Virtual power plant optimal scheduling method and system under active time-of-use electricity price
By introducing an active time-sharing electricity price adjustment model guided by carbon emission factor in virtual power plants, combined with multi-energy coupling and load response, the problems of isolated energy network and high carbon emissions in traditional power systems are solved, and the cost and carbon emission reduction are achieved and efficient consumption of renewable energy.
Patent Information
- Application Number
- CN202411212719.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-12-06
AI Technical Summary
The isolation of various energy networks in the traditional power system optimization scheduling method leads to low energy utilization efficiency, high operating costs and high carbon emissions, and lacks effective price incentives and load demand response mechanisms for power consumption units.
Using the virtual power plant optimization scheduling method under active time-sharing electricity price, the load-side comprehensive demand response model, electric-thermal-gas-hydrogen multi-energy coupling model, carbon trading model and green certificate trading model, the carbon emission factor coefficient is introduced, and the carbon emission factor coefficient is established. Carbon emission factor-guided active time-sharing electricity price adjustment model to optimize the operating strategies of virtual power plants.
It effectively reduces the operating costs and carbon emissions of the system, improves the renewable energy consumption capacity of virtual power plants, makes full use of the load demand response potential, and achieves subtle incentives for electricity consumption behavior.
Smart Images

Figure CN119090545A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the field of power optimization and dispatching, and specifically relates to a virtual power plant optimization and dispatching method and system under active time-of-use electricity prices, and in particular to a virtual power plant optimization and dispatching method and system under active time-of-use electricity prices guided by carbon emission factors. Background Art
[0002] The statements in this section merely provide background information related to the present invention and do not necessarily constitute prior art.
[0003] The continuous increase in the penetration rate of new energy in the context of the new power system has posed a huge challenge to the safe and stable operation of the power system. This invention is aimed at virtual power plants with a high proportion of renewable energy, and establishes a virtual power plant model that couples electricity, heat, gas, hydrogen and carbon. On this basis, it proposes an active time-of-use electricity price method guided by system carbon emissions, which is further applied to the optimization and scheduling of virtual power plants to guide the rational use of electricity by each power unit, which can effectively reduce the operating costs and carbon emissions of virtual power plants and improve their renewable energy absorption capacity.
[0004] Since the output of renewable energy is random and intermittent, it leads to serious problems of wind and solar abandonment. Improving the absorption capacity of renewable energy and reducing the carbon emission level of the system are of great practical significance to the transformation of the power system. Hydrogen, as a clean and environmentally friendly secondary energy carrier, plays a very important role in the low-carbon operation of the power system. In the traditional power system optimization and dispatching problem, the system architecture design usually isolates the electricity, heat, gas and other systems, without taking into account the coupling characteristics of multiple energy networks; in terms of energy price setting, most of the existing solutions adopt a fixed grid-connected electricity price or a fixed time-of-use electricity price model; in terms of load side demand setting, fixed rigid loads are usually used, and it is impossible to respond to demand information such as electricity prices; in terms of carbon emissions, the current market adopts a "quota-trading" method to allocate carbon emission rights according to parameters such as power generation capacity, calculate carbon emissions according to power generation, and trade; virtual power plants are power supply coordination management systems that use advanced information and communication technologies and software systems to achieve the aggregation and coordinated optimization of distributed energy, so as to participate in the power market and power grid operation as a special power plant.
[0005] The traditional method of optimizing the dispatch of isolated energy networks has low energy efficiency, high system operating costs and serious waste of new energy. In terms of energy pricing, the fixed pricing model lacks effective price incentives for electricity users. The use of time-of-use electricity prices can guide demand response to a certain extent, but the time-of-use electricity prices are also fixed and cannot more accurately motivate users' electricity consumption behavior. Loads can be divided into rigid loads and flexible loads. Flexible loads can respond to electricity prices through load transfer and load reduction. Only considering rigid loads cannot fully utilize the demand response potential of loads. Although the system carbon emission behavior guided by carbon quota trading has a certain effect, the carbon emission model that only considers the carbon quota allocated by power generation capacity and the power generation accounting is simple in form and lacks accuracy. Summary of the invention
[0006] In order to solve the above problems, the present invention proposes a virtual power plant optimization scheduling method and system under active time-of-use electricity prices. The present invention effectively overcomes the drawbacks of isolated energy networks in the traditional power system optimization scheduling problem, fully considers the multi-energy coupling characteristics and hydrogen energy potential, and based on the active time-of-use electricity price adjustment method, better guides the user's electricity consumption behavior, effectively reduces the system's operating costs and carbon emissions, and greatly improves the virtual power plant's renewable energy absorption capacity.
