to its complex functionality, aesthetics and structural stability requirements, a large number of steel meshes need to be reserved in the structural wall as support. The deviation of the steel bar position in the early construction process will have a serious impact on the strength of the wall structure, and the reasonable arrangement of the steel bar distribution and density in the steel mesh will greatly help save costs. During the construction of structural steel bars, the measurement accuracy is low and the construction error is large. It is impossible to accurately position and tie the structural steel bars, and it is impossible to predict the impact of the steel bar position deviation on the subsequent installation project construction. Therefore, it is urgent to propose a steel bar construction positioning method based on BIM. Summary of the invention
[0003] In view of the above-mentioned deficiencies in the prior art, the present invention provides a steel bar construction positioning method based on BIM, aiming to improve construction efficiency, reduce errors, and ensure the accuracy of steel bar positions.
[0004] In order to achieve the above-mentioned object of the invention, the technical solution adopted by the present invention is: A BIM-based steel bar construction positioning method is provided, which comprises the following steps: S1: Establish a 3D BIM model of the steel mesh according to the structural design parameters of the building, construct a 3D coordinate system on the 3D BIM model, and extract the coordinates of the connection points between the steel bars in the steel mesh in the 3D coordinate system ; u is the number of the steel bars in the steel mesh. i For steel bars u The connection point number on ; S2: Calculate the distance between connection points based on the coordinates of any two adjacent connection points on the same steel bar; ; in, For steel bars u On and connection point i Adjacent connection points m The coordinates of S3: As a connection point i With connection point m The width of the space between , then get the connection point i Steel bars installed on v Radius , calculate the connection points i Theoretical space width on both sides D i , , For steel bars v Designed spacing distance; S4: Determine the width of the space Theoretical space width D i size; like , then connect the points m Along the steel bars u To the connection point i Moving distance ; like , then connect the points m Along the steel bars u Departure from the connection point i Moving distance ; S5: According to the steel bar u Coordinates of the two endpoints , Create reinforcement u The linear equation of the line on which it lies; ; S6: Calculate connection points based on line equations m Coordinates after moving , for the connection point m The position of the connection point is corrected m The position after moving is the connection point m 1; ; S7: Repeat steps S2-S6 to correct the connection point positions on the steel bars from one end to the other end of the steel bars in sequence, and satisfy the strain constraint conditions for the steel mesh to form a concrete wall. After all the connection points on the steel bars in the steel mesh are corrected, the construction drawings of the steel mesh are output.
[0005] Furthermore, the strain constraint condition is: ;and ; in, t 0 is the service life of the concrete wall, A is the bearing area of the concrete wall, b is the width of the concrete wall section, h is the height of the concrete wall section, is the strain function, which indicates the stress change of the steel bars and concrete caused by the deformation of the concrete wall. k 0 is the strain threshold, i 1. i2 are the connection point numbers on the steel bars at the locations of the two opposite sides on the steel mesh section. The connection point on one side of the reinforcement i The coordinates of 1, The connection point on the other side of the reinforcement i 2 coordinates, I 1. I 2 are the number of connection points on the steel bars at the locations of two opposite sides on the steel mesh section, H It is the design thickness from the concrete wall surface to the steel mesh surface.
[0006] The beneficial effects of the present invention are as follows: the present invention is used to optimize the design layout of steel bars in reinforced concrete walls, and the connection position of each steel bar is corrected by using BIM technology and data calculation, so as to ensure that the output construction drawings are sufficiently accurate, and realize efficient and accurate positioning of steel bar construction. Accurate positioning of steel bar construction is realized, and the rework and correction time caused by inaccurate position is reduced; and construction costs are reduced. Accurate construction positioning reduces the waste of materials and the increase of labor costs, and improves the structural safety and durability of the overall wall project. BRIEF DESCRIPTION OF THE DRAWINGS
[0007] Figure 1 The figure is a flow chart of the BIM-based reinforcement construction positioning method. DETAILED DESCRIPTION
[0008] The specific implementation modes of the present invention are described below so that those skilled in the art can understand the present invention. However, it should be clear that the present invention is not limited to the scope of the specific implementation modes. For those of ordinary skill in the art, as long as various changes are within the spirit and scope of the present invention as defined and determined by the attached claims, these changes are obvious, and all inventions and creations utilizing the concept of the present invention are protected.
[0009] like Figure 1 As shown, a BIM-based steel bar construction positioning method includes the following steps: S1: Establish a 3D BIM model of the steel mesh according to the structural design parameters of the building, construct a 3D coordinate system on the 3D BIM model, and extract the coordinates of the connection points between the steel bars in the steel mesh in the 3D coordinate system ; u is the number of the steel bars in the steel mesh. i For steel bars u The connection point number on ; During the construction of building walls, a steel mesh is first built. The steel mesh is built with several steel bars and then welded and fixed. The steel bars can effectively improve the quality and strength of the building walls. When the layout of the steel bars is unreasonable or there are large deviations, it will inevitably affect the quality of the building walls. Therefore, during the design process, the relative position of the steel bars needs to be corrected to optimize the layout and density of the steel bars.
