Open excavation construction structure of subway station
By dividing the ancillary works of the subway station into two parts that are far away from the main project and those close to the main project, and using a stable supporting structure, the problem of the long construction period of the subway station is solved, synchronous construction is achieved, and construction efficiency and safety are improved.
Patent Information
- Application Number
- CN202420269472.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-04
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2034-02-04
AI Technical Summary
During the open-cut construction of subway stations, due to the constraints of urban traffic arteries, the construction period of the main project and ancillary projects is long, making it difficult to proceed simultaneously, affecting construction efficiency.
Divide the ancillary works of the subway station into the first ancillary project far away from the main project and the second ancillary project close to the main project. Use stable support structures, including connecting beams, crown beams, diagonal braces and retaining piles, to achieve simultaneous construction. , shorten the construction period.
By dividing the construction area and setting up a stable top support structure, the construction of the subway station can be carried out simultaneously, the construction period is shortened, and the construction efficiency and safety are improved.
Smart Images

Figure CN221798452U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of subway station construction, and more specifically, to an open-cut construction structure of a subway station. Background Art
[0002] Urban subway stations are typical representatives of large-scale underground projects, mostly located under urban roads, and there are many influencing factors during the construction process.
[0003] A subway station includes a main project located under the center of the road and ancillary projects located under both sides or one side of the road. Due to the heavy pressure of traffic relief during urban subway construction, temporary land restrictions, complex synchronous construction force system, and too many overlapping construction procedures, the open-cut construction structure of a subway station generally involves first constructing the foundation pit and structure of the main station project, and then constructing the foundation pit and structure of the ancillary projects of the station.
[0004] However, most subway stations are located on major urban traffic arteries. During construction, the original roads need to be relocated to one or both sides of the main project foundation pit. After the main structure is capped, the roads are relocated back to the foundation pit and structure of the auxiliary project. The construction period is relatively long. When the construction period is tight, corresponding measures need to be taken to ensure the construction period. Utility Model Content
[0005] In view of the above problems, the purpose of the utility model is to provide an open-cut construction structure for a subway station, which divides the station's ancillary projects into two parts. The part far away from the main project can be constructed simultaneously with the main project, and the part close to the main project can be constructed simultaneously with the remaining projects through a stable support structure, thereby effectively shortening the construction period of the subway station and ensuring safety.
[0006] The utility model provides an open-cut construction structure of a subway station, comprising a main project and an auxiliary project, wherein the auxiliary project comprises a first auxiliary project and a second auxiliary project arranged along the width direction of a road, the first auxiliary project is far away from the main project, the second auxiliary project is adjacent to the main project, a second foundation pit of the second auxiliary project is set in a rectangular shape, and the long side of the second foundation pit is along the length direction of the road; the first auxiliary project and the main project are constructed simultaneously, a connecting beam is arranged along the edge of the second foundation pit above the completed first auxiliary project or the main project, a second crown beam is arranged inside the second foundation pit, and a second diagonal brace is connected between the connecting beam and the second crown beam.
[0007] The connecting beam includes two corbel beams, and the two corbel beams are respectively arranged at two ends of the upper part of the top plate of the first auxiliary project or the main project close to the edge of the second foundation pit.
[0008] The length of the corbel beam is not greater than one third of the long side of the second foundation pit.
[0009] A row of second foundation pit retaining piles is arranged at both ends of the second foundation pit, the second crown beam is connected to the upper ends of the row of second foundation pit retaining piles, and the second diagonal brace is connected between the corbel beam and the second crown beam adjacent thereto.
[0010] The number of second diagonal braces connecting the corbel beam and the second crown beam adjacent thereto is at least two.
[0011] A circle of first crown beams is arranged on the upper part of the first auxiliary project, and a circle of main crown beams is arranged on the upper part of the main project.
[0012] A second cross brace is connected between the edge of the first crown beam close to the second foundation pit and the edge of the main crown beam close to the second foundation pit. The second cross brace is located in the middle of the second foundation pit and is parallel to the width direction of the second foundation pit.
[0013] The number of the second cross braces is at least two.