[0007] According to some embodiments, the present invention adopts the following technical solutions:
[0008] A virtual power plant optimization scheduling method under active time-of-use electricity price includes the following steps:
[0009] Integrate different types of load-side demand response to build a load-side comprehensive demand response model;
[0010] Comprehensive energy equipment constraints and energy network power balance, build an electricity-heat-gas-hydrogen multi-energy coupling model, and form a virtual power plant;
[0011] Construct carbon trading model and green certificate trading model;
[0012] Introduce carbon emission factor coefficients to guide time-of-use electricity prices, establish an active time-of-use electricity price adjustment model guided by carbon emission factors, and calculate the carbon emissions of virtual power plants at all times;
[0013] Taking the minimum total cost as the optimization scheduling objective function;
[0014] With the load-side comprehensive demand response model, electricity-heat-gas-hydrogen multi-energy coupling model, carbon trading model, green certificate trading model and active time-of-use electricity price adjustment model as constraints, the solution is obtained to obtain the final virtual power plant optimization scheduling plan.
[0015] As an optional implementation, the demand response model includes a price-based demand response model and an incentive-based demand response model;
[0016] The price-based demand response model is used to describe the relationship between user demand and energy price through the demand price elasticity matrix for the electric load and gas load participating in the price-based demand response, and has a limit constraint on the change amount after the load response price;
[0017] The incentive-based demand response model is used to indicate that when the system is at a peak load or in an emergency, users directly reduce or interrupt part of the load according to the compensation incentive strategy formulated by the operator, and has a load change limit constraint.
[0018] As an optional implementation method, the process of constructing an electricity-heat-gas-hydrogen multi-energy coupling model includes: determining external power purchase, gas purchase constraints, new energy output and load constraints, and constructing a single energy conversion equipment model and a gas-hydrogen mixed heat and power cogeneration model;
[0019] Added electricity network balance, thermal network balance, gas power balance and hydrogen network balance.
[0020] As an optional implementation method, the process of constructing a carbon trading model includes using a baseline method to allocate system carbon emission rights and constructing a carbon emission model.
[0021] As an optional implementation method, the process of constructing a green certificate trading model includes establishing a positive correlation between the number of green certificates obtained by the virtual power plant and the amount of renewable energy electricity generated by the system, and determining a positive correlation between the carbon quota of the virtual power plant and the amount of renewable energy electricity generated by the system.
[0022] As an optional implementation method, the process of establishing an active time-of-use electricity price adjustment model guided by a carbon emission factor includes: adding a carbon emission factor coefficient when constructing the time-of-use electricity price and the initial value of the gas price adjustment, and using the carbon emission factor coefficient as the calculation coefficient.
[0023] As an optional implementation, the total cost includes the total cost of the virtual power plant, the external power purchase cost, the total operating cost, as well as the carbon trading cost, the green certificate trading cost, the demand response cost and the cost of abandoned renewable energy.
[0024] A virtual power plant optimization dispatching system under active time-of-use electricity price, comprising:
[0025] A demand response model building module is configured to integrate different categories of load-side demand response to build a load-side integrated demand response model;
[0026] The energy coupling model building module is configured to integrate energy equipment constraints and energy network power balance, build an electricity-heat-gas-hydrogen multi-energy coupling model, and form a virtual power plant;
[0027] The trading model building module is configured to build a carbon trading model and a green certificate trading model;
[0028] A guided electricity price adjustment module is configured to introduce a carbon emission factor coefficient to guide the time-of-use electricity price, establish an active time-of-use electricity price adjustment model guided by the carbon emission factor, and calculate the carbon emissions of the virtual power plant at each moment;
[0029] The optimization scheduling module is configured to take the minimization of total cost as the optimization scheduling objective function, and to solve the load-side comprehensive demand response model, electricity-heat-gas-hydrogen multi-energy coupling model, carbon trading model, green certificate trading model and active time-of-use electricity price adjustment model with constraints to obtain the final virtual power plant optimization scheduling plan.
