Boiling box for cement experiment
By setting up an air inlet fan and an exhaust box in the boiling box to quickly discharge hot air, and using heat insulation pads and handles on the cooking bracket to facilitate the rapid cooling and removal of cement test blocks, the process of taking out cement test blocks in cement experiments is solved. Problems that require a long wait time improve work efficiency.
Patent Information
- Application Number
- CN202420309822.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-20
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2034-02-20
AI Technical Summary
In cement experiments, the process of taking out cement test blocks from the boiling box requires a long wait, resulting in low work efficiency.
The air inlet fan is fixedly connected to the rear side of the boiling box, and the left and right surfaces are connected to the exhaust box. The air inlet fan is opened and started by controlling the valve to input external air into the box, quickly discharge the hot air, accelerate the cooling of the cement test block, and place it on the cooking bracket. A heat-insulating pad and handle are provided for easy removal as a whole.
It improves the cooling speed and removal efficiency of cement test blocks, reduces waiting time, and improves work efficiency and convenience.
Smart Images

Figure CN221803878U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of building equipment technology, specifically to a boiling tank for cement experiments. Background Technology
[0002] Boiling chambers are commonly used equipment in cement laboratories to test the stability of cement. The general operating procedure is to place the Le Chatelier clamp or pre-made test cake on the grate or support inside the boiling chamber, then pour water into the chamber until the cement block is completely submerged, and then heat the cement block to a boiling state. After that, the chamber is adjusted to a heat preservation state for two hours, and then the hot water is drained through the copper faucet on the side wall of the chamber. After the cement test block cools down, the detector detects the changes after heating.
[0003] After the cement sample has been boiled, the hot water in the tap must be drained first, and then the cement sample block must be cooled before it can be manually removed. This process takes a long time to complete, which reduces work efficiency.
[0004] Therefore, it is necessary to invent a boiling tank for cement experiments to solve the above problems. Utility Model Content
[0005] The purpose of this invention is to provide a boiling tank for cement experiments, in order to solve the problem that the process of removing cement test blocks in the present invention requires a long waiting time, which reduces work efficiency.
[0006] To achieve the above objectives, this utility model provides the following technical solution: a boiling chamber for cement experiments, comprising a boiling chamber body, an air inlet fan fixedly connected to the rear side of the boiling chamber body, exhaust boxes fixedly connected to the left and right sides of the boiling chamber body, control valves provided on the surface of the exhaust boxes, an air supply duct fixedly connected between the exhaust boxes and the boiling chamber body, two sets of air inlet fan blades rotatably connected inside the air inlet fan, a cooking support frame provided inside the boiling chamber body, and two sets of storage trays fixedly connected inside the cooking support frame.
[0007] By adopting the above technical solution, after the cement has been boiled, the hot water inside the boiling chamber is drained, and then the air intake fan is started. The air intake fan delivers external air into the interior of the boiling chamber, which allows the internal hot air to be quickly discharged to the outside, accelerating the cooling speed of the cement block, making it easier to remove the cement quickly and increasing the testing efficiency.
[0008] Optionally, two sets of connecting rods are fixedly connected to the upper surface of the steaming rack, and a heat insulation pad is fixedly connected to the upper end of the connecting rod, and a handle is fixedly connected to the side of the heat insulation pad.
[0009] By adopting the above technical solution, the heat insulation pad prevents heat from being conducted to the surface of the connecting rod, and the cooking rack can be removed as a whole through the connecting rod.
[0010] Optionally, the side walls on both sides of the boiling tank are provided with slots near the top, and the heat insulation pad is engaged and fixed with the slots.
[0011] By adopting the above technical solution, the heat insulation pad is inserted into the slot, which not only provides heat insulation but also seals the slot to reduce the loss of internal heat.
[0012] Optionally, side supports are fixedly connected to the inner walls of both the left and right sides of the boiling tank, and heating tubes are fixedly connected to the front and rear surfaces of the boiling tank.
[0013] By adopting the above technical solution, the heating pipe heats the internal water source to cook the cement.
[0014] Optionally, a first locking block is rotatably connected to the front surface of the boiling tank near the upper position, and a first fixing shaft is fixedly connected to the rear surface of the boiling tank near the upper position.
[0015] Optionally, a sealing cover is provided above the boiling tank. A second locking block is fixedly connected to the front surface of the sealing cover. The second locking block is engaged and fixed with the first locking block. A second fixing shaft is fixedly connected to the rear side of the sealing cover. The second fixing shaft is rotatably connected to the first fixing shaft.
[0016] By adopting the above technical solution, the sealing cover plate is rotated around the boiling tank body by the first fixed shaft and the second fixed shaft. After the sealing cover plate is flipped down to close the upper end of the boiling tank body, the first locking block is flipped up and locked on the outside of the second locking block to fix the sealing cover plate.
