Building energy-saving monitoring method, electronic equipment, storage medium and program product
By establishing simulated building models and matching predicted energy consumption and actual energy consumption data, identifying abnormal areas, the problems of low manual operation efficiency and poor accuracy in existing building energy-saving monitoring methods are solved, and more efficient energy consumption monitoring and optimization are achieved.
Patent Information
- Application Number
- CN202411084844.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-08
- Publication Date
- 2024-12-06
AI Technical Summary
The existing building energy-saving monitoring methods rely on manual operations, are inefficient and susceptible to human factors, resulting in low accuracy of monitoring results.
By obtaining building parameters and historical operation data, establishing simulated building models, predicting energy consumption, and matching them with actual energy consumption data, identifying abnormal areas, reducing human participation, and improving the accuracy of monitoring results.
It improves the accuracy and accuracy of building energy-saving monitoring, reduces human operations, can promptly detect and optimize energy consumption abnormalities, and improve energy consumption waste.
Smart Images

Figure CN119090129A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of data monitoring technology, and in particular to a building energy-saving monitoring method, electronic equipment, storage medium and program product. Background Art
[0002] With the growth of global population and the acceleration of urbanization, the proportion of building energy consumption in the global total energy consumption continues to rise. Faced with increasingly scarce resources and increasingly serious environmental problems, energy conservation, emission reduction and sustainable development are becoming increasingly important. Therefore, it is particularly important to promote energy-saving transformation of buildings and the development of green buildings to achieve low energy consumption and environmental improvement.
[0003] A common way to promote building energy-saving renovation and the development of green buildings is to monitor building energy consumption, track and analyze building energy consumption in real time, identify areas or equipment with high energy consumption in the building, and then improve the building's energy efficiency through targeted energy-saving renovation or optimization to reduce unnecessary energy waste. However, since the relevant building energy-saving monitoring operations mainly rely on manual monitoring, the manual monitoring process is not only inefficient, but the monitoring results are also easily affected by human factors, which may lead to low accuracy of the monitoring results. Summary of the invention
[0004] In order to improve the accuracy of monitoring building energy conservation, the present application provides a building energy conservation monitoring method, electronic equipment, storage medium and program product.
[0005] In the first aspect, the present application provides a building energy-saving monitoring method, which adopts the following technical solution: A building energy-saving monitoring method, comprising: Acquire building parameters of the building to be monitored and historical operation data of each building area in the building to be monitored, the historical operation data including water supply and drainage data, lighting data, and ventilation data; Determine a simulated building model corresponding to the building to be monitored according to the building parameters, and predict the energy consumption of each building area of the building to be monitored within a preset time period based on the historical operation data corresponding to each building area and the simulated building model to obtain predicted energy consumption data, wherein the predicted energy consumption data includes regional predicted energy consumption data corresponding to each building area; Acquire actual energy consumption data corresponding to the building to be monitored within the preset time period, wherein the actual energy consumption data includes regional actual energy consumption data corresponding to each building area; The predicted energy consumption data is matched with the actual energy consumption data, abnormal building areas are determined, and the abnormal building areas are fed back.
[0006] By adopting the above technical scheme, the corresponding simulated building model is determined by the building parameters of the building to be monitored, instead of selecting any model for simulation, which facilitates improving the adaptability between the simulation process and the actual operation process of the building to be monitored, thereby facilitating improving the accuracy of the simulation results. In addition, by dividing the building to be monitored into areas and simulating based on the historical operation data of each building area, it is convenient to accurately monitor each building area, thereby facilitating improving the accuracy of the monitoring results. Finally, since the probability of interference from external factors during the simulated operation is low, the energy consumption data generated by the simulation is compared with the energy consumption data generated by the actual operation to determine the abnormal conditions that may exist in the actual operation process. After the abnormal conditions are fed back, it is convenient for relevant personnel to timely optimize or adjust the abnormal conditions in a targeted manner, thereby improving the waste of building energy consumption. The present application reduces human participation in the monitoring process and monitors building energy conservation through data-driven prediction and comparison, thereby facilitating improving the accuracy of the monitoring results.
[0007] In a possible implementation, matching the predicted energy consumption data with the actual energy consumption data to determine the abnormal building area includes: The predicted energy consumption data is matched with the actual energy consumption data according to a preset time series to obtain a plurality of matching data axes, each matching data axis corresponds to a sub-predicted energy consumption data, and each regional predicted energy consumption data includes a plurality of sub-predicted energy consumption data; Identify the area identifier corresponding to each matching data axis, and group the multiple matching data axes based on the identification result to obtain multiple data axis sets, each data axis set corresponding to a building area; Identify a target deviation axis region corresponding to each matching data axis in each data axis set, wherein the target deviation axis region is a region where the energy consumption difference between the sub-predicted energy consumption data and the corresponding sub-actual energy consumption data exceeds a preset energy consumption value range; The abnormal building area is determined based on the target deviation axis area corresponding to each data axis set.
[0008] By adopting the above technical solution, the predicted energy consumption data is matched with the actual energy consumption data through a preset time series, which is convenient for improving the accuracy of the data matching process, thereby facilitating improving the accuracy of the data matching results. Since the predicted energy consumption data contains multiple sub-predicted energy consumption data, the data axes belonging to the same building area are classified by grouping, so as to facilitate unified management of different data axes in the same area. In addition, by determining the target deviation axis area from the data axis, it is determined whether there is an abnormality in the corresponding building area, which is convenient for improving the accuracy of determining abnormal building areas.
