Mounting bracket of frame steel secondary beam

By designing a mounting bracket for frame steel structures, the installation process of steel secondary beams is simplified using screws and rolling systems, which solves the problem of high construction costs and achieves the effects of simple assembly, convenient operation, and cost reduction.

CN221799225UActive Publication Date: 2024-10-01BEIJING SHOUGANG CONSTR GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323664867.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-29
Publication Date
2024-10-01
Estimated Expiration
2033-12-29

AI Technical Summary

Technical Problem

In the construction of frame steel structures, the installation of steel secondary beams requires a large number of crane shifts, resulting in high construction costs.

Method used

An installation bracket is designed, which is fixed with screws between the slotted vertical plate and the main beam. The cantilever rod and rolling system are used to make the cantilever rod droop. The hanging rope is bound to the steel secondary beam, and is lifted to the installation position through the pull rope for welding and fixation. Reduce the use of cranes.

Benefits of technology

This method simplifies the assembly process, is easy to operate, reduces construction costs, avoids the use of a large number of cranes, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221799225U_ABST
    Figure CN221799225U_ABST
Patent Text Reader

Abstract

The utility model discloses a mounting bracket for a frame steel secondary beam and belongs to the technical field of frame steel structure mounting construction. Comprising a clamping groove vertical plate (1), a screw (2), a clamping groove transverse plate (3), a lower connecting rod (4), a stand column (5), an upper connecting rod (6), a lifting rope (7), a lifting lug (8), a cantilever rod (9), an upper sliding roller (10), an upper rolling shaft (11), a fixing ring (12), a lower rolling shaft (13), a lower sliding roller (14) and a pull rope (15). The device has the advantages of being simple to assemble, convenient to operate, simple and practical, avoiding the use of a large number of cranes, being convenient and fast, and greatly reducing the construction cost.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of frame steel structure installation and construction, and in particular provides a mounting bracket for a frame steel secondary beam. Background Art

[0002] During the installation and construction of frame steel structures, the installation of steel secondary beams is generally carried out with the cooperation of cranes. Since there are many secondary beams between the main beams, a large number of crane shifts are required, and the construction cost is high. Utility Model Content

[0003] The utility model aims to provide a mounting bracket for a frame steel secondary beam, which solves the problem of high construction cost.

[0004] The utility model fixes the installation bracket and the main beam on one side of the frame by screws on both sides of the slot vertical plate, and then releases the pull rope. Since the center of gravity of the cantilever rod is in front of the upper sliding roller, the upper sliding roller is rolled to make the front of the cantilever rod droop until it is above the position where the steel secondary beam is placed. Then the steel secondary beam is tied with a lifting rope, and then the pull rope is pulled to lift the steel secondary beam until it reaches the installation position of the frame steel secondary beam. Then the steel secondary beam is welded and fixed, and the installation of the steel secondary beam is completed.

[0005] The utility model installation bracket comprises a slot vertical plate 1, a screw 2, a slot horizontal plate 3, a lower connecting rod 4, a column 5, an upper connecting rod 6, a lifting rope 7, a lifting ear 8, a cantilever rod 9, an upper sliding roller 10, an upper roller 11, a fixing ring 12, a lower roller 13, a lower sliding roller 14, and a pull rope 15, which are used in combination to vertically weld the tops of the two slot vertical plates 1 to the two ends of the slot horizontal plate 3; the two screws 2 pass through the two slot vertical plates 1 respectively; the lower roller 13 and the lower roller 14 form a rolling system; the lower roller 13 is vertically welded to the slot horizontal plate 3; the two lower connecting rods 14 are connected to the slot vertical plate 3, and the lower roller 13 is connected to the slot horizontal plate 3. The lower end of the connecting rod 4 is welded to both sides of the lower roller 14, and the upper end is welded to both sides of the lower end of the column 5; the upper roller 10 and the upper roller shaft 11 form a rolling system; the lower ends of the two upper connecting rods 6 are welded to both sides of the upper end of the column 5, and the upper ends are vertically welded to the upper roller shaft 11; the cantilever rod 9 is welded to the upper part of the upper roller 10 at the third position; the lifting ear 8 is welded to the front end of the cantilever rod 9; one end of the lifting rope 7 is fixed to the lifting ear 8, and the other end is freely hanging; the fixing ring 12 is welded to the rear end of the cantilever rod 9; one end of the pull rope 15 is tied to the fixing ring 12, and the other end is freely hanging (see Figure 1 , Figure 2 ).

