Sealing installation structure and method for high-voltage bushing of oil-immersed transformer

By designing a combined structure of flange and sealing groove in an oil-immersed transformer, the problem of oil leakage caused by aging of seals is solved, and a stable seal between the sleeve and the box cover is achieved, which reduces maintenance costs.

CN119092253APending Publication Date: 2024-12-06GUANGZHOU POWER SUPPLY BUREAU GUANGDONG POWER GRID CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411401915.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-09
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The existing high-pressure sleeve installation method causes the seal to age, easily leak oil, and increase maintenance costs.

Method used

A high-voltage sleeve sealing installation structure of oil-immersed transformer is designed. By fixing the flange on the sleeve body, and a sealing groove and a sealing ring are provided between the flange and the transformer box cover, the locking assembly is used to adjust the method. The orchid piece is tightened to the box cover to form a clamped and extruded sealing connection to protect the sealing ring and avoid oil leakage.

Benefits of technology

Effectively protect the sealing ring, prevent aging, ensure the sealing between the sleeve and the box cover, reduce maintenance costs, and improve the reliability and service life of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119092253A_ABST
    Figure CN119092253A_ABST
Patent Text Reader

Abstract

The invention discloses a sealing installation structure and method for a high-voltage bushing of an oil-immersed transformer, and relates to the technical field of transformers, and the sealing installation structure for the high-voltage bushing comprises a bushing body, a transformer box cover, a locking assembly and a sealing ring; a flange piece is fixed on the sleeve body; an avoiding through hole penetrating through the transformer box cover and allowing the bottom end of the sleeve body to penetrate through is formed in the center of the front surface of the transformer box cover; the flange piece is located on the front face of the transformer box cover and is fastened to the transformer box cover through the locking assembly. A sealing groove surrounding the avoiding through hole is formed in the front face of the transformer box cover and / or the face, facing the transformer box cover, of the flange piece. And the sealing ring is arranged in the sealing groove and is clamped and extruded by the flange piece and the transformer box cover. Due to the fact that the sealing ring is arranged in the sealing groove, leakage of the sealing ring can be avoided, a certain protection effect on the sealing ring is achieved, the situation that the sealing ring is prone to aging is avoided, it is guaranteed that oil is not leaked between the sleeve body and the transformer box cover, and the maintenance cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of transformers, and in particular to a sealing installation structure and method for a high-voltage bushing of an oil-immersed transformer. Background Art

[0002] The high-voltage bushing is an important component in the transformer equipment. Currently, there are two installation methods between the high-voltage bushing and the transformer cover on the market: internal installation and external installation.

[0003] Among them, the internal installation method is to install the pressure plate inside the transformer (that is, on the back of the transformer box cover); specifically, a spring is connected between the internal pressure plate and the high-voltage bushing, and then a bolt threaded through the pressure plate is pressed against the back of the transformer box cover to tighten the spring, thereby fixing the high-voltage bushing.

[0004] The external installation method is to fix the pressing sheet or pressure plate to the outside of the transformer (i.e., installed on the front of the transformer box cover) using a pressing foot. Specifically, the pressing sheet or pressure plate presses the bottom of the high-voltage bushing, and then the pressing sheet or pressure plate is fixed by tightening the pressing foot to fix the high-voltage bushing.

[0005] However, after research, it was found that whether it is an internal or external installation method, the seals are lacking in protection, which can easily cause the seals to age, and then leak oil, increasing maintenance costs. Therefore, it is urgent to propose a new solution to solve the above problems. Summary of the invention

[0006] In view of this, the purpose of this application is to provide a sealing installation structure and method for a high-voltage bushing of an oil-immersed transformer, so as to solve the technical problem that the sealing parts of the existing internal or external installation methods are prone to aging, thereby causing oil leakage and increasing maintenance costs.

[0007] In order to achieve the above technical purpose, the present application provides a sealing installation structure of a high-voltage bushing of an oil-immersed transformer, comprising a bushing body, a transformer box cover, a locking assembly and a sealing ring;

[0008] A flange is fixed on the sleeve body;

[0009] The center of the front face of the transformer box cover is provided with an avoidance through hole which penetrates the transformer box cover and allows the bottom end of the bushing body to pass through;

[0010] The flange is located on the front side of the transformer cover and is fastened to the transformer cover through the locking assembly;

[0011] A sealing groove surrounding the avoidance through hole is provided on the front side of the transformer case cover and / or on a side of the flange member facing the transformer case cover;

[0012] The sealing ring is installed in the sealing groove and is clamped and squeezed by the flange and the transformer box cover.

