Cavern construction device and system

By designing removable fastening components and protective parts, the serious shaking of hand-wind drills in the drilling and explosion method is solved, the construction efficiency and safety are improved, and the health risks of workers are reduced.

CN119308687APending Publication Date: 2025-01-14SHANGHAI INVESTIGATION DESIGN & RES INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411485088.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-23
Publication Date
2025-01-14

Smart Images

  • Figure CN119308687A_ABST
    Figure CN119308687A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of cavern construction, and discloses a cavern construction device and system.The cavern construction device comprises a trolley, mounting frames and fastening assemblies, the multiple mounting frames are detachably mounted on the trolley and located on the construction side of the trolley, the multiple fastening assemblies are fixed to the mounting frames, and the fastening assemblies are suitable for fastening a rock drill; the fastening assembly has a fastening state for mounting the rock drill and a releasing state for dismounting the rock drill, the rock drill is detachably mounted in the fastening assembly on the mounting frame, the rock drill is clamped and fixed through the fastening assembly, it can be guaranteed that the rock drill is stably mounted on the mounting frame during construction, and the rock drill can be firmly mounted on the mounting frame. The jitter amplitude of the rock drill during working is reduced, an operator only needs to control the rock drill to move back and forth, the operator can control and operate the rock drill conveniently, the construction efficiency is improved, and meanwhile the construction safety is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of cavern construction, and in particular to a cavern construction device and system. Background Art

[0002] Cavern excavation refers to the process of loosening, crushing, excavating and transporting the soil or rock when building a tunnel. It is widely used in water diversion, drainage, diversion, transportation and other tunnel construction in water conservancy projects.

[0003] The main methods of cave excavation are shield tunneling and drilling and blasting. The drilling and blasting method is to drill a number of holes of appropriate depth on the rock blasting surface, load explosives and detonate them, thereby breaking the rock and completing the excavation of the tunnel. The drilling process in the drilling and blasting method mainly uses a pneumatic rock drill (hand pneumatic drill). While the drill rod is advancing, the operator needs to adjust the height of the pneumatic support legs and control the shaking of the hand pneumatic drill. Especially when the hole depth is shallow, the hand pneumatic drill shakes more severely, and the operator needs to spend a lot of force to control the hand pneumatic drill from turning forward, backward, left and right, which not only consumes a lot of physical strength of the operator, but also poses a safety hazard. Summary of the invention

[0004] In view of this, the present invention provides a cavern construction device and system to solve the problem of severe shaking of a hand pneumatic drill during drilling and blasting construction in the prior art.

[0005] In the first aspect, the present invention provides a cavern construction device, including a trolley, a mounting frame and a fastening assembly, wherein a plurality of mounting frames can be detachably mounted on the trolley and are located on the construction side of the trolley, a plurality of fastening assemblies are fixed on the mounting frame, the fastening assemblies are suitable for fastening a rock drill, and the fastening assemblies have a fastened state for installing the rock drill and a loosened state for disassembling the rock drill.

[0006] Beneficial effects: The present invention detachably mounts the rock drill in a fastening assembly on the mounting frame. The fastening assembly clamps and fixes the rock drill, thereby ensuring that the rock drill is stably mounted on the mounting frame during construction, reducing the vibration amplitude of the rock drill during operation. The operator only needs to control the forward and backward movement of the rock drill, which makes it easy for the operator to control and operate the rock drill, thereby improving construction efficiency and safety.

[0007] In an optional embodiment, the fastening assembly includes a first mounting portion and a second mounting portion, the first mounting portion is fixed on the mounting frame, the second mounting portion is movably connected to the first mounting portion, the first mounting portion and the second mounting portion enclose an installation cavity, the installation cavity is suitable for installing a rock drill, and the first mounting portion and the second mounting portion have a fastened state for installing the rock drill and a loosened state for disassembling the rock drill.

