Adjusting device for fixing photovoltaic pile foundation pouring mold

By designing an adjustment device that includes pile foundation molds, collars, poles, sleeves, connecting rods and levels, the problem of position adjustment errors of embedded parts in photovoltaic pile foundation pouring is solved, and a high-precision same straight line is achieved Positioning and high degree of uniformity reduce construction costs.

CN221919384UActive Publication Date: 2024-10-29HUIZE HUADIAN DAOCHENG CLEAN ENERGY DEV CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420521897.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-18
Publication Date
2024-10-29
Estimated Expiration
2034-03-18

AI Technical Summary

Technical Problem

During the current pouring process of photovoltaic pile foundations, there are errors in the position adjustment of embedded parts, resulting in uneven installation of columns and increased construction costs. Moreover, existing positioning tools and precision instruments are expensive and difficult to ensure a high degree of uniformity.

Method used

An adjustment device including pile foundation mold, collar, vertical rod, sleeve, connecting rod, positioning cylinder and level is designed. The height and horizontal positioning of embedded parts are realized through claw bolts and hinge seats, simplifying the positioning process. , reducing costs.

Benefits of technology

It achieves high-precision positioning of embedded parts in the same straight line, reduces construction costs, avoids height staggering of embedded parts, simplifies the adjustment process, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221919384U_ABST
    Figure CN221919384U_ABST
Patent Text Reader

Abstract

The adjusting device for fixing the photovoltaic pile foundation pouring mold comprises a pile foundation mold and an embedded part, the top face of the pile foundation mold is connected with a lantern ring in a sleeved mode, a vertical rod is vertically and fixedly installed on the surface of one side of the lantern ring, and the outer surface of the vertical rod is connected with a sleeve in a sliding and sleeved mode. The positioning device has the advantages that the connecting rod, the vertical rod and the positioning cylinder are adopted, when the embedded part is positioned and fixed, the lantern ring can be connected to the top faces of two pile foundation molds in a sleeved mode, the height of the connecting rod is adjusted up and down to the set elevation, and then the positioning cylinder is moved to be inserted into a gap between foundation bolts and abuts against the foundation bolts; the foundation bolts are positioned by abutting against the positioning cylinders, the foundation bolts are located on the same straight line, it can be guaranteed that the photovoltaic panel stand columns are located on the same straight line in the later period, later installation is facilitated, the device is simple in structure, complex instruments are omitted, and cost is lower.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of photovoltaic engineering construction equipment, and in particular to an adjusting device for fixing a photovoltaic pile foundation casting mold. Background Art

[0002] A photovoltaic power station is a system that utilizes solar energy and uses special materials such as crystalline silicon panels and other electronic components to connect to and transmit electricity to the power grid. During the construction of a photovoltaic power station, it is necessary to cast multiple groups of coaxial concrete pile foundations on the ground and set embedded parts on the pile foundations. If several concrete pile foundation embedded parts are not in the same position during the embedding process, the central plane projections of a group of concrete pile foundation embedded parts will not be on a straight line, resulting in the subsequent bulging of the columns before and after installation, making it impossible to install the purlins on the columns, increasing construction costs.

[0003] After searching, it was found that the publication number is CN217027187U, and the name is a photovoltaic installation foundation embedded parts positioning tool. The application proposes that when pouring concrete pile foundations, the embedded parts are buried in the concrete. The staff uses a ruler to measure and adjust the embedded parts of the pile foundations located in the same direction to keep them in the same straight line. In this way, during the pouring of the pile foundation, after the embedded parts are set in the pile foundation, in the process of adjusting the position of the embedded parts, there will be certain errors in manual measurement, which will affect the subsequent construction. By setting support components, fixing rods, positioning components and azimuth indicators The orientation is indicated by the orientation indicator, so that after the fixing rod is adjusted to the predetermined orientation, the positioning component fixes the embedded parts so that the embedded parts on adjacent pile foundations are located on the same straight line, thereby improving the adjustment accuracy of the embedded parts. However, the orientation indicator is a precision instrument, which is expensive to purchase and maintain, increasing the production and use costs, and is not conducive to large-scale promotion and use. Moreover, the orientation indicator mostly indicates the horizontal orientation, and the height positioning effect is not good. It is difficult to ensure the height uniformity of the embedded parts, which can easily lead to the height of the embedded parts being staggered, affecting the later installation. There are certain limitations and inconveniences in the adjustment and use, and further improvements can be made.

