Water injection mechanism of liquefied petroleum gas cylinder
Through the design of the LPG bottle water filling mechanism and the use of quantitative water filling buckets and automated equipment, the problems of uneven water filling and low efficiency of LPG cylinders are solved, achieving uniform water filling and efficient automatic water filling, saving water sources and reducing labor intensity.
Patent Information
- Application Number
- CN202323559871.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-26
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2033-12-26
AI Technical Summary
The existing water filling process of liquefied gas bottles relies on manual operation, resulting in uneven water filling, low efficiency, waste of water resources, and increased labor intensity for staff.
A water filling mechanism for liquefied petroleum gas bottles is designed. It uses a quantitative water filling barrel, a pump body, a water level detector, a solenoid valve and a conveying mechanism. Through the water filling of the pump body and water level detection, it ensures that each liquefied petroleum gas bottle is evenly filled with water, and an electric lifting rod is used. and conveyor belt automatically complete the water filling task.
It achieves uniform water filling of each liquefied gas bottle, saves water resources, improves water filling efficiency, reduces the labor intensity of staff, and improves the automation level of the water filling process.
Smart Images

Figure CN221825160U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of water injection into a liquefied petroleum gas cylinder, in particular to a water injection mechanism for a liquefied petroleum gas cylinder. Background Art
[0002] A liquefied gas tank refers to a tank used to store liquefied gas. When there is liquefied gas inside, the pressure is very high. Any improper operation may cause an explosion. The product itself is made of steel and has a certain pressure resistance. The maximum pressure that a liquefied gas cylinder can withstand is 2.1 MPa. After a certain number of years of use, the liquefied gas cylinder needs to be recycled. When processing it, it is necessary to inject water into the inside to expel the internal gas to prevent an explosion accident due to residual gas inside during later cutting.
[0003] However, the existing liquefied gas cylinders are mostly filled with water manually, and the water filling amount inside each liquefied gas cylinder cannot be guaranteed, resulting in water leaking out of the liquefied gas cylinder, causing a waste of water resources. In addition, when manually filling water, the time interval between filling water for each liquefied gas cylinder is long, and the water filling efficiency is low, which affects the processing progress of the later liquefied gas cylinders. Secondly, when manually completing the water filling work of the liquefied gas cylinder, it is time-consuming and laborious, and the pulling strength of the staff is increased. In view of the above problems, the inventor proposes a water filling mechanism for a liquefied petroleum gas cylinder to solve the above problems. Utility Model Content
[0004] In order to solve the problems that the existing liquefied gas cylinders are mostly filled manually, the water filling amount in each liquefied gas cylinder cannot be guaranteed, resulting in water leaking out of the liquefied gas cylinder, causing a waste of water resources, and the manual water filling leads to a long time interval between the water filling of each liquefied gas cylinder, low water filling efficiency, and affecting the processing progress of the later liquefied gas cylinders; the purpose of the utility model is to provide a water filling mechanism for a liquefied petroleum gas cylinder.
