Rare earth butadiene rubber post-treatment packaging line equipment installation method

By redetermining the equipment lifting sequence and plan, selecting appropriate broken house parts and lifting points, and using ground tanks and hanging cranes for equipment back-loading and installation, the traditional lifting method has solved the problems of high cost, long cycle and high risk, and achieved reduction Cost, efficiency and risk reduction effects.

CN119461070APending Publication Date: 2025-02-18CHINA CHEM ENG SECOND CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411683776.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-22
Publication Date
2025-02-18

AI Technical Summary

Technical Problem

The traditional rare earth butadiene rubber post-treatment finished workshop equipment lifting method is high cost, long cycle, and has high construction risks at high places.

Method used

By redetermining the equipment lifting sequence and plan, selecting the sides of the second and third floors as the location of the broken house, digging a hole, determining the lifting method and equipment selection of each equipment, lifting the second and third floor equipment into the corresponding floors respectively, and using The ground tank catches the equipment and transports it backwards to the near the equipment foundation for installation, determines the installation order of each layer of equipment, first installs the center of the equipment axis of the second layer, and then gradually installs the third layer and the first layer of equipment.

Benefits of technology

It reduces lifting costs, improves construction efficiency, reduces personnel and equipment investment, and reduces safety risks during construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119461070A_ABST
    Figure CN119461070A_ABST
Patent Text Reader

Abstract

The invention discloses a rare earth butadiene rubber post-treatment packaging line equipment mounting method which comprises the following steps: selecting side surfaces of a second floor and a third floor as house breaking positions, and digging holes in the house breaking positions; according to the position of the house breaking hole in the first step, the hoisting mode of each device and machine tool selection are determined; after the second-layer equipment and the third-layer equipment are hoisted into the corresponding floors, the ground tank receives the equipment, and then the equipment is transferred to the position near the equipment foundation and installed; the axis center of second-layer equipment is determined firstly, and then step-by-step installation is conducted on the third layer and the first layer at the same time according to the axis center of the second-layer equipment; and after the main equipment is installed in place, auxiliary matching equipment is installed. According to the method, by re-determining the correct equipment hoisting sequence and scheme, selecting the side faces of the second floor and the third floor as house breaking parts, selecting correct indoor hoisting point positions and determining the line forming equipment installation precision adjusting sequence, the personnel and machine tool investment is reduced, meanwhile, the construction efficiency is improved, and the safety risk in construction is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to an installation method for chemical equipment, and in particular to an installation method for rare earth butadiene rubber post-processing packaging line equipment. Background Art

[0002] In the rare earth butadiene rubber and supporting equipment project, the main equipment in the post-processing finished product workshop includes extrusion dehydrator, expansion dryer, vibrating conveyor, briquetting machine, etc. Among them, the expansion dryer and extrusion dehydrator equipment have large specifications and dimensions, dense installation distribution, and high installation precision. The post-processing finished product workshop has a total of three floors with a small space, which requires breaking the house for hoisting, and there is little space for personnel construction.

[0003] Traditionally, the lifting of equipment in finished product workshops is usually done by breaking down the roof, lifting important large equipment into place, and then lifting the remaining equipment in and then transporting it back. The installation sequence is to install the third-floor equipment first, and then lift and install the second-floor equipment. The above-mentioned lifting and installation method has high lifting costs, long construction periods, and high risks in high-altitude construction.

[0004] Therefore, it is the key to ensure efficiency to redefine the correct equipment hoisting sequence and plan, select the appropriate part of the broken house, choose the correct location of the hanging point inside the house, and determine the order of adjustment of the installation accuracy of the line equipment to reduce the investment in personnel and equipment. Summary of the invention

[0005] The invention provides a method for installing equipment of a rare earth butadiene rubber post-processing packaging line, which achieves the purpose of reducing the hoisting cost and improving the construction efficiency.