[0006] Among them, the slot vertical plate 1 is made of 20mm thick steel plate, with the size of (length * width) 300mm*200mm; the screw 2 is 16mm in diameter and 60mm in length; the slot horizontal plate 3 is made of 20mm thick steel plate, with the size of (length * width) 600mm*300mm; the lower connecting rod 4 is made of round steel with a diameter of 30mm and a length of 100mm; the column 5 is made of a square tube with a cross-sectional size of (length * width) 200mm*200mm and a length of 1000mm; the upper connecting rod 6 is made of round steel with a diameter of 30mm and a length of 100mm; the lifting rope 7 is made of a steel wire rope with a diameter of 14mm and a length of 1000 mm; the lifting ear 8 is made of 16mm thick steel plate, with a size (length*width) of 60mm*60mm, and a round hole with a diameter of 20mm is opened in the middle; the cantilever rod 9 is made of a round tube with a diameter of 120mm and a length of 5000mm; the upper sliding roller 10 has an outer diameter of 200mm and an inner diameter of 120mm; the upper roller 11 has a diameter of 120mm and a length of 200mm; the fixing ring 12 is made of a round tube with a diameter of 40mm and a length of 30mm; the lower roller 13 has a diameter of 120mm and a length of 200mm; the lower sliding roller 14 has an outer diameter of 200mm and an inner diameter of 120mm; the pull rope 15 is made of a brown hemp rope with a diameter of 20mm and a length of 6000mm.

[0007] When in use, fix the mounting bracket to the main beam 16 on one side of the frame through the screws 2 on both sides of the slotted vertical plate 1, and then release the pull rope 15. Since the center of gravity of the cantilever rod 9 is in front of the upper sliding roller 10, the upper sliding roller 10 rolls to make the front of the cantilever rod 9 droop until it is above the position of the steel secondary beam 17. Then use the lifting rope 7 to tie the steel secondary beam 17, and then pull the pull rope 15 to lift the steel secondary beam 17 to the installation position of the frame steel secondary beam 17. Then weld and fix the steel secondary beam 17, and the steel secondary beam 17 is installed. When the mounting bracket needs to be changed, just loosen the screw 2 (see Figure 3 , Figure 4 ).

[0008] The utility model has the advantages of simple assembly, convenient operation, simplicity and practicality, avoids the use of a large number of cranes, is convenient and fast, and greatly reduces the construction cost. BRIEF DESCRIPTION OF THE DRAWINGS

[0009] Figure 1 This is the front view of the mounting bracket.

[0010] Figure 2 The figure shows the side view of the mounting bracket.

[0011] Figure 3 Main view of the steel secondary beam being hoisted for installation support.

[0012] Figure 4 Main view of the steel secondary beam being hoisted into position for installation of brackets.

[0013] In the figure, there are a slot vertical plate 1, a screw 2, a slot horizontal plate 3, a lower connecting rod 4, a column 5, an upper connecting rod 6, a lifting rope 7, a lifting ear 8, a cantilever rod 9, an upper sliding roller 10, an upper roller 11, a fixing ring 12, a lower roller 13, a lower sliding roller 14, a pull rope 15, a main beam 16, and a steel secondary beam 17. DETAILED DESCRIPTION

[0014] Figure 1-Figure 4 This is a specific implementation of the utility model. The utility model is further described below in conjunction with the accompanying drawings.