[0009] In a possible implementation, determining the abnormal building area based on the target deviation axis area corresponding to each data axis set includes: Identify the deviation time period and the preset abnormality elimination time period of the target deviation axis area corresponding to each data axis set, determine the deviation axis elimination area corresponding to each data axis set, and the time period corresponding to the deviation axis elimination area is consistent with the preset abnormality elimination time period; According to the eliminated off-axis region contained in each data axis set, the target off-axis region contained in each data axis set is updated to obtain the updated off-axis region corresponding to each data axis set; Based on the deviation time period of the updated deviation axis area corresponding to each data axis set, an island axis area corresponding to each data axis set is determined, wherein there is no associated axis area in the island axis area, and an interval between deviation time periods corresponding to two updated deviation axis areas that are mutually associated axis areas is less than a preset interval; According to the island axis area contained in each data axis set, the target deviation axis area contained in each data axis set is updated to obtain the target updated deviation axis area corresponding to each data axis set; Identify the area amount of the target update deviation axis area corresponding to each data axis set, determine the data axis set with an area amount higher than a preset area amount threshold as an abnormal data axis set, and determine the building area corresponding to the abnormal data axis set as an abnormal building area.
[0010] By adopting the above technical solution, after the target deviation axis area is determined from the data axis, the abnormal building area is not determined directly based on the determined target deviation axis area, but it is judged whether the generation of the target deviation axis area is accidental through the deviation time period and the associated axis area. By eliminating accidental situations and then determining the abnormal building area based on the target updated deviation axis area, the accuracy of determining the abnormal building area is improved.
[0011] In one possible implementation, the method further includes: Determine similar building areas to the abnormal building area from other building areas according to the regional building parameters corresponding to the abnormal building area, wherein the other building areas are building areas other than the abnormal building area; Identify abnormal features corresponding to the abnormal building area, and acquire abnormal construction images corresponding to the abnormal building area and similar construction images corresponding to similar building areas from a historical image database based on the abnormal features; The abnormal construction image is compared with the similar construction image to determine construction difference parameters, and the construction difference parameters are fed back together with the abnormal building area.
[0012] By adopting the above technical solution, since the construction operations in the construction phase may affect the energy consumption data generated in the operation phase, by comparing the abnormal construction images with the similar construction images, it is convenient to determine the abnormal construction behaviors that may exist in the construction phase. Finally, by providing feedback on the identified construction difference parameters, relevant staff can make targeted optimization and adjustment plans.
[0013] In a possible implementation, before feeding back the construction difference parameter and the abnormal building area together, the method further includes: Optimizing the simulated building model according to the construction difference parameters corresponding to the abnormal building area to obtain an optimized simulated building model; Based on the historical operation data corresponding to the abnormal building area and the optimized simulated building model, the energy consumption of the abnormal building area within a preset time period is predicted to obtain optimized predicted energy consumption data; Determine an optimization type according to the optimized predicted energy consumption data, the regional predicted energy consumption data corresponding to the abnormal building area, and the preset standard energy consumption data, wherein the optimization type includes a positive optimization type and a reverse optimization type; When the optimization type is a positive optimization type, the construction difference parameter is fed back together with the abnormal building area.
[0014] By adopting the above technical solution, after the construction difference parameters are determined, the optimization type of the construction difference parameters can be identified and judged by optimizing the simulated building model. When the optimization type is a positive optimization type, the construction difference parameters and the abnormal building area are fed back together to improve the effectiveness of the feedback data, thereby providing valuable data reference for the energy-saving transformation of the monitored building.
[0015] In a possible implementation, when the number of abnormal building areas is higher than a preset number threshold, the method further includes: Identifying an area identifier corresponding to each abnormal building area, and identifying a corresponding simulated abnormal area from the simulated building model based on each area identifier; Identify the abnormal features corresponding to each simulated abnormal area, and determine the abnormal impact area of each abnormal feature based on each abnormal feature and the impact mapping relationship, wherein the impact mapping relationship is the corresponding relationship between the abnormal feature and the impact range; According to the abnormal impact area of each abnormal feature, an intersection area is determined, and intersection information corresponding to the intersection area is identified, wherein the intersection information includes the area of the intersection area and the number of intersection features, and the intersection feature is the abnormal feature contained in the intersection area; The intersection area corresponding to the intersection information that meets the preset conditions is determined as the focus area, and the focus area is fed back. The preset conditions include that the intersection area area is greater than a preset area threshold, or the number of intersection features is greater than a preset intersection number threshold.
[0016] By adopting the above technical solution, since different energy-consuming equipment in a building may affect each other, by analyzing the intersection area affected by multiple abnormal features, the intersection area affected by multiple abnormal features can be identified, and then the focus area can be screened out from the intersection area according to the area of the intersection area or the number of intersection features to ensure that the feedback information is highly accurate and targeted, which helps relevant staff to quickly locate and solve abnormal energy consumption problems.
[0017] In a second aspect, the present application provides an electronic device, which adopts the following technical solution: An electronic device, comprising: at least one processor; Memory; At least one application, wherein the at least one application is stored in a memory and configured to be executed by at least one processor, and the at least one application is configured to: execute the above-mentioned building energy-saving monitoring method.
[0018] In a third aspect, the present application provides a computer-readable storage medium, which adopts the following technical solution: A computer-readable storage medium includes: a computer program that can be loaded by a processor and execute the above-mentioned building energy-saving monitoring method.
[0019] In a fourth aspect, the present application provides a computer program product, which adopts the following technical solution: A computer program product includes a computer program, and when the computer program is executed by a processor, the building energy-saving monitoring method is implemented.
[0020] In summary, the present application includes at least one of the following beneficial technical effects: Determining the corresponding simulated building model through the building parameters of the building to be monitored, rather than selecting any model for simulation, facilitates improving the adaptability between the simulation process and the actual operation process of the building to be monitored, thereby facilitating improving the accuracy of the simulation results. In addition, by dividing the building to be monitored into areas and simulating based on the historical operation data of each building area, it is convenient to accurately monitor each building area, thereby facilitating improving the accuracy of the monitoring results. Finally, since the probability of interference from external factors during simulated operation is low, the energy consumption data generated by the simulation is compared with the energy consumption data generated by the actual operation to determine the abnormal conditions that may exist in the actual operation process. After the abnormal conditions are fed back, it is convenient for relevant personnel to timely optimize or adjust the abnormal conditions in a targeted manner, thereby improving the waste of building energy consumption. The present application reduces human participation in operations during the monitoring process, and monitors building energy conservation through data-driven prediction and comparison, thereby facilitating improving the accuracy of the monitoring results.