[0014] By using the above-mentioned open-cut construction structure of the subway station according to the utility model, the auxiliary project of the station is divided into two construction periods along the width direction of the road. The first auxiliary project far away from the main project of the station is constructed synchronously with the main project, and the second auxiliary project close to the main project is constructed after the main project or the first auxiliary project is completed. Since both sides of the second auxiliary project have been hollowed out, a connecting beam is set at the top of the completed project, and a second diagonal brace is connected between the connecting beam and the second crown beam of the second auxiliary construction period to form a stable top support structure. The top support structure supports the construction of the second auxiliary project. The utility model speeds up the construction speed, shortens the construction period, stably supports the construction, and ensures the construction quality. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] By referring to the following description in conjunction with the drawings and the contents of the claims, and with a more comprehensive understanding of the present invention, other objects and results of the present invention will become more apparent and easier to understand.
[0016] In the attached picture:
[0017] Figure 1 It is a schematic plan view of an open-cut construction structure of a subway station according to an embodiment of the utility model;
[0018] Figure 2 for Figure 1 BB cross-sectional view;
[0019] Figure 3 It is a schematic plan view of the first stage construction of the second auxiliary project according to an embodiment of the utility model;
[0020] Figure 4 for Figure 3 CC section view;
[0021] Figure 5 for Figure 3 DD cross-sectional view;
[0022] Figure 6 It is a schematic plan view of the second phase construction of the second auxiliary project according to an embodiment of the utility model;
[0023] Among them, 1-main project, 2-ancillary project, 3-first ancillary project, 4-second ancillary project, 5-connecting beam, 6-second crown beam, 7-second diagonal brace, 8-corbel beam, 9-first top plate, 10-second foundation pit, 11-second foundation pit retaining pile, 12-first crown beam, 13-first foundation pit retaining pile, 14-main crown beam, 15-main foundation pit retaining pile, 16-second cross brace, 17-second top plate, 18-main top plate;
[0024] The same reference numerals throughout the drawings indicate similar or corresponding features or functions. DETAILED DESCRIPTION
[0025] In the following description, for the purpose of illustration, in order to provide a comprehensive understanding of one or more embodiments, many specific details are set forth. However, it is apparent that these embodiments may also be implemented without these specific details. In other examples, for ease of describing one or more embodiments, known structures and devices are shown in the form of block diagrams.
[0026] The present invention can be subjected to various changes and can have various embodiments, and specific embodiments are illustrated and described in the accompanying drawings. However, the present invention is not limited to the specific implementation, and all changes, equivalents and substitutes falling within the concept and technical scope of the present invention are included, and should be understood to be included.
[0027] Ordinal terms such as first, second, etc. may be used to describe various components, but the components are not limited to the terms. The terms are only used to distinguish one component from another component. For example, without departing from the scope of the claims of the present invention, the second component may be named as the first component, and similarly, the first component may be named as the second component. The terms and / or include a combination of multiple items recorded in association or a certain item among multiple items recorded in association.
[0028] It should be understood that when a certain component is mentioned to be "connected" or "contacted" with other components, this includes not only the case where it is directly connected or contacted with other components, but also the case where other components exist in between. Conversely, when a certain component is mentioned to be "directly connected" or "directly contacted" with other components, it should be understood that there are no other components in between.
[0029] In the description of the embodiments, when it is described that a certain component is formed "on or under" another component, on or under includes two components directly contacting each other or at least one other component is arranged and formed between the two components. Moreover, when it is expressed as on or under, it refers to not only the upper direction but also the lower direction based on a certain component.
[0030] The terms used in this application are only used to illustrate specific embodiments and are not intended to limit the present invention. Unless the context clearly stipulates otherwise, singular expressions include plural expressions. In this application, it should be understood that terms such as "including" or "having" are used to specify the presence of features, numbers, steps, operations, constituent elements, parts or combinations thereof recorded in the specification, and do not preclude the presence or additional possibility of one or more other features, numbers, steps, operations, constituent elements, parts or combinations thereof.
[0031] Unless otherwise defined, all terms used herein, including technical or scientific terms, have the same meaning as those generally understood by those skilled in the art. Terms defined in commonly used dictionaries should be interpreted as having the same meaning as in the context of the relevant technology, and if not clearly defined in this application, they should not be interpreted as ideal or overly formal meanings.