[0008] Beneficial effects: The present invention adopts a method of active connection between the first mounting part and the second mounting part, which is convenient for disassembly, assembly and maintenance of the rock drill. When the rock drill is in a fastened state and installed in the mounting cavity, the first mounting part and the second mounting part can limit the rock drill, reduce the shaking of the rock drill during operation, and is more conducive to the operator's operation and control. When the rock drill is in a loosened state, the operator can remove the rock drill for maintenance or replacement. It has the advantages of simple structure and convenient operation.

[0009] In an optional embodiment, the first mounting portion is in a concave arc shape, the second mounting portion is in a convex arc shape, and the mounting cavity is circular.

[0010] Beneficial effect: The present invention sets the installation cavity to be circular to adapt to the shape of the rock drill, so that the rock drill can be installed more stably in the installation cavity.

[0011] In an optional embodiment, one side of the first mounting portion is hinged to one side of the second mounting portion.

[0012] In an optional embodiment, a buckle or a snap ring is provided on the first mounting portion, and a snap ring or a buckle is correspondingly provided on the second mounting portion, and the snap ring and the buckle are movably engaged with each other.

[0013] Beneficial effect: The first mounting part and the second mounting part of the present invention adopt a snap-on and snap-ring movable snap-on connection method, which is convenient for disassembly and assembly of the rock drill. It has a simple structure and a firm snap-on connection, which can ensure that the rock drill is firmly installed in the mounting cavity when working.

[0014] In an optional embodiment, the cavern construction device further includes a protective member, which is disposed on the trolley and faces one side of the construction surface.

[0015] Beneficial effect: The present invention provides a protective piece on the trolley facing the construction surface to block dust generated during construction and reduce the damage to the health of workers caused by mud and sand carried by the back-blown airflow.

[0016] In an optional embodiment, the trolley includes at least two vertically arranged columns and at least one horizontally arranged crossbar, the crossbar is connected to the columns, and the mounting frame is detachably mounted on the columns.

[0017] Beneficial effects: The present invention can detachably mount the mounting frame on the column. During construction, mounting frames of different sizes can be replaced according to the size of the construction cavern, so that different numbers of rock drills can work simultaneously, thereby improving the construction efficiency.

[0018] In an optional embodiment, a plurality of second fastening assemblies are provided on the column, and the mounting frame is detachably mounted in the second fastening assemblies.

[0019] In an optional embodiment, a plurality of mounting holes are provided on the mounting frame, wherein two adjacent mounting holes are located on both sides of the second fastening assembly, and latches are installed in the mounting holes.

[0020] Beneficial effect: The present invention provides a mounting hole on both sides of the second fastening component. When the mounting frame is installed in the second fastening component, inserting pins into the mounting holes on both sides of the second fastening component can limit the mounting frame, thereby avoiding displacement of the mounting frame during construction and ensuring the stability of the cave construction device.

[0021] In a second aspect, the present invention further provides a cavern construction system, comprising a rock drill and the above-mentioned cavern construction device, wherein a plurality of rock drills are respectively installed in fastening assemblies.

[0022] Since the cavern construction system adopts the cavern construction device of the present invention, it has the same beneficial effects as the cavern construction device, which will not be described in detail here. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0024] Figure 1 It is a structural schematic diagram of a cavern construction device according to an embodiment of the present invention;

[0025] Figure 2 It is a structural schematic diagram of a fastening assembly in a cave construction device according to an embodiment of the present invention in a fastened state;

[0026] Figure 3 It is a structural schematic diagram of a fastening assembly in a cave construction device according to an embodiment of the present invention in a loosened state;

[0027] Figure 4 The present invention is a schematic structural diagram of a column in a cavern construction device according to an embodiment of the present invention.

[0028] Description of reference numerals:

[0029] 1. Trolley; 11. Post; 111. Second fastening assembly; 12. Crossbar; 2. Mounting frame; 3. Fastening assembly; 31. First mounting portion; 311. Buckle; 32. Second mounting portion; 321. Snap ring; 33. Mounting cavity. DETAILED DESCRIPTION

[0030] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.

[0031] Combine the following Figures 1 to 4 , describing an embodiment of the present invention.

