Hoisting equipment for construction of high-altitude special-shaped beam sleeve
By adding tool hangers, tool box seats and rotary lighting to the construction and lifting equipment of high-altitude special-shaped beam sleeves, the problems of tool drop and low-light environment are solved, the operation safety and efficiency are improved, and the tool life is extended And reduce the risk of accidents.
Patent Information
- Application Number
- CN202411477212.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-22
- Publication Date
- 2024-12-10
AI Technical Summary
The existing high-altitude special-shaped beam sleeve construction and hoisting equipment lacks tool hangers, which leads to tools being easily dropped during operation and causing safety accidents.
A protective structure with tool hanger is designed, including base plate, connecting column, side plate, front plate and tool hanger, ensuring that the tool has a fixed storage position during operation, and providing a seat with tool box Structure and rotary lighting with warning lights.
It improves the safety and efficiency of operations, reduces errors and interruptions caused by tool loss and messy environments, extends the service life of the tool, and provides all-round lighting in low-light environments, reducing the probability of safety accidents.
Smart Images

Figure CN119100277A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of high-altitude special-shaped beam sleeve construction and hoisting, and specifically relates to high-altitude special-shaped beam sleeve construction and hoisting equipment. Background Art
[0002] High-altitude special-shaped beam sleeve construction hoisting equipment is a professional equipment specially used for hoisting special-shaped beam sleeves in high-altitude environments. It is usually powered by a lifting device, which may include a crane. The hoisting system, such as hooks and slings, is responsible for connecting the special-shaped beam sleeves and ensuring their safety and stability during the hoisting process. The control system is used to operate the various actions of the equipment and ensure safe operation. The equipment can adapt to the special environmental requirements of high-altitude operations, and hoist the special-shaped beam sleeves to the designated position efficiently and accurately to meet the needs of high-altitude special-shaped beam sleeve installation in the fields of construction.
[0003] In the high-altitude special-shaped beam sleeve construction hoisting equipment under the existing technology, there is no tool hanger in the protective structure. The tools may be placed on the equipment at will or held by the operator. During the operation, it is easy to fall due to shaking, operating errors, etc., which will injure personnel and equipment, thereby causing serious safety accidents. Summary of the invention
[0004] The purpose of the present invention is to provide a high-altitude special-shaped beam sleeve construction hoisting device in order to solve the above-mentioned safety problem.
[0005] The technical solution adopted by the present invention is as follows: a high-altitude special-shaped beam sleeve construction hoisting equipment, including a base plate, a plurality of connecting columns are fixedly connected to the upper surface of the base plate, a side plate is fixedly connected to one side of the connecting column, a front plate is fixedly connected to one side of the connecting column, a plurality of tool hangers are fixedly connected to one side of the front plate, and a top plate is fixedly connected to one end of the connecting column relative to the base plate.
[0006] By adopting the above technical scheme, a protective structure with a tool hanger is added to a high-altitude special-shaped beam sleeve construction hoisting equipment, in which the bottom plate provides a convenient place for operators to store and access tools. For complex operations such as special-shaped beam sleeve construction hoisting at high altitude, any small accident may lead to serious consequences. With a solid protective structure, the safety of the operation can be greatly improved. The tool hanger can ensure that the tools have a fixed storage position during the operation to prevent the tools from being placed randomly and accidentally falling. The tool hanger allows operators to access tools at any time, which improves work efficiency while reducing distractions and safety hazards caused by looking for tools. When performing hoisting operations, operators can quickly obtain the required tools from the tool hanger without spending time looking for tools around. This greatly saves operation time and improves work efficiency. Especially in emergency situations, being able to quickly get the right tools for processing is crucial to ensuring construction progress and safety. With the tool hanger, tools can be neatly hung in designated locations to avoid clutter at the work site. A clean working environment helps operators focus on their work and reduces errors and mistakes caused by a cluttered environment. It also makes it easier to count and organize tools after the job is done to ensure that they are not lost. Tools hung on protective structures can prevent them from directly contacting the ground or being hit and worn by other objects. This helps extend the service life of tools and reduces the cost of tool replacement. At the same time, it also reduces interruptions to operations caused by tool damage and improves the overall reliability of the equipment.