[0004] Currently, no effective solution has been proposed for the problems in the related technologies. Utility Model Content

[0005] 1. Technical issues to be resolved

[0006] In view of the deficiencies in the prior art, the utility model provides an adjustment device for fixing a photovoltaic pile foundation casting mold, which has the advantages of simple structure, low cost, and convenient linear and height positioning, thereby solving the problems in the above-mentioned background technology.

[0007] (II) Technical solution

[0008] In order to achieve the above advantages of simple structure, low cost, and convenience for straight line and height positioning, the specific technical solutions adopted by the utility model are as follows:

[0009] A kind of adjustment device for fixing the photovoltaic pile foundation casting mold comprises a pile foundation mold and an embedded part, the top surface of the pile foundation mold is sleeved with a collar, and a vertical pole is fixedly installed on one side surface of the collar, and a sleeve is slidably sleeved on the outer surface of the vertical pole, the collar is fixedly connected to the outer wall of the pile foundation mold by a second clevis bolt, the sleeve is fixedly connected to the vertical pole by a first clevis bolt, and a connecting rod is arranged between the vertical poles, and the two ends of the connecting rod are hinged to the outer wall of the sleeve by a hinge seat, the outer wall of the connecting rod is slidably sleeved with a positioning cylinder, and the top surface of the positioning cylinder is threadedly connected with a third clevis bolt, the top surface of the embedded part is welded with an anchor bolt, and a nut is sleeved on the top of the anchor bolt, and the bottom surface of the nut abuts against the top surface of the positioning cylinder, and a level ruler is fixedly installed on the outer surface of the connecting rod.

[0010] Furthermore, the width of the positioning tube is equal to the distance between the anchor bolts, and the positioning tube is a rectangular tube.

[0011] Furthermore, the first clevis bolt passes through the sleeve and is threadedly connected to the sleeve.

[0012] Furthermore, the second clevis bolt passes through the collar and is threadedly connected to the collar, and a plurality of second clevis bolts are provided.

[0013] Furthermore, the bottom anchor of the embedded part is inserted into the pile foundation form, and the anchor bolt is located above the pile foundation form.

[0014] Furthermore, the connecting rod is a square rod that is not easily deformed.

[0015] Furthermore, the level ruler is arranged parallel to the connecting rod.

[0016] Furthermore, the vertical rods and connecting rods are roughened.

[0017] (III) Beneficial effects

[0018] Compared with the prior art, the utility model provides an adjustment device for fixing a photovoltaic pile foundation casting mold, which has the following beneficial effects:

[0019] (1) The utility model adopts connecting rods, vertical rods and positioning cylinders. When positioning and fixing the embedded parts, the sleeves can be sleeved on the top surfaces of the two pile foundation molds, and the height of the connecting rods can be adjusted up and down to the set elevation. The position of the connecting rods is calibrated, and then the positioning cylinder is moved and inserted into the gaps between the anchor bolts and abutted against the anchor bolts. Since the positioning cylinders are arranged in a straight line along the connecting rods, the anchor bolts are positioned by abutting against the positioning cylinders, so that the anchor bolts are located in the same straight line, which can ensure that the photovoltaic panel columns are located in the same straight line in the later stage, which is convenient for the later installation. The device has a simple structure, eliminates the use of complex instruments, and is more cost-effective.

[0020] (2) The utility model adopts a nut and a level ruler. The staff can loosen the first handle bolt to slightly adjust the height of one end of the connecting rod, and then adjust the horizontality of the connecting rod. The level of the connecting rod can be calibrated by the level ruler. The staff can fix the height of the embedded parts by putting the nut on the top surface of the anchor bolt so that the bottom surface of the nut is tightly against the top surface of the positioning tube, thereby keeping the embedded parts at the same horizontal height, further improving the accuracy of positioning, and also avoiding the problem of displacement of the embedded parts during the casting process. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0022] Figure 1 This is a structural schematic diagram of an adjustment device for fixing a photovoltaic pile foundation casting mold proposed by the utility model;

[0023] Figure 2 This is a front view of an adjustment device for fixing a photovoltaic pile foundation casting mold proposed by the utility model;

[0024] Figure 3 This is an enlarged view of the A node of an adjustment device for fixing a photovoltaic pile foundation casting mold proposed by the utility model;

[0025] Figure 4 It is a structural schematic diagram of the connecting rod proposed by the utility model.

[0026] In the figure:

[0027] 1. Pile foundation formwork; 2. Ring; 3. Vertical pole; 4. Sleeve; 5. First clevis bolt; 6. Second clevis bolt; 7. Articulated seat; 8. Connecting rod; 9. Level ruler; 10. Embedded parts; 11. Positioning tube; 12. Anchor bolt; 13. Third clevis bolt; 14. Nut. DETAILED DESCRIPTION

[0028] To further illustrate each embodiment, the present invention provides drawings, which are part of the disclosure of the present invention and are mainly used to illustrate the embodiments. They can be used in conjunction with the relevant descriptions in the specification to explain the operating principles of the embodiments. With reference to these contents, ordinary technicians in the field should be able to understand other possible implementation methods and advantages of the present invention. The components in the figures are not drawn to scale, and similar component symbols are generally used to represent similar components.

