Mobile GIS equipment transfer device and construction method

By designing a mobile GIS equipment transfer device and using cylinders and wire pulling components to match the guide wheels, the problem of difficulty in handling GIS equipment is solved, a fast and simplified construction method is achieved, and efficiency and tool utilization is improved.

CN119240256APending Publication Date: 2025-01-03国网河南省电力公司中牟县供电公司 +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411321211.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-23
Publication Date
2025-01-03

AI Technical Summary

Technical Problem

During substation construction, GIS equipment is difficult to handle, and traditional methods require multiple staff members, which are inefficient and prone to equipment collision and deformation.

Method used

A mobile GIS equipment transfer device is designed, including a base plate, pillar and track, and the cylinder and wire assembly are used to match the guide wheel to achieve rapid movement and installation of the equipment, and only two staff members can complete the handling.

Benefits of technology

Improves work efficiency, reduces construction difficulty, simplifies operations, and reduces costs through a detachable design and improves tool utilization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119240256A_ABST
    Figure CN119240256A_ABST
Patent Text Reader

Abstract

The invention discloses a mobile GIS equipment transfer device and a construction method, and belongs to the technical field of transformer substation foundation construction.The mobile GIS equipment transfer device comprises a bottom plate, supporting columns and rails, the number of the rails is two, a connecting plate is arranged between the two rails, the supporting columns are arranged at the bottoms of the rails, the bottom plate is arranged at the bottoms of the supporting columns, and the bottom plate is arranged at the bottoms of the supporting columns; an air cylinder is arranged at the right end of the track, a wire pulling assembly is arranged at the left end of the track, and a guide wheel is arranged at the top of the track. The guide wheels are arranged at the top of the track, so that the GIS equipment can move horizontally along the track, the friction force at the bottom of the equipment is reduced, and the carrying efficiency is improved; by arranging the wire pulling assembly at the left end of the track and arranging the air cylinder at the right end of the track, the equipment can be quickly moved to the position above the mounting platform, the equipment can be transferred only by two persons, the working efficiency is improved, and the construction difficulty is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a large equipment transport tool, in particular to a mobile GIS equipment transport device and a construction method, belonging to the technical field of substation construction. Background Art

[0002] When installing GIS equipment in a substation, it is difficult to carry the equipment due to its large size and weight. The traditional construction method is to use a crowbar or steel pipe to move the GIS equipment horizontally. This method is time-consuming, labor-intensive, and inefficient. During the transportation process, at least 5-8 workers are required to cooperate in the transportation construction. In addition, during the transportation process, the equipment is prone to collision and deformation, which is not conducive to the smooth progress of the construction. Summary of the invention

[0003] The technical problem to be solved by the present invention is to overcome the deficiencies of the prior art and provide a mobile GIS equipment transfer device and construction method, which only requires two workers to quickly transport the GIS equipment, thereby improving work efficiency, reducing construction difficulty, and being easy to use and simple to operate.

[0004] The technical solution adopted by the present invention to solve the technical problem is: A mobile GIS equipment transfer device comprises a base plate, pillars and tracks, wherein there are two tracks, and a connecting plate is arranged between the two tracks, a pillar is arranged at the bottom of the track, and a base plate is arranged at the bottom of the pillar, a cylinder is arranged at the right end of the track, a wire pulling assembly is arranged at the left end of the track, and a guide wheel is arranged at the top of the track.

[0005] Extension plates are correspondingly arranged on both sides of the track, the outer extension plates are fixedly connected to the pillars by bolts, and the inner extension plates are connected with connecting plates by bolts.

[0006] The bottom plate is fixedly connected to the bottom surface through a positioning braze.

[0007] A U-shaped base is arranged at the bottom of the right end of the cylinder, and the U-shaped base is fixedly connected with the track by bolts.

[0008] A plug plate is arranged at the left end of the track, a U-shaped gusset plate is arranged outside the plug plate, and the U-shaped gusset plate is fixedly connected to the track by bolts.