[0007] In a preferred embodiment, a seat base is fixedly connected to the upper surface of the base plate, a toolbox is slidably connected to one side of the toolbox, a toolbox handle is fixedly connected to one side of the toolbox, a seat cushion is fixedly connected to one end of the seat base relative to the base plate, and a headrest is provided on one end of the seat cushion relative to the seat base.
[0008] By adopting the above technical solution, a seat structure with a toolbox is added to a high-altitude special-shaped beam sleeve construction hoisting equipment. The operator can slide the toolbox by holding the toolbox handle. Operators often need to use various tools when performing high-altitude special-shaped beam sleeve construction hoisting operations. With a seat with a toolbox, the tools can be neatly stored in the toolbox, and the operator does not need to leave the work position to find the tools, which greatly saves time and improves work efficiency. Long-term work will make the operator feel tired. With a seat, the operator can sit down when he needs to rest and relieve physical fatigue. This not only helps to improve the operator's work efficiency, but also reduces operational errors caused by fatigue. The existence of the seat allows the operator to take a short break between work, restore physical strength, and better devote himself to subsequent work. For example, when performing fine adjustments or installation work, the operator can sit on the seat and operate more attentively, reducing errors caused by body shaking.
[0009] In a preferred embodiment, an operating table is fixedly connected to the upper surface of the base plate, and a control panel is disposed on one side of the operating table.
[0010] By adopting the above technical solutions, the operating console is the main part for operators to control and operate the equipment. The operating console will be equipped with various control buttons, switches, instruments and other equipment, through which operators can start, stop, lift, rotate and other operations on the hoisting equipment. The control panel is the core control part of the hoisting equipment, which integrates various electronic control components and sensors to achieve precise control and monitoring of the equipment.
[0011] In a preferred embodiment, a plurality of support plates are fixedly connected to the upper surface of the base plate.
[0012] By adopting the above technical solution, the support plate mainly plays the role of supporting and fixing other components. In the lifting equipment, the support plate can ensure the stable and firm position of these lifting equipment. The support plate is made of solid metal material with good strength and rigidity to ensure that it can provide sufficient support force.
[0013] In a preferred embodiment, a support column is fixedly connected to one end of the support plate relative to the bottom plate, and a plurality of support rods are fixedly connected to the outer side of the lower end of the support column.
[0014] By adopting the above technical solution, the support column provides a stable support force for the equipment. The support column is usually made of high-strength steel with good compression and bending resistance to ensure that the equipment will not tilt or shake during the lifting operation. The support rod plays a role of auxiliary support and reinforcement in the equipment. It can be used in conjunction with support columns, support plates and other structures to enhance the overall strength and stability of the equipment.
[0015] In a preferred embodiment, a grooved sliding track is fixedly connected to one end of the support column relative to the support plate, and a sliding motor is slidably connected to the inner side of the upper surface of the grooved sliding track via a pulley.
[0016] By adopting the above technical solution, the grooved sliding track provides guidance and support for the moving parts of the lifting equipment. In the construction and lifting operation of the high-altitude special-shaped beam sleeve, it may be necessary to move the lifting equipment horizontally. The grooved sliding track can ensure that the moving parts move according to the predetermined trajectory, improving the operating accuracy and stability of the equipment. The sliding motor provides power for the moving parts of the lifting equipment. On the grooved sliding track, the sliding motor can drive the moving parts to move horizontally, realizing the position adjustment of the equipment and the expansion of the operating range.
[0017] In a preferred embodiment, a sliding frame is provided on one side of the sliding motor, and a plurality of adsorption pulleys are provided on both sides of the sliding frame.