[0017] Optionally, a sealing strip is fixedly connected to the lower surface of the sealing cover, and two sets of exhaust pipes are fixedly connected to the upper surface of the sealing cover.
[0018] By adopting the above technical solution, the sealing strip improves the sealing performance of the sealing cover.
[0019] Optionally, a drain pipe is fixedly connected to the right side surface of the boiling tank near the lower end, and a drain valve is provided on the surface of the drain pipe.
[0020] By adopting the above technical solution, the drainage pipe is used to drain the boiling water.
[0021] The technical effects and advantages provided by this utility model in the above technical solution are as follows:
[0022] 1. This utility model addresses the problem of reduced work efficiency by fixing an air intake fan to the rear side of the boiling chamber and fixing exhaust boxes to the left and right sides of the boiling chamber. Each exhaust box has a control valve. After boiling is complete, the control valves are opened, and the air intake fan is started. The air intake fan draws external air from the bottom of the boiling chamber, quickly expelling the hot air inside and simultaneously cooling the cement test blocks. This improves the cooling speed of the cement test blocks and increases work efficiency. The process of removing the cement test blocks takes a long time, which reduces work efficiency.
[0023] 2. This utility model has a cooking support inside the boiling chamber, and two sets of storage trays are fixedly connected inside the cooking support. After the cement test block has been boiled and cooled, the cement test block can be taken out as a whole, which improves the convenience of use and further increases the speed of material handling. Attached Figure Description
[0024] Figure 1 This is a schematic diagram of the overall front structure of this utility model;
[0025] Figure 2 This is a schematic diagram of the overall rear structure of this utility model;
[0026] Figure 3 This is a schematic diagram of the sealing cover structure of this utility model;
[0027] Figure 4 This is a schematic diagram of the boiling tank structure of this utility model;
[0028] Figure 5 This is a schematic diagram of the air intake structure of this utility model;
[0029] Figure 6 This is a schematic diagram of the steaming support structure of this utility model.
[0030] Explanation of reference numerals in the attached figures:
[0031] 1. Boiling chamber body; 11. Side support; 12. Heating element; 13. Drain pipe; 14. Drain valve; 15. First fixed shaft; 16. Slot; 17. First locking block; 2. Sealing cover plate; 21. Second fixed shaft; 22. Exhaust pipe; 23. Sealing strip; 24. Second locking block; 3. Air inlet fan; 31. Air inlet fan blade; 32. Air supply pipe; 33. Exhaust box body; 34. Control valve; 4. Cooking support; 41. Storage tray; 42. Connecting rod; 43. Heat insulation pad; 44. Handle. Detailed Implementation
[0032] To enable those skilled in the art to better understand the technical solution of this utility model, the present utility model will be further described in detail below with reference to the accompanying drawings.
[0033] Example 1:
[0034] See Figures 1 to 6 This utility model provides a boiling chamber for cement experiments, including a boiling chamber body 1. An air inlet fan 3 is fixedly connected to the rear side of the boiling chamber body 1. Exhaust boxes 33 are fixedly connected to the left and right sides of the boiling chamber body 1. Control valves 34 are provided on the surface of the exhaust boxes 33. An air supply pipe 32 is fixedly connected between the exhaust boxes 33 and the boiling chamber body 1. Two sets of air inlet fan blades 31 are rotatably connected inside the air inlet fan 3. A cooking support 4 is provided inside the boiling chamber body 1. Two sets of storage trays 41 are fixedly connected inside the cooking support 4.
[0035] During use, the cement test block is placed on the surface of the tray 41, and the cooking support 4 is placed inside the boiling chamber 1. The cement test block is cooked in the boiling chamber 1. During the cooking process, the control valve 34 is kept closed. After the boiling process is completed, the hot water inside the boiling chamber 1 is drained. Then, the control valve 34 is opened and the air intake fan 3 is started. The air intake fan 3 sends external air into the boiling chamber 1 through the air supply pipe 32 to accelerate the exhaust of air from the boiling chamber 1. At the same time, air is blown onto the cement test block to increase the cooling speed of the cement test block.
[0036] See Figure 4 and Figure 6 Two sets of connecting rods 42 are fixedly connected to the upper surface of the cooking support 4. A heat insulation pad 43 is fixedly connected to the upper end of the connecting rod 42. A handle 44 is fixedly connected to the side of the heat insulation pad 43. A slot 16 is provided on the side wall of the left and right sides of the boiling chamber 1 near the upper position. The heat insulation pad 43 is fixedly engaged with the slot 16. Side supports 11 are fixedly connected to the inner walls of the left and right sides of the boiling chamber 1. Heating tubes 12 are fixedly connected to the front and rear surfaces of the boiling chamber 1. A drain pipe 13 is fixedly connected to the lower end of the right side surface of the boiling chamber 1. A drain valve 14 is provided on the surface of the drain pipe 13.