[0009] The middle part of the plug plate is slidably connected with a displacement sleeve, the top of the displacement sleeve is provided with a wire pulling assembly, the wire pulling assembly consists of a winding frame and a motor, the winding frame is provided on the displacement sleeve, a motor is provided on one side of the winding frame, and a pulling rope is wound on the winding frame.

[0010] The construction method of the mobile GIS equipment transfer device comprises the following steps: S1. Prepare the tracks required for transportation according to the distance of the construction site, and determine the height of the pillars according to the height of the equipment installation platform to ensure that the equipment can be smoothly moved to the installation platform through the tracks; S2. Place a track on the installation platform, install pillars with bottom plates in the middle and both ends of the track, and fix the extension plates on the outside of the track to the pillars by bolts; S3. Unload the GIS equipment from the truck and place it on the hoisting track, then set lifting lugs at the bottom of the left and right ends of the equipment; S4. Install a cylinder with a U-shaped base at the right end of the track, install a plug plate at the left end of the track, and adjust the position of the wire assembly according to the middle position of the equipment; S5. Connect the pull rope in the pull rope assembly to the lifting lug at the bottom left end of the equipment, and use the cylinder to move the GIS equipment to the top of the installation platform; S6. After the equipment is moved to the installation location, use the lifting equipment to lift it, quickly remove the track and the bottom plate, and finally slowly lower the equipment.

[0011] The track spans over the mounting platform.

[0012] There are two pull-wire assemblies, which are respectively located on the plug board between the two tracks.

[0013] The positive beneficial effects of the present invention are: 1. The present invention arranges guide wheels at the top of the track to facilitate the horizontal movement of the GIS equipment along the track, reduce the friction at the bottom of the equipment, and improve the handling efficiency; arranges a wire drawing assembly at the left end of the track and an air cylinder at the right end of the track. When in use, the wire drawing assembly is connected to the left end of the equipment, and under the action of the air cylinder and the motor, the equipment can be quickly moved to the top of the installation platform. Only two people are needed to transport the equipment, which improves work efficiency and reduces construction difficulty.

[0014] 2. The present invention adopts the push-pull method to cooperate with each other, push the right end of the equipment, and pull the left end of the equipment, so as to quickly move the equipment to the installation platform; and then cooperate with the lifting equipment to partially lift the equipment, so as to quickly install the equipment in place, save time and labor, and be easy to promote.

[0015] 3. The rails and pillars of the present invention, as well as the pillars and the ground, are detachable and can be used repeatedly, which reduces construction costs, improves the utilization rate of the tool, and is easy to use and simple to operate. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1It is a structural schematic diagram of the present invention; Figure 2 It is a structural schematic diagram of the track of the present invention; Figure 3 It is a connection structure diagram between the tracks of the present invention; Figure 4 It is a structural schematic diagram of the base plate and the pillars of the present invention; Among them: 1-base plate, 2-pillar, 3-positioning drill, 4-track, 5-extension plate, 6-guide wheel, 7-connecting plate, 8-cylinder, 9-U-type base, 10-insertion plate, 11-U-type buckle plate, 12-winding frame, 13-motor, 14-displacement sleeve. DETAILED DESCRIPTION

[0017] The present invention will be further explained and illustrated below in conjunction with the accompanying drawings: Example 1, see Figure Figure 1-Figure 4 A mobile GIS equipment transfer device includes a base plate 1, a pillar 2 and a track 4. There are two tracks 4, and a connecting plate 7 is arranged between the two tracks 4. A pillar 2 is arranged at the bottom of the track 4, and a base plate 1 is arranged at the bottom of the pillar 2. A cylinder 8 is arranged at the right end of the track 4, a wire pulling assembly is arranged at the left end of the track 4, and a guide wheel 6 is arranged at the top of the track 4.