[0013] Further, the locking assembly includes a plurality of mounting rods and a plurality of fasteners;

[0014] The flange is provided with a plurality of mounting through holes distributed circumferentially around the central axis of the sleeve body;

[0015] A plurality of mounting rods are fixed on the transformer box cover and pass through the mounting through holes in a one-to-one correspondence;

[0016] A fastener capable of contacting and abutting against the flange is installed on the rod section of the mounting through hole through which each mounting rod passes, so as to fasten the flange and the transformer box cover together.

[0017] Further, the mounting rod is a screw rod;

[0018] The fastener nut.

[0019] Furthermore, a gasket is provided between the fastener and the flange.

[0020] Furthermore, the mounting rod is fixed to the transformer box cover by welding.

[0021] Furthermore, the flange is made of aluminum material.

[0022] Furthermore, there are at least four mounting through holes, which are evenly distributed around the circumference;

[0023] There are at least four mounting rods corresponding to the mounting through holes one by one.

[0024] The present application also discloses a method for sealing and installing a high-voltage bushing of an oil-immersed transformer, which is applied to the sealing and installing structure of the high-voltage bushing of an oil-immersed transformer, and comprises the following steps:

[0025] A flange is fixed on the bushing body, wherein a sealing groove is provided on a side of the flange facing the transformer box cover and / or on the front side of the transformer box cover;

[0026] A sealing ring is arranged in the sealing groove;

[0027] The flange and the transformer box cover are fastened together by a locking assembly, wherein the fastened flange and the transformer box cover clamp and squeeze the sealing ring.

[0028] It can be seen from the above technical solutions that the sealing installation structure of the oil-immersed transformer high-voltage bushing designed in the present application is to open a sealing groove on the side of the flange fixed on the bushing body facing the transformer box cover, and then set a sealing ring in the sealing groove. When the flange and the transformer box cover are pressed together, the sealing ring can be squeezed to achieve a sealed connection effect. Since the sealing ring is set in the sealing groove, it can prevent the sealing ring from leaking out, play a certain protective role on the sealing ring, and thus prevent the sealing ring from aging easily, ensure that there is no oil leakage between the bushing body and the transformer box cover, and reduce maintenance costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0030] Figure 1 This is a front view of a sealing installation structure for a high-voltage bushing of an oil-immersed transformer provided in the present application;

[0031] Figure 2 A partial cross-sectional view of the flange of a sealing installation structure for a high-voltage bushing of an oil-immersed transformer provided in the present application and the matching of the transformer box cover;

[0032] Figure 3 A partial cross-sectional view of the cooperation between the sealing groove and the sealing ring of a sealing installation structure for a high-voltage bushing of an oil-immersed transformer provided in the present application;

[0033] Figure 4 A schematic diagram of a process for sealing and installing a high-voltage bushing of an oil-immersed transformer provided in this application;

[0034] In the figure: 1. bushing body; 11. porcelain bottle; 12. conductive rod; 2. transformer box cover; 21. avoidance through hole; 3. flange; 31. sealing groove; 32. installation through hole; 4. installation rod; 5. fastener; 6. gasket; 7. sealing ring. DETAILED DESCRIPTION

[0035] The technical solutions of the embodiments of the present application will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the present application, not all of them. All other embodiments obtained by ordinary technicians in this field without creative work based on the embodiments in the embodiments of the present application are within the scope of protection of the embodiments of the present application.

[0036] In the description of the embodiments of the present application, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, which are only for the convenience of describing the embodiments of the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the embodiments of the present application. In addition, the terms "first", "second", and "third" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.

[0037] In the description of the embodiments of the present application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a replaceable connection, or an integral connection, it can be a mechanical connection, it can be an electrical connection, it can be a direct connection, it can be indirectly connected through an intermediate medium, and it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the embodiments of the present application can be understood according to specific circumstances.

[0038] The embodiment of the present application discloses a sealing installation structure and method for a high-voltage bushing of an oil-immersed transformer.

[0039] See also Figure 1 An embodiment of a sealing installation structure for a high-voltage bushing of an oil-immersed transformer provided in an embodiment of the present application includes:

[0040] Bushing body 1, transformer box cover 2, locking assembly and sealing ring 7. The front center of the transformer box cover 2 is provided with an avoidance through hole 21 penetrating through the transformer box cover and allowing the bottom end of the bushing body 1 to pass through; the main structure of the bushing body 1 is an existing design structure, for example, including a porcelain bottle 11 and a conductive rod 12, etc., which will not be described in detail.

[0041] A flange 3 is fixed on the bushing body 1, and the flange 3 is fixed to the outer periphery of the bushing body 1 (the bushing body 1 and the flange 3 are fixed by epoxy resin). The flange 3 is located on the front of the transformer box cover 2 and is fastened to the transformer box cover 2 by a locking assembly.

