Combined platform for positioning construction of underwater piles of temporary steel bridge
By designing the floating platform body, position adjustment components and underwater pile components of the combined platform, and using the transmission chain and self-locking manual winch to realize the free adjustment and righting of the underwater piles, the existing technology solves the problem of low efficiency and safety in the construction of underwater pile positioning for steel bridges. solve the problem of insufficient safety and improve construction efficiency and safety.
Patent Information
- Application Number
- CN202323556447.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-26
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2033-12-26
AI Technical Summary
The existing construction method of underwater pile positioning for steel bridges is inefficient, the pile positions are deviated, the verticality of the piles is difficult to control, and the safety of construction personnel is insufficient, making it impossible to efficiently arrange and install underwater piles.
A combined platform is designed, including a floating platform body, a positioning component and an underwater pile assembly. The underwater piles can be freely adjusted and straightened through a transmission chain and a self-locking manual winch to ensure installation verticality and position accuracy, and through the enclosure Improve operator safety.
It realizes the flexible installation position adjustment and righting of underwater piles, improves construction efficiency and safety, ensures the verticality and position accuracy of underwater piles, and simplifies the operation process.
Smart Images

Figure CN221918990U_ABST
Abstract
Description
Technical Field
[0001] The utility model specifically relates to a combined platform used for underwater pile positioning construction of a steel temporary bridge, and belongs to the technical field of underwater pile positioning platforms. Background Art
[0002] The conventional construction method of a steel temporary bridge is to construct the Bailey beam of the temporary bridge after the steel pipe piles are driven. The steel pipe piles in the water are positioned by surveyors on land using a prismless polar coordinate method through a guide frame. This construction method is inefficient, the pile positions are biased, the verticality of the piles is difficult to control, and the safety of the construction workers cannot be effectively guaranteed during the extension of the steel pipe piles. For this reason, Chinese Patent Publication No.: CN217026687U discloses a combined platform for underwater pile positioning construction of a steel temporary bridge, including a Bailey beam, and the front end of the Bailey beam is detachably connected to an underwater pile construction platform. The structure can realize the synchronous construction of underwater pile driving and Bailey beam laying, thereby ensuring the safety of construction workers, greatly improving the efficiency, and shortening the construction period of the steel temporary bridge. However, the installation positions of the Bailey beam and the underwater pile construction platform of the structure are limited, and there are different spans between the underwater piles. Therefore, it is impossible to efficiently arrange and install the underwater piles. Utility Model Content
[0003] In order to solve the above problems, the utility model proposes a combined platform for underwater pile positioning construction of steel temporary bridges, which can freely adjust the underwater pile installation position according to the positioning construction requirements and straighten the underwater pile during installation.
[0004] The utility model provides a combined platform for underwater pile positioning construction of a steel temporary bridge, comprising:
[0005] A floating platform body, wherein a through groove is provided in the middle of the floating platform body;
[0006] A positioning assembly, the positioning assembly includes a frame-type seat, the frame-type seat is fixed on the floating platform body and is arranged outside the through groove; a disc seat is fixed in the middle of the front end of the frame-type seat, a disc body is installed on the disc seat through a bearing, and a self-locking manual winch is fixed in the middle of the rear end of the frame-type seat directly opposite the disc seat; a groove seat is integrally formed on the top surface of the rear end of the frame-type seat; slide seats are slidably arranged on both sides of the frame-type seat; a frame plate is fixed on the top surface of the slide seat; a frame beam is integrally formed on the bottom of the inner side of the frame plate; ear seats are integrally formed in the middle of the front and rear ends of the frame plate respectively; the two ear seats, the disc body and the self-locking manual winch are connected by a transmission chain to form a closed loop;
[0007] Pedal; the pedal is provided with two pieces, and the self-locking manual winch is provided between the two pedals; the rear end of the pedal moves through the groove formed by the groove seat and the frame seat; the front end of the pedal is fixed to the rear end of the frame plate;
[0008] The underwater pile assembly comprises a seat plate movably arranged inside a frame plate and pressed with a frame beam, a plurality of straightening sleeves are fixed through the seat plate, and an adjusting bolt which is screwed to the end of the frame plate and pressed against the end of the seat plate is provided.