[0021] Since construction operations during the construction phase may affect the energy consumption data generated during the operation phase, by comparing abnormal construction images with similar construction images, it is convenient to determine abnormal construction behaviors that may exist during the construction phase. Finally, by providing feedback on the identified construction difference parameters, relevant staff can make targeted optimization and adjustment plans. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a flow chart of a building energy-saving monitoring method in an embodiment of the present application; Figure 2 It is a schematic flow chart of a method for determining an abnormal building area in an embodiment of the present application; Figure 3 is a schematic diagram of a target off-axis region in an embodiment of the present application; Figure 4 It is a structural schematic diagram of an electronic device in an embodiment of the present application. DETAILED DESCRIPTION
[0023] The following is combined with Figure 1-4 This application is described in further detail.
[0024] After reading this specification, those skilled in the art may make non-creative modifications to this embodiment as needed, but such modifications are protected by patent law as long as they are within the scope of the claims of this application.
[0025] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0026] It should be noted that in the optional embodiments of the present application, the object information and other related data involved, when the embodiments in the present application are applied to specific products or technologies, need to obtain the permission or consent of the object, and the collection, use and processing of the relevant data need to comply with the relevant laws, regulations and standards of the relevant countries and regions. In other words, if the embodiments of the present application involve data related to the object, it needs to be obtained with the authorization and consent of the object, the authorization and consent of the relevant departments, and in compliance with the relevant laws, regulations and standards of the country and region. If personal information is involved in the embodiments, the acquisition of all personal information needs to obtain the consent of the individual. If sensitive information is involved, the separate consent of the information subject needs to be obtained. The embodiments also need to be implemented with the authorization and consent of the object.
[0027] Specifically, the embodiment of the present application provides a building energy-saving monitoring method, which is executed by an electronic device, which can be a server or a terminal device, wherein the server can be an independent physical server, or a server cluster or distributed system composed of multiple physical servers, or a cloud server that provides cloud computing services. The terminal device can be a smart phone, a tablet computer, a laptop computer, a desktop computer, etc., but is not limited thereto. The terminal device and the server can be directly or indirectly connected via wired or wireless communication, which is not limited in the embodiment of the present application.
[0028] refer to Figure 1 , Figure 1 : is a flow chart of a building energy-saving monitoring method in an embodiment of the present application, the method comprises steps S110-S140, wherein: Step S110: Acquire the building parameters of the building to be monitored and the historical operation data of each building area in the building to be monitored, where the historical operation data includes water supply and drainage data, lighting data, and ventilation data.
[0029] Specifically, the building to be monitored is a building that needs to be monitored for energy conservation, or a building that needs to be diagnosed for energy conservation. Building parameters are physical characteristics of the building to be monitored, and may include the building area, structure, insulation materials, window area, building orientation, etc. of the building to be monitored. The specific content is not specifically limited in the embodiments of the present application. As long as the corresponding building to be monitored can be determined by the building parameters, the building parameters can be uploaded to the electronic device in advance by the relevant staff. The building to be monitored includes multiple building areas, and the area division method of different buildings to be monitored may be different. For example, each floor of the building can be determined as a building area, or a multi-story building can be determined as a building area. The specific area division method is not specifically limited in the embodiments of the present application.
[0030] The historical operation data is generated during the operation phase and can be collected by sensors installed in the building to be monitored and uploaded to electronic equipment. Different historical operation data correspond to different transmitters. The historical operation data include but are not limited to water supply and drainage data, lighting data and ventilation data. Among them, the water supply and drainage data involve the operating time and operating flow of water supply and drainage equipment in the corresponding building area, which are used to reflect the energy consumption of water supply and drainage equipment; the lighting data involve the opening time, power, lighting efficiency, etc. of the lighting equipment in the corresponding building area, which are used to reflect the energy consumption of the lighting equipment; the ventilation data involve the operating mode, ventilation times, fresh air volume, etc. of the ventilation equipment in the corresponding building area, which are used to reflect the energy consumption of the ventilation equipment.
[0031] Step S120: Determine the simulated building model corresponding to the monitored building according to the building parameters, and predict the energy consumption of each building area of the monitored building within a preset time period based on the historical operation data and the simulated building model corresponding to each building area to obtain predicted energy consumption data, which includes regional predicted energy consumption data corresponding to each building area.
[0032] Specifically, different building parameters correspond to different simulated building models. When determining the simulated building model corresponding to the building parameters, it can be determined directly according to the model mapping relationship, wherein the model mapping relationship includes different building parameters and their corresponding simulated building models. The specific content of the model mapping relationship is not specifically limited in the embodiments of this application and can be set by relevant technical personnel. Since the various building areas in the building to be monitored are interrelated, such as lighting equipment and water supply and drainage equipment, if only a certain building area is simulated, it may cause a large error in the simulation result. Therefore, in this application, it is necessary to simulate and predict the entire building to be monitored based on the historical operation data corresponding to each building area.
[0033] The preset time period can be 1 hour after the current moment, or it can be 2 hours after the current moment. The duration corresponding to the preset time period is not specifically limited in the embodiment of the present application. The historical operation data corresponding to each building area is imported into the simulated building model, and the simulated building model can be trained using a machine learning algorithm so that it can learn and understand the energy consumption patterns under different conditions. Among them, the machine learning algorithm can use regression analysis, time series analysis or neural network, etc. The specific training method and machine learning algorithm are not specifically limited in the embodiment of the present application, as long as the predicted energy consumption data of the building to be monitored can be obtained through the simulated building model. The predicted energy consumption data is the energy consumption usage corresponding to the building to be monitored, that is, it can reflect the energy consumption usage of each building area in the building to be monitored. The energy consumption usage of each building area corresponds to the historical operation data, that is, the predicted energy consumption data can at least reflect the energy consumption usage of each building area for water supply and drainage, lighting and ventilation.
[0034] Step S130: Acquire actual energy consumption data corresponding to the building to be monitored within a preset time period, where the actual energy consumption data includes regional actual energy consumption data corresponding to each building area.
