Greenhouse structure
By introducing vertical corridors and cross-connected tie rod and arch rod structures into the greenhouse structure, the problems of greenhouse stability and floor space are solved, and the stability and deformation resistance of the greenhouse structure are improved. It is suitable for multiple greenhouses. connectivity and production management.
Patent Information
- Application Number
- CN202323502517.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-21
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2033-12-21
AI Technical Summary
The existing greenhouse structure has poor stability while reducing the floor space, making it difficult to ensure the stability and anti-torsion performance of the structure.
By setting up corridors perpendicular to the length of the greenhouse, and introducing tie rods, arch rods and diagonal tie rod structures into the greenhouse and corridors to form intersections for fixed connections, ensuring even distribution of stress and avoiding distortion and vibration, while using rollers and Track devices enable movement and height adjustment of the structure.
It has improved the stability and durability of the greenhouse structure, reduced the floor space, and improved the structure's anti-deformation ability and mechanization and digitalization level. It is suitable for the connection and production management of multiple greenhouses.
Smart Images

Figure CN221901639U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of greenhouses, in particular to a greenhouse structure. Background Art
[0002] In the prior art, each greenhouse is relatively independent. In order for operators or production machinery to enter the greenhouse, it is often necessary to build production roads at both ends of the greenhouse, which greatly increases the floor area of the greenhouse. Although the prior art connects the greenhouses through corridors to reduce the floor area of the greenhouse, the stability of the greenhouse is low after the corridors are set up.
[0003] For example, the roof in patent document CN208080023U includes two side roofs, and the side roofs are composed of at least one arc-shaped arch frame set on the basic frame and arranged longitudinally; at least one arc-shaped air guide bracket is provided at the end of the multi-span greenhouse; a corridor is provided between adjacent roofs; the corridor is fixed on the basic frame; it can be seen that although the patent document can reduce the floor area of the greenhouse by setting up a corridor, the stability of the greenhouse is poor.
[0004] Therefore, how to reduce the floor space occupied by the greenhouse structure while ensuring the stability of the greenhouse structure has become a technical problem that technical personnel in this field urgently need to solve. Utility Model Content
[0005] The purpose of the utility model is to provide a greenhouse structure to solve the problems existing in the above-mentioned prior art, so as to reduce the floor area occupied by the greenhouse structure while ensuring the stability of the greenhouse structure.
[0006] To achieve the above purpose, the utility model provides the following solutions:
[0007] The utility model provides a greenhouse structure, comprising a plurality of greenhouses arranged in parallel and side by side, and a corridor for connecting adjacent greenhouses, wherein the extension direction of the corridor is perpendicular to the length direction of the greenhouses, any one of the greenhouses comprises a shelf and a thermal insulation film covered on the shelf, the shelf comprises a greenhouse tie rod passing through the entire length direction of the greenhouse, the corridor comprises a corridor frame and a thermal insulation layer covered on the corridor frame, and the corridor frame comprises a corridor tie rod passing through the entire extension direction of the corridor.
[0008] Preferably, a plurality of greenhouse tie rods are arranged on the top of the scaffolding, and a plurality of first arch rods are arranged at intervals along the extension direction of the greenhouse tie rods, any one of the first arch rods extends along the width direction of the greenhouse, the first arch rods intersect with the greenhouse tie rods to form a first intersection, and the first arch rods at the first intersection are fixedly connected to the greenhouse tie rods; the scaffolding also includes a diagonal tie rod, one end of the diagonal tie rod is fixedly connected to the greenhouse tie rod located at the bottom end of the first arch rod, and the other end is fixedly connected to the greenhouse tie rod located at the top of the first arch rod, the diagonal tie rod forms a second intersection with the first arch rod passing along the way, and the diagonal tie rod at the second intersection is fixedly connected to the first arch rod.
[0009] Preferably, a plurality of corridor tie rods are provided at the top of the corridor frame, and a plurality of second arch rods are arranged at intervals along the extension direction of the corridor tie rods, any of the second arch rods extend along the width direction of the corridor frame, the second arch rods intersect with the corridor tie rods located at the highest point to form a third intersection, the second arch rods intersect with the corridor tie rods located at a non-highest point to form a fourth intersection, the second arch rods at the third intersection are fixedly connected to the corridor tie rods located at the highest point, and the second arch rods at the fourth intersection are fixedly connected to the corridor tie rods located at a non-highest point.