[0018] By adopting the above technical solution, the sliding frame is a moving part installed on the grooved sliding track, which is used in conjunction with the sliding motor to achieve the position adjustment of the lifting equipment. The adsorption pulley plays a role in reducing friction and improving the moving efficiency in the lifting equipment. It is usually installed on the sliding frame and contacts the grooved sliding track. The surface of the adsorption pulley is usually made of special materials with good adsorption performance and wear resistance. During the movement process, the adsorption pulley can reduce the friction resistance between the moving part and the track by adsorbing on the sliding track, thereby improving the operation efficiency of the equipment.
[0019] In a preferred embodiment, a connecting block is provided on one side of the adsorption pulley, and a hoist casing is provided at the lower end of the connecting block.
[0020] By adopting the above technical solution, the connecting block connects the adsorption pulley and the crane housing, which ensures the stability of the overall structure. The crane housing provides protection for the internal structure of the crane. In an aerial working environment, the crane housing can prevent external objects from causing damage to the motor, rope turns and other components inside the crane.
[0021] In a preferred embodiment, a rope turn is provided on the inner side of the hoist housing, a hoist motor is provided on one side of the hoist housing, a movable pulley is also provided at one end of the hoist motor, and a hook is provided at the lower end of the movable pulley.
[0022] By adopting the above technical solution, the hoist motor is the core power component of the hoisting equipment, which provides power for the operation of the hoist. The rope turn is a component of the hoist used to wind the wire rope. During the hoisting operation, the wire rope is connected to the hoist motor through the rope turn to realize the lifting and lowering of the special-shaped beam sleeve. The movable pulley plays a labor-saving role in the hoisting equipment. It is used in conjunction with the hook, wire rope and other components to realize the lifting of the special-shaped beam sleeve by changing the direction and magnitude of the force. The hook is a component of the hoisting equipment used to connect the special-shaped beam sleeve. It is usually made of high-strength metal material with good tensile and bending resistance to ensure that the special-shaped beam sleeve can be safely connected and lifted.
[0023] In a preferred embodiment, a connecting rod is provided on the upper surface of the sliding frame, a rotating motor is provided on the upper end of the connecting rod, a rotating block is rotatably connected to the upper end of the rotating motor, a plurality of lighting lamps are rotatably connected to the outer side of the rotating block, and a warning light is fixedly connected to the upper end of the rotating block.
[0024] By adopting the above technical scheme, a rotating lighting structure with a warning light is added to a high-altitude special-shaped beam sleeve construction hoisting equipment, wherein the rotating motor can provide the power required for the rotating block to rotate. In the high-altitude special-shaped beam sleeve construction environment, the light conditions may be poor, especially at night or in dim weather conditions. The rotating lighting can provide all-round lighting to ensure that the construction area is clearly visible. This helps operators to accurately judge the position, state and surrounding environment of the special-shaped beam sleeve, and reduce operational errors and safety accidents caused by unclear vision. For example, when performing hoisting operations at night, the rotating lighting can illuminate the entire operating area, allowing operators to clearly see the connection between the hook and the special-shaped beam sleeve, ensuring the safety and stability of the hoisting process. The structure with a warning light can attract people's attention at a long distance, reminding the surrounding personnel to pay attention to the high-altitude working area and avoid entering the dangerous area by mistake. The flashing of the warning light can effectively convey danger information, keep the surrounding personnel alert and stay away from the construction area, thereby reducing the probability of accidents. For example, when there are other workers or pedestrians around the construction site, the warning lights can serve as an obvious warning, preventing them from approaching the area where lifting operations are being carried out, thereby ensuring their personal safety.