[0032] In order to more clearly illustrate the technical solution of the present invention, some technical terms involved in the present invention are briefly explained below.
[0033] Cut and Cover Method: refers to an underground construction method that first digs up the ground, builds the lining in the open air, and then covers and backfills. It is mostly used for shallow buried tunnels. Cut and Cover Method is the most basic and most commonly used construction method in soft soil underground construction.
[0034] Retaining piles: Their function is to block the earthwork of the roads outside the foundation pit after excavation to protect the safety of construction inside the foundation pit. At the same time, the retaining piles also have a water-stopping effect, which can prevent external water from flowing into the foundation pit.
[0035] Crown beam: A reinforced concrete continuous beam installed on the top of the supporting (enclosing) structure (mostly piles and walls) around the foundation pit. Its function is to connect all the piles together to prevent the top edge of the foundation pit from collapsing.
[0036] The specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings.
[0037] like Figure 1-Figure 6 As shown together, the open-cut construction structure of the subway station proposed in this embodiment can be used to construct the main project and ancillary projects inside the subway station, and can also be used to construct other underground spaces by the open-cut method.
[0038] The subway station includes a main project 1 and an ancillary project 2 connected to the main project 1. In the existing technology, the main project 1 is constructed first, and the ancillary project 2 is not constructed. The upper part of the ancillary project 2 is used as a relief road for vehicles. After the main project 1 is completed, the ancillary project 2 is constructed. The upper part of the main project 1 is used as a relief road. The main project 1 and the ancillary project 2 are constructed successively, which prolongs the construction period. The open-cut construction structure of the local subway station can make the ancillary project 2 and the main project 1 constructed simultaneously, which can effectively shorten the construction period and ensure the construction quality.
[0039] The open-cut construction structure of the subway station includes a main project 1 and an ancillary project 2. The ancillary project 2 includes a first ancillary project 3 and a second ancillary project 4 arranged along the width direction of the road. The first ancillary project 3 is far away from the main project 1, and the second ancillary project 4 is adjacent to the main project 1.
[0040] In order to construct synchronously with the main project 1, the station's ancillary project 2 is divided into a first ancillary project 3 and a second ancillary project 4. The first ancillary project 3, which is not adjacent to the main project 1, can be constructed synchronously with the main project 1. The stone of the middle second ancillary project 4 can support the construction of the main project 1 and the first ancillary project 3 to ensure the safety of the construction.
[0041] The boundaries of the first auxiliary project 3 and the second auxiliary project 4 can be divided according to the specific conditions of road driving and construction. In order to facilitate construction in the later stage, the second foundation pit 10 of the second auxiliary project 4 in this embodiment is set to a rectangular shape, and the long side of the second foundation pit 10 is along the length direction of the road.
[0042] The main project 1 and the first ancillary project 3 are constructed simultaneously using the open-cut method, and the upper road of the unconstructed second ancillary project 4 is used as a relief road.
[0043] The construction scope of the main project 1 and the first ancillary project 3 is fenced and constructed by open excavation method. The top of the second ancillary project 4 is used for vehicle driving, which can not only reduce the construction period but also ensure road driving.
[0044] The method of constructing the main body project 1 may include constructing the main body foundation pit retaining piles 15 and the main body temporary columns, constructing the main body crown beam 14, constructing the main body diagonal brace, constructing the main body retaining wall, constructing the main body structure, and backfilling the main body road surface. The construction sequence can be adjusted according to the specific conditions on site.
[0045] The construction of the main body foundation pit retaining piles 15 and the main body temporary columns may include: the main body foundation pit retaining piles 15 are set around the main body project 1, and the main body foundation pit retaining piles 15 can be concrete cast-in-place piles. The main body foundation pit retaining piles 15 are used to block the earthwork of the road outside the main body foundation pit after the main body foundation pit is excavated, and to protect the construction safety in the main body foundation pit; a number of main body temporary columns are set at appropriate positions inside the main body project 1. During the excavation of the main body foundation pit, the main body temporary columns can play an auxiliary supporting role for the main body foundation pit.
