Underground oil and gas pipeline maintenance culvert
By designing the maintenance culvert for buried oil and gas pipelines, the problem of maintenance of buried oil and gas pipelines crossing the bottom of the highway is solved, pipeline inspection and maintenance can be carried out without affecting traffic, the impact of pipeline vibration and environmental impact is reduced, and safety and The smoothness of the traffic area.
Patent Information
- Application Number
- CN202323413333.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-14
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2033-12-14
AI Technical Summary
When buried oil and gas pipelines cross the bottom of the road, existing technology makes it difficult to perform maintenance without affecting public transportation, causing maintenance work to hinder the road surface.
Design a buried oil and gas pipeline maintenance culvert. By setting supports, partitions and observation parts underground, the buried area for pipeline burial and the passage area for maintenance personnel to pass through are separated to ensure that the highway can be laid directly above the culvert. , and perform maintenance by breaking through the partition wall when necessary.
It realizes pipeline inspection and maintenance without affecting the ground, reduces the impact of vibration on the pipeline, improves safety and smoothness of the passage area, and reduces environmental impact and cost.
Smart Images

Figure CN221837627U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of buried pipeline maintenance, and more specifically, to a buried oil and gas pipeline maintenance culvert. Background Art
[0002] In pipeline transportation, buried oil and gas pipelines are a common way of laying pipelines. In actual layout, due to the limitation of spatial layout, some buried oil and gas pipelines inevitably pass under the road. How to inspect and repair these buried oil and gas pipelines is an unavoidable problem.
[0003] A Chinese patent discloses a buried oil and gas pipeline leak detector and detection method. The detector of the invention includes five parts: a frame module, a ground penetrating radar module, an inhalation combustible gas detector array module, a satellite positioning module and a computer system. The buried oil and gas pipeline leak detector of the invention can be towed by humans or motor vehicles, which is convenient for pipeline inspection personnel to carry. It is suitable for buried oil and gas pipeline leak detection operations under different terrain conditions in oil fields. While detecting pipeline leaks, it can also complete pipeline route detection work, which is convenient for later pipeline maintenance. However, the equipment faces a problem. When performing maintenance operations, the equipment needs to occupy ground space for detection and maintenance. When the operation time is long, it will cause great obstacles to public transportation. The form of channel culvert protection can effectively avoid this problem. Therefore, for buried oil and gas pipelines crossing the bottom of the highway, a buried oil and gas pipeline protection culvert structure is proposed, which can not only meet the requirements of daily operation and maintenance, but also avoid affecting the road surface during maintenance work. Utility Model Content
[0004] The utility model aims to overcome the deficiencies of the prior art and provide a buried oil and gas pipeline inspection culvert, which can carry out inspection or maintenance work on the buried oil and gas pipeline without affecting the road surface.
[0005] In order to solve the above technical problems, the technical solution adopted by the utility model is:
[0006] Provided is a buried oil and gas pipeline maintenance culvert, comprising a top plate, a support member, a partition wall and a pipeline all arranged underground, wherein the top plate is arranged on the top of the support member, and a receiving hole is formed around the inside of the support member and between the top plates, the partition wall is arranged in the support member and divides the receiving hole into a buried area and a passage area, an observation portion is also provided on the partition wall, and the end of the passage area is connected to the surface, and the pipeline is buried in the buried area.
[0007] When a newly built highway intersects with an underground oil and gas pipeline, a culvert of appropriate depth is first dug underground, and then support members are erected on the culvert wall to form a receiving hole in the middle of the support member. Then, a partition wall is built at an appropriate position in the receiving hole to divide the receiving hole into a buried area for burying pipelines and a passage area for maintenance personnel to pass through. An observation section is opened on the partition wall at the same height as the pipeline, and finally a top plate is laid above the support member, and the road surface can be laid directly above the top plate. With this setting, the highway can be laid directly from above the culvert, and the force of vehicles running above the highway will not be transmitted to the buried pipeline; when the staff needs to inspect the pipeline, they can enter the culvert from the end of the passage area to carry out maintenance work, and smell whether there is oil and gas through the observation section. No oil smell indicates that the pipeline is operating normally. If there is oil smell, it means that the buried oil and gas pipeline is leaking. The partition wall is broken by external force, and the soil layer of the buried area is excavated from the side, and the buried oil and gas pipeline is inspected.