[0025] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:
[0026] 1. In the present invention, a protective structure with a tool hanger is added to a high-altitude special-shaped beam sleeve construction hoisting equipment, wherein the bottom plate provides a convenient place for operators to store and take tools. For the complex operation of special-shaped beam sleeve construction hoisting at high altitude, any small accident may lead to serious consequences. With a solid protective structure, the safety of the operation can be greatly improved. The tool hanger can ensure that the tools have a fixed storage position during the operation, and avoid the tools from being placed randomly and accidentally falling. The tool hanger allows operators to take tools at any time, improves work efficiency, and also reduces distractions and safety hazards caused by looking for tools. When performing hoisting operations, operators can quickly obtain the required tools from the tool hanger without spending time looking for tools around. This greatly saves operation time and improves work efficiency. Especially in an emergency, being able to quickly get the right tools for processing is crucial to ensuring construction progress and safety. With a tool hanger, tools can be neatly hung in designated locations, avoiding the mess at the work site. A clean working environment helps operators focus on their work and reduces errors and mistakes caused by a cluttered environment. It also makes it easier to count and organize tools after the job is done to ensure that they are not lost. Tools hung on protective structures can prevent them from directly contacting the ground or being hit and worn by other objects. This helps extend the service life of tools and reduces the cost of tool replacement. At the same time, it also reduces interruptions to operations caused by tool damage and improves the overall reliability of the equipment.
[0027] 2. In the present invention, a seat structure with a toolbox is added to a high-altitude special-shaped beam sleeve construction hoisting equipment. The operator can slide the toolbox by holding the toolbox handle. When the operator is performing the high-altitude special-shaped beam sleeve construction hoisting operation, various tools are often needed. With a seat with a toolbox, the tools can be neatly stored in the toolbox, and the operator does not need to leave the work position to find the tools, which greatly saves time and improves work efficiency. Long-term work will make the operator feel tired. With a seat, the operator can sit down when he needs to rest to relieve physical fatigue. This not only helps to improve the work efficiency of the operator, but also reduces operational errors caused by fatigue. The existence of the seat allows the operator to take a short break between work, restore physical strength, and better devote himself to subsequent work. For example, when performing fine adjustments or installation work, the operator can sit on the seat and operate more attentively to reduce errors caused by body shaking.
[0028] 3. In the present invention, a rotating lighting structure with a warning light is added to a high-altitude special-shaped beam sleeve construction hoisting equipment, wherein the rotating motor can provide the power required for the rotating block to rotate. In the high-altitude special-shaped beam sleeve construction environment, the light conditions may be poor, especially at night or in dim weather conditions. The rotating lighting can provide all-round lighting to ensure that the construction area is clearly visible. This helps operators to accurately judge the position, state and surrounding environment of the special-shaped beam sleeve, and reduce operational errors and safety accidents caused by unclear vision. For example, when performing hoisting operations at night, the rotating lighting can illuminate the entire operating area, allowing operators to clearly see the connection between the hook and the special-shaped beam sleeve, ensuring the safety and stability of the hoisting process. The structure with a warning light can attract people's attention at a long distance, reminding the surrounding personnel to pay attention to the high-altitude working area and avoid entering the dangerous area by mistake. The flashing of the warning light can effectively convey danger information, keep the surrounding personnel alert and stay away from the construction area, thereby reducing the probability of accidents. For example, when there are other workers or pedestrians around the construction site, the warning lights can serve as an obvious warning, preventing them from approaching the area where lifting operations are being carried out, thereby ensuring their personal safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0030] Figure 2 It is a schematic diagram of the protection structure in the present invention;
[0031] Figure 3 It is a schematic diagram of the operating table and seat structure of the present invention;
[0032] Figure 4 It is a schematic diagram of the hoisting structure in the present invention;
[0033] Figure 5 It is a schematic diagram of the structure of the crane in the present invention.
[0034] Figure 6 It is a schematic diagram of the structure of the rotating lighting lamp in the present invention.