[0006] In order to solve the above technical problems, the technical solution adopted by the present invention is: a method for installing equipment of a rare earth butadiene rubber post-processing packaging line, wherein the rare earth butadiene rubber post-processing packaging line equipment comprises a three-layer equipment, a two-layer equipment and a one-layer equipment; wherein the three-layer equipment comprises an extrusion dehydrator, and the two-layer equipment comprises an expansion dryer, a vibration conveyor and a drying box; the installation of the above equipment comprises the following steps: Step 1: Select the sides of the second and third floors as the locations of the broken houses, and dig holes at the locations of the broken houses; Step 2: Determine the hoisting method and selection of equipment for each device according to the location of the hollow space in step 1; Step 3: After hoisting the second-floor equipment and the third-floor equipment into the corresponding floors, use the ground tank to catch the equipment, and then transport each equipment to the vicinity of the equipment foundation and install it; Step 4: Determine the installation sequence of the equipment on each floor, that is, first determine the center of the axis of the equipment on the second floor, and then gradually install it on the third floor and the first floor based on the center of the axis of the equipment on the second floor; Step 5: After the main equipment is installed in place, install the auxiliary supporting equipment.

[0007] As a preferred implementation, in step one, a 2m×3m hole is chiseled at the location of the dilapidated house.

[0008] As a preferred embodiment, in step 2, the extrusion dehydrator, expansion dryer and drying box equipment are hoisted by disassembly and then installation. The equipment is first disassembled and hoisted into the factory building, and then the equipment is installed and assembled.

[0009] As a preferred implementation, in step three, when the second-floor equipment is transported and installed, a manual hoist is used to fix the equipment lifting position at the front end of the equipment, and a traveling crane is used to fix the equipment lifting position at the rear end. Both sides are lifted simultaneously, and after the equipment is lifted to the equipment foundation, another manual hoist is used to pull the side and install the equipment on the equipment foundation.

[0010] As a preferred implementation, in step three, when the three-layer equipment is transported and installed, an electric floor tank and a traveling crane are used to lift it into place. The electric floor tank transports the equipment to the side of the equipment foundation, and then the traveling crane is used to lift the equipment into place.

[0011] As a preferred embodiment, the packaging line equipment of one layer is firstly located with an infrared level to find the axis position of the equipment group, and then installed one by one.

[0012] The present invention reduces the input of personnel and equipment by redetermining the correct equipment hoisting sequence and plan, selecting the sides of the second and third floors as the damaged house parts, choosing the correct hanging point positions in the house, and determining the precision adjustment sequence of the line equipment installation, thereby improving the construction efficiency and reducing the safety risks in the construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 The installation sequence of the rare earth butadiene rubber post-processing packaging line equipment of the present invention; Figure 2 This is the schematic diagram of the mainframe hoisting of the extrusion dehydration machine; Figure 3 This is the schematic diagram of the motor hoisting of the extrusion dehydrator; Figure 4 This is the schematic diagram of the expansion dryer host hoisting; Figure 5 This is the schematic diagram of the expansion dryer motor hoisting; Figure 6 This is a schematic diagram of the hoisting of the vibrating conveyor; Figure 7 This is a schematic diagram of drying box hoisting; Figure 8 This is a schematic diagram of buffer tank hoisting; Fig. 9 This is a schematic diagram of dust collector hoisting; Fig.10 This is a schematic diagram of the expansion dryer installation; Fig.11 This is a schematic diagram of the installation of a vibrating conveyor; Fig.12 This is a schematic diagram of the drying box installation; Fig.13 This is a schematic diagram of the installation of the transition hopper between the first and second layers; Fig.14 This is the installation diagram of the extrusion dehydration machine; Fig.15 Installation diagram of transition hopper between the second and third layers; In the figure, 1-motor, 2-coupling shield, 3-coupling, 4-expansion dryer mainframe, 5-discharging box, 6-vibration conveyor support, 7-lubricator support, 8-exhaust system, 9-drying box, 10-vibration conveyor, 11-transition hopper, 12-briquetting machine, 13-support barrel, 14-oblique barrel, 15-straight barrel, 16-support frame, 17-expansion dryer, 18-extrusion dehydrator mainframe; B1-anchor bolt M36×500 B2-bolt M10×35, B3-expansion bolt M16×150, B4-bolt M12×35, B5-expansion bolt M10×110. DETAILED DESCRIPTION