[0035] Specifically, when simulating and predicting the energy consumption of the building to be monitored within a preset time period based on the historical operation data of each building area, the building to be monitored does not stop using energy, that is, the water supply and drainage equipment, lighting equipment and ventilation equipment in the building to be monitored are all working normally during the prediction simulation, and the actual energy consumption data generated within the preset time period can be collected by the sensors set in the equipment to be monitored and uploaded to the electronic device. Consistent with the preset energy consumption data, the actual energy consumption data can reflect the actual energy consumption of each building area in the building to be monitored, that is, the actual energy consumption data includes the actual energy consumption data of multiple areas, and the predicted energy consumption data also includes the predicted energy consumption data of multiple areas.
[0036] Step S140: Match the predicted energy consumption data with the actual energy consumption data, determine the abnormal building area, and provide feedback on the abnormal building area.
[0037] Specifically, since the predicted energy consumption data is composed of regional predicted energy consumption data corresponding to multiple building areas, and the actual energy consumption data is composed of regional actual energy consumption data corresponding to multiple building areas, when matching the predicted energy consumption data and the actual energy consumption data, the matching can be performed after one-to-one correspondence between the building areas. The abnormal building area is a building area where the regional actual energy consumption data is higher than the regional predicted energy consumption data. The number of abnormal building areas can be 0 or more, and the specific number is not specifically limited in the embodiments of the present application.
[0038] Furthermore, in order to improve the accuracy in determining abnormal building areas, the predicted energy consumption data and the actual energy consumption data are matched to determine the abnormal building areas, which may specifically include: matching the predicted energy consumption data with the actual energy consumption data according to a preset time series to obtain multiple matching data axes, each matching data axis corresponds to a sub-predicted energy consumption data, and each regional predicted energy consumption data contains multiple sub-predicted energy consumption data; identifying the area identifier corresponding to each matching data axis, and grouping the multiple matching data axes based on the identification result to obtain multiple data axis sets, each data axis set corresponding to a building area; identifying the target deviation axis area corresponding to each matching data axis in each data axis set, the target deviation axis area being the energy consumption difference between the sub-predicted energy consumption data and the corresponding sub-actual energy consumption data, which exceeds the preset energy consumption value range; determining the abnormal building area based on the target deviation axis area corresponding to each data axis set.
[0039] Specifically, the preset time series corresponds to the preset time period. When determining the preset time series, the preset time period can be directly divided into time periods. For example, when the preset time period is 10:00-12:00, the preset time series can be 10:00-10:10, 10:50-11:00, 11:10-11:20, 11:30-11:40, that is, when matching the predicted energy consumption data with the actual energy consumption data, the data comparison can be performed in a spot check manner to reduce the amount of calculation when matching the data, or all the data can be matched according to actual needs. The preset time series corresponding to different preset time periods may be different. In the embodiment of the present application, the preset time series can be uploaded to the electronic device by the relevant staff from the terminal device.
[0040] Each sub-predicted energy consumption data corresponds to a matching data axis, which contains two types of lines, one of which is predicted data and the other is actual data. If the preset time series is continuous, the corresponding matching data axis is a continuous line. If the preset time series is a spot check time segment in a preset time period, the corresponding matching data axis is a discontinuous line. Since a building area may contain water supply and drainage equipment, lighting equipment, and ventilation equipment at the same time, each regional predicted energy consumption data may contain multiple sub-predicted energy consumption data. One sub-predicted energy consumption data corresponds to one matching data axis. Correspondingly, one regional predicted energy consumption data may correspond to multiple matching data axes.
[0041] In order to facilitate data retrieval, the predicted energy consumption data and the actual energy consumption data were not initially managed separately, but mixed together, and data matching was performed through multi-channel matching. However, the area identifiers corresponding to different building areas are different. Correspondingly, the regional predicted energy consumption data and the regional actual energy consumption data corresponding to different building areas carry corresponding regional identifiers. By identifying the regional identifier, all sub-predicted energy consumption data with the same regional identifier can be determined, that is, by identifying the regional identifier, all matching data axes with the same regional identifier can be determined.
[0042] Each data axis set corresponds to a building area, and the set contains matching data axes corresponding to all energy-consuming devices in the building area. For any matching data axis, the energy consumption difference between the predicted energy consumption data and the corresponding actual energy consumption data in the matching data axis can be identified to determine whether there is a target deviation axis area in the matching data axis. When the energy consumption difference exceeds the preset energy consumption value range, it indicates that the corresponding matching data axis has a target deviation axis area. The matching data axis may contain a target deviation axis area or may not contain a target deviation axis area. When it does, the number of target deviation axis areas is not specifically limited in the embodiments of the present application. The building area corresponding to the matching data axis containing the target deviation axis area can be directly determined as an abnormal building area. The preset energy consumption range can be set by relevant technical personnel, and is not specifically limited in the embodiments of the present application. It is normal to fluctuate within the preset energy consumption range. If it exceeds the preset energy consumption range, it indicates an abnormal situation.
[0043] After the abnormal building area is determined, the abnormal building area and the corresponding area identification can be fed back to the terminal equipment of the relevant staff, so that the relevant staff can make targeted optimization and adjustments to the energy consumption in a timely manner.
[0044] For the embodiments of the present application, the corresponding simulated building model is determined by the building parameters of the building to be monitored, rather than selecting any model for simulation, so as to improve the adaptability between the simulation process and the actual operation process of the building to be monitored, thereby facilitating the improvement of the accuracy of the simulation results. In addition, by dividing the building to be monitored into areas and performing simulation based on the historical operation data of each building area, it is convenient to accurately monitor each building area, thereby facilitating the improvement of the accuracy of the monitoring results. Finally, since the probability of interference from external factors during the simulated operation is low, the energy consumption data generated by the simulation is compared with the energy consumption data generated by the actual operation to determine the abnormal conditions that may exist in the actual operation process. After the abnormal conditions are fed back, it is convenient for relevant personnel to timely optimize or adjust the abnormal conditions in a targeted manner, thereby improving the waste of building energy consumption. The present application reduces human participation in operations during the monitoring process, and monitors building energy conservation through data-driven prediction and comparison, thereby facilitating the improvement of the accuracy of the monitoring results.
