Pier column and straining beam synchronous construction formwork

Through the design of synchronous construction formwork for pier columns and tie beams, and the use of formwork splicing and fasteners, the problem of poor fastening of pier columns and tie beams in the existing technology is solved, achieving a more stable connection and simplified construction operations.

CN221918993UActive Publication Date: 2024-10-29CCCC SHEC FIRST HIGHWAY ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420030282.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-05
Publication Date
2024-10-29
Estimated Expiration
2034-01-05

AI Technical Summary

Technical Problem

When the existing bridge piers and tie beams are fastened through tie rods, the fastening effect is not good, and the expansion of the cement mixture easily causes angle changes, resulting in loosening and instability.

Method used

Design a formwork for the simultaneous construction of piers and tie beams. Through the splicing of the formwork and the use of fasteners, the rotary valve and the regulating valve are used to drive the threaded rods for tightening to ensure the firm connection between the piers and the tie beams.

Benefits of technology

It achieves a more stable connection between pier columns and tie beams, prevents loosening, simplifies synchronous construction operations, and improves the stability and safety of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221918993U_ABST
    Figure CN221918993U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of bridge construction, in particular to a pier column and straining beam synchronous construction formwork which comprises a formwork body, a pier column is arranged on the inner wall of the formwork body, a straining beam is arranged on the outer wall of one side of the pier column, and a synchronous construction assembly is arranged on the outer wall of the formwork body. According to the pier stud and tie beam synchronous construction formwork, the pier stud and tie beam synchronous construction formwork is designed, a plurality of sets of formworks surround the outer walls of a pier stud and a tie beam needing injection molding in a splicing mode and are fastened through fasteners, and therefore the pier stud and tie beam synchronous construction formwork is formed. The two ends of the straight rod are arranged between the second vertical plate and the first vertical plate correspondingly, fastening is conducted through the rotary adjusting valve and the rotary valve, the upper end and the lower end of the formwork are operated synchronously, fastening of the formwork is facilitated, and therefore the pier column and the straining beam are firmer and prevented from loosening during injection molding, and synchronous construction operation of the pier column and the straining beam is facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of bridge construction, in particular to a synchronous construction template for pier columns and tie beams. Background Art

[0002] At present, it is difficult to build highway deep gully bridges in mountainous areas. Bridges generally refer to structures built on rivers, lakes and seas to enable vehicles and pedestrians to pass smoothly. Bridges are generally composed of superstructure, substructure, supports and auxiliary structures. The superstructure is also called the span structure, which is the main structure for crossing obstacles; the substructure includes abutments, piers and foundations; the supports are force transmission devices set at the supporting places between the span structure and the piers or abutments.

[0003] In the patent with the publication number CN216074778U, a square pier column and tie beam integral construction template is proposed. In the patent, the pier column and tie beam connection template, the tie beam bottom template is connected to the top of the pier column template, the tie beam side template is connected to the tie beam bottom template, and the side is connected to the pier column and tie beam connection template. The tie beam bottom template is provided with multiple supporting rods at the bottom, and the two sides are connected to the pier column template. The tie rod is provided between the pier column templates. The two pier column templates can be pulled together to prevent loosening. However, the following problems still exist in the patent:

[0004] The piers and tie beams of the above-mentioned bridge are fastened by tie rods, but the fastening effect is not good. Since the piers and tie beams are both formed by cement mixtures and are heavy, it is easy to cause the angle of the tie rods to change, resulting in insufficient and unstable fastening.

[0005] In view of the above problems, it is necessary to design a synchronous construction template for piers and tie beams to overcome the above problems. Utility Model Content

[0006] The main purpose of the utility model is to provide a synchronous construction template for pier columns and tie beams, which can effectively solve the problems in the background technology.