[0014] A typical embodiment of the present invention provides a method for installing equipment of a rare earth butadiene rubber post-processing packaging line, wherein the rare earth butadiene rubber post-processing packaging line equipment comprises a three-layer equipment, a two-layer equipment and a one-layer equipment; The third-layer equipment includes an extrusion dehydrator, and the second-layer equipment includes an expansion dryer, a vibration conveyor, and a drying box; the installation of the above equipment includes the following steps: Step 1: Select the sides of the second and third floors as the locations of the broken houses, and dig holes at the locations of the broken houses; Step 2: Determine the hoisting method and selection of equipment for each device according to the location of the hollow space in step 1; Step 3: After hoisting the second-floor equipment and the third-floor equipment into the corresponding floors, use the ground tank to catch the equipment, and then transport each equipment to the vicinity of the equipment foundation and install it; Step 4: Determine the installation sequence of the equipment on each floor, that is, first determine the center of the axis of the equipment on the second floor, and then gradually install it on the third floor and the first floor based on the center of the axis of the equipment on the second floor; Step 5: After the main equipment is installed in place, install the auxiliary supporting equipment.

[0015] This implementation method redefines the correct equipment hoisting sequence and plan, selects the appropriate damaged house location, chooses the correct indoor hoisting point location, and determines the installation accuracy adjustment sequence of the line equipment to reduce the investment in personnel and equipment.

[0016] The technical solution claimed in the present invention is further clearly and completely described below through a relatively specific embodiment.

[0017] This embodiment takes a rare earth butadiene rubber and supporting equipment project as an example. Its post-processing finished product workshop mainly includes: 3 extrusion dehydrators, 3 expansion dryers, 9 vibration conveyors, 6 briquetting machines, 3 mechanical arms and more than 300 other equipment. Among them, the expansion dryer is 28 tons, the dehydrator is 19 tons, the equipment specifications are large, the installation distribution is dense, and the installation precision is high.

[0018] In this embodiment, the requirements for equipment lifting are as follows: (1) For equipment with lifting eyes and lifting rings weighing less than 2.5 tons, three specifications of round strand steel wire ropes with fiber core, nominal tensile strength of 1770MPa, nominal diameter of φ12, and length of 6m, 8m and 10m can be used. One steel wire rope can be used with two strands to lift equipment weighing less than 1 ton, and two steel wire ropes can be used with four strands to lift equipment weighing 1 ton to 2.5 tons. (2) For equipment weighing 1 ton to 2.5 tons with lifting holes, the above steel wire ropes can be used. Two steel wire ropes can be used with four strands. If necessary, the steel wire ropes should be equipped with soft protection to avoid damaging the surface of the equipment. (3) For parts weighing more than 1 ton without lifting eyes, lifting rings or lifting holes, the above steel wire ropes should be used. The steel wire ropes should be equipped with soft protection to avoid damaging the surface of the equipment. For parts weighing less than 1 ton, synthetic fiber flat slings or synthetic fiber flexible slings should be used, and both should meet the requirements specified in JB / T 8521-1997.

[0019] In this embodiment, the sides of the second and third floors are selected as the locations for breaking down the houses, and 2m×3m holes are chiseled out in each of them, which are used for hoisting the third-floor equipment and the second-floor equipment respectively.

[0020] The main equipment on the third floor includes extrusion dehydration machine, extrusion dehydration machine oil station, drying box exhaust fan, mist exhaust hood, buffer tank, and dust collector. The main equipment on the second floor includes expansion dryer, expansion machine reducer oil pump, vibration conveyor, drying box, hot water pump, washing water pump, wastewater pump, and heat exchanger. The main equipment on the first floor is the packaging line equipment, which mainly includes briquetting machine, roller conveyor, bagging machine, and robotic arm.

[0021] The selection of the location of each equipment lifting point is as follows: Figure 2-9 As shown. Among them, the important second-layer equipment expansion dryer, expansion drying box, and third-layer equipment extrusion dehydrator, because these equipment are large in size before dismantling, the overall equipment is particularly heavy, difficult to hoist, high in hoisting cost, long in construction period, and high in high-altitude construction risk, so we adopt the method of dismantling, hoisting and reinstallation for installation. After dismantling, the equipment does not exceed 15 tons, the size is greatly reduced, and an 80-ton crane can be used.

[0022] The expansion dryer weighs 28 tons as a whole, and is mainly composed of motor 1, coupling 3, and host 4. We disassemble the motor 1 and host 4 of the expansion dryer at coupling 3. After disassembly, the motor alone weighs about 13 tons, and the reducer and host weigh 15 tons. An 80-ton crane is used to slowly move the equipment close to the second-floor hoisting hole. After the tail of the host enters the second-floor floor, 6 electric tanks are used to catch the tail of the host and slowly transport it to the equipment foundation.