[0046] The main foundation pit retaining piles 15 are arranged around the inside of the main project 1, and the main temporary columns are distributed inside the main project 1. After the supporting piles of the main project 1 are set, the main foundation pit is excavated. The main foundation pit retaining piles 15 close to the second auxiliary project 4 separate the inside of the main project 1 from the inside of the second auxiliary project 4.
[0047] In order to stably support the main foundation pit retaining piles 15 and the main temporary columns, the main crown beam 14 is constructed. The construction of the main crown beam 14 may include connecting a circle of main crown beams 14 to the upper ends of a circle of main foundation pit retaining piles 15 when excavating the surface earth and stone of the main project 1. The main crown beam 14 supports and connects all the main foundation pit retaining piles 15 together to prevent the top edge of the main foundation pit from collapsing.
[0048] The main crown beam 14 is connected to the upper part of the main foundation pit retaining piles 15 around the body, forming a reinforced concrete frame at the upper edge of the main foundation pit.
[0049] In order to further stabilize the support of the main crown beam 14, the main diagonal brace is constructed. Inside the main crown beam 14 of the reinforced concrete frame, several main diagonal braces are connected according to the construction situation. The main diagonal brace plays a role of supporting the main crown beam 14 in the inner circle of the main crown beam 14, thereby supporting the main foundation pit retaining piles 15 to prevent collapse during excavation. The two ends of some main diagonal braces are connected to the inner side of the main crown beam 14, and the middle is connected to the upper part of the temporary main column. The three points are connected to the main diagonal brace together, and the support is more stable.
[0050] In order to ensure the stability and safety of the construction during the excavation process, the main retaining wall is constructed and a circle of main retaining wall is set up around the main foundation pit.
[0051] The main retaining wall is set around the upper part of the main foundation pit, separating the construction site and the relief road, ensuring construction safety and traffic safety.
[0052] After the upper support of the main foundation pit is completed, the open excavation method is adopted to continue the construction, and the excavation is carried out to the bottom of the main foundation pit. The main bottom plate, main side plate, main top plate 18, main middle plate, etc. are constructed in the main foundation pit to form the main structure.
[0053] After the main roof is capped, the main road surface is backfilled, a waterproof layer is constructed on the upper part of the main roof 18, and then the soil is backfilled to restore the main road surface, and the construction of the main project 1 is completed.
[0054] The first ancillary project 3 is constructed while the main project 1 is constructed, and the second ancillary project 4 is not constructed as a relief road.
[0055] The method of constructing the first auxiliary project 3 may include constructing the first foundation pit retaining pile 13 and the first temporary column, constructing the first crown beam 12, constructing the first diagonal brace, constructing the first retaining wall, constructing the first structure, and backfilling the first road surface. The construction sequence may be adjusted according to the specific conditions on site.
[0056] The construction of the first foundation pit retaining piles 13 and the first temporary columns may include driving the first foundation pit retaining piles 13 inside the first ancillary project 3, arranging the first foundation pit retaining piles 13 around the inside of the first ancillary project 3, and setting a number of first temporary columns inside the first ancillary project 3 according to the construction situation.
[0057] The first foundation pit retaining piles 13 close to the second auxiliary project 4 separate the interior of the first auxiliary project 3 from the interior of the second auxiliary project 4. The first foundation pit retaining piles 13 in one circle jointly block the earthwork of the road outside the first foundation pit to protect the construction safety in the first foundation pit. The first temporary columns are distributed inside the first auxiliary project 3 and can play an auxiliary supporting role for the first foundation pit. After the piles inside the first auxiliary project 3 are set, the first foundation pit is excavated.
[0058] In order to stably support the first foundation pit retaining piles 13 and the first temporary columns, the first crown beam 12 is constructed. The construction of the first crown beam 12 may include, when excavating the surface earth and stone of the first ancillary project 3, connecting a circle of first crown beams 12 to the upper ends of the first foundation pit retaining piles 13, the first crown beam 12 supports and connects all the first foundation pit retaining piles 13 together to prevent the top edge of the first foundation pit from collapsing.
[0059] The first cap beam 12 is connected to the upper part of all the first foundation pit retaining piles 13 to form a reinforced concrete frame at the upper edge of the first foundation pit.