[0005] In order to solve the above technical problems, the utility model adopts the following technical scheme: a water filling mechanism for a liquefied petroleum gas cylinder, comprising a workbench, a fixing frame is fixedly installed on the top surface of the workbench, a quantitative water filling bucket is symmetrically installed on the top surface of the fixing frame, the number of the quantitative water filling buckets is two, a mounting frame is fixedly installed in the middle of the top surface of the two quantitative water filling buckets, a pump body is fixedly installed on the inner top surface of the two mounting frames, a water filling pipe is fixedly installed on the output end of the two pump bodies, one end of the two water filling pipes is respectively fixedly installed in the two quantitative water filling buckets, a water level detector is installed in the two quantitative water filling buckets, a drainage pipe is installed through the fixing frame in the middle of the bottom surface of the two quantitative water filling buckets, a solenoid valve is fixedly installed on the surface of the two drainage pipes, the solenoid valve and the water level detector cooperate with each other, one end of the two drainage pipes is fixedly connected with a connector, a water filling hose is fixedly installed on one side of the connector, a water filling head is fixedly installed on one end of the water filling hose, and a water flow monitor is installed on the surface of the water filling hose close to the water filling head;
[0006] The water injected into the liquefied gas cylinder is respectively injected into the corresponding quantitative water injection barrels through two pump bodies for storage and standby. The water volume injected into the quantitative water injection barrel is detected by a water level detector to ensure that the water injected each time completes the water injection volume of a liquefied gas cylinder. The water in the two quantitative water injection barrels flows into the water injection hose through the corresponding drainage pipes respectively, and the water injection work in the liquefied gas cylinder is completed through the water injection head. After the water in one quantitative water injection barrel completes the water injection task of a liquefied gas cylinder through the water injection head, the electromagnetic valve on the surface of the drainage pipe corresponding to the bottom of the quantitative water injection barrel that has completed the water injection is closed, and the electromagnetic valve switch on the surface of the drainage pipe corresponding to the bottom of the other quantitative water injection barrel is opened to inject the water in the other quantitative water injection barrel into the next liquefied gas cylinder. While the other quantitative water injection barrel is being injected with water, the empty barrel completes the quantitative water storage work under the operation of the corresponding pump body. By analogy, the two quantitative water injection barrels are used to replace the water injection, and the water injection work of each liquefied gas cylinder is completed in a timely and quantitative manner to ensure that the water injection volume of each liquefied gas cylinder is the same, saving water resources while improving the water injection efficiency of the liquefied gas cylinder.
[0007] Preferably, an electric lifting rod is installed in the middle of the top surface of the fixing frame, and a fixing piece is fixedly installed at the output end of the electric lifting rod. One end of the water injection hose is fixedly sleeved in the fixing piece and passes through the fixing piece. The water flow monitor is fixedly installed on the top surface of the fixing piece through the water injection hose. When the liquefied gas cylinder that needs to be filled with water is transported to the bottom of the water injection head through the conveyor belt, the switch of the electric lifting rod is turned on, and the fixing piece is controlled by the electric lifting rod to drive the water injection hose to descend. The water injection head installed at the end of the water injection hose is inserted into the top opening of the liquefied gas cylinder. The electric lifting rod stops working, and the water in the designated quantitative water injection bucket is injected into the liquefied gas cylinder through the water injection head. There is no need to manually complete the water filling of the liquefied gas cylinder, which saves time and effort and reduces the labor intensity of the staff.
[0008] Preferably, a conveying mechanism is installed in the top surface of the workbench, and the conveying mechanism includes a conveyor belt, which is driven by a motor and a conveyor roller to run. The liquefied gas cylinder that needs to be filled with water is transported by the conveyor belt of the conveying mechanism. When the liquefied gas cylinder is transported to the bottom of the water filling head through the conveyor belt, the transportation is stopped to complete the water filling task of the liquefied gas cylinder. Similarly, the input ends of the two pump bodies are installed with connecting pipes, one end of the two connecting pipes passes through the mounting frame and is fixedly connected to a water storage pipe, and the two connecting pipes cooperate with the water storage pipe. When it is necessary to fill water into the corresponding quantitative water filling buckets through the two pump bodies, the water is injected into the designated quantitative water filling buckets respectively through the water storage pipe and the two connecting pipes.
[0009] Preferably, an observation window is provided in one side of the two quantitative water filling barrels, and the observation window cooperates with the quantitative water filling barrels. The observation windows provided in the two quantitative water filling barrels are convenient for observing the inside of the quantitative water filling barrels. A support frame is fixedly installed on the bottom surface of the workbench, and the support frame cooperates with the workbench. The workbench is supported and fixed by the support frame. The device is installed in a designated area through the support frame to carry out water filling work on the liquefied gas cylinders.