[0045] Furthermore, since a data time axis may contain multiple target deviation axis areas, not all abnormal conditions generated by the target deviation axis areas are energy consumption abnormalities, and there may also be equipment abnormalities or power outages. Therefore, when determining the abnormal building area based on the target deviation axis area, it is necessary to perform denoising on the multiple target deviation axis areas to improve the effectiveness of the target deviation axis area. Therefore, in order to further improve the accuracy of determining the abnormal building area, based on the target deviation axis area corresponding to each data axis set, determining the abnormal building area can specifically include steps S1 to S5, such as Figure 2 As shown, where: Step S1: Identify the deviation time period and preset abnormality elimination time period of the target deviation axis area corresponding to each data axis set, determine the deviation axis elimination area corresponding to each data axis set, and the time period corresponding to the deviation axis elimination area is consistent with the preset abnormality elimination time period.
[0046] Step S2: According to the eliminated off-axis region contained in each data axis set, the target off-axis region contained in each data axis set is updated to obtain the updated off-axis region corresponding to each data axis set.
[0047] Specifically, each data axis set may contain multiple matching data axes, and each matching data axis may contain multiple target deviation axis regions, such as Figure 3 As shown, Figure 3 There are three target deviation axis areas included, and the actual energy consumption data in the target deviation axis area is not within the corresponding preset energy consumption data range. The preset abnormality elimination time period can be a power outage time period or an equipment maintenance time period. Since the actual energy consumption data of the equipment during the power outage time period and the equipment maintenance time period may be lower than the preset energy consumption data range, it is not the case that there is an abnormality in the energy consumption of the building. Therefore, it is necessary to eliminate the abnormalities that occur during the power outage time period or the equipment maintenance time period, that is, to eliminate the target deviation axis area whose deviation time period coincides with the preset abnormality elimination time period. By eliminating the deviation axis area from multiple target deviation axis areas, an updated deviation axis area can be obtained. The number of eliminated deviation axis areas is not specifically limited in the embodiment of the present application.
[0048] Step S3: Based on the deviation time period of the updated deviation axis area corresponding to each data axis set, determine the island axis area corresponding to each data axis set, there is no associated axis area in the island axis area, and the interval between the deviation time periods corresponding to two updated deviation axis areas that are mutually associated axis areas is lower than the preset interval.
[0049] Step S4: According to the island axis region included in each data axis set, the target deviation axis region included in each data axis set is updated to obtain the target updated deviation axis region corresponding to each data axis set.
[0050] Specifically, when there is only one target deviation time axis in the matching data axis, the probability that the target deviation time axis is an island axis area is relatively high. If the duration corresponding to the deviation time period corresponding to the target deviation time axis is lower than the preset island duration, the target deviation time axis is characterized as an island axis area, wherein the preset island duration can be 5 seconds or 10 seconds, and the specific duration is not specifically limited in the embodiment of the present application. When there is more than one target deviation time axis in the matching data axis, there may also be an island axis area. For any matching data axis, the deviation time period corresponding to each updated deviation axis area in the matching data axis is identified, and the interval between each updated deviation axis area is calculated according to the time sequence and the deviation time period corresponding to each updated deviation axis, and it is determined whether the two updated deviation axes are related axis areas. For example, there are 4 existing updated deviation time axis areas, namely, updated deviation time axis area a, updated deviation time axis area b, updated deviation time axis area c, and updated deviation time axis area d. Among them, the deviation time period corresponding to the update deviation time axis area a is 10:10-10:15, the deviation time period corresponding to the update deviation time axis area b is 10:18-10:28, the deviation time period corresponding to the update deviation time axis area c is 12:00-12:05, and the deviation time period corresponding to the update deviation time axis area d is 12:10-12:15. The preset interval is 6 minutes. At this time, the update deviation time axis area a and the update deviation time axis area b are mutually related axis areas, and the update deviation time axis area c and the update deviation time axis area d are mutually related axis areas. Among them, the specific preset interval is not specifically limited in the embodiment of the present application.
[0051] The island axis region is an update deviation axis region where there is no associated axis region. After the island axis region is determined, the target update axis region can be obtained by removing the island axis region from the update deviation axis region.
[0052] Step S5: Identify the area amount of the target update deviation axis area corresponding to each data axis set, determine the data axis set with an area amount higher than a preset area amount threshold as an abnormal data axis set, and determine the building area corresponding to the abnormal data axis set as an abnormal building area.
[0053] Specifically, since a data axis set may contain multiple matching data axes, and a matching data axis may contain multiple target update deviation axis areas, when determining the abnormal building area, it is necessary to count the target update deviation axis areas in the data axis set corresponding to each building area as the area quantity of each data axis set, and finally determine the abnormal building area by comparing the area quantity of each data axis set with the preset area quantity threshold. The abnormal building area is a building area whose area quantity of the corresponding data axis set is higher than the preset area quantity threshold.
[0054] After determining the target deviation axis area from the data axis, the abnormal building area is not determined directly based on the determined target deviation axis area. Instead, it is judged whether the generation of the target deviation axis area is accidental through the deviation time period and the associated axis area. By eliminating accidental situations and then determining the abnormal building area based on the target updated deviation axis area, the accuracy of determining the abnormal building area is improved.
[0055] Furthermore, in order to facilitate relevant staff to make targeted optimization and adjustment plans, the method provided by this application also includes: According to the regional building parameters corresponding to the abnormal building area, similar building areas to the abnormal building area are determined from other building areas, where the other building areas are building areas other than the abnormal building area; the abnormal features corresponding to the abnormal building area are identified, and based on the abnormal features, the abnormal construction images corresponding to the abnormal building area and the similar construction images corresponding to the similar building areas are obtained from a historical image database; the abnormal construction images are compared with the similar construction images to determine the construction difference parameters, and the construction difference parameters are fed back together with the abnormal building area.