[0035] Markings in the figure: 1-bottom plate, 2-connecting column, 3-side plate, 4-front plate, 5-tool hanger, 6-top plate, 7-seat base, 8-tool box, 9-tool box handle, 10-seat cushion, 11-headrest, 12-operating table, 13-control panel, 14-support plate, 15-support column, 16-support rod, 17-slotted sliding track, 18-sliding motor, 19-sliding frame, 20-adsorption pulley, 21-connecting block, 22-hoisting machine housing, 23-hoisting machine motor, 24-rope turn, 25-movable pulley, 26-hook, 27-connecting rod, 28-rotating motor, 29-rotating block, 30-lighting lamp, 31-warning lamp. DETAILED DESCRIPTION
[0036] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0037] Reference Figure 1-6 ,
[0038] Reference Figure 1-2, a plurality of connecting columns 2 are fixedly connected to the upper surface of the bottom plate 1, a side plate 3 is fixedly connected to one side of the connecting column 2, a front plate 4 is fixedly connected to one side of the connecting column 2, a plurality of tool hangers 5 are fixedly connected to one side of the front plate 4, and a top plate 6 is fixedly connected to one end of the connecting column 2 relative to the bottom plate 1. A protective structure with a tool hanger is added to a high-altitude special-shaped beam sleeve construction and hoisting equipment, wherein the bottom plate 1 provides a convenient place for operators to store and take tools. For complex operations such as special-shaped beam sleeve construction and hoisting at high altitudes, any small accident may cause serious consequences. With a solid protective structure, the safety of the operation can be greatly improved. The tool hanger can ensure that the tools have a fixed storage position during the operation process to prevent the tools from being placed randomly and accidentally falling. The tool hanger allows operators to take tools at any time, improves work efficiency, and reduces distractions and safety hazards caused by looking for tools. When performing hoisting operations, operators can quickly obtain the required tools from the tool hanger without spending time looking for tools around. This greatly saves operation time and improves work efficiency. Especially in emergency situations, being able to quickly get the right tools to handle is crucial to ensuring construction progress and safety. With tool hangers, tools can be neatly hung in designated locations, avoiding clutter on the job site. A neat working environment helps operators focus more on their work and reduces errors and mistakes caused by a messy environment. It also makes it easier to count and organize tools after the job is completed to ensure that the tools are not lost. Hanging tools on protective structures can prevent tools from directly contacting the ground or being hit and worn by other objects. This helps to extend the service life of the tools and reduce the cost of tool replacement. At the same time, it also reduces work interruptions caused by tool damage and improves the overall reliability of the equipment.
[0039] Reference Figure 1 , Figure 3The upper surface of the base plate 1 is fixedly connected with a seat base 7, one side of the tool box 8 is slidably connected with the tool box 8, one side of the tool box 8 is fixedly connected with a tool box handle 9, one end of the seat base 7 relative to the base plate 1 is fixedly connected with a seat cushion 10, and one end of the seat cushion 10 relative to the seat base 7 is provided with a headrest 11. A seat structure with a tool box is added to a high-altitude special-shaped beam sleeve construction and hoisting equipment. The operator can slide the tool box 8 by holding the tool box handle 9. When the operator performs the high-altitude special-shaped beam sleeve construction and hoisting operation, various tools are often needed. With a seat with a tool box, the tools can be neatly stored in the tool box, and the operator does not need to leave the work position to find the tools, which greatly saves time and improves work efficiency. Long-term work will make the operator feel tired. With a seat, the operator can sit down when he needs to rest to relieve physical fatigue. This not only helps to improve the work efficiency of the operator, but also reduces operational errors caused by fatigue. The existence of the seat allows operators to take a short break between work, recover their physical strength, and better devote themselves to subsequent work. For example, when performing fine adjustments or installation work, operators can sit on the seat and operate more attentively, reducing errors caused by body shaking.
[0040] Reference Figure 1 , Figure 3 The upper surface of the bottom plate 1 is fixedly connected with an operating table 12, and a control panel 13 is arranged on one side of the operating table 12. The operating table 12 is the main part for operators to control and operate the equipment. The operating table 12 will be installed with various control buttons, switches, instruments and other equipment, through which operators can start, stop, lift, rotate and other operations on the hoisting equipment. The control panel 13 is the core control part of the hoisting equipment, which integrates various electronic control components and sensors to achieve precise control and monitoring of the equipment.
[0041] Reference Figure 1 , Figure 4 , a plurality of support plates 14 are fixedly connected to the upper surface of the bottom plate 1. The support plates 14 mainly play the role of supporting and fixing other components. In the hoisting equipment, the support plates 14 can ensure the stable and firm position of these hoisting equipment. The support plates 14 are made of solid metal materials with good strength and rigidity to ensure that sufficient supporting force can be provided.