[0015] The utility model mounting bracket comprises a slot vertical plate 1, a screw 2, a slot horizontal plate 3, a lower connecting rod 4, a column 5, an upper connecting rod 6, a lifting rope 7, a lifting ear 8, a cantilever rod 9, an upper sliding roller 10, an upper roller 11, a fixing ring 12, a lower roller 13, a lower sliding roller 14, and a pull rope 15, which are used in combination to vertically weld the tops of the two slot vertical plates 1 to the two ends of the slot horizontal plate 3; the two screws 2 pass through the two slot vertical plates 1 respectively; the lower roller 13 and the lower roller 14 form a rolling system; the lower roller 13 is vertically welded to the slot horizontal plate 3; the two lower rollers 13 and the lower roller 14 form a rolling system; the lower roller 13 is vertically welded to the slot horizontal plate 3; the two lower rollers 13 and the lower roller 14 form a rolling system; the lower roller 13 and the slot horizontal plate 3 are vertically welded; the two lower rollers 13 and the lower roller 14 are vertically welded to the slot horizontal plate 3; the two lower rollers 13 and the lower roller 14 are vertically welded to the slot horizontal plate 3; the two lower rollers 13 and the lower roller 14 are vertically welded to the slot horizontal plate 3; the two lower rollers 13 and the upper ... The lower end of the connecting rod 4 is welded to both sides of the lower sliding roller 14, and the upper end is welded to both sides of the lower end of the column 5; the upper sliding roller 10 and the upper roller shaft 11 constitute a rolling system; the lower ends of the two upper connecting rods 6 are welded to both sides of the upper end of the column 5, and the upper ends are vertically welded to the upper roller shaft 11; the cantilever rod 9 is welded to the upper part of the upper sliding roller 10 at the one-third position; the lifting ear 8 is welded to the front end of the cantilever rod 9; one end of the lifting rope 7 is fixed to the lifting ear 8, and the other end is freely hanging; the fixing ring 12 is welded to the rear end of the cantilever rod 9; one end of the pull rope 15 is tied to the fixing ring 12, and the other end is freely hanging.

[0016] When in use, the mounting bracket is fixed to the main beam 16 on one side of the frame through the screws 2 on both sides of the slotted vertical plate 1, and then the pull rope 15 is released. Since the center of gravity of the cantilever rod 9 is in front of the upper sliding roller 10, the upper sliding roller 10 is rolled to make the front of the cantilever rod 9 droop until it is above the position of the steel secondary beam 17, and then the steel secondary beam 17 is tied with the hanging rope 7, and then the pull rope 15 is pulled to lift the steel secondary beam 17 to the installation position of the frame steel secondary beam 17, and then the steel secondary beam 17 is welded and fixed, and the steel secondary beam 17 is installed. When the mounting bracket needs to be changed, it only needs to loosen the screw 2.

[0017] During the construction of the light steel frame structure of the office building, a frame steel secondary beam installation bracket was used for the installation of the steel secondary beam, which achieved good results. The installation bracket is used in combination, and the tops of the two slot vertical plates are vertically welded to the two ends of the slot horizontal plate; two screws pass through the two slot vertical plates respectively; the lower roller and the lower roller form a rolling system; the lower roller is vertically welded to the slot horizontal plate; the lower ends of the two lower connecting rods are welded to the two sides of the lower roller, and the upper ends are welded to the two sides of the lower end of the column; the upper roller and the upper roller form a rolling system; the lower ends of the two upper connecting rods are welded to the two sides of the upper end of the column, and the upper ends are vertically welded to the upper roller; the cantilever rod is welded to the upper part of the upper roller at the one-third position; the lifting lug is welded to the front end of the cantilever rod; one end of the lifting rope is fixed to the lifting lug, and the other end is freely hanging; the fixing ring is welded to the rear end of the cantilever rod; one end of the pull rope is tied to the fixing ring, and the other end is freely hanging. When in use, fix the mounting bracket to the main beam on one side of the frame through the screws on both sides of the slotted vertical plate, and then release the pull rope. Since the center of gravity of the cantilever rod is in front of the upper sliding roller, the upper sliding roller is rolled to make the front of the cantilever rod droop until it is above the position of the steel secondary beam. Then use the lifting rope to tie the steel secondary beam, and then pull the pull rope to lift the steel secondary beam to the installation position of the frame steel secondary beam. Then weld and fix the steel secondary beam, and the steel secondary beam is installed. When the mounting bracket needs to change its position, just loosen the screws. The mounting bracket is simple to assemble, easy to operate, simple and practical, avoids the use of a large number of cranes, is convenient and fast, and greatly reduces construction costs.