[0030] A computer-readable storage medium is used to store computer instructions, and when the computer instructions are executed by a processor, the steps in the above method are completed.
[0031] An electronic device comprises a memory and a processor, and computer instructions stored in the memory and executed on the processor. When the computer instructions are executed by the processor, the steps in the above method are completed.
[0032] Compared with the prior art, the present invention has the following beneficial effects:
[0033] The present invention comprehensively considers the coupling between various energy networks, and establishes a multi-link utilization model of hydrogen energy, giving full play to the new energy consumption and emission reduction potential of hydrogen energy. Secondly, the present invention fully considers the demand response behavior of the load, introduces a price-based demand response model and an incentive demand response model, and introduces a carbon emission factor coefficient to achieve the time-of-use electricity price in each period. It can be fine-tuned according to the carbon emissions in the period, thereby affecting the load-side demand response and optimized scheduling behavior of the virtual power plant; breaking the traditional fixed time-of-use electricity price barriers, by adjusting the time-of-use electricity price in real time, it can more accurately reflect the source-grid-load-storage interactive behavior of the virtual power plant system in different periods, and can effectively improve the utilization rate of renewable energy in the virtual power plant.
[0034] At the same time, the present invention takes into account the emission reduction requirements for virtual power plants and comprehensively considers the carbon quota trading and green certificate trading models. On this basis, a carbon emission-guided time-of-use electricity price active adjustment model is proposed to further guide the load-side demand response of virtual power plants.
[0035] The present invention effectively overcomes the drawbacks of isolated energy networks in the traditional power system optimization and scheduling problems, fully considers the multi-energy coupling characteristics and hydrogen energy potential, and better guides users' electricity consumption behavior based on the active time-of-use electricity price adjustment method, effectively reduces the system's operating costs and carbon emissions, and greatly improves the virtual power plant's renewable energy absorption capacity.
[0036] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, preferred embodiments are given below and described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] The accompanying drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.
[0038] Figure 1 This is a schematic diagram of a virtual power plant structure framework of electricity-heat-gas-hydrogen-carbon multi-energy coupling in one embodiment;
[0039] Figure 2 is a demand response and load classification diagram of an embodiment;
[0040] Figure 3 It is a flow chart for solving the optimal scheduling of virtual power plants under active time-of-use electricity prices guided by the carbon emission factor proposed in the present invention. DETAILED DESCRIPTION
[0041] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0042] It should be noted that the following detailed descriptions are all illustrative and intended to provide further explanation of the present invention. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present invention belongs.
[0043] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit exemplary embodiments according to the present invention. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprising" and / or "including" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.
[0044] In the absence of conflict, the embodiments in this application and the features in the embodiments may be combined with each other.
[0045] Embodiment 1
[0046] A virtual power plant optimization scheduling method under carbon emission-guided active time-of-use electricity price adjustment includes the following steps:
[0047] Step 1: Build a comprehensive demand response model on the load side
[0048] like Figure 2As shown, there are three types of demand response models, namely price-based demand response, incentive-based demand response and substitution-based demand response. The first two are considered as the main load-side demand response types.
[0049] Price-based demand response model
[0050] The electricity load and gas load that participate in price-based demand response can describe the relationship between user demand and energy price through the demand price elasticity matrix. The dispatch cycle is divided into three periods: peak, flat, and valley, and represented by subscripts p, f, and v respectively. The demand price elasticity matrix is Ei It is expressed as follows:
[0051]
[0052] In the formula, the subscript i represents electrical energy or gas energy; E i,pp 、E i,ff 、E i,vv are the self-elastic coefficients of the i-th type load elastic matrix, and the others are cross elastic coefficients.
[0053] At the same time, price-based demand response needs to meet the constraints:
[0054]
[0055] In the formula, ΔL i,TSL,t , ΔL i,TSL,max are the change amount and the upper limit of the change amount after the i-th type of load responds to the price; L i,0,t is the i-th type of initial load; t is the t-th time period, T is the scheduling period, c i,0,t 、c i,t are the initial price and the price after response of the i-th type of energy respectively.
[0056] Incentive Demand Response
[0057] Incentive demand response means that when the system is at peak load or in an emergency, users directly reduce or interrupt part of the load according to the compensation incentive strategy formulated by the operator. The loads participating in incentive demand response include electricity load, gas load and heat load.