[0009] The stabilizing sleeve of the underwater pile assembly can guide the underwater pile when the underwater pile is installed to ensure the verticality of the underwater pile installation; the underwater pile assembly can be adjusted left and right. During adjustment, the position of the underwater pile assembly can be adjusted by screwing in and out the two adjusting bolts respectively; when it is necessary to adjust the front and rear position, the operator's feet are separated from the pedal. At this time, the crank handle of the self-locking manual winch is rotated forward or reversely, thereby driving the transmission chain to rotate clockwise or counterclockwise. When the transmission chain is in motion, the frame plate is driven forward or backward through the ear seat of the frame plate. When the frame plate is in motion, the sliding seat and the frame seat cooperate to achieve linear sliding guidance; after the position adjustment is completed, the position is self-locked by the self-locking manual winch; thereby the underwater pile assembly in the frame plate is positioned and limited; then step on the pedal, and operate the underwater pile to be sent into the stabilizing sleeve to install the underwater pile to the positioning position.
[0010] Furthermore, flanges are provided on both sides of the groove seat; the flanges are fastened to the front end of the Bailey beam through a transition beam by bolts and nuts; the floating platform body and the Bailey beam can be installed in one piece through the transition beam.
[0011] Furthermore, a notch is provided in the middle of the slot seat, and the self-locking manual winch is arranged at the notch, so that the crank handle of the self-locking manual winch can be operated conveniently through the notch.
[0012] Furthermore, the periphery of the floating platform body is provided with a fence, and the safety of operators on the floating platform body can be improved by enclosing the periphery of the floating platform body with the fence.
[0013] Furthermore, the transmission chain is a chain or a steel rope, and the chain or the steel rope can drive the positioning component to adjust the position.
[0014] Compared with the prior art, the combined platform for underwater pile positioning construction of steel temporary bridges of the utility model can freely adjust the underwater pile installation position according to the positioning construction requirements, facilitate the underwater pile positioning construction, and can straighten the underwater piles when they are installed, and the operation is simple and convenient. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of the overall structure of the floating platform body of the utility model.
[0016] Figure 2 It is a schematic diagram of the overall structure of the position adjustment component, pedal and underwater pile component of the utility model.
[0017] Figure 3It is a schematic diagram of the overall structure of the combined platform of the utility model.
[0018] Figure numerals: 1, floating platform, 2, through groove, 3, frame seat, 4, disc seat, 5, disc body, 6, self-locking manual winch, 7, groove seat, 8, sliding seat, 9, frame plate, 10, frame beam, 11, ear seat, 12, transmission chain, 13, pedal, 14, seat plate, 15, straightening sleeve, 16, adjusting bolt, 17, flange, 18, transition beam, 19, notch. DETAILED DESCRIPTION
[0019] Example:
[0020] like Figures 1 to 3 The combined platform shown for underwater pile positioning construction of a steel temporary bridge includes:
[0021] A floating platform body 1, wherein a through groove 2 is provided in the middle of the floating platform body 1;
[0022] A positioning assembly, the positioning assembly includes a frame seat 3, the frame seat 3 is fixed on the floating platform body 1, and is arranged outside the through groove 2; a disc seat 4 is fixed in the middle of the front end of the frame seat 3, a disc body 5 is installed on the disc seat 4 through a bearing, and a self-locking manual winch 6 is fixed in the middle of the rear end of the frame seat 3 facing the disc seat 4; a groove seat 7 is integrally formed on the top surface of the rear end of the frame seat 3; slide seats 8 are slidably arranged on both sides of the frame seat 3; a frame plate 9 is fixed on the top surface of the slide seat 8; a frame beam 10 is integrally formed on the inner bottom of the frame plate 9; ear seats 11 are respectively integrally formed in the middle of the front and rear ends of the frame plate 9; the two ear seats 11, the disc body 5 and the self-locking manual winch 6 are connected by a transmission chain 12 to form a closed loop;
[0023] Pedal 13; the pedal 13 is provided with two pieces, the self-locking manual winch 6 is provided between the two pedals 13; the rear end of the pedal 13 moves through the groove formed by the groove seat 7 and the frame seat 3; the front end of the pedal 13 is fixed to the rear end of the frame plate 9;
[0024] The underwater pile assembly includes a seat plate 14 movably arranged on the inner side of the frame plate 9 and pressed with the frame beam 10, and a plurality of straightening sleeves 15 are fixed through the seat plate 14; and an adjusting bolt 16 is screwed on the end of the frame plate 9 and pressed against the end of the seat plate 14.