[0018] Extension plates 5 are correspondingly arranged on both sides of the track 4 . The outer extension plates 5 are fixedly connected to the pillars 2 by bolts, and the inner extension plates 5 are connected with connecting plates 7 by bolts.

[0019] The bottom plate 1 is fixedly connected to the bottom surface by means of positioning pins 3 .

[0020] A U-shaped base 9 is provided at the bottom of the right end of the cylinder 8 , and the U-shaped base 9 is fixedly connected to the track 4 by bolts.

[0021] A plug plate 10 is arranged at the left end of the track 4 , and a U-shaped gusset plate 11 is arranged outside the plug plate 10 . The U-shaped gusset plate 11 is fixedly connected to the track 4 by bolts.

[0022] A displacement sleeve 14 is slidably connected to the middle of the plug board 10, and a wire pulling assembly is arranged on the top of the displacement sleeve 14. The wire pulling assembly consists of a winding frame 12 and a motor 13. The winding frame 12 is arranged on the displacement sleeve 14, and the motor 13 is arranged on one side of the winding frame 12. A pull rope is wound on the winding frame 12.

[0023] In the above description, the length of the pull wire is sufficient to move the device to the installation location.

[0024] In the above description, the position of the cylinder can be adjusted according to the position of the device movement, that is, changing the position of the U-shaped base on the track.

[0025] In the above description, the extension plate is located on the support column, and more than half of the track is located on the support column.

[0026] In the above description, positioning pins are provided at both ends of the bottom plate to facilitate fixing the bottom plate to the ground.

[0027] Embodiment 2, the construction method of the above-mentioned mobile GIS equipment transfer device comprises the following steps: S1. Prepare the tracks required for transportation according to the distance of the construction site, and determine the height of the pillars according to the height of the equipment installation platform to ensure that the equipment can be smoothly moved to the installation platform through the tracks; S2. Place the track 4 on the installation platform, and install the support 2 with the bottom plate 1 in the middle and both ends of the track 4, and fix the extension plate 5 on the outer side of the track 4 to the support 2 by bolts; S3, unload the GIS equipment from the truck and place it on the hoisting track 4, and then set lifting lugs at the bottom of the left and right ends of the equipment; S4. Install the cylinder 8 with the U-shaped base 9 at the right end of the track 4, install the plug plate 10 at the left end of the track 4, and adjust the position of the wire pull assembly according to the middle position of the equipment; S5. Connect the pull rope in the pull rope assembly to the lifting lug at the bottom left end of the equipment, and use the cylinder to move the GIS equipment to the top of the installation platform; S6. After the equipment is moved to the installation location, use the lifting device to lift the equipment, quickly remove the track 4 and the bottom plate 1, and finally slowly lower the equipment.

[0028] Track 4 spans across the top of the mounting platform.

[0029] There are two pull-wire assemblies, which are respectively located on the plug board 10 between the two tracks 4 .

[0030] In the above description, under the action of the motor, the connecting shaft of the winding frame can be driven to rotate, thereby playing the role of pulling or releasing the wire.

[0031] In the above description, the device can also be used for moving equipment on flat ground, that is, the support at the bottom of the track is removed, and then the positioning rod is penetrated through the bolt hole on the extension plate to fix the track.

[0032] In the above description, bolts are arranged at the top of the pillars. When in use, corresponding screw holes are dug on the extension plate, the extension plate passes through the bolts, and is fixed by matching nuts.

[0033] In the above description, bolts are arranged on the inner extension plate of the track, and bolt holes are dug at both ends of the connecting plate. The bolt holes at the ends of the connecting plate are sleeved on the bolts and fixed by matching nuts.

[0034] In the above description, the size of the U-shaped base matches the size of the upper portion of the track.

[0035] In the above description, the size of the U-shaped gusset plate matches the size of the plug plate.

[0036] When in use, only two workers are needed, one standing on the left side of the equipment and the other standing on the right side of the equipment to observe whether the equipment will deviate during transportation.