[0007] In order to achieve the above purpose, the technical solution adopted by the utility model is:

[0008] A synchronous construction template for pier columns and tie beams, comprising a template, wherein the inner wall of the template is provided with pier columns, the outer wall of one side of the pier columns is provided with tie beams, and the outer wall of the template is provided with synchronous construction components;

[0009] The synchronous construction component includes a second steel column arranged on the left outer wall of the template, second vertical plates are arranged at both upper and lower ends of the second steel column, a regulating valve is arranged in the middle of the second vertical plate, and a second threaded rod is arranged at one end of the regulating valve, a first steel column is arranged on the right outer wall of the template, first vertical plates are arranged at both upper and lower ends of the first steel column, a rotary valve is arranged on one side of the first vertical plate, a first threaded rod is arranged at one end of the rotary valve, a threaded sleeve is arranged on the other side of the first vertical plate, one end of the first threaded rod is connected to a toothed block, and the template is spliced ​​by several sections of templates, and an extension plate is connected at the splicing point, and a fastener is arranged in the middle of the extension plate.

[0010] As a preferred solution of the utility model, a group of the first steel columns are provided with two groups of first vertical plates on the top, a group of the second steel columns are provided with two groups of second vertical plates on the top, a group of the second vertical plates are provided with two groups of regulating valves and two groups of second threaded rods, the two groups of first vertical plates are provided with two groups of rotary valves, a straight rod is connected between the two groups of the toothed blocks, and a limiting block is provided at one end of the straight rod.

[0011] As a preferred solution of the utility model, the pier is fixedly connected to the tie beam, the template is detachably connected to the pier, the template is detachably connected to the tie beam, and the first steel column is non-detachably connected to the template.

[0012] As a preferred solution of the utility model, the second steel column and the template are non-detachably connected, the first vertical plate and the first steel column are fixedly connected, the rotary valve and the first threaded rod are fixedly connected, the threaded sleeve and the first vertical plate are fixedly connected, and the first threaded rod and the threaded sleeve are threadedly connected.

[0013] As a preferred solution of the utility model, the toothed block is non-detachably connected to the first threaded rod, the toothed block is threadedly connected to one end of the straight rod, the straight rod is fixedly connected to the limit block, and the second vertical plate is fixedly connected to the second steel column.

[0014] As a preferred solution of the utility model, the regulating valve is fixedly connected to the second threaded rod, the second threaded rod is rotationally connected to the second vertical plate via a roller, the two groups of the second threaded rods are threadedly connected to the other end of the straight rod, the template is fixedly connected to the extension plate, and the fastener is detachably connected to the extension plate.

[0015] Beneficial Effects

[0016] Compared with the prior art, the utility model has the following beneficial effects:

[0017] In the utility model, a synchronous construction template for piers and tie beams is designed, a plurality of groups of templates are spliced ​​to surround the outer walls of the piers and tie beams of the injection molding, and are fastened by fasteners, and the two ends of the straight rod are respectively placed between the second vertical plate and the first vertical plate, and are fastened by a rotary regulating valve and a rotary valve, and the upper and lower ends of the template are synchronously operated, which is convenient for fastening the template, thereby facilitating the injection molding of the piers and tie beams to be more firm and prevent loosening, and facilitating the synchronous construction operation of the piers and tie beams. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a structural schematic diagram of the utility model;

[0019] Figure 2 It is a schematic diagram of the structure of the first steel column and the second steel column of the utility model;

[0020] Figure 3 This is a schematic diagram of the structure of the rotary valve and the tooth pattern block of the utility model;

[0021] Figure 4 It is a schematic diagram of the structure of point A of the utility model.

[0022] In the figure: 1. formwork; 2. pier; 3. tie beam; 4. synchronous construction components; 401. first steel column; 402. first vertical plate; 403. rotary valve; 404. first threaded rod; 405. threaded sleeve; 406. toothed block; 407. second steel column; 408. second vertical plate; 409. regulating valve; 410. second threaded rod; 411. straight rod; 412. limit block; 413. extension plate; 414. fasteners. DETAILED DESCRIPTION

[0023] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.