[0042] Reference Figure 4, a support column 15 is fixedly connected to one end of the support plate 14 relative to the bottom plate 1, and a plurality of support rods 16 are fixedly connected to the outer side of the lower end of the support column 15. The support column 15 provides a stable support force for the equipment. The support column is usually made of high-strength steel with good compression and bending resistance to ensure that the equipment will not tilt or shake during the lifting operation. The support rod 16 plays a role of auxiliary support and reinforcement in the equipment. It can be used in conjunction with structures such as support columns and support plates to enhance the overall strength and stability of the equipment.
[0043] Reference Figure 4 , a support column 15 is fixedly connected with a grooved sliding track 17 at one end relative to the support plate 14, and a sliding motor 18 is slidably connected to the inner side of the upper surface of the grooved sliding track 17 through a pulley. The grooved sliding track 17 provides guidance and support for the moving parts of the lifting equipment. In the construction and lifting operation of high-altitude special-shaped beam sleeves, it may be necessary to move the lifting equipment horizontally. The grooved sliding track 17 can ensure that the moving parts move according to the predetermined trajectory, thereby improving the operating accuracy and stability of the equipment. The sliding motor 18 provides power for the moving parts of the lifting equipment. On the grooved sliding track 17, the sliding motor 18 can drive the moving parts to move horizontally, thereby realizing the position adjustment of the equipment and the expansion of the operating range.
[0044] Reference Figure 4-5 A sliding frame 19 is provided on one side of the sliding motor 18, and a plurality of adsorption pulleys 20 are provided on both sides of the sliding frame 19. The sliding frame 19 is a moving component installed on a grooved sliding rail, and it is used in conjunction with the sliding motor to achieve position adjustment of the lifting equipment. The adsorption pulley 20 plays a role in reducing friction and improving movement efficiency in the lifting equipment. It is usually installed on the sliding frame 19 and contacts the grooved sliding rail. The surface of the adsorption pulley is usually made of special materials with good adsorption performance and wear resistance. During the movement, the adsorption pulley 20 can reduce the friction resistance between the moving component and the rail by being adsorbed on the sliding rail, thereby improving the operation efficiency of the equipment.
[0045] Reference Figure 5 A connection block 21 is provided on one side of the adsorption pulley 20, and a hoist housing 22 is provided at the lower end of the connection block 21. The connection block 21 connects the adsorption pulley 20 and the hoist housing 22, which ensures the stability of the overall structure. The hoist housing 22 provides protection for the internal structure of the hoist. In an aerial working environment, the hoist housing can prevent external objects from causing damage to the motor, rope turns and other components inside the hoist.
[0046] Reference Figure 5, a rope turn 24 is arranged on the inner side of the hoist housing 22, a hoist motor 23 is arranged on one side of the hoist housing 22, a movable pulley 25 is arranged at one end of the hoist motor 23, and a hook 26 is arranged at the lower end of the movable pulley 25. The hoist motor 23 is the core power component of the hoisting equipment, which provides power for the operation of the hoist. The rope turn 24 is a component of the hoist used to wind the wire rope. During the hoisting operation, the wire rope is connected to the hoist motor through the rope turn 24 to realize the lifting and lowering of the special-shaped beam sleeve. The movable pulley 25 plays a labor-saving role in the hoisting equipment. It is used in conjunction with the hook, wire rope and other components to realize the lifting of the special-shaped beam sleeve by changing the direction and magnitude of the force. The hook 26 is a component of the hoisting equipment used to connect the special-shaped beam sleeve. It is usually made of high-strength metal material with good tensile and bending resistance to ensure that the special-shaped beam sleeve can be safely connected and lifted.
