High-performance concrete combined trestle plate and preparation method thereof
By using a combined structure of steel beam parts, steel plates and ribs, combined with concrete pouring, the problems of large weight and poor seismic resistance of concrete trench plates are solved, and the structure is lightweight, seismic resistance enhancement and cost-saving effects are achieved.
Patent Information
- Application Number
- CN202411808859.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-10
- Publication Date
- 2025-02-11
AI Technical Summary
Due to the high density of existing concrete trench panels, the weight is heavier, which increases the installation cost and difficulty, and the earthquake resistance is poor.
The combined structure of multiple steel beam parts and steel plates and ribs is adopted. By welding and pouring concrete, the use of concrete is reduced and the seismic resistance and strength are increased.
It realizes the weight of the structure, enhances seismic resistance and strength, saves costs, and ensures the durability of the structure through concrete covering ribs and steel mesh.
Smart Images

Figure CN119411469A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a high-performance concrete composite trestle board and a preparation method thereof. Background Art
[0002] The trestle board is a kind of board used to build a trestle. A trestle is a building shaped like a bridge, usually built on the water, between buildings or in terrain such as valleys, for the passage of people, transportation of goods or placement of equipment.
[0003] Trestle boards can be made of a variety of materials, the most common of which are wood, steel and concrete. Wood trestle boards have a certain elasticity and natural beauty, but their durability is relatively poor and they need to be treated for corrosion; steel trestle boards have high strength and good toughness, can withstand large loads, and are relatively easy to install; concrete trestle boards have good durability and stability, and high compressive strength.
[0004] Due to the high density of concrete itself, the concrete trestle board has a heavy weight, which will increase the construction cost and difficulty of installation, and its earthquake resistance is poor. Summary of the invention
[0005] The purpose of the present invention is to overcome the existing defects and provide a high-performance concrete composite trestle board and a preparation method thereof, which can reduce the weight while enhancing the earthquake resistance and saving the cost.
[0006] The technical solution to achieve the above-mentioned purpose is: a high-performance concrete composite trestle board, including multiple steel beams, each of which is parallel to each other, with the same spacing between each of the steel beams, a steel plate welded on the upper surface of each of the steel beams, the steel plate is perpendicular to the multiple connected steel beams, and multiple strip holes are evenly opened on the steel plate.
[0007] Preferably, a rib is welded between every two adjacent steel beams.
[0008] Preferably, the upper end of each rib passes through two corresponding strip holes and is welded to the steel plate.
[0009] Preferably, a steel mesh is installed on the upper surface of each of the steel plates, and concrete is poured on the upper surface of each of the steel plates, and the concrete covers the upper end of each rib and the steel mesh.
[0010] Preferably, the steel beams include but are not limited to H-shaped steels, channel steels and I-shaped steels.
[0011] A method for preparing a high-performance concrete composite trestle slab comprises the following steps: S1 places the steel beams in parallel and installs all the ribs between the steel beams; S2: Multiple strip holes are evenly opened on the steel plate, and then the steel plate is vertically laid on each steel beam, so that each strip hole of each steel plate is just fitted on the corresponding rib plate, and then the contact surfaces of the steel plate and each rib plate are welded together, and then the steel plate and each steel beam are welded together; S3 installs a steel mesh on the upper surface of the steel plate, and then pours concrete on the upper surface of the steel plate.
[0012] The beneficial effects of the present invention are as follows: a steel plate is welded on the upper surface of each steel beam, a rib is connected to every two adjacent steel beams, the upper end of each rib passes through the steel plate and is welded thereto, concrete is poured on each steel plate, replacing the traditional integral casting, which greatly reduces the amount of concrete used, thereby reducing the weight of the structure, and installing multiple ribs and steel plates can enhance the seismic resistance and strength of the structure, saving costs; Concrete covers the upper end of each rib and the steel mesh, and the steel mesh can prevent the subsequent covering concrete from cracking, thereby ensuring the durability of the structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 is a top view of the present invention; Figure 2 yes Figure 1 Partial cross-sectional view at point A.
[0014] In the figure: 1. Steel beam; 2. Steel plate; 3. Rib plate; 4. Concrete. DETAILED DESCRIPTION
[0015] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. In the description of the present invention, it should be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, which are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.