[0058] The incentive demand response model for electricity and gas loads is:
[0059]
[0060] 0≤|ΔL i,IL,t |≤ΔL i,IL,max
[0061] In the formula, C i,m is the incentive subsidy cost of the i-th load at the m-th time scale; m is the time scale; ε i,mis the incentive subsidy coefficient of the i-th type of load; ΔL i,IL,t , ΔL i,IL,max are the load change and the upper limit of the change in the tth time period respectively.
[0062] The incentive demand response model for heat load is:
[0063]
[0064] ΔL h,t =f(T h,in,t )-f(T h,in,t -ΔT h,in,t )
[0065] 0≤|ΔL h,t |≤ΔL h,max
[0066] T h,in,min ≤T h,in,t -ΔT h,in,t ≤T h,in,max
[0067]
[0068] Where, L h,t Heating load for users; T h,in,t 、T h,out,t are the indoor temperature and outdoor temperature of the building respectively; S is the indoor heating area; δ h is the indoor heat loss per unit temperature difference under unit heating area; C air is the equivalent heat capacity of the building; Δt is the time interval; ΔL h,t , ΔL h,max are the user's heating load change and its upper limit; ΔT h,in,t is the indoor temperature change; C h is the heat load incentive subsidy; h is the incentive subsidy coefficient; c h,t is the unit price of the incentive subsidy in the tth period.
[0069] Step 2: Constructing an electricity-heat-gas-hydrogen multi-energy coupling model
[0070] like Figure 1 As shown, the virtual power plant is a multi-energy coupling of electricity, heat, gas and hydrogen.
[0071] Energy equipment constraints
[0072] External power and gas purchase constraints:
[0073] 0≤P e,t ≤P e,max
[0074] 0≤Pg,t ≤P g,max
[0075] Where P e,t , P g,t are the power of electricity and gas purchased in the tth period respectively; P e,max , P g,max are the power limits for purchasing electricity and gas in the tth period respectively.
[0076] New energy output and load constraints:
[0077]
[0078] Where P RES,t , P L,i,t are the renewable energy output and actual load power consumption in the tth period respectively; They represent the upper limit of renewable energy output and load forecast value in the tth period respectively.
[0079] The virtual power plant contains single energy conversion equipment, which is used to convert one energy into another. Such equipment includes electrolyzers, methane reactors, and gas boilers. Its model is:
[0080] P equip,i,t =η equip P equip,j,t
[0081] P equip,i,min ≤P equip,i,t ≤P equip,i,max
[0082] ΔP equip,i,min ≤P equip,i,t+1 -P equip,i,t ≤ΔP equip,i,max
[0083] Where P equip,i,t , P equip,i,max , P equip,i,min Respectively represent the output power of the i-th energy source in the t-th period and its maximum and minimum values; P equip,j,t represents the input power of the jth energy source in the tth period; η equip Represents the energy conversion efficiency of the device.
[0084] Gas-hydrogen cogeneration model:
[0085] P CHP,e,t =η CHP,e P CHP,g,t
[0086] P CHP,h,t =η CHP,h P CHP,g,t
[0087] P CHP,e,min ≤P CHP,e,t ≤P CHP,e,max
[0088] ΔP CHP,e,min ≤P CHP,e,t+1 -P CHP,e,t ≤ΔP CHP,e,t
[0089] Energy storage equipment includes batteries, heat storage tanks and gas storage tanks, and their models are:
[0090] E i,t =δ loss E i,t-1 +P i,c,t η i,c -P i,d,t / η i,d
[0091] E i,min ≤E i,t ≤E i,max
[0092] 0≤P i,c,t ≤I i,c,t P i,c,max
[0093] 0≤P i,d,t ≤I i,d,t P i,d,max
[0094] I i,c,t +I i,d,t ≤1
[0095] In the formula, E i,t 、E i,max 、E i,min Represents the storage capacity of the i-th energy source in the t-th period of the energy storage device and its maximum and minimum capacity; δ loss represents energy loss efficiency; P i,c,t , P i,d,t Respectively represent the charging and discharging power of the energy storage device at time t; η i,c , η i,d Respectively represent the charge and discharge efficiency; I i,c,t ,
[0096] I i,d,t Respectively represent the state of charge and discharge; P i,c,max , P i,d,max They represent the charging and discharging power limits of the energy storage device respectively.