[0010] Preferably, both ends of the gallery are further provided with a vertical pole group and a horizontal pole group connected to the gallery, the vertical pole group includes a plurality of vertical poles, the horizontal pole group includes a plurality of horizontal poles, the vertical poles and the horizontal poles intersect to form a fifth intersection, and the horizontal poles and the vertical poles at the fifth intersection are fixedly connected; the vertical pole group also includes a first vertical pole fixedly connected to the third intersection at one end, and the other end of the vertical pole is supported on the ground, and the horizontal pole group also includes a first horizontal pole fixedly connected to the fourth intersection at both ends; doors for entry of personnel or machinery are provided at both ends of the gallery, and / or the door for entry of personnel or machinery is provided at the corridor between two adjacent greenhouses.
[0011] Preferably, the greenhouse pull rod is provided with a slot for laying the thermal insulation film, the slot is opened along the extension direction of the greenhouse pull rod, and a retaining spring for fixing the thermal insulation film in the slot is provided in the slot; an antifreeze film is also provided between the thermal insulation film and the shed; a ventilation channel for ventilating the greenhouse is provided on the side of the shed, and the thermal insulation film and the antifreeze film laid in the ventilation channel can be lifted up; both sides of the shed are provided with film rolling rods for facilitating the unfolding or retracting of the thermal insulation film, and a driving assembly for driving the two film rolling rods to move toward or away from each other.
[0012] Preferably, a groove is provided along the arch direction of the first arch rod, the thermal insulation film is provided in the groove, and a fixing strip for fixing the thermal insulation film in the groove is provided.
[0013] Preferably, the two ends of the first arch rod are respectively connected to support rods, and the two ends of the first arch rod are provided with reducing plugs, and the end of the support rod connected to the first arch rod is plugged into the reducing plug, or the end of the support rod connected to the first arch rod is provided with a reducing plug, and the reducing plug is plugged into the end connected to the first arch rod; the connection between the first arch rod and the support rod is provided with a fastening bolt for improving the connection strength.
[0014] Preferably, the bottom of the greenhouse and the corridor are provided with rollers, tracks matching the rollers, and driving devices for pushing the greenhouse and the corridor to move along the tracks.
[0015] Preferably, a base is provided between the roller and the bottom of the greenhouse and the bottom of the corridor, the top of the base is connected to the bottom of the greenhouse and the corridor, the bottom of the base is connected to the roller, and a lifting assembly is provided at the bottom of the greenhouse, the lifting assembly includes a lifting rod connected to the top of the base, a fastening rod connected to the bottom of the greenhouse and the corridor, the fastening rod is sleeved on the outside of the lifting rod, a plurality of through holes are opened in the vertical direction of the fastening rod, a plurality of sockets matching the through holes are provided in the vertical direction of the lifting rod, and the lifting assembly also includes a plug rod for inserting into the plug rod and the through hole to achieve height adjustment of the greenhouse and the corridor.
[0016] Preferably, an external circulation fan is provided at the ventilation passage, a plurality of internal circulation fans are provided inside the greenhouse, and the external circulation fan and the internal circulation fan are arranged toward the ventilation passage on either side of the two sides of the shelf.
[0017] Compared with the prior art, the utility model has achieved the following technical effects:
[0018] The utility model connects a plurality of greenhouses by arranging corridors, so that when operators or production machines enter different greenhouses, they only need to enter different positions of the corridors, thereby avoiding the problem of a large greenhouse structure occupying an area due to the need to configure corresponding production roads for different greenhouses; at the same time, the greenhouse pull rods and the corridor pull rods allow the weight of the greenhouse and the corridor to be evenly distributed on the corridor or the greenhouse, respectively, thereby achieving uniform distribution of stress, avoiding distortion or deformation of the greenhouse structure, reducing the vibration frequency of the corridor and the greenhouse, and thus improving the stability and durability of the greenhouse structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0020] Figure 1 It is a top view schematic diagram of the greenhouse structure;
[0021] Figure 2 It is a north-south view of the greenhouse structure;
[0022] Figure 3 East and west views of the shed structure;
[0023] Figure 4 It is a structural diagram of the greenhouse structure;
[0024] Figure 5 This is a structural diagram of the greenhouse structure from another perspective;
[0025] Among them, 1. Greenhouse; 2. Corridor; 3. Greenhouse tie rod; 4. Diagonal tie rod; 5. Ventilation duct; 6. First arch rod; 7. Door; 8. Corridor tie rod; 9. Insulation film. DETAILED DESCRIPTION
[0026] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0027] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0028] like Figure 1-Figure 5 As shown, the utility model discloses a greenhouse structure, including a plurality of greenhouses 1 arranged in parallel and side by side, and a corridor 2 for connecting adjacent greenhouses 1, the extension direction of the corridor 2 is perpendicular to the length direction of the greenhouse 1, any greenhouse 1 includes a shelf and a thermal insulation film 9 covering the shelf, the shelf includes a greenhouse tie rod running through the entire length direction of the greenhouse 1, the corridor 2 includes a shelf and a thermal insulation layer covering the shelf, and the shelf includes a corridor tie rod 8 running through the entire extension direction of the corridor 2.