[0060] In order to further stabilize the support of the first crown beam 12, the first diagonal brace is constructed. Inside the first crown beam 12 of the reinforced concrete frame, several first diagonal braces are connected according to the construction situation. The first diagonal brace plays the role of supporting the first crown beam 12 in the inner circle of the first crown beam 12, thereby supporting the first foundation pit retaining pile to prevent collapse during excavation. Some first diagonal braces have their two ends connected to the inside of the first crown beam 12 and the middle connected to the upper part of the first temporary column. The three points are connected to the first diagonal brace together, and the support is more stable.
[0061] In order to ensure the stability and safety of the construction during the excavation process, the first retaining wall is constructed and a circle of the first retaining wall is set around the first foundation pit. The first retaining wall is set around the upper part of the first foundation pit, separating the construction site from the relief road, ensuring the safety of construction and traffic.
[0062] After the upper support of the first foundation pit is completed, the open excavation method is adopted to continue the construction, excavating to the bottom of the first foundation pit, constructing the first bottom plate, the first side plate, the first top plate 9, etc. in the first foundation pit to form the first structure, and the internal structure construction of the first auxiliary project 3 of the auxiliary project 2 is completed.
[0063] The first road surface is backfilled, a waterproof layer is constructed on the upper part of the first top plate 9, and then soil is backfilled to restore the first road surface.
[0064] In order to quickly construct the second auxiliary project 4, once one of the first auxiliary project 3 or the main project 1 has been capped, the second auxiliary project 4 will be started. The completed first auxiliary project 3 or the main project 1 will be used as a relief road. The second auxiliary project 4 will be carried out simultaneously with the remaining projects, saving man-hours.
[0065] In order to ensure the stable construction of the second ancillary project 4, a connecting beam 5 is arranged above the completed first ancillary project 3 or the main project 1 near the edge of the second foundation pit. The connecting beam 5 is along the length direction of the road. A second crown beam 6 is arranged inside the second ancillary project 4. A second diagonal brace 7 is connected between the connecting beam 5 and the second crown beam 6 of the second ancillary project 4 to form a top support structure of the second ancillary project 4.
[0066] The top support structure can support the stable excavation of the second auxiliary project 4 that has been hollowed out on both sides, as well as the construction of the second structure.
[0067] The connecting beam 5 may include two corbel beams 8, the length of which is no more than one third of the side length of the second foundation pit 10 along the road direction, and can be sufficient to stably install the second diagonal brace 7. The corbel beams 8 are arranged at both ends of the upper part of the top plate of the first auxiliary project 3 or the main project 1 that is capped first, close to the edge of the second foundation pit, so as to facilitate connecting the second diagonal brace 7 between the corbel beams 8 and the second crown beams 6 adjacent thereto.
[0068] A corbel beam 8 is arranged on the top plate of the first auxiliary project 3 or the main project 1 which is capped first, so as to be connected to the second diagonal support 7 of the second foundation pit 10 .
[0069] If the first auxiliary project 3 is to be capped before or at the same time as the main project 1, the corbel beam 8 is constructed before backfilling the first road surface during the construction of the first auxiliary project 3. A corbel beam 8 is respectively set at both ends of the edge of the first top plate 9 close to the second auxiliary project 4, and the corbel beam 8 is parallel to the length direction of the road. When backfilling the first road surface, the position of the corbel beam 8 is temporarily not backfilled.
[0070] If the main project 1 is capped before the first ancillary project 3, a corbel is constructed before backfilling the main road surface. A corbel is set at both ends of the edge of the main top plate 18 close to the second ancillary project 4. The corbel is parallel to the length direction of the road. When backfilling the main road surface, the position of the corbel is reserved and not backfilled temporarily.
[0071] In this embodiment, the first auxiliary project 3 is completed first, and the corbel beam 8 is arranged above the first top plate 9. Figure 1 and Figure 2 After the corbel beam 8 is set, the second auxiliary project 4 is started to be constructed.
[0072] The construction of the second auxiliary project 4 may include the construction of the second foundation pit retaining pile 11, the construction of the second crown beam 6, the construction of the second diagonal brace 7, the construction of the second horizontal brace 16, the construction of the second retaining wall, the construction of the second structure, and the backfilling of the second road surface. The construction sequence can be adjusted according to the site conditions.