[0010] Compared with the prior art, the beneficial effects of the utility model are:
[0011] 1. In the utility model, the water injected into the liquefied gas cylinder is respectively injected into the corresponding quantitative water injection barrels through two pump bodies for storage and standby. The water level detector is used to ensure that the water injected into the quantitative water injection barrel each time can complete the water injection amount of a liquefied gas cylinder. The two quantitative water injection barrels are used to replace the water injection, and the water injection work of each liquefied gas cylinder is completed in a timely and quantitative manner, ensuring that the water injection amount of each liquefied gas cylinder is the same, saving water resources while improving the water injection efficiency of the liquefied gas cylinder;
[0012] 2. In the utility model, the liquefied gas cylinders that need to be filled with water are transported to the bottom of the water filling head in sequence through the conveyor belt of the conveying mechanism, the switch of the electric lifting rod is turned on, the fixing part is controlled by the electric lifting rod to drive the water filling hose to descend, and the water filling head installed at the end of the water filling hose is inserted into the top opening of the liquefied gas cylinder. The water in the designated quantitative water filling bucket is injected into the liquefied gas cylinder through the water filling head, and the water filling work of the liquefied gas cylinder does not need to be completed manually, which saves time and effort and reduces the labor intensity of the staff. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0014] Figure 1 This is a schematic diagram of the overall structure of the utility model.
[0015] Figure 2 This is the main view of the overall structure of the utility model.
[0016] Figure 3 For this utility model Figure 2 A magnified view of the structure in the middle.
[0017] Figure 4 For this utility model Figure 2 Enlarged view of the structure at point B in the middle.
[0018] In the figure: 1. workbench; 11. support frame; 2. fixed frame; 3. quantitative water filling bucket; 31. observation window; 32. water level detector; 33. mounting frame; 4. connecting pipe; 41. water storage pipe; 5. pump body; 51. water filling pipe; 6. drainage pipe; 61. solenoid valve; 62. connecting piece; 63. water filling hose; 631. water filling head; 64. water flow monitor; 7. electric lifting rod; 71. fixing piece; 8. conveying mechanism; 81. conveyor belt. DETAILED DESCRIPTION
[0019] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0020] Example: Figure 1-4 As shown, the utility model provides a water filling mechanism for a liquefied petroleum gas cylinder, comprising a workbench 1, a fixing frame 2 is fixedly installed on the top surface of the workbench 1, a quantitative water filling bucket 3 is symmetrically installed on the top surface of the fixing frame 2, the number of the quantitative water filling bucket 3 is two, a mounting frame 33 is fixedly installed in the middle of the top surface of the two quantitative water filling buckets 3, a pump body 5 is fixedly installed on the inner top surface of the two mounting frames 33, a water filling pipe 51 is fixedly installed on the output end of the two pump bodies 5, one end of the two water filling pipes 51 is fixedly installed in the two quantitative water filling buckets 3, and the two A water level detector 32 is installed in each quantitative water filling bucket 3. A drainage pipe 6 is installed through the fixed frame 2 in the middle of the bottom surface of each of the two quantitative water filling buckets 3. A solenoid valve 61 is fixedly installed on the surface of the two drainage pipes 6. The solenoid valve 61 cooperates with the water level detector 32. A connector 62 is fixedly connected to one end of the two drainage pipes 6. A water injection hose 63 is fixedly installed on one side of the connector 62. A water injection head 631 is fixedly installed on one end of the water injection hose 63. A water flow monitor 64 is installed on the surface of the water injection hose 63 near the water injection head 631.
[0021] The water injected into the liquefied gas cylinder is respectively injected into the corresponding quantitative water injection bucket 3 through the two pump bodies 5 for storage and standby. The amount of water injected into the quantitative water injection bucket 3 is detected by the water level detector 32 to ensure that the water injected each time completes the water injection amount of a liquefied gas cylinder. The water in the two quantitative water injection buckets 3 flows into the water injection hose 63 through the corresponding drain pipes 6, and the water injection work in the liquefied gas cylinder is completed through the water injection head 631. When the water in one quantitative water injection bucket 3 completes the water injection task of a liquefied gas cylinder through the water injection head 631, the quantitative water injection completed by the water injection is completed. The electromagnetic valve 61 on the surface of the drain pipe 6 corresponding to the bottom of the barrel 3 is closed, and the electromagnetic valve 61 on the surface of the drain pipe 6 corresponding to the bottom of the other quantitative water filling barrel 3 is opened to inject the water in the other quantitative water filling barrel 3 into the next liquefied gas cylinder. While the other quantitative water filling barrel 3 is filling with water, the empty barrel completes the quantitative water storage work under the operation of the corresponding pump body 5, and so on. The water is replaced by the two quantitative water filling barrels 3, and the water filling work of each liquefied gas cylinder is completed in a timely and quantitative manner, ensuring that the water filling amount of each liquefied gas cylinder is the same, saving water resources while improving the water filling efficiency of the liquefied gas cylinder.