[0008] Preferably, the buried area includes a buffer portion and a buried portion, both of which are located below the top plate and are arranged in sequence, and the pipeline is installed in the buried portion.
[0009] With this arrangement, when a vehicle passes over the culvert, the buffer part can fully absorb the vibration generated by the vehicle passing over the top plate, thereby preventing the pipeline in the buried part from being affected by the vibration for a long time and thus ruptured; at the same time, the buffer part can prevent oil and gas accumulation to ensure safety.
[0010] Furthermore, the buffer part is filled with fine sand, and the buried part is backfilled with soil from the original soil layer. Using fine sand as the buffer material can not only obtain excellent buffering performance without affecting the environment, but also save costs.
[0011] Preferably, the support member comprises two support walls, which are symmetrically arranged on both sides of the culvert, and the cross-section of the support wall is an inverted T-shaped structure.
[0012] Through this arrangement, the support wall can maintain the stability of the culvert on both sides of the culvert, and the cross-section of the support wall is an inverted T-shaped structure, that is, a platform is provided at the bottom. When installed, the bottom of the support wall can be buried in the soil, and the material in the culvert and the soil and rocks outside the culvert act together on the platform at the bottom of the support wall, making the installation of the support wall more stable, preventing the support wall from collapsing, and improving the safety performance of the culvert.
[0013] Furthermore, a groove is provided on the top of the supporting wall, and the top plate abuts against the supporting wall through the groove.
[0014] With this arrangement, the top plate can abut against the groove at the top of the supporting wall, thereby fitting more closely with the supporting wall and effectively preventing the top plate from shifting in the horizontal direction, thereby improving the stability of the culvert structure.
[0015] Preferably, a boss is provided at the bottom of the partition wall, and the boss is protruded toward the passage area, and the boss is buried in the bottom of the passage area.
[0016] With this arrangement, the soil on the boss can act on the boss to keep the partition wall stable; on the other hand, the length of the boss in the passage area is greater than the length of the boss in the buried area. Since the buried area contains soil for buried pipes and sand for buffering, the pressure on the partition wall on the buried area side is greater than the pressure on the passage area side. By setting a longer boss at the bottom of the passage area, the compressive resistance of the partition wall can be improved, preventing the partition wall from collapsing toward the passage area due to excessive pressure in the buried area, thereby increasing the safety of the culvert.
[0017] Furthermore, a hollow groove is provided between the partition wall and the top plate, and there is no contact between the partition wall and the top plate.
[0018] With this arrangement, the pressure from the top plate will not act on the partition wall, and the partition wall does not bear the supporting function of the top plate. When the staff observes that the pipeline is leaking and needs to be repaired, they can directly dig up the partition wall to repair the pipeline in the buried area without affecting the top plate, thus ensuring smooth traffic on the highway above.
[0019] Furthermore, the partition wall is a brick wall structure.
[0020] This arrangement ensures that the partition wall is structurally stable and can be easily removed when it is necessary to break open the partition wall to inspect the buried pipes.
[0021] Preferably, the observation portion comprises a plurality of observation wells, and the observation wells are arranged in an equidistant array along the extension direction of the partition wall.
[0022] With this setup, workers can observe the pipelines in the buried area through the observation well to determine the condition of the pipelines.
[0023] Furthermore, the observation well is penetrated through the partition wall, with one end located beside the pipeline and the other end located in the passage area.
[0024] With this setting, when a pipeline leaks, the staff can more intuitively notice the changes on the side of the pipeline and perform maintenance on the pipeline.
[0025] Preferably, the distance between the top of the pipeline and the top plate is more than 1m. It can be seen from the "Notice on Standardizing the Management of Highway Bridge and Petroleum and Natural Gas Pipeline Crossing Projects" (Jiaogonglufa
[2015] No. 36) that when a highway crosses a pipeline, the top of the pipe should be no less than 1 meter from the natural ground under the bridge. If the actual elevation of the newly built highway site is insufficient or the pipeline is shallow, the clearance height of the channel culvert protection directly above the pipeline is insufficient, and the channel culvert operation cannot be implemented. This setting method can ensure that the pipeline has an appropriate buried depth and that the pipeline is buried within a safe range.