[0029] The corridor 2 connects multiple greenhouses 1, so that when operators or production machinery enter different greenhouses 1, they only need to enter different positions of the corridor 2, avoiding the problem of the greenhouse structure occupying a large area due to the need to configure corresponding production roads for different greenhouses 1; at the same time, the greenhouse pull rods and corridor pull rods 8 allow the weight of the greenhouse 1 and the corridor 2 to be evenly distributed on the corridor 2 or the greenhouse 1, respectively, achieving uniform distribution of stress, avoiding distortion or deformation of the greenhouse structure, reducing the vibration frequency of the corridor 2 and the greenhouse 1, thereby improving the stability and durability of the greenhouse structure.
[0030] like Figure 1-Figure 5 As shown, a plurality of greenhouse tie rods are arranged on the top of the scaffolding, and a plurality of first arch rods 6 are arranged at intervals along the extension direction of the greenhouse tie rods, and any first arch rod 6 extends along the width direction of the greenhouse 1, and the first arch rod 6 intersects with the greenhouse tie rod to form a first intersection, and the first arch rod 6 at the first intersection is fixedly connected to the greenhouse tie rod; the scaffolding also includes a diagonal tie rod 4, one end of the diagonal tie rod 4 is fixedly connected to the greenhouse tie rod located at the bottom end of the first arch rod 6, and the other end is fixedly connected to the greenhouse tie rod located at the top of the first arch rod 6, and the diagonal tie rod 4 forms a second intersection with the first arch rod 6 passing along the way, and the diagonal tie rod 4 at the second intersection is fixedly connected to the first arch rod 6.
[0031] like Figure 1-Figure 5 As shown, a plurality of corridor tie rods are provided at the top of the corridor, and a plurality of second arch rods are arranged at intervals along the extension direction of the corridor tie rods, and any second arch rod extends along the width direction of the corridor, and the second arch rod intersects with the corridor tie rod located at the highest point to form a third intersection, and the second arch rod intersects with the corridor tie rod located at a non-highest point to form a fourth intersection, and the second arch rod at the third intersection is fixedly connected to the corridor tie rod located at the highest point, and the second arch rod at the fourth intersection is fixedly connected to the corridor tie rod located at a non-highest point.
[0032] like Figure 1-Figure 5 As shown, both ends of the gallery are also provided with a vertical pole group and a horizontal pole group connected to the gallery, the vertical pole group includes a plurality of vertical poles, the horizontal pole group includes a plurality of horizontal poles, the vertical poles and the horizontal poles intersect to form a fifth intersection, and the horizontal poles and the vertical poles at the fifth intersection are fixedly connected; the vertical pole group also includes a first vertical pole with one end fixedly connected to the third intersection, and the other end of the vertical pole is supported on the ground, and the horizontal pole group also includes a first horizontal pole with both ends fixedly connected to the fourth intersection; doors 7 for entry of personnel or machinery are provided at both ends of the gallery, and / or a door 7 for entry of personnel or machinery is provided at the corridor 2 between two adjacent greenhouses 1.
[0033] Through the structure described in the above paragraphs, the greenhouse structure is more stable, with stronger anti-deformation ability and higher stability.