[0097] Energy network power balancing
[0098] Power network balance:
[0099] P grid,t +P RES,t +P CHP,t +P HFC,t +P BT,d,t =L e,IDR,t +P BT,t +P EL,e,t
[0100] Where P grid,t , P RES,t , P CHP,t , P HFC,t , P BT,d,t , L e,IDR,t , P BT,t , P EL,e,t They represent the external grid purchased electricity power, new energy output, cogeneration equipment power, hydrogen fuel cell power, battery discharge power, load after demand response, battery charging power, and electrolyzer power at time t respectively.
[0101] Thermal network balance
[0102] H GB,h,t +H CHP,h,t +H HFC,h,t +H HST,d,t =L h,IDR,t +H HST,c,t
[0103] In the formula, H GB,h,t , H CHP,h,t , H HFC,h,t , H HST,d,t , L h,IDR,t , H HST,c,t They represent the gas boiler thermal power, cogeneration output thermal power, hydrogen fuel cell thermal power, heat storage tank output thermal power, heat load, and heat storage tank input thermal power at time t respectively.
[0104] Gas power balance
[0105] G gas,t +G GST,d,t +G MR,g,t =L g,IDR,t +G CHP,t +G GB,g,t +G GST,c,t
[0106] In the formula, G gas,t , G GST,d,t , G MR,g,t , L g,IDR,t , G CHP,t , G GB,g,t , G GST,c,tThey represent external gas purchase power, gas storage tank output gas power, methane reactor output gas power, gas load, gas boiler input gas power, gas boiler input power, and gas storage tank input gas power respectively.
[0107] Hydrogen network balance
[0108] HY EL,H,t +HY HES,c,t =HY MR,H,t +HY HFC,H,t +HY HES,d,t +HY CHP,H,t
[0109] In the formula, HY EL,H,t HY HES,c,t HY MR,H,t HY HFC,H,t HY HES,d,t HY CHP,H,t They represent the hydrogen power of the electrolyzer, the hydrogen filling power of the hydrogen storage tank, the hydrogen input power of the methane reactor, the hydrogen input power of the hydrogen fuel cell, the hydrogen discharge power of the hydrogen storage tank, and the hydrogen input power of the cogeneration.
[0110] Step 3: Construct carbon trading model and green certificate trading model
[0111] Carbon trading model
[0112] The carbon emission sources of virtual power plants mainly come from external power purchases, gas boilers and cogeneration equipment. Existing studies mostly use the baseline method to allocate system carbon emission rights. The specific model is:
[0113] E=E grid +E CHP +E GB
[0114]
[0115] Where E represents the total carbon quota of the virtual power plant; E grid 、E CHP 、E GB Represent the carbon quotas of external electricity purchase, combined heat and power, and gas boilers; ε c , ε h Represent the carbon quota coefficients for coal and gas respectively.
[0116] In addition to the above carbon emission sources, the total carbon emissions of the virtual power plant will also be generated by the methane reactor, which will absorb a portion of carbon dioxide as raw material during operation. The carbon emission model of the system is:
[0117] E C =E grid,C +E total,C -E MR,C
[0118]
[0119] P total,t =P CHP,t +P GB,t
[0120] In the formula, E C Represents the total carbon emissions of the system; E grid,C 、E total,C 、E MR,C They represent carbon emissions from external electricity purchases, carbon emissions from gas boilers and cogeneration, and carbon emissions absorbed by methane reactors; x1, y1, z1 and x2, y2, z2 represent carbon emission coefficients for coal and gas respectively; a MR,C Represents the carbon absorption coefficient of the methane reactor.
[0121] Green Certificate Trading Model
[0122] The green certificate trading mechanism works through market transactions. The number of green certificates obtained by the virtual power plant is positively correlated with the amount of renewable energy power generation used by the system. Its model is:
[0123]
[0124] Where G represents the number of green certificates obtained by the virtual power plant; P RES,t Represents the renewable energy consumption of the virtual power plant.
[0125]
[0126] In the formula, G p is the carbon quota of the virtual power plant; η e Represents the specified renewable energy power generation quota coefficient; P e,t is the total power generation of the virtual power plant.