[0026] Furthermore, the height of the passage area is 1.8 m or more, and the width of the passage area is 2 m or more.
[0027] This setting ensures that there is a suitable passage area in the passage area, which is convenient for staff to carry out maintenance work.
[0028] Compared with the prior art, the beneficial effects of the utility model are:
[0029] (1) By setting up a passage area parallel to the pipeline in the culvert, workers can inspect or repair the pipeline without affecting the ground.
[0030] (2) The buffer section reduces the impact of road vibration on the pipeline and reduces the probability of leakage. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 This is a structural schematic diagram of a first embodiment of a buried oil and gas pipeline maintenance culvert according to the utility model;
[0032] Figure 2 This is a schematic structural diagram of a second embodiment of a buried oil and gas pipeline maintenance culvert according to the utility model;
[0033] Figure 3 for Figure 2 Sectional view AA.
[0034] The illustrations are as follows:
[0035] 1. Top plate; 2. Support member; 21. Support wall; 22. Groove; 3. Partition wall; 31. Boss; 4. Pipeline; 5. Accommodation hole; 51. Buried area; 511. Buffer part; 512. Buried part; 52. Passage area; 54. Empty groove; 6. Observation part; 61. Observation well. DETAILED DESCRIPTION
[0036] The utility model is further described below in conjunction with specific implementation methods. The drawings are only used for exemplary descriptions, and are only schematic diagrams, not actual pictures, and cannot be understood as limitations on this patent; in order to better illustrate the embodiments of the utility model, some parts of the drawings may be omitted, enlarged or reduced, and do not represent the size of the actual product; for those skilled in the art, it is understandable that some well-known structures and their descriptions in the drawings may be omitted.
[0037] The same or similar numbers in the drawings of the embodiments of the present invention correspond to the same or similar parts; in the description of the present invention, it should be understood that if the terms "upper", "lower", "left", "right" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the drawings, it is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, the terms describing the positional relationship in the drawings are only used for illustrative purposes and cannot be understood as limitations on this patent. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.
[0038] Example 1
[0039] like Figure 1 The figure shows a first embodiment of a buried oil and gas pipeline maintenance culvert of the utility model, which provides a buried oil and gas pipeline maintenance culvert, including a top plate 1, a support member 2, a partition wall 3 and a pipeline 4 all arranged underground, the top plate 1 is arranged on the top of the support member 2, and a receiving hole 5 is formed between the support member 2 and the top plate 1, the partition wall 3 is arranged in the support member 2 and divides the receiving hole 5 into a buried area 51 and a passage area 52, the end of the passage area 52 is connected to the ground surface, and an observation part 6 is also provided on the partition wall 3, and the pipeline 4 is buried in the buried area 51.
[0040] When a new highway intersects with an existing buried oil and gas pipeline, a culvert of appropriate depth is first dug underground, and then a support 2 is set up on the culvert wall to form a receiving hole 5 in the middle of the support 2. Then, a partition wall 3 is built at a suitable position in the receiving hole 5 to divide the receiving hole 5 into a buried area 51 for burying the pipeline 4 and a passage area 52 for maintenance personnel to pass through. An observation section 6 is opened on the partition wall 3 at a height consistent with the pipeline 4. Finally, a top plate 1 is laid above the support 2, and the road surface can be directly laid above the top plate 1. Through this arrangement, the top of the culvert is consistent with the surrounding road surface, so that the car above can pass smoothly. When the staff needs to inspect the pipeline 4, they can enter the culvert from the end of the passage area 52 to carry out maintenance work, and judge whether there is oil and gas leakage through the observation section 6. No oil smell indicates that the pipeline 4 is operating normally. If there is oil smell, it means that the pipeline 4 is leaking. The partition wall 3 is broken by external force, and the soil in the buried area 51 is excavated from the side, and then the pipeline 4 is inspected.
[0041] As an embodiment of the present utility model, the support member 2 includes two support walls 21. The support walls 21 are symmetrically arranged on both sides of the culvert, and the cross-section of the support wall 21 is an inverted T-shaped structure.