[0056] Among them, when determining similar building areas of abnormal building areas, the regional building parameters corresponding to the abnormal building areas can be matched with the regional building parameters corresponding to all other building areas, and the other building areas with the highest matching values are determined as similar building areas of the abnormal building areas. Different abnormal building areas may correspond to different abnormal features, and the abnormal features correspond to energy-consuming equipment. For example, when the energy-consuming equipment includes water supply and drainage equipment, lighting equipment, and ventilation equipment, the abnormal features correspond to water supply and drainage abnormal features, lighting abnormal features, and ventilation abnormal features. The specific abnormal feature types are not specifically limited in the embodiments of this application.
[0057] The historical image database contains construction images of all building areas during the construction phase. Since different building areas correspond to different energy-consuming equipment, the construction images corresponding to different building areas are also different. In addition, the construction time of different energy-consuming equipment in the same building area may be different. Therefore, the same building area may contain multiple construction images, and each energy-consuming equipment corresponds to a construction image. The construction images containing abnormal features in the abnormal building area are determined as abnormal construction images, and the construction images containing abnormal features in the similar building area are determined as similar construction images. After comparing the abnormal construction images with the similar construction images, the construction difference parameters between the two can be determined. The construction difference parameters may include construction materials, construction methods, construction steps, etc.
[0058] When comparing an abnormal construction image with a similar construction image, the two images may be preprocessed first. The preprocessing includes but is not limited to normalization to ensure that the illumination, contrast and size of the two images are consistent; image noise reduction to reduce the noise in the image. After preprocessing, a feature detection algorithm may be used to extract key points and descriptors in the two images, and then the two images may be feature matched based on the key points and descriptors in the two images, and finally the construction difference parameters between the two images may be determined based on the matching results. Among them, the SIFT feature detection algorithm or the ORB feature detection algorithm is used when extracting the key points and descriptors in the two images. The specific detection algorithm is not specifically limited in the embodiments of the present application, as long as the key points and descriptors contained in the image can be identified.
[0059] After determining the construction difference parameters between the abnormal construction image and the similar construction image, the optimization type of the construction difference parameters can be identified and judged by optimizing the simulated building model. When the optimization type is a positive optimization type, the construction difference parameters and the abnormal building area are fed back together. The method of determining the optimization type may include: According to the construction difference parameters corresponding to the abnormal building area, the simulated building model is optimized to obtain the optimized simulated building model; based on the historical operation data corresponding to the abnormal building area and the optimized simulated building model, the energy consumption of the abnormal building area within a preset time period is predicted to obtain the optimized predicted energy consumption data; according to the optimized predicted energy consumption data, the regional predicted energy consumption data corresponding to the abnormal building area and the preset standard energy consumption data, the optimization type is determined, and the optimization type includes a positive optimization type and a reverse optimization type; when the optimization type is the positive optimization type, the construction difference parameters are fed back together with the abnormal building area.
[0060] Specifically, since the simulated building model of the building area is determined based on the building parameters of the building area, the simulated building model can be optimized by optimizing the corresponding building parameters through abnormal construction parameters. When optimizing the corresponding building parameters, the optimization can be performed by adjusting the parameters or adding parameters. First, the regional parameters corresponding to the abnormal building area are determined from the building parameters, and then the regional parameters are matched with the construction difference parameters to determine the common parameter type and the difference parameter type. For the common parameter type, the construction difference parameters can be used to replace the corresponding regional parameters. For the difference parameter type, the construction difference parameters are added to the regional parameters.
[0061] After determining the optimized simulation building model, the historical operation data corresponding to the abnormal building area can be imported into the optimized simulation building model for simulation again to obtain the optimized preset energy consumption data. If the optimized predicted energy consumption data is closer to the preset standard energy consumption data than the regional predicted energy consumption data corresponding to the abnormal building area, the optimization type can be determined to be a positive optimization type, otherwise it is a reverse optimization type. When judging whether the optimized predicted energy consumption data is closer to the preset standard energy consumption data than the regional predicted energy consumption data corresponding to the abnormal building area, the predicted energy consumption data, the regional predicted energy consumption data corresponding to the abnormal building area, and the preset standard energy consumption data can be imported into a preset coordinate system, and the first degree of fit between the predicted energy consumption data and the preset standard energy consumption data, and the second degree of fit between the regional predicted energy consumption data and the preset standard energy consumption data are calculated respectively. If the first degree of fit is higher than the second degree of fit, it indicates that the predicted energy consumption data is closer to the preset standard energy consumption data than the regional predicted energy consumption data corresponding to the abnormal building area. Among them, the specific preset standard energy consumption data is not specifically limited in the embodiments of the present application. The construction difference parameters are fed back together with the abnormal building areas to improve the effectiveness of the feedback data, thereby providing valuable data reference for the energy-saving renovation of the monitored buildings.
[0062] Furthermore, in order to facilitate relevant staff to quickly locate and solve the abnormal energy consumption problem, when the number of abnormal building areas is higher than a preset number threshold, the method provided in the embodiment of the present application further includes: Identify the area identifier corresponding to each abnormal building area, and identify the corresponding simulated abnormal area from the simulated building model based on each area identifier; identify the abnormal features corresponding to each simulated abnormal area, and determine the abnormal impact area of each abnormal feature based on each abnormal feature and the impact mapping relationship, where the impact mapping relationship is the correspondence between the abnormal feature and the impact range.
[0063] Specifically, different area identifiers correspond to different simulation areas, and all simulation areas constitute a simulated building area. The simulation area corresponding to the abnormal building area is a simulated abnormal area, wherein each area identifier corresponds to an area coordinate. According to the area identifier corresponding to the abnormal building area, the corresponding simulated abnormal area can be quickly located. The impact mapping relationship includes the impact range corresponding to different abnormal features. For example, when the abnormal feature is an abnormal lighting feature, the corresponding impact range can be a range consisting of a preset radius distance with the lighting device that currently has the abnormal lighting feature as the center, wherein the preset radius distance and the impact mapping relationship are not specifically limited in the embodiments of the present application, and different abnormal features have different impact ranges. In the same way, the abnormal impact area corresponding to each abnormal feature in each abnormal building area can be determined.