[0042] A sealing groove 31 is provided on the front of the transformer cover 2 and / or on the side of the flange 3 facing the transformer cover 2, and is arranged around the avoidance through hole 21; the sealing ring 7 is installed in the sealing groove 31, and is clamped and squeezed by the flange 3 and the transformer cover 2. Since the thickness of the transformer cover 2 is not very large, it is preferred to provide the sealing groove 31 on the flange 3, and there is no specific limitation.

[0043] The sealing installation structure of the oil-immersed transformer high-voltage bushing designed in the present application is provided with a sealing groove 31 on the side of the flange 3 fixed on the bushing body 1 facing the transformer box cover 2, and then a sealing ring 7 is arranged in the sealing groove 31. When the flange 3 and the transformer box cover 2 are pressed together, the sealing ring 7 can be squeezed to achieve a sealed connection effect. Since the sealing ring 7 is arranged in the sealing groove 31, it can prevent the sealing ring 7 from leaking out, play a certain protective role on the sealing ring 7, and thus prevent the sealing ring 7 from being easily aged, ensure that there is no oil leakage between the bushing body 1 and the transformer box cover 2, and reduce the maintenance cost.

[0044] The above is an embodiment of the present invention provided by the embodiment of the oil-immersed transformer high-voltage bushing sealing installation structure of the first embodiment, the following is an embodiment of the present invention provided by the embodiment of the oil-immersed transformer high-voltage bushing sealing installation structure of the second embodiment, please refer to the specific Figures 1 to 3 .

[0045] Based on the solution of the above embodiment 1:

[0046] Furthermore, for the design of the locking assembly, it includes multiple mounting rods 4 and multiple fasteners 5; the flange 3 is provided with multiple mounting through holes 32 distributed circumferentially around the central axis of the bushing body 1 (the mounting through holes 32 are located outside the sealing groove 31 to avoid interference with the sealing effect); multiple mounting rods 4 are fixed on the transformer box cover 2, and pass through the mounting through holes 32 one by one; the rod sections of the mounting through holes 32 passed by each mounting rod 4 are all equipped with fasteners 5 that can contact with the flange 3, which are used to fasten the flange 3 and the transformer box cover 2 together. By fixing the flange 3 with multiple mounting through holes 32 on the bushing body 1, and then installing the fasteners 5 on the rod sections of the flange 3 passing through the mounting through holes 32, the fasteners 5 are pressed together by the flange 3 and the transformer box cover 2. This method of directly fixing the flange 3 with the mounting rods 4 on the transformer box cover 2 is convenient to install and effectively improves the installation efficiency. Of course, the installation through hole 32 may not be provided, and the installation may be located outside the flange 3. The fastener 5 fixed on the flange 3 may directly press against the edge of the flange 3 to fasten the flange 3 and the transformer box cover 2 together without limitation.

[0047] Furthermore, the mounting rod 4 is preferably a screw rod, and correspondingly, the fastener 5 is a nut. This design can tightly press the flange 3 and the transformer cover 2 together by virtue of the effect of the thread simply by turning the fastener 5, i.e., the nut. This connection method has significant characteristics, and its operation process is simple and clear, without the need for complex tools and cumbersome steps, which can greatly improve work efficiency. Moreover, it is extremely convenient in installation and disassembly. When equipment maintenance or replacement of parts is required, the flange 3 can be quickly separated or reassembled from the transformer cover 2, saving a lot of time and labor costs for engineering construction and equipment maintenance.

[0048] Furthermore, a gasket 6 is provided between the fastener 5 and the flange 3. The gasket 6 can provide a certain degree of protection for the flange 3 and increase the stability of the fastening. During the fastening process, the gasket 6 can effectively buffer the pressure and friction between the fastener 5 and the flange 3, and prevent the surface of the flange 3 from being excessively worn or scratched due to direct contact, thereby extending the service life of the flange 3 and ensuring the stable performance of its performance. At the same time, the presence of the gasket 6 can also significantly increase the stability of the fastening. It can fill the tiny gap between the fastener 5 and the flange 3, making the contact between the two closer and more uniform, thereby dispersing the fastening force and improving the stability and reliability of the entire connection structure.

[0049] Furthermore, the mounting rod 4 can be welded and fixed to the transformer cover 2, so that the mounting rod 4 and the transformer cover 2 are directly and firmly fixed together to form a stable overall structure. The advantage of this connection method is that it can ensure that the connection strength between the mounting rod 4 and the transformer cover 2 is extremely high, and it can remain stable in the face of various external forces and complex working environments, and it is not easy to loosen or separate, providing a solid guarantee for the overall stability of the equipment.