[0042] Through this arrangement, the support wall 21 can maintain the stability of the culvert on both sides of the culvert, and the cross-section of the support wall 21 is an inverted T-shaped structure, that is, a platform is provided at the bottom. When installed, the bottom of the support wall 21 can be buried in the soil, and the material in the culvert and the soil and rocks outside the culvert act together on the platform at the bottom of the support wall 21, making the installation of the support wall 21 more stable, preventing the support wall 21 from collapsing, and improving the safety performance of the culvert.
[0043] Example 2
[0044] like Figure 2 and Figure 3 The second embodiment of the utility model for a buried oil and gas pipeline maintenance culvert is shown. This embodiment is similar to the first embodiment, except that the structures of the support wall 21, the buried area 51 and the partition wall 3 are different.
[0045] As an embodiment of the present invention, the buried area 51 includes a buffer portion 511 and a buried portion 512 which are both located below the top plate 1 and are sequentially arranged, and the pipeline 4 is installed in the buried portion 512 .
[0046] With this arrangement, when a vehicle passes over the culvert, the buffer portion 511 can fully absorb the vibration generated by the vehicle passing over the top plate 1, thereby preventing the pipeline 4 located in the buried portion 512 from being affected by the vibration for a long time and thus from rupturing. At the same time, the buffer portion 511 can prevent oil and gas from accumulating, ensuring safety.
[0047] As an embodiment of the present invention, the buffer part 511 is filled with fine sand, and the buried part is backfilled with soil from the original soil layer. Using fine sand as a buffer material can not only obtain excellent buffering performance without affecting the environment, but also save costs.
[0048] As an embodiment of the present utility model, a groove 22 is provided on the top of the supporting wall 21 , and the top plate 1 abuts against the supporting wall 21 through the groove 22 .
[0049] With this arrangement, the top plate 1 can abut against the groove 22 at the top of the support wall 21, thereby fitting more closely with the support wall 21 and effectively preventing the top plate 1 from shifting horizontally, thereby improving the stability of the culvert structure.
[0050] As an embodiment of the present utility model, a boss 31 is provided at the bottom of the partition wall 3 , and the boss 31 is protruded toward the passage area 52 , and the boss 31 is buried in the bottom of the passage area 52 .
[0051] With this arrangement, the soil on the boss 31 can act on the boss 31 to keep the partition wall 3 stable; on the other hand, the length of the boss 31 in the passage area 52 is greater than the length of the boss 31 in the buried area 51. Since the buried area 51 contains soil for burying the pipe 4 and sand for buffering, the pressure on the partition wall 3 in the buried area 51 is greater than the pressure on the passage area 52. By arranging a longer boss 31 at the bottom of the passage area 52, the compressive resistance of the partition wall 3 can be improved, thereby preventing the partition wall 3 from collapsing toward the passage area 52 due to excessive pressure in the buried area 51, thereby increasing the safety of the culvert.
[0052] Furthermore, a hollow groove 54 is provided between the partition wall 3 and the top plate 1 , and there is no contact between the partition wall 3 and the top plate 1 .
[0053] As an embodiment of the present utility model, a hollow groove 54 is provided between the partition wall 3 and the top plate 1 , and there is no contact between the partition wall 3 and the top plate 1 .
[0054] With this arrangement, the pressure of the roof 1 will not act on the partition wall 3, and the partition wall 3 does not bear the supporting function of the roof 1. When the staff observes that the pipeline 4 is leaking and needs to be repaired, they can directly dig up the partition wall 3 to repair the pipeline 4 in the buried area 51 without affecting the top plate 1, thereby ensuring smooth traffic on the highway above.
[0055] As an embodiment of the present utility model, the partition wall 3 is a brick wall structure.
[0056] This arrangement ensures that the structure of the partition wall 3 is stable and facilitates removal when the partition wall 3 needs to be broken to inspect the pipeline 4 in the buried area 51.
[0057] As an embodiment of the present invention, the observation portion 6 includes a plurality of observation wells 61 , and the observation wells 61 are arranged in an equidistant array along the extension direction of the partition wall 3 .