[0034] Furthermore, in the utility model, a slot for laying a thermal insulation film 9 is provided on the greenhouse pull rod, and the slot is opened along the extension direction of the greenhouse pull rod. A retaining spring is provided in the retaining spring for fixing the thermal insulation film 9 in the slot. The cooperation of the retaining spring and the retaining groove can refer to the role of the retaining spring and the retaining groove in the patent document CN206851494U; an antifreeze film is also provided between the thermal insulation film 9 and the scaffolding; a ventilation channel 5 for ventilation of the greenhouse 1 is provided on the side of the scaffolding, and the thermal insulation film 9 and the antifreeze film laid at the ventilation channel 5 are provided. It can be opened (the antifreeze film refers to a film with good light transmittance, and the thermal insulation film 9 refers to a film with poor light transmittance or no light transmittance, so the thermal insulation film 9 needs to be unfolded when there is sunlight outside, so that the outside light can smoothly enter the greenhouse 1, which is convenient for the growth of plants in the greenhouse 1); both sides of the shed are provided with a film rolling rod for facilitating the unfolding or retracting of the thermal insulation film 9, and a driving component for driving the two film rolling rods to move toward or away from each other, and the driving component can specifically be a linear driving device such as an electric push rod.
[0035] Alternatively, the utility model may not adopt the setting mode of the spring clamping groove, and select the structure of the groove clamping strip to realize the fixing of the thermal insulation film 9. Specifically, the utility model is provided with a groove along the arch direction of the first arch rod 6, and the thermal insulation film 9 is provided in the groove, and the clamping strip for fixing the thermal insulation film 9 in the groove. When the thermal insulation film 9 is not installed in the groove, the groove can also be used to drain the accumulated water on the top of the greenhouse 1, so as to ensure the light transmittance and thermal insulation performance of the greenhouse 1.
[0036] In the utility model, the two ends of the first arch rod 6 are respectively connected with support rods, and the two ends of the first arch rod 6 are provided with reducing plugs, and the end of the support rod connected to the first arch rod 6 is plugged and matched with the reducing plug, or the end of the support rod connected to the first arch rod 6 is provided with a reducing plug, and the reducing plug is plugged and matched with the end connected to the first arch rod 6; the connection between the first arch rod 6 and the support rod is provided with a fastening bolt for improving the connection strength. In this way, the arched beam column is set as a split structure, which facilitates the handling and transportation of the first arch rod 6; by setting the plug-in point between the first arch rod 6 and the support rod at the two ends of the first arch rod 6, it is avoided that the plug-in structure of the arch is set at the middle position of the top of the arch in the prior art. When the plug-in point is slightly loose, the middle position of the top of the arch will collapse downward, and the greenhouse pull rod is inconvenient to be connected to the arch, and the overall stability and strength of the greenhouse 1 are low.
[0037] In the utility model, the bottom of the greenhouse 1 and the corridor 2 are provided with rollers, tracks matching the rollers, and driving devices for driving the greenhouse 1 and the corridor 2 to move along the tracks. This allows the operator to adjust the position of the greenhouse structure according to the position of the sun in different seasons to maximize the use of light, increase light intensity, promote plant photosynthesis, and increase yield. In addition, by driving the greenhouse 1 and the corridor 2 to move, excessive fatigue of the soil in the greenhouse 1 can be prevented: due to planting in the same piece of soil for a long time, the nutrients in the soil are excessively exhausted.
[0038] In the utility model, a base is provided between the roller and the bottom of the greenhouse 1 and the bottom of the corridor 2, the top of the base is connected to the bottom of the greenhouse 1 and the corridor 2, the bottom of the base is connected to the roller, and a lifting assembly is provided at the bottom of the greenhouse 1, the lifting assembly includes a lifting rod connected to the top of the base, a fastening rod connected to the bottom of the greenhouse 1 and the corridor 2, the fastening rod is sleeved on the outside of the lifting rod, a plurality of through holes are opened in the vertical direction of the fastening rod, a plurality of sockets matching the through holes are provided in the vertical direction of the lifting rod, and the lifting assembly also includes a plug rod for inserting into the plug hole and the through hole to realize height adjustment of the greenhouse 1 and the corridor 2. By setting the above-mentioned lifting component, when it is necessary to adjust the height of the greenhouse 1, first take out the insertion rod, move the greenhouse 1 up or down, and when the greenhouse 1 moves to the required height, align the socket and the through hole, and insert the insertion rod into the socket and the through hole of the corresponding height, so as to adjust the height of the greenhouse 1; and in order to save manpower, the utility model also provides a driving component on the base for driving the greenhouse 1 to rise and fall, and the driving component can be a linear driving device such as a hydraulic cylinder, an electric push rod or a cylinder.
[0039] In the utility model, an external circulation fan is provided at the ventilation channel 5, and a plurality of internal circulation fans are provided inside the greenhouse 1, and the external circulation fan and the internal circulation fan are arranged toward the ventilation channel 5 on either side of the shed. Through the cooperation of the external circulation fan and the internal circulation fan, the ventilation efficiency of the greenhouse 1 is effectively improved.