[0050] Of course, the mounting rod 4 is formed on the transformer box cover 2 by integral casting, and there is no limitation thereto.

[0051] Furthermore, in order to ensure sufficient connection strength, the flange 3 is made of metal materials such as aluminum, and its thickness can be greater than 18 mm, without specific limitation.

[0052] Furthermore, in order to improve the stability of the connection, there are at least four mounting holes 32, which are evenly distributed around the circumference; there are at least four mounting rods 4, which correspond one to one with the mounting holes 32. The specific number can be changed and designed according to actual needs, and there is no limitation.

[0053] The present application also discloses a method for sealing and installing a high-voltage bushing of an oil-immersed transformer, which is applied to the above-designed sealing and installing structure of a high-voltage bushing of an oil-immersed transformer, and comprises the following steps:

[0054] S1, fixing a flange 3 on the bushing body 1, wherein a sealing groove is provided on a side of the flange 3 facing the transformer cover 2 and / or on the front side of the transformer cover 2;

[0055] S2, setting a sealing ring 7 in the sealing groove;

[0056] S3, fasten the flange 3 and the transformer cover 2 together through a locking assembly, wherein the fastened flange 3 and the transformer cover 2 clamp and squeeze the sealing ring 7.

[0057] The above is a detailed introduction to the sealing installation structure and method of the high-voltage bushing of an oil-immersed transformer provided in the present application. For a person skilled in the art, according to the idea of ​​the embodiments of the present application, there may be changes in the specific implementation method and application scope. In summary, the content of this specification should not be understood as a limitation on the present application.

Claims

1. A sealing installation structure for a high-voltage bushing of an oil-immersed transformer, characterized in that: It comprises a bushing body (1), a transformer box cover (2), a locking assembly and a sealing ring (7); A flange (3) is fixed on the sleeve body (1); The transformer box cover (2) is provided at the center of its front face with an avoidance through hole (21) penetrating the transformer box cover and allowing the bottom end of the bushing body (1) to pass through; The flange (3) is located on the front side of the transformer box cover (2) and is fastened together with the transformer box cover (2) via the locking assembly; A sealing groove (31) arranged around the avoidance through hole (21) is provided on the front side of the transformer case cover (2) and / or on a side of the flange (3) facing the transformer case cover (2); The sealing ring (7) is installed in the sealing groove (31) and is clamped and squeezed by the flange (3) and the transformer box cover (2).

2. The sealing and mounting structure of the high-voltage bushing of an oil-immersed transformer according to claim 1 is characterized in that: The locking assembly comprises a plurality of mounting rods (4) and a plurality of fasteners (5); The flange (3) is provided with a plurality of mounting through holes (32) distributed circumferentially around the central axis of the sleeve body (1); A plurality of mounting rods (4) are fixed on the transformer box cover (2) and pass through the mounting through holes (32) in a one-to-one correspondence; A fastener (5) capable of contacting and abutting against the flange member (3) is installed on the rod section of the mounting through hole (32) through which each mounting rod (4) passes, and is used to fasten the flange member (3) and the transformer box cover (2) together.

3. The sealing and mounting structure of the high-voltage bushing of an oil-immersed transformer according to claim 2 is characterized in that: The mounting rod (4) is a screw rod; The fastener (5) is a nut.

4. The sealing and mounting structure of the high-voltage bushing of an oil-immersed transformer according to claim 2 is characterized in that: A gasket (6) is also provided between the fastener (5) and the flange (3).

5. The sealing and mounting structure of the high-voltage bushing of an oil-immersed transformer according to claim 3 is characterized in that: The mounting rod (4) is fixed to the transformer box cover (2) by welding.

6. The sealing and mounting structure of the high-voltage bushing of an oil-immersed transformer according to claim 1, characterized in that: The flange (3) is made of aluminum material.

7. The sealing and mounting structure of the high-voltage bushing of an oil-immersed transformer according to claim 4 is characterized in that: There are at least four mounting through holes (32) which are evenly distributed around the circumference; There are at least four mounting rods (4), corresponding one to one with the mounting through holes (32).

8. A sealing and installation method for a high-voltage bushing of an oil-immersed transformer, characterized in that: The sealing installation structure for high-voltage bushing of an oil-immersed transformer as claimed in any one of claims 1 to 7 comprises the following steps: A flange member (3) is fixed on the bushing body (1), wherein a sealing groove is provided on a side of the flange member (3) facing the transformer box cover (2) and / or on a front side of the transformer box cover (2); A sealing ring (7) is arranged in the sealing groove; The flange member (3) and the transformer box cover (2) are fastened together by a locking assembly, wherein the fastened flange member (3) and the transformer box cover (2) clamp and squeeze the sealing ring (7).