[0064] According to the abnormal impact area of each abnormal feature, the intersection area is determined, and the intersection information corresponding to the intersection area is identified. The intersection information includes the area of the intersection area and the number of intersection features. The intersection feature is the abnormal feature contained in the intersection area; the intersection area corresponding to the intersection information that meets the preset conditions is determined as the focus area, and the focus area is fed back. The preset conditions include that the area of the intersection area is greater than the preset area threshold, or the number of intersection features is greater than the preset intersection number threshold.
[0065] Specifically, after each abnormal impact area is determined, each abnormal impact area is superimposed according to the position of the simulated abnormal area corresponding to each abnormal impact area in the simulated building model to determine the intersection area. When the areas are superimposed, the abnormal features corresponding to the abnormal impact areas can be superimposed as indicator information.
[0066] After all the intersection areas are determined, the intersection area corresponding to each intersection area can be calculated. When the intersection area is greater than the preset area threshold, the corresponding intersection area can be determined as the focus area, wherein the preset area threshold is not specifically limited in the embodiment of the present application. After all the intersection areas are determined, the number of intersection features contained in each intersection area can also be counted, that is, the intersection area is composed of several abnormal impact areas. When the number of intersection features is greater than the preset intersection number threshold, the corresponding intersection area can be determined as the focus area, wherein the preset intersection number threshold is not specifically limited in the embodiment of the present application.
[0067] Since different energy-consuming equipment in a building may affect each other, by analyzing the intersection areas affected by multiple abnormal features, the intersection areas affected by multiple abnormal features can be identified, and then the focus areas can be screened out from the intersection areas based on the area of the intersection area or the number of intersection features to ensure that the feedback information is highly accurate and targeted, which helps relevant staff to quickly locate and solve abnormal energy consumption problems.
[0068] An electronic device is provided in an embodiment of the present application, such as Figure 4 As shown, Figure 4 The electronic device 400 shown includes: a processor 401 and a memory 403. The processor 401 and the memory 403 are connected, such as through a bus 402. Optionally, the electronic device 400 may also include a transceiver 404. It should be noted that in actual applications, the transceiver 404 is not limited to one, and the structure of the electronic device 400 does not constitute a limitation on the embodiments of the present application.
[0069] Processor 401 may be a CPU (Central Processing Unit), a general-purpose processor, a DSP (Digital Signal Processor), an ASIC (Application Specific Integrated Circuit), an FPGA (Field Programmable Gate Array) or other programmable logic devices, transistor logic devices, hardware components or any combination thereof. It may implement or execute various exemplary logic blocks, modules and circuits described in conjunction with the disclosure of this application. Processor 401 may also be a combination that implements computing functions, such as a combination of one or more microprocessors, a combination of a DSP and a microprocessor, etc.
[0070] The bus 402 may include a path to transmit information between the above components. The bus 402 may be a PCI (Peripheral Component Interconnect) bus or an EISA (Extended Industry Standard Architecture) bus. The bus 402 may be divided into an address bus, a data bus, a control bus, etc. For ease of representation, Figure 4 The fact that only one line is used in the diagram does not mean that there is only one bus or only one type of bus.
[0071] The memory 403 may be a ROM (Read Only Memory) or other types of static storage devices that can store static information and instructions, a RAM (Random Access Memory) or other types of dynamic storage devices that can store information and instructions, or an EEPROM (Electrically Erasable Programmable Read Only Memory), a CD-ROM (Compact Disc Read Only Memory) or other optical disk storage, optical disk storage (including compressed optical disk, laser disk, optical disk, digital versatile disk, Blu-ray disk, etc.), a magnetic disk storage medium or other magnetic storage device, or any other medium that can be used to carry or store the desired program code in the form of instructions or data structures and can be accessed by a computer, but is not limited thereto.
[0072] The memory 403 is used to store the application code for executing the solution of the present application, and the execution is controlled by the processor 401. The processor 401 is used to execute the application code stored in the memory 403 to implement the contents shown in the above method embodiment.
[0073] The electronic devices include, but are not limited to, mobile terminals such as mobile phones, laptop computers, digital broadcast receivers, PDAs (personal digital assistants), PADs (tablet computers), PMPs (portable multimedia players), vehicle-mounted terminals (such as vehicle-mounted navigation terminals), and fixed terminals such as digital TVs, desktop computers, etc. It can also be a server, etc. Figure 4 The electronic device shown is merely an example and should not bring any limitation to the functions and scope of use of the embodiments of the present application.
[0074] An embodiment of the present application provides a computer-readable storage medium, on which a computer program is stored. When the computer-readable storage medium is run on a computer, the computer can execute the corresponding content in the aforementioned method embodiment.
[0075] An embodiment of the present application provides a computer program product, which includes a computer program. When the computer program is executed by a processor, the method in any of the above embodiments is implemented.
[0076] It should be understood that, although the steps in the flowchart of the accompanying drawings are displayed in sequence as indicated by the arrows, these steps are not necessarily executed in sequence in the order indicated by the arrows. Unless otherwise specified herein, there is no strict order restriction on the execution of these steps, and they can be executed in other orders. Moreover, at least a part of the steps in the flowchart of the accompanying drawings may include multiple sub-steps or multiple stages, and these sub-steps or stages are not necessarily executed at the same time, but can be executed at different times, and their execution order is not necessarily sequential, but can be executed in turn or alternately with other steps or at least a part of the sub-steps or stages of other steps.
[0077] The above is only a partial implementation method of the present application. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present application. These improvements and modifications should also be regarded as the scope of protection of the present application.