[0047] Reference Figure 1 , Figure 6 , a connecting rod 27 is provided on the upper surface of the sliding frame 19, a rotating motor 28 is provided on the upper end of the connecting rod 27, a rotating block 29 is rotatably connected to the upper end of the rotating motor 28, a plurality of lighting lamps 30 are rotatably connected to the outer side of the rotating block 29, and a warning light 31 is fixedly connected to the upper end of the rotating block 29. A rotating lighting structure with a warning light is added to a high-altitude special-shaped beam sleeve construction hoisting equipment, wherein the rotating motor 28 can provide the power required for the rotation of the rotating block 29. In the high-altitude special-shaped beam sleeve construction environment, the light conditions may be poor, especially at night or in dim weather conditions. The rotating lighting lamp can provide all-round lighting to ensure that the construction area is clearly visible. This helps operators to accurately judge the position, state and surrounding environment of the special-shaped beam sleeve, and reduce operational errors and safety accidents caused by unclear vision. For example, when performing hoisting operations at night, the rotating lighting lamp can illuminate the entire operating area, so that the operator can clearly see the connection between the hook and the special-shaped beam sleeve, ensuring the safety and stability of the hoisting process. The structure with warning lights can attract people's attention from a distance, reminding people around to pay attention to the high-altitude working area and avoid entering the dangerous area by mistake. The flashing of the warning light can effectively convey the danger information, so that people around can stay alert and stay away from the construction area, thereby reducing the probability of accidents. For example, when there are other workers or pedestrians around the construction site, the warning light can play an obvious warning role, preventing them from approaching the area where the hoisting operation is being carried out, and ensuring their personal safety.
[0048] Working principle:
[0049] In the present invention, a protective structure with a tool hanger is added to a high-altitude special-shaped beam sleeve construction hoisting equipment. For the complex operation of special-shaped beam sleeve construction hoisting at high altitude, any small accident may lead to serious consequences. With a solid protective structure, the safety of the operation can be greatly improved. The tool hanger can ensure that the tools have a fixed storage position during the operation, avoiding the tools from being placed randomly and accidentally falling. The tool hanger allows operators to take tools at any time, improves work efficiency and reduces distractions and safety hazards caused by finding tools. When performing hoisting operations, operators can quickly obtain the required tools from the tool hanger without spending time looking for tools around. This greatly saves operation time and improves work efficiency. Especially in an emergency, being able to quickly get the right tools for processing is crucial to ensuring construction progress and safety. With the tool hanger, the tools can be neatly hung in the designated position to avoid the mess at the operation site. A neat working environment helps operators to work more attentively and reduce errors and mistakes caused by a chaotic environment. At the same time, it is also convenient to count and organize the tools after the operation to ensure that the tools will not be lost. Hanging the tools on the protective structure can prevent the tools from directly contacting the ground or being hit and worn by other objects. This helps to extend the service life of the tools and reduce the cost of tool replacement. At the same time, it also reduces the interruption of operations caused by tool damage and improves the overall reliability of the equipment.
[0050] In the present invention, a seat structure with a toolbox is added to a high-altitude special-shaped beam sleeve construction hoisting equipment. Operators often need to use various tools when performing high-altitude special-shaped beam sleeve construction hoisting operations. With a seat with a toolbox, the tools can be neatly stored in the toolbox, and the operator does not need to leave the work position to find the tools, which greatly saves time and improves work efficiency. Long-term work will make the operator feel tired. With a seat, the operator can sit down when he needs to rest to relieve physical fatigue. This not only helps to improve the work efficiency of the operator, but also reduces operational errors caused by fatigue. The presence of the seat allows the operator to take a short break between work, restore physical strength, and better devote himself to subsequent work. For example, when performing fine adjustments or installation work, the operator can sit on the seat and operate more attentively to reduce errors caused by body shaking.