[0127] Step 4: Construct an active time-of-use electricity price model guided by carbon emissions
[0128] The traditional time-of-use electricity price method uses a fixed time-of-use electricity price to guide the load to respond to demand, and guides the load adjustment through different prices in different time periods. Considering that the traditional time-of-use electricity price is fixed and cannot be accurately adjusted according to different source-load situations, the carbon emission factor is introduced to guide the time-of-use electricity price, forming an active time-of-use electricity price and gas price affected by carbon emissions. The specific model is as follows:
[0129] Δpr e,0,t =kE C,t
[0130] Δpr c,0,t =kE C,t
[0131]
[0132] pr e,CI,t =pr e,t +Δpr e,t
[0133] pr c,CI,t =pr c,t +Δpr c,t
[0134] Where Δpr e,0,t , Δpr c,0,t is the initial value of the time-of-use electricity price and gas price adjustment in the tth period; k is the carbon emission factor coefficient; is the average value of the initial value of the time-of-use electricity price and gas price adjustment; pr e,CI,t ,pr c,CI,t It is the adjusted time-of-use electricity and gas prices.
[0135] Step 5: Construct the virtual power plant optimization scheduling objective function and solve the optimization scheduling problem.
[0136] like Figure 3 As shown, after the above four steps, the electricity-heat-gas-hydrogen coupled virtual power plant model proposed in this embodiment has been constructed, and the demand response model, carbon trading and green certificate trading model and carbon emission-guided active time-of-use electricity price model have been introduced. The above models are all introduced into the problem solving in the form of constraints, and the objective function of optimal scheduling is constructed and solved under this constraint.
[0137] The optimization scheduling objective function is:
[0138] minC VPP =C grid +C ope +C c +C G +C IDR +C RES
[0139]
[0140] In the formula, C VPP , C grid , C ope , C c , C G , C IDR , C RES Respectively represent the total cost of the virtual power plant, external power purchase cost, total operating cost, carbon trading cost, green certificate trading cost, demand response cost and renewable energy abandonment cost; α j , β kare the operation and maintenance coefficients of the j-th energy supply equipment and the k-th energy storage equipment respectively; P j,t , P k,c,t , P k,d,t are the output power of the jth type supply equipment and the charging and discharging power of the kth type energy storage equipment respectively; C e , C h , C g are the demand response subsidy costs for electricity, gas and heat respectively; δ e P is the penalty coefficient for abandoning new energy; RES,pre,t , P RES,t They are respectively the predicted power of renewable energy and the power consumed by renewable energy.
[0141] All of the above models can be implemented based on the MATLAB platform using the GUROBI solver in the YALMIP toolbox. The solver solves based on the given data, objective function and constraints to obtain the globally optimal scheduling result.
[0142] Embodiment 2
[0143] A virtual power plant optimization dispatching system under active time-of-use electricity price, comprising:
[0144] A demand response model building module is configured to integrate different categories of load-side demand response to build a load-side integrated demand response model;
[0145] The energy coupling model building module is configured to integrate energy equipment constraints and energy network power balance, build an electricity-heat-gas-hydrogen multi-energy coupling model, and form a virtual power plant;
[0146] The trading model building module is configured to build a carbon trading model and a green certificate trading model;
[0147] A guided electricity price adjustment module is configured to introduce a carbon emission factor coefficient to guide the time-of-use electricity price, establish an active time-of-use electricity price adjustment model guided by the carbon emission factor, and calculate the carbon emissions of the virtual power plant at each moment;
[0148] The optimization scheduling module is configured to take the minimization of total cost as the optimization scheduling objective function, and to solve the load-side comprehensive demand response model, electricity-heat-gas-hydrogen multi-energy coupling model, carbon trading model, green certificate trading model and active time-of-use electricity price adjustment model with constraints to obtain the final virtual power plant optimization scheduling plan.
[0149] Those skilled in the art will appreciate that embodiments of the present invention may be provided as methods, systems, or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.
[0150] The present invention is described with reference to flowcharts and / or block diagrams of methods, devices (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0151] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0152] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0153] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made by those skilled in the art within the spirit and principle of the present invention without creative labor shall be included in the protection scope of the present invention.