[0032] According to an embodiment of the present invention, on the one hand, Figures 1 to 4 As shown, a cavern construction device is provided, including a trolley 1, a mounting frame 2 and a fastening assembly 3. A plurality of mounting frames 2 are detachably mounted on the trolley 1 and are located on the construction side of the trolley 1. A plurality of fastening assemblies 3 are fixed on the mounting frame 2. The fastening assemblies 3 are suitable for fastening a rock drill. The fastening assemblies 3 have a fastened state for installing the rock drill and a loosened state for disassembling the rock drill.

[0033] Specifically, Figure 1 As shown, in this embodiment, the size of the trolley 1 is set according to the diameter of the cave excavation, and a frame structure is adopted. The trolley 1 is provided with a multi-layer operating platform. For example, in this embodiment, according to the size of the operating platform, a mounting frame 2 is detachably installed in the upper middle part of the upper and lower operating platforms where operators stand and walk on the trolley 1, and a mounting frame 2 is added at the bottom of the operating platform. The mounting frame 2 on the trolley 1 is arranged in three layers, and the mounting frame 2 is detachably installed on the side of the trolley 1 close to the excavation surface. The height of the mounting frame 2 is adjusted according to the size of the trolley 1 and the position of the cave drilling hole, and the installation position can be adjusted at any time.

[0034] In this embodiment, the structural part of the trolley 1 is not specifically limited. In this embodiment, the trolley 1 is welded into a frame structure using I-beams and channel steels.

[0035] In this embodiment, a plurality of fastening assemblies 3 are installed on the mounting frame 2 at intervals, and the intervals between the fastening assemblies 3 are determined according to the hole spacing of the blasting design, ensuring that there is a fastening assembly 3 at the drilling position of each construction rock drill.

[0036] In this embodiment, during use, the position and quantity of the mounting bracket 2 and the fastening assembly 3 can be partially increased or decreased according to the adjustment of the drilling position.

[0037] In this embodiment, the rock drill is a handheld rock drill, which can be detachably installed in each fastening assembly 3. During construction, the rock drill is in a fastened state and fixed in the fastening assembly 3, the drill head of the rock drill faces the cavern to be constructed, and the other end of the rock drill is controlled by an operator. When the construction is stopped, the operator can adjust the fastening assembly 3 to a loose state, so as to take out the rock drill for maintenance or replacement.

[0038] The present invention detachably mounts the rock drill in the fastening assembly 3 on the mounting frame 2. The fastening assembly 3 clamps and fixes the rock drill, thereby ensuring that the rock drill is stably mounted on the mounting frame 2 during construction, reducing the vibration amplitude of the rock drill during operation, and only requires the operator to control the forward and backward movement of the rock drill, which is convenient for the operator to control and operate the rock drill, thereby improving construction efficiency and safety.

[0039] In one embodiment, Figure 2 and Figure 3 As shown, the fastening assembly 3 includes a first mounting portion 31 and a second mounting portion 32, the first mounting portion 31 is fixed on the mounting frame 2, the second mounting portion 32 is movably connected to the first mounting portion 31, and the first mounting portion 31 and the second mounting portion 32 enclose an installation cavity 33, which is suitable for installing a rock drill, and the first mounting portion 31 and the second mounting portion 32 have a fastened state for installing the rock drill and a loosened state for disassembling the rock drill.

[0040] The present invention adopts a method of movably connecting the first mounting portion 31 and the second mounting portion 32, which is convenient for disassembly, assembly and maintenance of the rock drill. When the rock drill is in a fastened state and installed in the mounting cavity 33, the first mounting portion 31 and the second mounting portion 32 can limit the rock drill, reduce the shaking of the rock drill during operation, and be more conducive to the operator's operation and control. When the rock drill is in a loosened state, the operator can remove the rock drill for maintenance or replacement. It has the advantages of simple structure and convenient operation.

[0041] In one embodiment, Figure 2 and Figure 3 As shown, the first mounting portion 31 is in a concave arc shape, the second mounting portion 32 is in a convex arc shape, and the mounting cavity 33 is circular.