[0023] The extrusion dehydrator weighs 19 tons, consisting of a motor 1, a coupling 3, and a main machine 18. We also disassembled the motor and the main machine of the dehydrator. After disassembly, the single machine weighs about 9 tons, and the main machine weighs 10 tons. It is hoisted into the third-floor hoisting hole in the same way as the above-mentioned expansion dryer, and then transported to the side of the third-floor equipment foundation.

[0024] The drying box weighs 3.7 tons as a whole. The equipment is 9 meters long, 1.7 meters wide and 3.95 meters high. The equipment specifications and dimensions are too large. We split the drying box 9 into three small drying boxes at the connection. Each small drying box is 3 meters long, and then hoist the small drying boxes.

[0025] After hoisting the equipment on the second and third floors respectively between the floors, each equipment is hoisted and transported backwards.

[0026] The equipment on the second floor is transported by a 15-ton overhead crane, three 10-ton manual hoists, and six electric tanks in the factory. Two manual hoists are used to fix the equipment hoisting position at the front end of the equipment, and a 15-ton overhead crane is used to fix the hoisting position at the rear end of the equipment. Both sides are lifted at the same time. After the equipment is raised to the equipment foundation, another manual hoist is used to pull the equipment on the side and install it on the equipment foundation.

[0027] The three-layer equipment is hoisted into place by electric tanks and 15-ton cranes. The electric tanks are used to transport the equipment to the side of the equipment foundation, and then the cranes are used to hoist the equipment into place.

[0028] In this embodiment, the equipment of the post-processing packaging line is distributed on three layers. The transition equipment between each layer is the transition barrel 11. The axis of the three-layer equipment group must be in a straight line. Therefore, the second-layer equipment is installed first to determine the central axis position of the complete set of equipment, and then the transition hopper is gradually installed, and then the central axis position of the three-layer equipment is determined.

[0029] (1) From the second floor to the first floor: The motor 1 and the main body 4 of the expansion dryer are installed, such as Fig.10As shown, reconnect the motor and the main body with a coupling, lift the expansion dryer main unit 4 and motor 1 assembly into place according to the plan and elevation layout, and adjust their positions so that the center of the motor assembly conveying shaft is aligned with the center of the body input shaft. Use an inclined iron pad to adjust the motor shaft to horizontal under the machine base, and use a level to check whether the main shaft of the main unit is horizontal. If it is not horizontal, use an inclined iron pad to level the main shaft under the machine base. Use coupling 3 to connect the output shaft of the motor assembly and the input shaft of the main unit. The total runout tolerance of the two parts of coupling 3 is 0.04, and the axial non-straightness tolerance is 0.03 / 100. Re-tighten the positioning bolts of the motor, and finally install the coupling shield 2. After the production line is installed and adjusted, connect the static grounding wire, extend the anchor bolt B1 from the side of the reserved hole of the expansion dryer, place it in the position shown in the drawing and pre-tighten it, and perform secondary grouting. Requirements for secondary grouting of anchor bolts: The concrete for secondary pouring should be fine stone concrete one grade higher than the foundation concrete, or use expansive cement.

[0030] like Fig.11 As shown, the vibration conveyor support 6 is hoisted into place, and the lubricator support 7 is placed in place. After the production line is installed and adjusted, the static grounding wires of each machine are connected, and the foot of the vibration conveyor support 6 is welded to the embedded steel plate, and the foot of the lubricator support 7 is fixed with the expansion bolt B3.

[0031] like Fig.12 As shown, the drying box 9 is hoisted into place and adjusted to completely cover the vibration conveyor support 6. The exhaust system 8 is installed on the drying box 9 with bolts B2. After the production line is installed and adjusted, the foot of the drying box 9 is welded to the pre-buried steel plate on site.

[0032] like Fig.13 As shown, install the transition hopper 11 connecting the first and second layers, lift the transition hopper 11 into place, align the feed port with the discharge port of the drying box, install the transition hopper 11 on the briquetting machine 12 with bolts B4, and then install the subsequent packaging line equipment including roller conveyors, bagging machines and robotic arms.