[0024] like Figure 1-4 As shown, a synchronous construction template of a pier column and a tie beam comprises a template 1, a pier column 2 is arranged on the inner wall of the template 1, a tie beam 3 is arranged on the outer wall of one side of the pier column 2, and a synchronous construction component 4 is arranged on the outer wall of the template 1;

[0025] The synchronous construction component 4 includes a second steel column 407 arranged on the left outer wall of the template 1, and second vertical plates 408 are arranged at both upper and lower ends of the second steel column 407, a regulating valve 409 is arranged in the middle of the second vertical plate 408, and a second threaded rod 410 is arranged at one end of the regulating valve 409, and a first steel column 401 is arranged on the right outer wall of the template 1, and first vertical plates 402 are arranged at both upper and lower ends of the first steel column 401, a rotary valve 403 is arranged on one side of the first vertical plate 402, a first threaded rod 404 is arranged at one end of the rotary valve 403, a threaded sleeve 405 is arranged on the other side of the first vertical plate 402, and a toothed block 406 is connected to one end of the first threaded rod 404. The template 1 is spliced ​​by several sections of templates, and an extension plate 413 is connected at the splicing point, and a fastener 414 is arranged in the middle of the extension plate 413.

[0026] Please see attached Figure 1 , Attachment Figure 2 and attached Figure 3 As shown, two groups of first vertical plates 402 are arranged on the top of a group of first steel columns 401, two groups of second vertical plates 408 are arranged on the top of a group of second steel columns 407, two groups of regulating valves 409 and two groups of second threaded rods 410 are arranged on a group of second vertical plates 408, two groups of rotary valves 403 are arranged on the two groups of first vertical plates 402, a straight rod 411 is connected between the two groups of toothed blocks 406, a limiting block 412 is arranged at one end of the straight rod 411, the pier 2 is fixedly connected to the tie beam 3, the template 1 is detachably connected to the pier 2, the template 1 is detachably connected to the tie beam 3, the first steel column 401 is non-detachably connected to the template 1, the second steel column 407 is non-detachably connected to the template 1, the first vertical plate 402 is fixedly connected to the first steel column 401, the rotary valve 403 is connected to the first A threaded rod 404 is fixedly connected, a threaded sleeve 405 is fixedly connected to the first vertical plate 402, the first threaded rod 404 is threadedly connected to the threaded sleeve 405, a toothed block 406 is non-detachably connected to the first threaded rod 404, a toothed block 406 is threadedly connected to one end of a straight rod 411, the straight rod 411 is fixedly connected to a limit block 412, the second vertical plate 408 is fixedly connected to the second steel column 407, the regulating valve 409 is fixedly connected to the second threaded rod 410, the second threaded rod 410 is rotationally connected to the second vertical plate 408 via a roller, two groups of second threaded rods 410 are threadedly connected to the other end of the straight rod 411, the template 1 is fixedly connected to the extension plate 413, and the fastener 414 is detachably connected to the extension plate 413;

[0027] Among them, the two groups of tooth blocks 406 corresponding to the first vertical plate 402 are engaged with the threads at one end of the straight rod 411 in both directions, and the two groups of second threaded rods 410 are engaged with the threads at the other end of the straight rod 411 in both directions, so as to facilitate tightening the straight rod 411 through adjusting the regulating valve 409 and the rotary valve 403 to prevent the straight rod 411 from sliding.