[0042] Specifically, in this embodiment, the first mounting part 31 and the second mounting part 32 can be made of a steel pipe cut along the center line, and the lower half is slightly processed to reduce its diameter and welded to the mounting frame 2 as the first mounting part 31, and the upper half is used as the movable second mounting part 32.

[0043] In this embodiment, a buffer pad is provided inside the first mounting portion 31 and the second mounting portion 32. The buffer pad contacts the outer wall of the rock drill and is used to buffer the rock drill and reduce the vibration generated by the rock drill during operation. In this embodiment, the buffer pad is not specifically limited and can be a rubber pad, a silicone pad, a sponge pad, etc.

[0044] The present invention sets the installation cavity 33 to be circular to adapt to the shape of the rock drill, so that the rock drill can be installed more stably in the installation cavity 33.

[0045] In one embodiment, Figure 2 and Figure 3 As shown, one side of the first mounting portion 31 is hinged to one side of the second mounting portion 32 .

[0046] Specifically, in this embodiment, one end of the first mounting portion 31 and the second mounting portion 32 are connected by a heavy-duty hinge, and the other end is detachably connected.

[0047] In one embodiment, Figure 2 and Figure 3 As shown, a buckle 311 or a snap ring 321 is provided on the first mounting portion 31 , and a snap ring 321 or a buckle 311 is correspondingly provided on the second mounting portion 32 , and the snap ring 321 is movably engaged with the buckle 311 .

[0048] Specifically, in this embodiment, the first mounting portion 31 and the movable end of the second mounting portion 32 are detachably connected by a lock, the buckle 311 in the lock is installed on the movable end of the second mounting portion 32, and the snap ring 321 in the lock is installed on the movable end of the first mounting portion 31. The first mounting portion 31 and the second mounting portion 32 can be locked by engaging the buckle 311 with the snap ring 321, so that they are in a fastened state to firmly clamp the rock drill.

[0049] The first mounting portion 31 and the second mounting portion 32 of the present invention are movably connected by means of a buckle 311 and a clamping ring 321, which is convenient for disassembly and assembly of the rock drill. The structure is simple and the connection is firm, which can ensure that the rock drill is firmly installed in the mounting cavity 33 when working.

[0050] In one embodiment, the cave construction device further includes a protective member, which is disposed on the trolley 1 and faces one side of the construction surface.

[0051] Specifically, in the process of using the cavern construction device in this embodiment, after the rock drill is watered, there is a lot of dust, and the back-blown airflow carries mud and sand, which can easily cause damage to the health of the operators. Therefore, in actual use, a protective member can be fixed at the front end of the trolley 1 to prevent the airflow from carrying mud and sand to harm the operators. This embodiment does not specifically limit the protective member, and the protective member can be a soft rubber plate or a soft plastic hanging curtain.

[0052] In the present invention, a protective piece is provided on the trolley 1 facing the construction surface to block dust generated during construction and reduce the damage to the health of workers caused by mud and sand carried by the back-blown airflow.

[0053] In one embodiment, Figure 1 As shown, the trolley 1 includes at least two vertically arranged columns 11 and at least one horizontally arranged crossbar 12 , the crossbar 12 is connected to the columns 11 , and the mounting frame 2 is detachably mounted on the columns 11 .

[0054] Specifically, in this embodiment, no specific limitation is made to the upright posts 11 and the crossbar 12 . In this embodiment, the upright posts 11 are made of I-beams, the crossbar 12 are made of channel steels, and the upright posts 11 and the crossbar 12 are connected by welding.

[0055] The present invention detachably mounts the mounting frame 2 on the column 11. During construction, mounting frames 2 of different sizes can be replaced according to the size of the construction cavern, so that different numbers of rock drills can work simultaneously, thereby improving the construction efficiency.

[0056] In one embodiment, Figure 4 As shown, a plurality of second fastening components 111 are provided on the column 11 , and the mounting frame 2 can be detachably mounted in the second fastening components 111 .

[0057] Specifically, the second fastening assembly 111 is not specifically limited in this embodiment, and the second fastening member in this embodiment adopts the same structure as the fastening assembly 3 on the mounting frame 2. A plurality of second fastening assemblies 111 are vertically arranged on the side of the column 11 along the height of the column 11, and the mounting frame 2 is detachably mounted in the second fastening assemblies 111.