[0022] An electric lifting rod 7 is installed in the middle of the top surface of the fixing frame 2, and a fixing piece 71 is fixedly installed at the output end of the electric lifting rod 7. One end of the water injection hose 63 is fixedly sleeved in the fixing piece 71 and penetrates the fixing piece 71. The water flow monitor 64 is fixedly installed on the top surface of the fixing piece 71 through the water injection hose 63.
[0023] By adopting the above-mentioned technical scheme, when the liquefied gas cylinder that needs to be filled with water is transported to the bottom of the water filling head 631 through the conveyor belt 81, the switch of the electric lifting rod 7 is turned on, and the fixing part 71 is controlled by the electric lifting rod 7 to drive the water filling hose 63 to descend, and the water filling head 631 installed at the end of the water filling hose 63 is inserted into the top opening of the liquefied gas cylinder. The electric lifting rod 7 stops working, and the water in the designated quantitative water filling bucket 3 is injected into the liquefied gas cylinder through the water filling head 631. There is no need to manually complete the water filling work of the liquefied gas cylinder, which saves time and effort and reduces the labor intensity of the staff.
[0024] A conveying mechanism 8 is installed on the top surface of the workbench 1. The conveying mechanism 8 includes a conveying belt 81. The conveying belt 81 is driven by a motor and a conveying roller.
[0025] By adopting the above technical solution, the liquefied gas cylinder that needs to be filled with water is transported by the conveyor belt 81 of the conveying mechanism 8. When the liquefied gas cylinder is transported to the bottom of the water filling head 631 by the conveyor belt 81, the transportation is stopped to complete the water filling task of the liquefied gas cylinder, and so on.
[0026] The input ends of the two pump bodies 5 are both installed with connecting pipes 4, one end of the two connecting pipes 4 passes through the mounting frame 33 and is fixedly connected with a water storage pipe 41, and the two connecting pipes 4 cooperate with the water storage pipe 41;
[0027] By adopting the above technical solution, when it is necessary to respectively fill water into the corresponding quantitative water filling buckets 3 through the two pump bodies 5, the water is respectively injected into the designated quantitative water filling buckets 3 through the water storage pipe 41 in coordination with the two connecting pipes 4.
[0028] An observation window 31 is provided in one side of the two quantitative water filling barrels 3, and the observation window 31 cooperates with the quantitative water filling barrels 3;
[0029] By adopting the above technical solution, the interior of the two quantitative water filling barrels 3 can be easily observed through the observation windows 31 provided in the two quantitative water filling barrels 3 .
[0030] A support frame 11 is fixedly mounted on the bottom surface of the workbench 1, and the support frame 11 cooperates with the workbench 1;
[0031] By adopting the above technical solution, the workbench 1 is supported and fixed by the support frame 11, and the device is installed in a designated area by the support frame 11 to perform water filling work on the liquefied gas cylinder.