[0016] The present invention will be further described below in conjunction with the accompanying drawings.
[0017] like Figure 1-2 As shown, a high-performance concrete composite trestle slab comprises a plurality of steel beams 1, a steel plate 2 and a plurality of ribs 3.
[0018] Specifically, the steel beams 1 are parallel to each other, the spacing between the steel beams 1 is the same, a steel plate 2 is welded on the upper surface of each steel beam 1, the steel plate 2 is perpendicular to the multiple connected steel beams 1, and a plurality of strip holes are evenly opened on the steel plate 2; a rib 3 is welded between every two adjacent steel beams 1; the upper end of each rib 3 passes through two corresponding strip holes and is welded to the steel plate 2.
[0019] Specifically, a steel mesh is installed on the upper surface of each steel plate 2, and concrete 4 is poured on the upper surface of each steel plate 2, replacing the traditional integral casting molding, which greatly reduces the use of concrete, thereby reducing the weight of the structure. At the same time, installing multiple ribs 3 and steel plates 2 can enhance the seismic resistance and strength of the structure and save costs; concrete 4 covers the upper end of each rib 3 and the steel mesh, and the steel mesh can prevent the concrete 4 covered later from cracking, thereby ensuring the durability of the structure.
[0020] Specifically, the steel beam 1 includes but is not limited to H-shaped steel, channel steel and I-shaped steel.
[0021] Another aspect of the present invention provides a method for preparing a high performance concrete composite trestle slab, comprising the following steps: S1 places the steel beams 1 in parallel and installs all the ribs 3 between the steel beams 1; S2 evenly opens a plurality of strip holes on the steel plate 2, and then vertically lays the steel plate 2 on each steel beam 1, so that each strip hole of each steel plate 2 is just fitted on the corresponding rib plate 3, and then welds the contact surfaces of the steel plate 2 and each rib plate 3 together, and then welds the steel plate 2 and each steel beam 1 together; S3 installs a steel mesh on the upper surface of the steel plate 2, and then pours concrete 4 on the upper surface of the steel plate 2.
[0022] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the above embodiments, those skilled in the art should understand that the technical solutions described in the above embodiments may still be modified, or some or all of the technical features may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the scope of the technical solutions of the embodiments of the present invention.
Claims
1. A high performance concrete composite trestle board, characterized in that: The invention comprises a plurality of steel beam members (1), each of the steel beam members (1) is parallel to each other, the spacing between the steel beam members (1) is the same, a steel plate (2) is welded on the upper surface of each of the steel beam members (1), the steel plate (2) is perpendicular to the plurality of connected steel beam members (1), and a plurality of strip holes are evenly opened on the steel plate (2).
2. The high performance concrete composite trestle slab according to claim 1, characterized in that: A rib plate (3) is welded between every two adjacent steel beam members (1).
3. The high performance concrete composite trestle slab according to claim 2, characterized in that: The upper end of each rib plate (3) passes through two corresponding strip holes and is welded to the steel plate (2).
4. The high performance concrete composite trestle slab according to claim 3, characterized in that: A steel mesh is installed on the upper surface of each steel plate (2), and concrete (4) is poured on the upper surface of each steel plate (2), wherein the concrete (4) covers the upper end of each rib plate (3) and the steel mesh.
5. The high performance concrete composite trestle slab according to claim 1, characterized in that: The steel beam (1) includes but is not limited to H-shaped steel, channel steel and I-shaped steel.
6. A method for preparing a high performance concrete composite trestle board according to any one of claims 1 to 5, characterized in that: The steps include: S1: placing the steel beams (1) in parallel and installing all the ribs (3) between the steel beams (1); S2: a plurality of strip holes are evenly opened on the steel plate (2), and then the steel plate (2) is vertically laid on each steel beam member (1), so that each strip hole of each steel plate (2) is exactly fitted on the corresponding rib plate (3), and then the contact surfaces of the steel plate (2) and each rib plate (3) are welded together, and then the steel plate (2) and each steel beam member (1) are welded together; S3: installing a steel mesh on the upper surface of the steel plate (2), and then pouring concrete (4) on the upper surface of the steel plate (2).