[0037] The present invention arranges guide wheels at the top of the track to facilitate the horizontal movement of the GIS equipment along the track, reduces the friction at the bottom of the equipment, and improves the handling efficiency; arranges a wire pulling assembly at the left end of the track and an air cylinder at the right end of the track. When in use, the wire pulling assembly is connected to the left end of the equipment, and under the action of the air cylinder and the motor, the equipment can be quickly moved to the top of the installation platform. Only two people are needed to transport the equipment, which improves work efficiency and reduces construction difficulty.

Claims

1. A mobile GIS equipment transfer device, comprising a base plate (1), a support (2) and a track (4), characterized in that: There are two rails (4), and a connecting plate (7) is arranged between the two rails (4). A support (2) is arranged at the bottom of the rail (4), and a bottom plate (1) is arranged at the bottom of the support (2). A cylinder (8) is arranged at the right end of the rail (4), a wire pulling assembly is arranged at the left end of the rail (4), and a guide wheel (6) is arranged at the top of the rail (4).

2. A mobile GIS equipment transfer device according to claim 1, characterized in that: Extension plates (5) are correspondingly arranged on both sides of the track (4); the outer extension plates (5) are fixedly connected to the pillars (2) by bolts, and the inner extension plates (5) are connected with connecting plates (7) by bolts.

3. A mobile GIS equipment transfer device according to claim 1, characterized in that: The bottom plate (1) is fixedly connected to the bottom surface via a positioning pin (3).

4. A mobile GIS equipment transfer device according to claim 1, characterized in that: A U-shaped base (9) is provided at the bottom of the right end of the cylinder (8), and the U-shaped base (9) is fixedly connected to the track (4) by bolts.

5. A mobile GIS equipment transfer device according to claim 1, characterized in that: A plug plate (10) is provided at the left end of the track (4), a U-shaped gusset plate (11) is provided outside the plug plate (10), and the U-shaped gusset plate (11) is fixedly connected to the track (4) by bolts.

6. A mobile GIS equipment transfer device according to claim 1, characterized in that: A displacement sleeve (14) is slidably connected to the middle of the plug plate (10), a wire pulling assembly is arranged on the top of the displacement sleeve (14), the wire pulling assembly is composed of a winding frame (12) and a motor (13), the winding frame (12) is arranged on the displacement sleeve (14), a motor (13) is arranged on one side of the winding frame (12), and a pulling rope is wound on the winding frame (12).

7. The construction method of a mobile GIS equipment transfer device according to any one of claims 1 to 6, characterized in that: The steps include: S1. Prepare the tracks required for transportation according to the distance of the construction site, and determine the height of the pillars according to the height of the equipment installation platform to ensure that the equipment can be smoothly moved to the installation platform through the tracks; S2. Place a track (4) above the installation platform, and install pillars (2) with bottom plates (1) in the middle and at both ends of the track (4), and fix the extension plates (5) on the outside of the track (4) to the pillars (2) by bolts; S3, unload the GIS equipment from the truck and place it on the hoisting rail (4), and then set lifting lugs at the bottom of the left and right ends of the equipment; S4. Install a cylinder (8) with a U-shaped base (9) at the right end of the track (4), install a plug plate (10) at the left end of the track (4), and adjust the position of the wire pull assembly according to the position in the middle of the device; S5. Connect the pull rope in the pull rope assembly to the lifting lug at the bottom left end of the equipment, and use the cylinder to move the GIS equipment to the top of the installation platform; S6. After the equipment is moved to the installation location, the equipment is lifted up using a lifting device, and the track (4) and the bottom plate (1) are quickly removed. Finally, the equipment is slowly lowered.

8. The construction method of a mobile GIS equipment transfer device according to claim 7, characterized in that: The track (4) spans above the installation platform.

9. The construction method of a mobile GIS equipment transfer device according to claim 7, characterized in that: There are two pull-wire assemblies, each located on a plug board (10) between two tracks (4).