[0073] The construction of the second foundation pit retaining piles 11 may include respectively driving a plurality of second foundation pit retaining piles 11 at the edges of the second auxiliary project 4 that are not in contact with the first auxiliary project 3 and the main project 1. A row of second foundation pit retaining piles 11 is provided at both ends of the second auxiliary project 4 to block the road earthwork at both ends of the second foundation pit 10 and protect the construction safety in the second foundation pit 10.
[0074] After the piles inside the second auxiliary project 4 are set, the second foundation pit 10 is excavated.
[0075] In order to stably support the second foundation pit retaining piles 11, a second crown beam 6 is constructed. The construction of the second crown beam 6 may include connecting the second crown beam 6 to the upper ends of two rows of second foundation pit retaining piles 11 when excavating the surface earth and stone of the second ancillary project 4. The second crown beam 6 supports and connects a row of second foundation pit retaining piles 11 together to prevent the top edge of the second foundation pit 10 from collapsing.
[0076] The second cap beam 6 is connected to the upper part of a row of second foundation pit retaining piles 11 to form a reinforced concrete cross beam at the upper edge of the second foundation pit 10 .
[0077] In order to further stabilize the support, the second diagonal brace 7 is constructed. Between the inner side of the second crown beam 6 of the reinforced concrete cross beam and the adjacent corbel beam 8, at least two second diagonal braces 7 are connected according to the construction situation. The second diagonal brace 7 plays the role of supporting the second crown beam 6, thereby supporting the second foundation pit retaining pile 11 to prevent collapse during the excavation of the second foundation pit 10. The second diagonal brace 7 is connected between the corbel beam 8 and the second crown beam 6 adjacent to the corbel beam 8, which facilitates the removal of the main foundation pit retaining pile 15, the first foundation pit retaining pile 13 and the crown beam inside the second foundation pit 10.
[0078] In order to strengthen the support, the top support structure may further include a second cross brace 16, which is connected between the edge of the first crown beam 12 close to the second auxiliary project 4 and the edge of the main crown beam 14 close to the second auxiliary project 4, and is located in the middle of the second auxiliary project 42. The second cross brace 16 is along the width direction of the road.
[0079] At least two second cross braces 16 are connected between the main crown beam 14 and the middle part of the first crown beam 12. The second cross braces 16 can be located between the two corbel beams 8 to support and connect the main crown beam 14 and the first crown beam 12, facilitating subsequent construction.
[0080] In order to ensure the stability and safety of the construction during the excavation process, a second retaining wall is constructed. The second retaining wall is set around the second foundation pit 10 to separate the construction site and the relief road, thereby ensuring construction safety and traffic safety.
[0081] After the upper support of the second foundation pit 10 is completed, excavation construction is continued to remove the first crown beam 12, the first foundation pit retaining piles 13, the main crown beam 14, and the main foundation pit retaining piles 15 within the second foundation pit 10, and construct the second bottom plate, the second side wall, the second top plate 17, etc. in the second foundation pit 10 to form a second structure. The second structure connects the main structure and the first structure respectively to form a complete underground structure.
[0082] In order to stabilize the construction and facilitate construction support during the construction of the second structure, the construction is carried out in two stages. The first stage is the construction of the structures at both ends, and the second stage is the construction of the middle structure.
[0083] Specifically, Figure 3 , Figure 4 and Figure 5 As shown, the first stage of construction may include, as the second foundation pit 10 is excavated, chiseling out the first crown beam 12, the first foundation pit retaining piles 13, the main crown beam 14, and the main foundation pit retaining piles 15 within the range below the corbel beam 8; after the second foundation pit 10 is excavated to the bottom, constructing the second bottom plate and the second top plate 17 within the range below the corbel beam 8, constructing the second side wall, etc.
[0084] During the process of removing the supporting piles at both ends of the second foundation pit 10, the second diagonal brace 7 between the second crown beam 6 and the corbel beam 8 and the second cross brace 16 in the middle are used for support to prevent collapse during the excavation process. The parts at both ends of the second foundation pit 10 are first connected with the main project 1 and the first auxiliary project 3 for construction, and the second cross brace 16 in the middle of the second foundation pit 10 is not removed first, so as to facilitate auxiliary support during the construction of the parts at both ends.