[0025] The stabilizing sleeve 15 of the underwater pile assembly can guide the underwater pile when the underwater pile is installed to ensure the verticality of the underwater pile installation; the underwater pile assembly can be adjusted left and right. During adjustment, the position of the underwater pile assembly can be adjusted by screwing in and out the two adjusting bolts 16 respectively; when it is necessary to adjust the front and rear position, the operator's foot is separated from the pedal 13. At this time, the crank handle of the self-locking manual winch 6 is rotated forward or reversely, thereby driving the transmission chain 12 to rotate clockwise or counterclockwise. When the transmission chain 12 is activated, the frame plate 9 is driven forward or backward through the ear seat 11 of the frame plate 9. When the frame plate 9 is activated, the sliding seat 8 and the frame seat 3 cooperate to realize linear sliding guidance; after the position adjustment is completed, the position is self-locked by the self-locking manual winch 6; thereby the underwater pile assembly in the frame plate 9 is positioned and limited; then step on the pedal 13, and operate the underwater pile to be sent into the stabilizing sleeve 15, and the underwater pile is installed to the positioning position.
[0026] Flanges 17 are provided on both sides of the groove seat 7; the flanges 17 are fastened to the front end of the Bailey beam through a transition beam 18 by bolts and nuts; the floating platform body 1 and the Bailey beam can be installed as one through the transition beam 18.
[0027] A notch 19 is provided in the middle of the notch seat 7 , and the self-locking manual winch 6 is arranged at the notch 19 , so that the handle of the self-locking manual winch 6 can be easily operated through the notch 19 .
[0028] The periphery of the floating platform body 1 is provided with enclosures, and the safety of operators on the floating platform body 1 can be improved by enclosing the periphery of the floating platform body 1 with enclosures.
[0029] The transmission chain 12 is a chain or a steel rope, and the chain or the steel rope can drive the positioning component to adjust the position.
[0030] The above embodiments are only preferred implementations of the present invention, so any equivalent changes or modifications made according to the structures, features and principles described in the scope of application of the present invention are included in the scope of application of the present invention.
Claims
1. A combined platform for underwater pile positioning construction of steel temporary bridge, characterized by: include: A floating platform body, wherein a through groove is provided in the middle of the floating platform body; A positioning assembly, the positioning assembly includes a frame-type seat, the frame-type seat is fixed on the floating platform body and is arranged outside the through groove; a disc seat is fixed in the middle of the front end of the frame-type seat, a disc body is installed on the disc seat through a bearing, and a self-locking manual winch is fixed in the middle of the rear end of the frame-type seat directly opposite the disc seat; a groove seat is integrally formed on the top surface of the rear end of the frame-type seat; slide seats are slidably arranged on both sides of the frame-type seat; a frame plate is fixed on the top surface of the slide seat; a frame beam is integrally formed on the bottom of the inner side of the frame plate; ear seats are integrally formed in the middle of the front and rear ends of the frame plate respectively; the two ear seats, the disc body and the self-locking manual winch are connected by a transmission chain to form a closed loop; Pedal; the pedal is provided with two pieces, and the self-locking manual winch is provided between the two pedals; the rear end of the pedal moves through the groove formed by the groove seat and the frame seat; the front end of the pedal is fixed to the rear end of the frame plate; The underwater pile assembly comprises a seat plate movably arranged inside a frame plate and pressed with a frame beam, a plurality of straightening sleeves are fixed through the seat plate, and an adjusting bolt which is screwed to the end of the frame plate and pressed against the end of the seat plate is provided.
2. The combined platform for underwater pile positioning construction of steel temporary bridge according to claim 1 is characterized by: Flanges are arranged on both sides of the groove seat; the flanges are fastened to the front end of the Bailey beam through the transition beam and bolts and nuts.
3. The combined platform for underwater pile positioning construction of steel temporary bridge according to claim 1 is characterized by: A notch is provided in the middle of the slot seat, and the self-locking manual winch is arranged at the notch.
4. The combined platform for underwater pile positioning construction of steel temporary bridge according to claim 1 is characterized by: The periphery of the floating platform body is arranged in an enclosure.
5. The combined platform for underwater pile positioning construction of steel temporary bridge according to claim 1 is characterized by: The transmission chain is a chain or a steel rope.