[0029] According to an embodiment of the utility model, an adjustment device for fixing a photovoltaic pile foundation casting mold is provided.

[0030] The present invention is now further described in conjunction with the accompanying drawings and specific implementation methods. Figure 1-4As shown, according to an embodiment of the utility model, an adjusting device for fixing a photovoltaic pile foundation casting mold comprises a pile foundation mold 1 and an embedded part 10, a collar 2 is sleeved on the top surface of the pile foundation mold 1, the collar 2 is located outside the top opening of the pile foundation mold 1, and a vertical pole 3 is fixedly installed on one side surface of the collar 2, and a sleeve 4 is slidably sleeved on the outer surface of the vertical pole 3, the inner diameter of the sleeve 4 is larger than the outer diameter of the vertical pole 3, and there is a gap between the inner wall of the sleeve 4 and the outer wall of the vertical pole 3, so that when the first clevis bolt 5 is loosened, the sleeve 4 can be slightly displaced in the horizontal direction, so that the connecting rod 8 can be slightly adjusted in angle, and the collar 2 is connected to the second clevis bolt 6 through the collar 2. The outer wall of the pile foundation mold 1 is fixedly connected, and the sleeve 4 is fixedly connected to the vertical pole 3 through the first clevis bolt 5, wherein the first clevis bolt 5 passes through the sleeve 4 and is threadedly connected to the sleeve 4, wherein the second clevis bolt 6 passes through the collar 2 and is threadedly connected to the collar 2, and a plurality of second clevis bolts 6 are provided, which is a common locking structure, and a connecting rod 8 is provided between the vertical poles 3, and the two ends of the connecting rod 8 are hinged to the outer wall of the sleeve 4 through a hinge seat 7, which is convenient for lifting and lowering adjustment, the outer wall of the connecting rod 8 is slidably sleeved with a positioning tube 11, and the top surface of the positioning tube 11 passes through a third clevis bolt 13 threadedly connected, and the top surface of the embedded part 10 is welded with an anchor bolt 12, and the ground A nut 14 is sleeved on the top of the anchor bolt 12, and the bottom surface of the nut 14 abuts against the top surface of the positioning tube 11. A level ruler 9 is fixedly installed on the outer surface of the connecting rod 8. When positioning and fixing the embedded part 10, the collar 2 can be sleeved on the top surfaces of the two pile foundation molds 1, and the height of the connecting rod 8 can be adjusted up and down to the set elevation. Then, the positioning tube 11 is moved and inserted into the gap between the anchor bolts 12 and abuts against the anchor bolts 12. Since the positioning tube 11 is arranged in a straight line along the connecting rod 8, the anchor bolts 12 are positioned by abutting against the positioning tube 11, so that the anchor bolts 12 are located in the same straight line, which can ensure that the photovoltaic panel columns are located in the same straight line in the later stage. , which is convenient for later installation. The device has a simple structure, eliminates the need for complex instruments, and has a lower cost. At the same time, the staff can loosen the first handle bolt to slightly adjust the height of one end of the connecting rod 8, and then adjust the horizontality of the connecting rod 8. The connecting rod 8 can be calibrated horizontally through the level ruler 9. The staff can fix the height of the embedded part 10 by sleeve-fitting the nut 14 on the top surface of the anchor bolt 12 so that the bottom surface of the nut 14 is tightly against the top surface of the positioning tube 11, thereby keeping the embedded part 10 at the same horizontal height, further improving the accuracy of positioning, and also avoiding the problem of displacement of the embedded part 10 during the pouring process.

[0031] In one embodiment, the width of the positioning tube 11 is equal to the distance between the anchor bolts 12 , and the positioning tube 11 is a rectangular tube, which is convenient for the nut 14 to be tightly fixed and the anchor bolt 12 to be positioned.

[0032] In one embodiment, the bottom anchor of the embedded part 10 is inserted into the pile foundation mold 1, and the anchor bolts 12 are located above the pile foundation mold 1, which is a common structure. The anchor bolts 12 on the top surface of the embedded part 10 are convenient for connecting the photovoltaic panel columns.

[0033] In one embodiment, the connecting rod 8 is a square rod that is not easily deformed to avoid positioning problems caused by deformation.