[0010] S2: Calculate the distance between connection points based on the coordinates of any two adjacent connection points on the same steel bar; ; in, For steel bars u On and connection point i Adjacent connection points m The coordinates of S3: As a connection point i With connection point m The width of the space between , then get the connection point i Steel bars installed on v Radius , calculate the connection points i Theoretical space width on both sides D i , , For steel bars v Designed spacing distance; S4: Determine the width of the space Theoretical space width D i size; like , then connect the points m Along the steel bars u To the connection point i Moving distance ; like , then connect the points m Along the steel bars u Departure from the connection point i Moving distance ; Arrange the spacing between the steel bars according to the different steel bar sizes in the steel mesh to ensure the rationality of the steel bar layout.
[0011] S5: According to the steel bar u Coordinates of the two endpoints , Create reinforcement u The linear equation of the line on which it lies; ; S6: Calculate connection points based on line equations m Coordinates after moving , for the connection point m The position of the connection point is corrected m The position after moving is the connection point m 1; ; S7: Repeat steps S2-S6 to correct the connection point positions on the steel bars from one end to the other end of the steel bars in sequence, and satisfy the strain constraint conditions for the steel mesh to form a concrete wall. After all the connection points on the steel bars in the steel mesh are corrected, the construction drawings of the steel mesh are output.
[0012] The strain constraint condition is: ;and ; in, t 0 is the service life of the concrete wall, A is the bearing area of the concrete wall, b is the width of the concrete wall section, h is the height of the concrete wall section, is the strain function, which indicates the stress change of the steel bars and concrete caused by the deformation of the concrete wall. k 0 is the strain threshold, i 1. i 2 are the connection point numbers on the steel bars at the locations of the two opposite sides on the steel mesh section. The connection point on one side of the reinforcement i The coordinates of 1, The connection point on the other side of the reinforcement i 2 coordinates, I 1. I 2 are the number of connection points on the steel bars at the locations of two opposite sides on the steel mesh section, H It is the design thickness from the concrete wall surface to the steel mesh surface.
[0013] The present invention is used to optimize the steel bar design layout in reinforced concrete walls, and uses BIM technology and data calculation to correct the connection position of each steel bar, ensuring that the output construction drawings are sufficiently accurate, and realizing efficient and accurate positioning of steel bar construction. Accurate positioning of steel bar construction is realized, reducing rework and correction time caused by inaccurate position; reducing construction costs. Accurate construction positioning reduces material waste and increased labor costs, and improves the structural safety and durability of the overall wall project.
Claims
1. A BIM-based steel bar construction positioning method, characterized in that: The following steps are involved: S1: Establish a 3D BIM model of the steel mesh according to the structural design parameters of the building, construct a 3D coordinate system on the 3D BIM model, and extract the coordinates of the connection points between the steel bars in the steel mesh in the 3D coordinate system ; u is the number of the steel bars in the steel mesh. i For steel bars u The connection point number on ; S2: Calculate the distance between connection points based on the coordinates of any two adjacent connection points on the same steel bar; ; in, For steel bars u On and connection point i Adjacent connection points m The coordinates of S3: As a connection point i With connection point m The width of the space between , then get the connection point i Steel bars installed on v Radius , calculate the connection points i Theoretical space width on both sides D i , , For steel bars v Designed spacing distance; S4: Determine the width of the space Theoretical space width D i size; like , then connect the points m Along the steel bars u To the connection point i Moving distance ; like , then connect the points m Along the steel bars u Departure from the connection point i Moving distance ; S5: According to the steel bar u Coordinates of the two endpoints , Create reinforcement u The linear equation of the line on which it lies; ; S6: Calculate connection points based on line equations m Coordinates after moving , for the connection point m The position of the connection point is corrected m The position after moving is the connection point m 1; ; S7: Repeat steps S2-S6 to correct the connection point positions on the steel bars from one end to the other end of the steel bars in sequence, and satisfy the strain constraint conditions for the steel mesh to form a concrete wall. After all the connection points on the steel bars in the steel mesh are corrected, the construction drawings of the steel mesh are output.
2. The BIM-based steel bar construction positioning method according to claim 1, characterized in that: The strain constraint condition is: ;and ; in, t 0 is the service life of the concrete wall, A is the bearing area of the concrete wall, b is the width of the concrete wall section, h is the height of the concrete wall section, is the strain function, which indicates the stress change of the steel bars and concrete caused by the deformation of the concrete wall. k 0 is the strain threshold, i 1. i 2 are the connection point numbers on the steel bars at the locations of the two opposite sides on the steel mesh section. The connection point on one side of the reinforcement i The coordinates of 1, The connection point on the other side of the reinforcement i 2 coordinates, I 1. I 2 are the number of connection points on the steel bars at the locations of two opposite sides on the steel mesh section, H It is the design thickness from the concrete wall surface to the steel mesh surface.
Citation Information
Patent Citations
Positioning method for special-shaped concrete counterfort rebar
CN106245852A
Construction method for accurately pre-burying pipeline group in concrete structure
CN110046363A
Ring beam joint BIM auxiliary construction method capable of avoiding concrete pouring blocking
CN115952589A
BIM-based complex reinforcement node design optimization method and device, equipment and medium
CN116167125A
Embedded part precise positioning construction technology based on BIM technology
CN116451309A