[0085] like Figure 6 As shown, the second stage of construction may include chiseling out the first crown beam 12, the first foundation pit retaining pile 13, the main crown beam 14, the main foundation pit retaining pile 15, and the second cross brace 16 within the range between the two corbel beams 8, constructing the remaining parts of the second bottom plate and the second top plate 17, and completing the construction of the second structure.
[0086] The supporting piles in the range between the two corbel beams 8 are chiseled out, the middle part of the second foundation pit 10 is connected with the main project 1 and the first auxiliary project 3, and the middle part of the second structure is constructed.
[0087] After the construction of the second structure is completed, the second diagonal brace 7, the corbel beam 8 and the second retaining wall are removed, a waterproof layer is constructed on the upper part of the second top plate 17, and then the soil is backfilled to restore the second road surface.
[0088] Regardless of whether the corbel beam 8 is arranged on the main top plate 18 of the main project 1 or on the first top plate 9 of the first auxiliary project 3, the support structure of the second auxiliary project 4 of this construction can be used for construction.
[0089] If ancillary projects 2 are set up on both sides of the main project 1, the ancillary projects 2 on both sides are constructed simultaneously.
[0090] The construction of auxiliary project 2 and main project 1 has been completed, and the station construction has been completed. The main structure, the second structure, and the first structure are connected to form a complete internal structure of the station. The main pavement, the second pavement, and the first pavement are connected to restore the original state of the road.
[0091] As described above, the open-cut construction structure of a subway station according to the utility model is described by way of example with reference to the accompanying drawings. However, those skilled in the art should understand that various improvements can be made to the open-cut construction structure of a subway station proposed by the utility model without departing from the content of the utility model. Therefore, the protection scope of the utility model should be determined by the content of the attached claims.
Claims
1. An open-cut construction structure of a subway station, including a main project and ancillary projects, It is characterized in that The ancillary project comprises a first ancillary project and a second ancillary project arranged along the width direction of the road, the first ancillary project is far away from the main project, the second ancillary project is adjacent to the main project, the second foundation pit of the second ancillary project is set to be rectangular, and the long side of the second foundation pit is along the length direction of the road; The first ancillary project and the main project are constructed simultaneously, a connecting beam is arranged above the completed first ancillary project or the main project and near the edge of the second foundation pit, a second crown beam is arranged inside the second foundation pit, and a second diagonal brace is connected between the connecting beam and the second crown beam.
2. The open-cut construction structure of a subway station as claimed in claim 1, It is characterized in that The connecting beam includes two corbel beams, and the two corbel beams are respectively arranged at two ends of the upper part of the top plate of the first auxiliary project or the main project close to the edge of the second foundation pit.
3. The open-cut construction structure of a subway station as claimed in claim 2, It is characterized in that The length of the corbel beam is not greater than one third of the long side of the second foundation pit.
4. The open-cut construction structure of a subway station as claimed in claim 2, It is characterized in that A row of second foundation pit retaining piles is arranged at both ends of the second foundation pit, the second crown beam is connected to the upper ends of the row of second foundation pit retaining piles, and the second diagonal brace is connected between the corbel beam and the second crown beam adjacent thereto.
5. The open-cut construction structure of a subway station as claimed in claim 4, It is characterized in that The number of second diagonal braces connecting the corbel beam and the second crown beam adjacent thereto is at least two.
6. The open-cut construction structure of a subway station as claimed in claim 1, It is characterized in that A circle of first crown beams is arranged on the upper part of the first auxiliary project, and a circle of main crown beams is arranged on the upper part of the main project.
7. The open-cut construction structure of a subway station as claimed in claim 6, It is characterized in that A second cross brace is connected between the edge of the first crown beam close to the second foundation pit and the edge of the main crown beam close to the second foundation pit. The second cross brace is located in the middle of the second foundation pit and is parallel to the width direction of the second foundation pit.
8. The open-cut construction structure of a subway station as claimed in claim 7, It is characterized in that The number of the second cross braces is at least two.