Claims
1. A virtual power plant optimization scheduling method under active time-of-use electricity prices, characterized in that: The following steps are involved: Integrate different types of load-side demand response to build a load-side comprehensive demand response model; Comprehensive energy equipment constraints and energy network power balance, build an electricity-heat-gas-hydrogen multi-energy coupling model, and form a virtual power plant; Construct carbon trading model and green certificate trading model; Introduce carbon emission factor coefficients to guide time-of-use electricity prices, establish an active time-of-use electricity price adjustment model guided by carbon emission factors, and calculate the carbon emissions of virtual power plants at all times; Taking the minimum total cost as the optimization scheduling objective function; With the load-side comprehensive demand response model, electricity-heat-gas-hydrogen multi-energy coupling model, carbon trading model, green certificate trading model and active time-of-use electricity price adjustment model as constraints, the solution is obtained to obtain the final virtual power plant optimization scheduling plan.
2. The virtual power plant optimization scheduling method under active time-of-use electricity price according to claim 1 is characterized in that: The demand response model includes a price-based demand response model and an incentive-based demand response model; The price-based demand response model is used to describe the relationship between user demand and energy price through the demand price elasticity matrix for the electric load and gas load participating in the price-based demand response, and has a limit constraint on the change amount after the load response price; The incentive-based demand response model is used to indicate that when the system is at a peak load or in an emergency, users directly reduce or interrupt part of the load according to the compensation incentive strategy formulated by the operator, and has a load change limit constraint.
3. The virtual power plant optimization scheduling method under active time-of-use electricity price according to claim 1 is characterized in that: The process of constructing the electricity-heat-gas-hydrogen multi-energy coupling model includes: determining external power purchase, gas purchase constraints, new energy output and load constraints, constructing a single energy conversion equipment model and a gas-hydrogen mixed heat and power cogeneration model; Added electricity network balance, thermal network balance, gas power balance and hydrogen network balance.
4. The virtual power plant optimization scheduling method under active time-of-use electricity price according to claim 1 is characterized in that: The process of building a carbon trading model includes using the baseline method to allocate system carbon emission rights and building a carbon emission model.
5. The virtual power plant optimization scheduling method under active time-of-use electricity price according to claim 1 is characterized in that: The process of building a green certificate trading model includes establishing a positive correlation between the number of green certificates obtained by the virtual power plant and the amount of renewable energy electricity generated by the system, and determining a positive correlation between the carbon quota of the virtual power plant and the amount of renewable energy electricity generated by the system.
6. The virtual power plant optimization scheduling method under active time-of-use electricity price according to claim 1 is characterized in that: The process of establishing an active time-of-use electricity price adjustment model guided by a carbon emission factor includes: adding a carbon emission factor coefficient when constructing the time-of-use electricity price and the initial value of the gas price adjustment, and using the carbon emission factor coefficient as the calculation coefficient.
7. The virtual power plant optimization scheduling method under active time-of-use electricity price according to claim 1 is characterized in that: The total cost includes the total cost of the virtual power plant, external power purchase cost, total operating cost, as well as carbon trading cost, green certificate trading cost, demand response cost and abandoned renewable energy cost.
8. A virtual power plant optimization dispatching system under active time-of-use electricity price, characterized by: include: A demand response model building module is configured to integrate different categories of load-side demand response to build a load-side integrated demand response model; The energy coupling model building module is configured to integrate energy equipment constraints and energy network power balance, build an electricity-heat-gas-hydrogen multi-energy coupling model, and form a virtual power plant; The trading model building module is configured to build a carbon trading model and a green certificate trading model; A guided electricity price adjustment module is configured to introduce a carbon emission factor coefficient to guide the time-of-use electricity price, establish an active time-of-use electricity price adjustment model guided by the carbon emission factor, and calculate the carbon emissions of the virtual power plant at each moment; The optimization scheduling module is configured to take the minimization of total cost as the optimization scheduling objective function, and to solve the load-side comprehensive demand response model, electricity-heat-gas-hydrogen multi-energy coupling model, carbon trading model, green certificate trading model and active time-of-use electricity price adjustment model with constraints to obtain the final virtual power plant optimization scheduling plan.
9. A computer-readable storage medium, characterized in that: Used to store computer instructions, which, when executed by a processor, complete the steps of the method according to any one of claims 1 to 7.
10. An electronic device, characterized in that: The method comprises a memory and a processor, and computer instructions stored in the memory and executed on the processor, wherein when the computer instructions are executed by the processor, the steps in the method according to any one of claims 1 to 7 are completed.
Citation Information
Cited By
Virtual power plant time-of-use electricity price dynamic optimization method and system
CN120746212A
Virtual power plant double-layer optimization scheduling method and system, storage medium and electronic equipment
CN122475313A