Claims

1. A mounting bracket for a frame steel secondary beam, It is characterized in that The invention comprises a slot vertical plate (1), a screw (2), a slot horizontal plate (3), a lower connecting rod (4), a column (5), an upper connecting rod (6), a lifting rope (7), a lifting ear (8), a cantilever rod (9), an upper sliding roller (10), an upper roller shaft (11), a fixing ring (12), a lower roller shaft (13), a lower sliding roller (14), and a pull rope (15); the tops of the two slot vertical plates (1) are vertically welded to the two ends of the slot horizontal plate (3); the two screws (2) pass through the two slot vertical plates (1) respectively; the lower roller shaft (13) and the lower sliding roller (14) form a rolling system; the lower roller shaft (13) is vertically welded to the slot horizontal plate (3); the two lower connecting rods (4) The lower end is welded to both sides of the lower roller (14), and the upper end is welded to both sides of the lower end of the column (5); the upper roller (10) and the upper roller shaft (11) form a rolling system; the lower ends of the two upper connecting rods (6) are welded to both sides of the upper end of the column (5), and the upper ends are vertically welded to the upper roller shaft (11); the cantilever rod (9) is welded to the upper part of the upper roller (10) at the one-third position; the lifting ear (8) is welded to the front end of the cantilever rod (9); one end of the lifting rope (7) is fixed to the lifting ear (8), and the other end is freely hanging; the fixing ring (12) is welded to the rear end of the cantilever rod (9); one end of the pull rope (15) is tied to the fixing ring (12), and the other end is freely hanging.

2. The mounting bracket for the frame steel secondary beam according to claim 1, It is characterized in that The slot vertical plate (1) is made of 20mm thick steel plate, with a length*width of 300mm*200mm; the screw (2) is 16mm in diameter and 60mm in length; the slot horizontal plate (3) is made of 20mm thick steel plate, with a length*width of 600mm*300mm; the lower connecting rod (4) is made of round steel with a diameter of 30mm and a length of 100mm; the column (5) is made of a square tube with a cross-sectional size of 200mm*200mm in length*width and a length of 1000mm; the upper connecting rod (6) is made of round steel with a diameter of 30mm and a length of 100mm; the lifting rope (7) is made of a steel wire rope with a diameter of 14mm and a length of 1000mm; the lifting lug (8) is made of 16mm thick steel plate, with dimensions of length*width of 60mm*60mm, and a round hole of 20mm diameter is opened in the middle; the cantilever rod (9) is made of a round tube with a diameter of 120mm and a length of 5000mm; the upper sliding roller (10) has an outer diameter of 200mm and an inner diameter of 120mm; the upper roller (11) has a diameter of 120mm and a length of 200mm; the fixing ring (12) is made of a round tube with a diameter of 40mm and a length of 30mm; the lower roller (13) has a diameter of 120mm and a length of 200mm; the lower sliding roller (14) has an outer diameter of 200mm and an inner diameter of 120mm; the pull rope (15) is made of a brown hemp rope with a diameter of 20mm and a length of 6000mm.