[0040] In the utility model, a mounting frame is provided in the greenhouse 1, and the mounting frame includes a first inclined frame and a second inclined frame. The first inclined frame is provided with a solar power generation component on the light-facing side, and the second inclined frame is provided with a solar heating component on the backlight side; the light-facing side refers to the side that can be irradiated by the sun in the morning, and the backlight side refers to the side that can be irradiated by the sun in the afternoon. In this way, the solar power generation component can convert solar energy into electrical energy to power the electrical devices in the greenhouse, and the solar heating component can convert solar energy into thermal energy and maintain a suitable temperature in the greenhouse 11 under low temperature conditions. And through the arrangement of the solar power generation component and the solar heating component, a greater degree of utilization of solar energy is achieved.
[0041] In the utility model, the greenhouse tie rod and the first arch rod 6 are both in an arc shape. By setting the greenhouse tie rod and the first arch rod 6 in an arc shape, rain and snow on the roof can slide down along the greenhouse tie rod and the first arch rod 6 to the ground, thereby preventing rain and snow from being pressed on the greenhouse 1 for a long time and avoiding the collapse of the greenhouse 1; when the wind blows towards the greenhouse structure, the greenhouse tie rod and the first arch rod 6 will promote the wind to be diagonally upward along the wind-resistant insulation film 9, and leave the greenhouse 1 and enter the air after reaching the top of the greenhouse 1, thereby reducing the wind pressure on the top and sides of the greenhouse 1, thereby effectively avoiding the problem of the greenhouse 1 being blown down by the wind.
[0042] The greenhouse 1 in the utility model can be a sloping roof greenhouse, a flat roof greenhouse, a sawtooth greenhouse; a greenhouse with an arched roof such as a semicircular or parabolic one. When the greenhouse 1 is a ridge-type greenhouse, a Wenluo-type greenhouse 1 can be selected, that is, the roof of the ridge-type greenhouse is divided into 2 to 4 small roofs with a span of 3.2m, thereby reducing the roof height of the greenhouse 1 and reducing the impact of wind load on the greenhouse 1; the greenhouse tie rod, the corridor tie rod 8, and the inclined tie rod 4 in the utility model can use DN25*1.5mm galvanized steel pipes, and the first arch rod 6 and the second arch rod use DN32*2.0mm galvanized steel pipes.
[0043] In addition, the corridor 2 in the utility model shortens the commuting distance in the greenhouse during the production process, strengthens the integration of people, objects and sites in all links such as crop sowing, production management and harvesting, saves costs and improves efficiency. In rainy and snowy weather scenarios, the corridor 2 makes the greenhouse structure easier to manage. The corridor 2 improves the mechanization and digitalization level of agricultural production, facilitates the use of greenhouse rail cars, and realizes the transportation of goods in the greenhouse 1 and the outside world; it is convenient to use the Internet of Things control equipment to control the ventilation, water and fertilizer integrated irrigation, and lighting of the entire greenhouse structure. It can save the investment in mechanized and digital equipment and achieve a higher level of mechanization and digitalization.
[0044] The present invention uses specific examples to illustrate the principle and implementation of the present invention. The above examples are only used to help understand the method and core idea of the present invention. At the same time, for those skilled in the art, according to the idea of the present invention, there will be changes in the specific implementation and application scope. In summary, the content of this specification should not be understood as limiting the present invention.
Claims
1. A greenhouse structure, characterized in that: It includes a plurality of greenhouses arranged in parallel and side by side, and a corridor for connecting adjacent greenhouses, wherein the extension direction of the corridor is perpendicular to the length direction of the greenhouses, and any one of the greenhouses includes a shelf and an insulation film covering the shelf, and the shelf includes a greenhouse tie rod that runs through the entire length direction of the greenhouse, and the corridor includes a shelf and an insulation layer covering the shelf, and the shelf includes a corridor tie rod that runs through the entire extension direction of the corridor.
2. The greenhouse structure according to claim 1, characterized in that: A plurality of greenhouse tie rods are arranged on the top of the scaffolding, and a plurality of first arch rods are arranged at intervals along the extension direction of the greenhouse tie rods, and any one of the first arch rods extends along the width direction of the greenhouse, and the first arch rods intersect with the greenhouse tie rods to form a first intersection, and the first arch rod at the first intersection is fixedly connected to the greenhouse tie rod; the scaffolding also includes a diagonal tie rod, one end of the diagonal tie rod is fixedly connected to the greenhouse tie rod located at the bottom end of the first arch rod, and the other end is fixedly connected to the greenhouse tie rod located at the top of the first arch rod, and the diagonal tie rod forms a second intersection with the first arch rod passing along the way, and the diagonal tie rod at the second intersection is fixedly connected to the first arch rod.