[0058] With this arrangement, the staff can observe the pipeline 4 in the buried area 51 through the observation well 61 to determine the condition of the pipeline 4 .
[0059] As an embodiment of the present utility model, the observation well 61 is penetrated through the partition wall 3 , with one end located beside the pipeline 4 and the other end located in the passage area 52 .
[0060] With this arrangement, when a leak occurs in the pipeline 4 , the staff can more intuitively notice the changes on the side of the pipeline 4 and thus perform maintenance on the pipeline 4 .
[0061] Example 3
[0062] The following is a third embodiment of a buried oil and gas pipeline maintenance culvert of the utility model. This embodiment is similar to the second embodiment, except that the size setting of the structure in the culvert is different.
[0063] As an embodiment of the present invention, the distance between the top of the pipeline 4 and the top plate 1 is more than 1m. Through this arrangement, it can be ensured that the pipeline 4 has an appropriate buried depth and that the pipeline 4 is affected by the road surface within a limited range.
[0064] As an embodiment of the present invention, the height in the passage area 52 is 1.8 m or more, and the width in the passage area 52 is 2 m or more.
[0065] This arrangement ensures that the passage area 52 has a suitable passage area 52, making it easier for workers to carry out maintenance work.
[0066] Obviously, the above embodiments of the utility model are only examples for clearly explaining the utility model, and are not intended to limit the implementation methods of the utility model. For ordinary technicians in the relevant field, other different forms of changes or modifications can be made on the basis of the above description. It is not necessary and impossible to list all the implementation methods here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the utility model should be included in the protection scope of the claims of the utility model.
Claims
1. A buried oil and gas pipeline maintenance culvert, characterized in that: The invention comprises a top plate (1), a support member (2), a partition wall (3) and a pipeline (4) all arranged underground, wherein the top plate (1) is arranged on the top of the support member (2), a receiving hole (5) is formed around the inside of the support member (2) and between the top plate (1), the partition wall (3) is arranged in the support member (2) and divides the receiving hole (5) into a buried area (51) and a passage area (52), the end of the passage area (52) is connected to the ground surface, an observation part (6) is also arranged on the partition wall (3), and the pipeline (4) is installed in the buried area (51).
2. The buried oil and gas pipeline maintenance culvert according to claim 1, characterized in that: The buried area (51) comprises a buffer portion (511) and a buried portion (512) which are both located below the top plate (1) and are arranged in sequence, and the pipeline (4) is installed in the buried portion (512).
3. The buried oil and gas pipeline maintenance culvert according to claim 1 is characterized in that: The support member (2) comprises two support walls (21), the support walls (21) are symmetrically arranged on both sides of the culvert, and the cross-section of the support wall (21) is an inverted T-shaped structure.
4. The buried oil and gas pipeline maintenance culvert according to claim 3 is characterized in that: A groove (22) is provided at the top of the support wall (21), and the top plate (1) abuts against the support wall (21) via the groove (22).
5. The buried oil and gas pipeline maintenance culvert according to claim 1, characterized in that: A boss (31) is provided at the bottom of the partition wall (3), and the boss (31) is arranged to protrude toward the passage area (52), and the boss (31) is buried in the bottom of the passage area (52).
6. The buried oil and gas pipeline maintenance culvert according to claim 5, characterized in that: A hollow groove (54) is provided between the partition wall (3) and the top plate (1), and there is no contact between the partition wall (3) and the top plate (1).
7. The buried oil and gas pipeline maintenance culvert according to claim 6, characterized in that: The partition wall (3) is a brick wall structure.
8. The buried oil and gas pipeline maintenance culvert according to claim 1, characterized in that: The distance between the top of the pipeline (4) and the top plate (1) is more than 1 m.
9. A buried oil and gas pipeline maintenance culvert according to any one of claims 1 to 8, characterized in that: The observation portion (6) comprises a plurality of observation wells (61), and the observation wells (61) are arranged in an equidistant array along the extension direction of the partition wall (3).
10. The buried oil and gas pipeline maintenance culvert according to claim 9, characterized in that: The observation well (61) is disposed through the partition wall (3), with one end located beside the pipeline (4) and the other end located in the passage area (52).