[0058] In one embodiment, the mounting frame 2 is provided with a plurality of mounting holes, wherein two adjacent mounting holes are located on both sides of the second fastening assembly 111 , and latches are installed in the mounting holes.

[0059] The present invention provides a mounting hole on both sides of the second fastening component 111. When the mounting frame 2 is installed in the second fastening component 111, inserting pins into the mounting holes on both sides of the second fastening component 111 can limit the mounting frame 2, thereby preventing the mounting frame 2 from being displaced during construction, thereby ensuring the stability of the cave construction device.

[0060] According to an embodiment of the present invention, on the other hand, a cavern construction system is provided, comprising a rock drill and the above-mentioned cavern construction device, wherein a plurality of rock drills are respectively installed in the fastening assembly 3 .

[0061] The present invention detachably mounts the rock drill in the fastening assembly 3 on the mounting frame 2. The fastening assembly 3 clamps and fixes the rock drill, thereby ensuring that the rock drill is stably mounted on the mounting frame 2 during construction, reducing the vibration amplitude of the rock drill during operation, and only requires the operator to control the forward and backward movement of the rock drill, which is convenient for the operator to control and operate the rock drill, thereby improving construction efficiency and safety.

[0062] Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations are all within the scope defined by the appended claims.

Claims

1. A cavern construction device, characterized in that: include: Trolley (1); A mounting frame (2), wherein a plurality of mounting frames (2) are detachably mounted on the trolley (1) and are located on the construction side of the trolley (1); A fastening assembly (3), a plurality of the fastening assemblies (3) are fixed on the mounting frame (2), the fastening assembly (3) is suitable for fastening a rock drill, and the fastening assembly (3) has a fastened state for installing the rock drill and a loosened state for disassembling the rock drill.

2. The cavern construction device according to claim 1, characterized in that: The fastening assembly (3) comprises: A first mounting portion (31), wherein the first mounting portion (31) is fixed on the mounting frame (2); A second mounting portion (32), the second mounting portion (32) being movably connected to the first mounting portion (31), a mounting cavity (33) being enclosed between the first mounting portion (31) and the second mounting portion (32), the mounting cavity (33) being suitable for mounting a rock drill, and a fastened state for mounting the rock drill and a loosened state for disassembling the rock drill being provided between the first mounting portion (31) and the second mounting portion (32).

3. The cavern construction device according to claim 2, characterized in that: The first mounting portion (31) is in a concave arc shape, the second mounting portion (32) is in a convex arc shape, and the mounting cavity (33) is circular.

4. The cavern construction device according to claim 2 or 3, characterized in that: One side of the first mounting portion (31) is hinged to one side of the second mounting portion (32).

5. The cavern construction device according to claim 4, characterized in that: The first mounting portion (31) is provided with a buckle (311) or a snap ring (321), and the second mounting portion (32) is correspondingly provided with the snap ring (321) or the buckle (311), and the snap ring (321) is movably snap-connected with the buckle (311).

6. The cavern construction device according to claim 1, characterized in that: Also includes: A protective member is arranged on the trolley (1) and faces a side of the construction surface.

7. The cavern construction device according to claim 1, characterized in that: The trolley (1) comprises at least two vertically arranged columns (11) and at least one horizontally arranged crossbar (12); the crossbar (12) is connected to the columns (11); and the mounting frame (2) is detachably mounted on the columns (11).

8. The cavern construction device according to claim 7, characterized in that: A plurality of second fastening components (111) are provided on the upright column (11), and the mounting frame (2) can be detachably mounted in the second fastening components (111).

9. The cavern construction device according to claim 8, characterized in that: The mounting frame (2) is provided with a plurality of mounting holes, wherein two adjacent mounting holes are located on both sides of the second fastening component (111), and latches are installed in the mounting holes.

10. A cavern construction system, characterized in that: include: Rock drill; The cavern construction device according to any one of claims 1 to 9, wherein a plurality of said rock drills are respectively installed in said fastening assembly (3).