3. The greenhouse structure according to claim 1, characterized in that: A plurality of corridor tie rods are provided on the top of the corridor frame, and a plurality of second arch rods are provided at intervals along the extension direction of the corridor tie rods, and any of the second arch rods extends along the width direction of the corridor frame, and the second arch rods intersect with the corridor tie rods located at the highest point to form a third intersection, and the second arch rods intersect with the corridor tie rods located at a non-highest point to form a fourth intersection, and the second arch rods at the third intersection are fixedly connected to the corridor tie rods located at the highest point, and the second arch rods at the fourth intersection are fixedly connected to the corridor tie rods located at a non-highest point.
4. The greenhouse structure according to claim 3, characterized in that: Both ends of the gallery are also provided with a vertical pole group and a horizontal pole group connected to the gallery, the vertical pole group includes a plurality of vertical poles, the horizontal pole group includes a plurality of horizontal poles, the vertical poles and the horizontal poles intersect to form a fifth intersection, and the horizontal poles and the vertical poles at the fifth intersection are fixedly connected; the vertical pole group also includes a first vertical pole with one end fixedly connected to the third intersection, and the other end of the vertical pole is supported on the ground, and the horizontal pole group also includes a first horizontal pole with both ends fixedly connected to the fourth intersection; both ends of the gallery are provided with doors for entry of personnel or machinery, and / or the corridor between two adjacent greenhouses is provided with the door for entry of personnel or machinery.
5. The greenhouse structure according to claim 1, characterized in that: The greenhouse pull rod is provided with a slot for laying the thermal insulation film, the slot is opened along the extension direction of the greenhouse pull rod, and the slot is provided with a retaining spring for fixing the thermal insulation film in the slot; an antifreeze film is also provided between the thermal insulation film and the shed; the side of the shed is provided with a ventilation channel for ventilating the greenhouse, and the thermal insulation film and the antifreeze film laid in the ventilation channel can be lifted up; both sides of the shed are provided with a film rolling rod for facilitating the unfolding or retracting of the thermal insulation film, and a driving component for driving the two film rolling rods to move toward or away from each other.
6. The greenhouse structure according to claim 2, characterized in that: A groove is provided along the arch direction of the first arch rod, the thermal insulation film is provided in the groove, and a fixing strip for fixing the thermal insulation film in the groove is provided.
7. The greenhouse structure according to claim 2, characterized in that: The two ends of the first arch rod are respectively connected to support rods, and the two ends of the first arch rod are provided with reducing plugs, and the end of the support rod connected to the first arch rod is plugged into the reducing plug, or the end of the support rod connected to the first arch rod is provided with a reducing plug, and the reducing plug is plugged into the end connected to the first arch rod; the connection between the first arch rod and the support rod is provided with a fastening bolt for improving the connection strength.
8. The greenhouse structure according to claim 1, characterized in that: The bottoms of the greenhouse and the corridor are both provided with rollers, tracks matching the rollers, and driving devices for pushing the greenhouse and the corridor to move along the tracks.
9. The greenhouse structure according to claim 8, characterized in that: A base is provided between the roller and the bottom of the greenhouse and the bottom of the corridor, the top of the base is connected to the bottom of the greenhouse and the corridor, the bottom of the base is connected to the roller, and a lifting assembly is provided at the bottom of the greenhouse, the lifting assembly includes a lifting rod connected to the top of the base, a fastening rod connected to the bottom of the greenhouse and the corridor, the fastening rod is sleeved on the outside of the lifting rod, a plurality of through holes are opened in the vertical direction of the fastening rod, a plurality of sockets matching the through holes are provided in the vertical direction of the lifting rod, and the lifting assembly also includes a plug rod for inserting into the plug hole and the through hole to achieve height adjustment of the greenhouse and the corridor.
10. The greenhouse structure according to claim 5, characterized in that: An external circulation fan is arranged at the ventilation passage, and a plurality of internal circulation fans are arranged inside the greenhouse, and the external circulation fan and the internal circulation fan are arranged toward the ventilation passage on any one side of the two sides of the shelf.