[0028] The working process of the utility model is as follows: the synchronous construction template of the pier column and the tie beam designed by the scheme is used. When working, several groups of templates 1 are spliced ​​and fastened through the extension plate 413 and the fastener 414, and around the outer wall of the pier column 2 and the tie beam 3 of the injection mold, two groups of regulating valves 409 on one side of the second vertical plate 408 are manually adjusted to drive the two groups of second threaded rods 410 to rotate, thereby fastening one end of the straight rod 411, and adjusting the outer wall of the first vertical plate 402 at the upper and lower ends of the first steel column 401. The rotary valve 403, and the two sets of rotary valves 403 are screwed at the same time, which can drive the first threaded rod 404 and the inner wall of the threaded sleeve 405 to move through the thread, so that the toothed block 406 at one end of the first threaded rod 404 is fastened to one end of the straight rod 411, and then the upper and lower sides of the template 1 are fastened to make it more firmly fastened to prevent the template 1 from being damaged by expansion during the injection molding process. The pier 2 and the tie beam 3 are simultaneously injected, which is convenient for the synchronous construction of the pier 2 and the tie beam 3, and the operation is simpler.

[0029] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A synchronous construction template for pier columns and tie beams, comprising a template (1), characterized in that: The inner wall of the template (1) is provided with a pier column (2), the outer wall of one side of the pier column (2) is provided with a tie beam (3), and the outer wall of the template (1) is provided with a synchronous construction component (4); The synchronous construction assembly (4) comprises a second steel column (407) arranged on the left outer wall of the template (1), the second steel column (407) is provided with a second vertical plate (408) at both upper and lower ends, a regulating valve (409) is provided in the middle of the second vertical plate (408), and a second threaded rod (410) is provided at one end of the regulating valve (409), and a first steel column (401) is provided on the right outer wall of the template (1), and the first steel column (401) is provided with a first vertical plate (410) at both upper and lower ends. The first vertical plate (402) is provided with a rotary valve (403) on one side, a first threaded rod (404) is provided at one end of the rotary valve (403), a threaded sleeve (405) is provided on the other side of the first vertical plate (402), a toothed block (406) is connected to one end of the first threaded rod (404), the template (1) is formed by splicing several sections of templates, and an extension plate (413) is connected at the splicing point, and a fastener (414) is provided in the middle of the extension plate (413).

2. A synchronous construction formwork for pier columns and tie beams according to claim 1, characterized in that: Two groups of first vertical plates (402) are arranged on the top of a group of the first steel columns (401), two groups of second vertical plates (408) are arranged on the top of a group of the second steel columns (407), two groups of regulating valves (409) and two groups of second threaded rods (410) are arranged on one group of the second vertical plates (408), two groups of rotary valves (403) are arranged on the two groups of the first vertical plates (402), a straight rod (411) is connected between the two groups of the toothed blocks (406), and a limiting block (412) is arranged at one end of the straight rod (411).

3. A synchronous construction formwork for pier columns and tie beams according to claim 2, characterized in that: The pier column (2) and the tie beam (3) are fixedly connected, the template (1) and the pier column (2) are detachably connected, the template (1) and the tie beam (3) are detachably connected, and the first steel column (401) and the template (1) are non-detachably connected.

4. A synchronous construction formwork for pier columns and tie beams according to claim 3, characterized in that: The second steel column (407) is non-detachably connected to the template (1), the first vertical plate (402) is fixedly connected to the first steel column (401), the rotary valve (403) is fixedly connected to the first threaded rod (404), the threaded sleeve (405) is fixedly connected to the first vertical plate (402), and the first threaded rod (404) is threadedly connected to the threaded sleeve (405).

5. A synchronous construction formwork for pier columns and tie beams according to claim 4, characterized in that: The toothed block (406) is non-detachably connected to the first threaded rod (404), the toothed block (406) is threadedly connected to one end of the straight rod (411), the straight rod (411) is fixedly connected to the limit block (412), and the second vertical plate (408) is fixedly connected to the second steel column (407).

6. A synchronous construction formwork for pier columns and tie beams according to claim 5, characterized in that: The regulating valve (409) is fixedly connected to the second threaded rod (410), the second threaded rod (410) is rotationally connected to the second vertical plate (408) via a roller, two groups of the second threaded rods (410) are threadedly connected to the other ends of the straight rods (411), the template (1) is fixedly connected to the extension plate (413), and the fastener (414) is detachably connected to the extension plate (413).