[0051] In the present invention, a rotating lighting structure with a warning light is added to a high-altitude special-shaped beam sleeve construction hoisting equipment. In the high-altitude special-shaped beam sleeve construction environment, the light conditions may be poor, especially at night or in dim weather conditions. The rotating lighting can provide all-round lighting to ensure that the construction area is clearly visible. This helps operators to accurately judge the position, state and surrounding environment of the special-shaped beam sleeve, and reduce operational errors and safety accidents caused by unclear vision. For example, when performing hoisting operations at night, the rotating lighting can illuminate the entire operating area, so that the operator can clearly see the connection between the hook and the special-shaped beam sleeve, ensuring the safety and stability of the hoisting process. The structure with a warning light can attract people's attention at a long distance, reminding the surrounding personnel to pay attention to the high-altitude working area and avoid entering the dangerous area by mistake. The flashing of the warning light can effectively convey the danger information, so that the surrounding personnel remain vigilant and stay away from the construction area, thereby reducing the probability of accidents. For example, when there are other staff or pedestrians around the construction site, the warning light can play an obvious warning role, preventing them from approaching the area where the hoisting operation is being carried out, and ensuring their personal safety.
[0052] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A high-altitude special-shaped beam sleeve construction hoisting equipment, comprising a bottom plate (1), characterized in that: A plurality of connecting columns (2) are fixedly connected to the upper surface of the base plate (1), a side of the connecting column (2) is fixedly connected to a side plate (3), a side of the connecting column (2) is fixedly connected to a front plate (4), a side of the front plate (4) is fixedly connected to a plurality of tool hangers (5), and one end of the connecting column (2) relative to the base plate (1) is fixedly connected to a top plate (6).
2. A high altitude special-shaped beam sleeve construction hoisting equipment as claimed in claim 1, characterized in that: The upper surface of the base plate (1) is fixedly connected to a seat base (7); one side of the tool box (8) is slidably connected to a tool box (8); one side of the tool box (8) is fixedly connected to a tool box handle (9); one end of the seat base (7) relative to the base plate (1) is fixedly connected to a seat cushion (10); and one end of the seat cushion (10) relative to the seat base (7) is provided with a headrest (11).
3. The high altitude special-shaped beam sleeve construction hoisting equipment according to claim 1, characterized in that: An operating table (12) is fixedly connected to the upper surface of the base plate (1), and a control panel (13) is provided on one side of the operating table (12).
4. The high altitude special-shaped beam sleeve construction hoisting equipment according to claim 1, characterized in that: A plurality of support plates (14) are fixedly connected to the upper surface of the bottom plate (1).
5. The high altitude special-shaped beam sleeve construction hoisting equipment as claimed in claim 4, characterized in that: One end of the support plate (14) relative to the bottom plate (1) is fixedly connected to a support column (15), and the outer side of the lower end of the support column (15) is fixedly connected to a plurality of support rods (16).
6. The high altitude special-shaped beam sleeve construction hoisting equipment as claimed in claim 5, characterized in that: One end of the support column (15) relative to the support plate (14) is fixedly connected to a grooved sliding track (17), and the inner side of the upper surface of the grooved sliding track (17) is slidably connected to a sliding motor (18) via a pulley.
7. The high altitude special-shaped beam sleeve construction hoisting equipment as claimed in claim 6, characterized in that: A sliding frame (19) is provided on one side of the sliding motor (18), and a plurality of adsorption pulleys (20) are provided on both sides of the sliding frame (19).
8. The high altitude special-shaped beam sleeve construction and hoisting equipment as claimed in claim 7, characterized in that: A connection block (21) is provided on one side of the adsorption pulley (20), and a hoist casing (22) is provided at the lower end of the connection block (21).
9. The high altitude special-shaped beam sleeve construction hoisting equipment as claimed in claim 8, characterized in that: A rope loop (24) is arranged on the inner side of the hoist housing (22), a hoist motor (23) is arranged on one side of the hoist housing (22), a movable pulley (25) is arranged at one end of the hoist motor (23), and a hook (26) is arranged at the lower end of the movable pulley (25).
10. The high altitude special-shaped beam sleeve construction and hoisting equipment according to claim 7, characterized in that: A connecting rod (27) is provided on the upper surface of the sliding frame (19), a rotating motor (28) is provided at the upper end of the connecting rod (27), a rotating block (29) is rotatably connected to the upper end of the rotating motor (28), a plurality of lighting lamps (30) are rotatably connected to the outer side of the rotating block (29), and a warning light (31) is fixedly connected to the upper end of the rotating block (29).