[0034] In one embodiment, the level rod 9 is arranged parallel to the connecting rod 8. The level rod 9 is an existing device and will not be described in detail here.

[0035] In one embodiment, both the vertical rod 3 and the connecting rod 8 are roughened to increase friction and improve the stability of fixation.

[0036] Working principle:

[0037] When positioning and fixing the embedded part 10, the collar 2 can be sleeved on the top surfaces of the two pile foundation molds 1, and the height of the connecting rod 8 can be adjusted up and down to the set elevation. Then, the positioning cylinder 11 is moved and inserted into the gap between the anchor bolts 12 and abuts against the anchor bolts 12. Since the positioning cylinder 11 is arranged in a straight line along the connecting rod 8, the anchor bolts 12 are positioned by abutting against the positioning cylinder 11, so that the anchor bolts 12 are located on the same straight line, which can ensure that the photovoltaic panel columns are located on the same straight line in the later stage, which is convenient for later installation. The device has a simple structure and eliminates the need for complex instruments. The cost of putting it into use is even lower. At the same time, the staff can loosen the first handle bolt to slightly adjust the height of one end of the connecting rod 8, and then adjust the horizontality of the connecting rod 8. The level of the connecting rod 8 can be calibrated by the level ruler 9. The staff can fix the height of the embedded part 10 by sleeve-fitting the nut 14 on the top surface of the anchor bolt 12 so that the bottom surface of the nut 14 is tightly against the top surface of the positioning tube 11, thereby keeping the embedded part 10 at the same horizontal height, further improving the accuracy of positioning, and also avoiding the problem of displacement of the embedded part 10 during the pouring process.

[0038] In the present utility model, unless otherwise clearly stipulated and limited, the terms such as "installation", "setting", "connection", "fixation" and "screw-on" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integrated connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. Unless otherwise clearly defined, ordinary technicians in this field can understand the specific meanings of the above terms in the utility model according to the specific circumstances.

[0039] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. An adjustment device for fixing a photovoltaic pile foundation casting mold, It is characterized in that The invention comprises a pile foundation mold (1) and an embedded part (10), wherein a collar (2) is sleeved on the top surface of the pile foundation mold (1), and a vertical pole (3) is vertically fixedly installed on one side surface of the collar (2), and a sleeve (4) is slidably sleeved on the outer surface of the vertical pole (3), the collar (2) is fixedly connected to the outer wall of the pile foundation mold (1) by a second clevis bolt (6), the sleeve (4) is fixedly connected to the vertical pole (3) by a first clevis bolt (5), and a connecting rod (8) is arranged between the vertical poles (3), and the connecting rod The two ends of the connecting rod (8) are hinged to the outer wall of the sleeve (4) through a hinge seat (7); the outer wall of the connecting rod (8) is slidably sleeved with a positioning tube (11), and the top surface of the positioning tube (11) is threadedly connected with a third horn bolt (13); the top surface of the embedded part (10) is welded with an anchor bolt (12), and the top of the anchor bolt (12) is sleeved with a nut (14), and the bottom surface of the nut (14) is in contact with the top surface of the positioning tube (11); the outer surface of the connecting rod (8) is fixedly mounted with a level ruler (9).

2. An adjusting device for fixing a photovoltaic pile foundation casting mold according to claim 1, It is characterized in that The width of the positioning tube (11) is equal to the distance between the anchor bolts (12), and the positioning tube (11) is a rectangular tube.

3. The adjusting device for fixing a photovoltaic pile foundation casting mold according to claim 1, It is characterized in that The first clevis bolt (5) passes through the sleeve (4) and is threadedly connected to the sleeve (4).

4. The adjusting device for fixing a photovoltaic pile foundation casting mold according to claim 1, It is characterized in that The second clevis bolt (6) passes through the collar (2) and is threadedly connected to the collar (2), and a plurality of second clevis bolts (6) are provided.

5. The adjusting device for fixing a photovoltaic pile foundation casting mold according to claim 1, It is characterized in that The bottom anchor of the embedded part (10) is inserted into the pile foundation form (1), and the anchor bolt (12) is located above the pile foundation form (1).

6. The adjusting device for fixing a photovoltaic pile foundation casting mold according to claim 1, It is characterized in that The connecting rod (8) is a square rod that is not easily deformed.

7. The adjusting device for fixing a photovoltaic pile foundation casting mold according to claim 1, It is characterized in that The level ruler (9) is arranged parallel to the connecting rod (8).

8. The adjusting device for fixing a photovoltaic pile foundation casting mold according to claim 1, It is characterized in that The vertical rod (3) and the connecting rod (8) are both roughened.