[0033] (2) From the second floor to the third floor: like Fig.14As shown, place the main machine 18 of the extrusion dehydrator and the motor crane 1 in place according to the plan and elevation layout, adjust their positions, align the main machine feed bucket center with the upstream feeding center, align the motor shaft conveying center with the main machine input center, connect the motor output shaft and the main machine reducer input shaft with the coupling 3, and use shims to level the components to ensure that the coupling has a total runout tolerance of 0.04 and an axial straightness tolerance of 0.03 / 100. After the production line is installed and adjusted, extend the anchor bolt B1 from the side of the reserved hole of the extrusion dehydrator, place it in the position shown in the drawing and pre-tighten it, and perform secondary grouting. Requirements for secondary grouting of anchor bolts: The secondary poured concrete should use fine stone concrete one grade higher than the foundation concrete, or use expansive cement.

[0034] Then install the transition hopper 11 between the second and third layers, such as Fig.15 As shown, the upper end of the support barrel 13 is inserted into the discharge barrel of the extrusion dehydrator 18, and fixed with expansion bolts B5 to assemble the barrel. The straight barrel is installed on the expansion dryer 17 with bolts B4, and the inclined barrel support frame is fixed with expansion bolts B3. Then the washing glue tank and buffer tank are hoisted and installed.

[0035] After the extrusion dehydrator and expansion dryer are installed, the lubrication system is hoisted and placed in place according to the plan and elevation layout drawings, and its anchors are fixed with anchor bolts.

[0036] Finally, here is the installation method for the packaging line equipment: Use an infrared level to lay out the center axis of the briquetting machine, and install the equipment from front to back. If the equipment body blocks the infrared level, we use the method of leading the wire horizontally, then along the axis, and then leading the wire back. After each lead, use an ink fountain to pop out the lead-out line segment.

Claims

1. A method for installing equipment of a rare earth butadiene rubber post-processing packaging line, wherein the rare earth butadiene rubber post-processing packaging line equipment comprises a three-layer equipment, a two-layer equipment and a first-layer equipment; in, The third-layer equipment includes an extrusion dehydrator, and the second-layer equipment includes an expansion dryer, a vibration conveyor, and a drying box; the installation of the above equipment includes the following steps: Step 1: Select the sides of the second and third floors as the locations of the broken houses, and dig holes at the locations of the broken houses; Step 2: Determine the hoisting method and selection of equipment for each device according to the location of the hollow space in step 1; Step 3: After hoisting the second-floor equipment and the third-floor equipment into the corresponding floors, use the ground tank to catch the equipment, and then transport each equipment to the vicinity of the equipment foundation and install it; Step 4: Determine the installation sequence of the equipment on each floor, that is, first determine the center of the axis of the equipment on the second floor, and then gradually install it on the third floor and the first floor based on the center of the axis of the equipment on the second floor; Step 5: After the main equipment is installed in place, install the auxiliary supporting equipment.

2. The method for installing the equipment of the rare earth butadiene rubber post-processing packaging line according to claim 1, characterized in that: In step one, a 2m×3m hole is chiseled at the location of the dilapidated house.

3. The method for installing the equipment of the rare earth butadiene rubber post-processing packaging line according to claim 1 or 2, characterized in that: In step 2, the extrusion dehydrator, expansion dryer and drying box equipment are hoisted by disassembly and installation. The equipment is first disassembled and hoisted into the factory, and then the equipment is installed and assembled.

4. The method for installing the equipment of the rare earth butadiene rubber post-processing packaging line according to claim 3, characterized in that: In step three, when the second-floor equipment is transported and installed, a manual hoist is used to fix the equipment lifting position at the front end of the equipment, and a traveling crane is used to fix the equipment lifting position at the rear end. Both sides are lifted simultaneously. After the equipment is lifted to the equipment foundation, another manual hoist is used to pull the equipment from the side and install it on the equipment foundation.

5. The method for installing the equipment of the rare earth butadiene rubber post-processing packaging line according to claim 4, characterized in that: In step three, when the three-layer equipment is transported and installed, an electric floor tank and a traveling crane are used to lift it into place. The electric floor tank transports the equipment to the equipment foundation, and then the traveling crane is used to lift the equipment into place.

6. The method for installing the equipment of the rare earth butadiene rubber post-processing packaging line according to claim 1 or 5, characterized in that: For the packaging line equipment on the first floor, first use an infrared level to find the axis position of the equipment group, and then install them one by one.