[0037] Specifically, cement test blocks are placed sequentially on the surface of the tray 41. Then, the cooking rack 4 is placed inside the boiling chamber 1 using the handles 44 on both sides, and the heat insulation pad 43 is secured inside the slot 16. Water is then injected into the boiling chamber 1 and heated through the heating pipe 12 to cook the cement test blocks. After cooking is complete, the drain valve 14 is opened to drain the hot water from the boiling chamber 1, and the cement test blocks are removed from the surface of the cooking rack 4 using the handle 44.
[0038] See Figure 3 and Figure 4A first locking block 17 is rotatably connected to the upper part of the front surface of the boiling tank 1. A first fixing shaft 15 is fixedly connected to the upper part of the rear surface of the boiling tank 1. A sealing cover 2 is provided on the top of the boiling tank 1. A second locking block 24 is fixedly connected to the front surface of the sealing cover 2. The second locking block 24 is locked and fixed to the first locking block 17. A second fixing shaft 21 is fixedly connected to the rear side of the sealing cover 2. The second fixing shaft 21 is rotatably connected to the first fixing shaft 15. A sealing strip 23 is fixedly connected to the lower surface of the sealing cover 2. Two sets of exhaust pipes 22 are fixedly connected to the upper surface of the sealing cover 2.
[0039] After the cement test block is placed into the boiling chamber 1, the sealing cover 2 is rotated downwards. The sealing cover 2 and the sealing strip 23 cooperate to seal the upper end of the boiling chamber 1. Then, the first locking block 17 is flipped upwards and locked with the second locking block 24 to fix the sealing cover 2.
[0040] The working principle of this utility model is as follows: In order to improve the cooling speed of the cement test block and increase the work efficiency, after the boiling process is completed, the hot water inside the boiling tank 1 is drained, and then the control valve 34 is opened and the air intake fan 3 is started. The air intake fan 3 sends the outside air into the inside of the boiling tank 1 through the air supply pipe 32, which accelerates the exhaust of the air inside the boiling tank 1 and blows air on the cement test block at the same time.
[0041] The foregoing has shown and described the basic principles, main features, and advantages of this utility model. Those skilled in the art should understand that this utility model is not limited to the above embodiments. The embodiments and descriptions in the specification are merely preferred examples and are not intended to limit the utility model. Various changes and modifications can be made to this utility model without departing from its spirit and scope, and all such changes and modifications fall within the scope of the claimed utility model.
Claims
1. A boiling box for cement experiment, comprising a boiling box body (1), characterized in that: The rear side of the boiling box (1) is fixedly connected to an air intake fan (3), the left and right side surfaces of the boiling box (1) are fixedly connected to exhaust boxes (33), the surfaces of the exhaust boxes (33) are provided with control valves (34), an air supply duct (32) is fixedly connected between the exhaust boxes (33) and the boiling box (1), two groups of air intake fan blades (31) are rotatably connected inside the air intake fan (3), a cooking bracket (4) is provided inside the boiling box (1), and two groups of storage trays (41) are fixedly connected inside the cooking bracket (4).
2. A cement experiment boiling box according to claim 1, characterized in that: Two groups of connecting rods (42) are fixedly connected to the upper surface of the cooking support (4), the upper ends of the connecting rods (42) are fixedly connected to heat insulation pads (43), and the sides of the heat insulation pads (43) are fixedly connected to handles (44).
3. A cement experiment boiling box according to claim 2, characterized in that: The side walls on the left and right sides of the boiling box (1) are provided with slots (16) near the top, and the heat insulation pad (43) is fixedly connected to the slots (16).
4. A cement experiment boiling box according to claim 1, characterized in that: The inner walls on the left and right sides of the boiling box (1) are both fixedly connected to side brackets (11), and the front and rear side surfaces of the boiling box (1) are both fixedly connected to heating tubes (12).
5. The cement experiment boiling box according to claim 1, characterized in that: A first clamping block (17) is rotatably connected to the front surface of the boiling box (1) near the upper position, and a first fixed shaft (15) is fixedly connected to the rear surface of the boiling box (1) near the upper position.
6. A cement experiment boiling box according to claim 5, characterized in that: A sealing cover plate (2) is arranged above the boiling box body (1); a second clamping block (24) is fixedly connected to the front surface of the sealing cover plate (2); the second clamping block (24) is clamped and fixed to the first clamping block (17); a second fixed shaft (21) is fixedly connected to the rear side of the sealing cover plate (2); the second fixed shaft (21) is rotatably connected to the first fixed shaft (15).
7. A cement experiment boiling box according to claim 6, characterized in that: A sealing strip (23) is fixedly connected to the lower surface of the sealing cover plate (2), and two groups of exhaust pipes (22) are fixedly connected to the upper surface of the sealing cover plate (2).
8. The cement experiment boiling box according to claim 1, characterized in that: A drainage pipe (13) is fixedly connected to the right side surface of the boiling box (1) near the lower end, and a drainage valve (14) is provided on the surface of the drainage pipe (13).