[0032] Working principle: The water injected into the liquefied gas cylinder is respectively injected into the corresponding quantitative water injection bucket 3 through the two pump bodies 5 for storage and standby. The amount of water injected into the quantitative water injection bucket 3 is detected by the water level detector 32 to ensure that the water injected each time completes the water injection of a liquefied gas cylinder. The water in the two quantitative water injection buckets 3 flows into the water injection hose 63 through the corresponding drain pipes 6, and the water injection work in the liquefied gas cylinder is completed through the water injection head 631. When the water in one quantitative water injection bucket 3 completes the water injection task of a liquefied gas cylinder through the water injection head 631, the quantitative water injection bucket 3 that has completed the water injection is filled with water. The electromagnetic valve 61 on the surface of the drainage pipe 6 corresponding to the bottom of the quantitative water filling bucket 3 is closed, and the electromagnetic valve 61 on the surface of the drainage pipe 6 corresponding to the bottom of the other quantitative water filling bucket 3 is opened to inject the water in the other quantitative water filling bucket 3 into the next liquefied gas cylinder. While the other quantitative water filling bucket 3 is filling water, the empty bucket completes the quantitative water storage work under the operation of the corresponding pump body 5, and so on. The two quantitative water filling buckets 3 are used to replace the water filling, and the water filling work of each liquefied gas cylinder is completed in a timely and quantitative manner, ensuring that the water filling amount of each liquefied gas cylinder is the same, saving water resources while improving the water filling efficiency of the liquefied gas cylinder;
[0033] When the liquefied gas cylinder that needs to be filled with water is transported to the bottom of the water filling head 631 through the conveyor belt 81, turn on the switch of the electric lifting rod 7, control the fixing part 71 through the electric lifting rod 7 to drive the water filling hose 63 to descend, and insert the water filling head 631 installed at the end of the water filling hose 63 into the top opening of the liquefied gas cylinder. The electric lifting rod 7 stops working, and the water in the designated quantitative water filling bucket 3 is injected into the liquefied gas cylinder through the water filling head 631.
[0034] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.
Claims
1. A water filling mechanism for a liquefied petroleum gas cylinder, comprising a workbench (1), characterized in that: A fixing frame (2) is fixedly mounted on the top surface of the workbench (1), and a quantitative water injection bucket (3) is symmetrically mounted on the top surface of the fixing frame (2), and the number of the quantitative water injection buckets (3) is two, and a mounting frame (33) is fixedly mounted in the middle of the top surfaces of the two quantitative water injection buckets (3), and a pump body (5) is fixedly mounted on the inner top surfaces of the two mounting frames (33), and a water injection pipe (51) is fixedly mounted on the output ends of the two pump bodies (5), and one end of the two water injection pipes (51) is fixedly mounted in the two quantitative water injection buckets (3) respectively; A water level detector (32) is installed in each of the two quantitative water filling buckets (3); a drainage pipe (6) is installed through the fixed frame (2) in the middle of the bottom surface of each of the two quantitative water filling buckets (3); a solenoid valve (61) is fixedly installed on the surface of the two drainage pipes (6); the solenoid valve (61) cooperates with the water level detector (32); one end of the two drainage pipes (6) is fixedly connected to a connecting piece (62); a water injection hose (63) is fixedly installed on one side of the connecting piece (62); a water injection head (631) is fixedly installed on one end of the water injection hose (63); and a water flow monitor (64) is installed on the surface of the water injection hose (63) at one end close to the water injection head (631).
2. A water filling mechanism for a liquefied petroleum gas cylinder as claimed in claim 1, characterized in that: An electric lifting rod (7) is installed in the middle of the inner top surface of the fixing frame (2); a fixing piece (71) is fixedly installed at the output end of the electric lifting rod (7); one end of the water injection hose (63) is fixedly sleeved in the fixing piece (71) and passes through the fixing piece (71); and the water flow monitor (64) is fixedly installed on the top surface of the fixing piece (71) through the water injection hose (63).
3. A water filling mechanism for a liquefied petroleum gas cylinder as claimed in claim 1, characterized in that: A conveying mechanism (8) is installed in the top surface of the workbench (1), and the conveying mechanism (8) comprises a conveying belt (81). The conveying belt (81) is driven by a motor in cooperation with a conveying roller to run.
4. A water filling mechanism for a liquefied petroleum gas cylinder as claimed in claim 1, characterized in that: The input ends of the two pump bodies (5) are both equipped with connecting pipes (4), one end of the two connecting pipes (4) passes through the mounting frame (33) and is fixedly connected to a water storage pipe (41), and the two connecting pipes (4) cooperate with the water storage pipe (41).
5. The water filling mechanism of a liquefied petroleum gas cylinder as claimed in claim 1, characterized in that: An observation window (31) is provided in one side of the two quantitative water filling buckets (3), and the observation window (31) cooperates with the quantitative water filling buckets (3).
6. A water filling mechanism for a liquefied petroleum gas cylinder as claimed in claim 1, characterized in that: A support frame (11) is fixedly mounted on the bottom surface of the workbench (1), and the support frame (11) and the workbench (1) cooperate with each other.