Claims
1. A building energy-saving monitoring method, characterized in that: include: Acquire building parameters of the building to be monitored and historical operation data of each building area in the building to be monitored, the historical operation data including water supply and drainage data, lighting data, and ventilation data; Determine a simulated building model corresponding to the building to be monitored according to the building parameters, and predict the energy consumption of each building area of the building to be monitored within a preset time period based on the historical operation data corresponding to each building area and the simulated building model to obtain predicted energy consumption data, wherein the predicted energy consumption data includes regional predicted energy consumption data corresponding to each building area; Acquire actual energy consumption data corresponding to the building to be monitored within the preset time period, wherein the actual energy consumption data includes regional actual energy consumption data corresponding to each building area; The predicted energy consumption data is matched with the actual energy consumption data, abnormal building areas are determined, and the abnormal building areas are fed back.
2. A building energy-saving monitoring method according to claim 1, characterized in that: The matching of the predicted energy consumption data with the actual energy consumption data to determine the abnormal building area includes: The predicted energy consumption data is matched with the actual energy consumption data according to a preset time series to obtain a plurality of matching data axes, each matching data axis corresponds to a sub-predicted energy consumption data, and each regional predicted energy consumption data includes a plurality of sub-predicted energy consumption data; Identify the area identifier corresponding to each matching data axis, and group the multiple matching data axes based on the identification result to obtain multiple data axis sets, each data axis set corresponding to a building area; Identify a target deviation axis region corresponding to each matching data axis in each data axis set, wherein the target deviation axis region is a region where the energy consumption difference between the sub-predicted energy consumption data and the corresponding sub-actual energy consumption data exceeds a preset energy consumption value range; The abnormal building area is determined based on the target deviation axis area corresponding to each data axis set.
3. A building energy-saving monitoring method according to claim 2, characterized in that: The determining of the abnormal building area based on the target deviation axis area corresponding to each data axis set includes: Identify the deviation time period and the preset abnormality elimination time period of the target deviation axis area corresponding to each data axis set, determine the deviation axis elimination area corresponding to each data axis set, and the time period corresponding to the deviation axis elimination area is consistent with the preset abnormality elimination time period; According to the eliminated off-axis region contained in each data axis set, the target off-axis region contained in each data axis set is updated to obtain the updated off-axis region corresponding to each data axis set; Based on the deviation time period of the updated deviation axis area corresponding to each data axis set, an island axis area corresponding to each data axis set is determined, wherein there is no associated axis area in the island axis area, and an interval between deviation time periods corresponding to two updated deviation axis areas that are mutually associated axis areas is less than a preset interval; According to the island axis area contained in each data axis set, the target deviation axis area contained in each data axis set is updated to obtain the target updated deviation axis area corresponding to each data axis set; Identify the area amount of the target update deviation axis area corresponding to each data axis set, determine the data axis set with an area amount higher than a preset area amount threshold as an abnormal data axis set, and determine the building area corresponding to the abnormal data axis set as an abnormal building area.
4. A building energy-saving monitoring method according to claim 1, characterized in that: Also includes: Determine similar building areas to the abnormal building area from other building areas according to the regional building parameters corresponding to the abnormal building area, wherein the other building areas are building areas other than the abnormal building area; Identify abnormal features corresponding to the abnormal building area, and acquire abnormal construction images corresponding to the abnormal building area and similar construction images corresponding to similar building areas from a historical image database based on the abnormal features; The abnormal construction image is compared with the similar construction image to determine construction difference parameters, and the construction difference parameters are fed back together with the abnormal building area.
5. A building energy-saving monitoring method according to claim 4, characterized in that: Before feeding back the construction difference parameter and the abnormal building area together, the method further includes: Optimizing the simulated building model according to the construction difference parameters corresponding to the abnormal building area to obtain an optimized simulated building model; Based on the historical operation data corresponding to the abnormal building area and the optimized simulated building model, the energy consumption of the abnormal building area within a preset time period is predicted to obtain optimized predicted energy consumption data; Determine an optimization type according to the optimized predicted energy consumption data, the regional predicted energy consumption data corresponding to the abnormal building area, and the preset standard energy consumption data, wherein the optimization type includes a positive optimization type and a reverse optimization type; When the optimization type is a positive optimization type, the construction difference parameter is fed back together with the abnormal building area.
6. A building energy-saving monitoring method according to claim 1, characterized in that: When the number of abnormal building areas is higher than a preset number threshold, the method further includes: Identifying an area identifier corresponding to each abnormal building area, and identifying a corresponding simulated abnormal area from the simulated building model based on each area identifier; Identify the abnormal features corresponding to each simulated abnormal area, and determine the abnormal impact area of each abnormal feature based on each abnormal feature and the impact mapping relationship, wherein the impact mapping relationship is the corresponding relationship between the abnormal feature and the impact range; According to the abnormal impact area of each abnormal feature, an intersection area is determined, and intersection information corresponding to the intersection area is identified, wherein the intersection information includes the area of the intersection area and the number of intersection features, and the intersection feature is the abnormal feature contained in the intersection area; The intersection area corresponding to the intersection information that meets the preset conditions is determined as the focus area, and the focus area is fed back. The preset conditions include that the intersection area area is greater than a preset area threshold, or the number of intersection features is greater than a preset intersection number threshold.
7. An electronic device, characterized in that: The electronic device includes: at least one processor; Memory; At least one application, wherein the at least one application is stored in a memory and configured to be executed by at least one processor, and the at least one application is configured to: execute a building energy-saving monitoring method according to any one of claims 1-6.
8. A computer-readable storage medium, characterized in that: include: A computer program is stored which can be loaded by a processor and executes a building energy-saving monitoring method as described in any one of claims 1 to 6.
9. A computer program product, characterized in that It comprises a computer program, which, when executed by a processor, implements the steps of a building energy-saving monitoring method according to any one of claims 1 to 6.
Citation Information
Cited By
Digital construction site supervision method and system, storage medium and electronic equipment
CN119991353A
A digital construction site supervision method, system, storage medium and electronic device
CN119991353B
Method for calculating energy-saving amount of lighting system after building lighting energy-saving transformation
CN120873972A
A method for calculating energy saving of a lighting system after energy-saving reconstruction of building lighting
CN120873972B