Water stop structure for top pipe access hole portal
By reserving grouting holes in the well wall and injecting polyurethane foam, the problem of water and sand intrusion during the pipe jacking process is solved, emergency water stop when the water stop device fails, and construction risks and costs are reduced.
Patent Information
- Application Number
- CN202420768914.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-15
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-04-15
AI Technical Summary
During pipe jacking construction, especially during the process of exiting large-diameter pipe jacking holes, existing technology cannot effectively prevent water and sand intrusion, resulting in high construction difficulty and cost, as well as a high risk of exiting the hole.
Reserve grouting holes on the well wall, and inject polyurethane foam when the water stop device fails. Use the combined structure of the first and second grouting holes, hinged hinged steel pressure plates and rubber water stop plates to ensure that the well wall and Effective water stop between concrete pipe walls.
Under complex construction conditions, it ensures that the jacking pipe can exit the hole smoothly, reduces the risk of water and sand intrusion, simplifies operations, significantly saves construction costs, and reduces the risk of exiting the hole.
Smart Images

Figure CN221920978U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction, in particular to a water-stop structure for a top pipe inlet and outlet tunnel door. Background Art
[0002] With the continuous expansion of urban construction and the development of water intake projects, sewage projects, ultra-deep shaft parking lots and other projects, there are more and more pipe jacking constructions, especially large-diameter pipe jacking operations, which are very difficult to construct. Pipe jacking exit technology is one of the key processes in pipe jacking construction, and whether the water stop at the hole is effective is the top priority in determining whether the pipe jacking can exit the hole smoothly. Therefore, inventing a water stop structure for the entrance and exit of the pipe jacking hole is the key to solving the above technical problems. Summary of the invention
[0003] The purpose of the utility model is to provide a water-stopping structure for a tunnel entrance and exit of a jacking pipe in response to the deficiencies of the above-mentioned prior art. The structure reserves grouting holes on the well wall on the basis of installing a water-stopping device. If the water-stopping device has limited effect during the exit process, polyurethane foam is immediately injected through the grouting holes to achieve the purpose of water-stopping the tunnel entrance and prevent water and sand gushing.
[0004] The purpose of this utility model is achieved by the following technical solutions:
[0005] A water-stopping structure for a tunnel entrance and exit of a jacking pipe, used for water-stopping between a well wall and a concrete pipe wall, characterized in that the water-stopping structure comprises a first grouting hole, a hinged articulated steel pressure plate, and a rubber water-stopping plate, wherein the first grouting hole passes through the well wall and its outlet is located between the well wall and the concrete pipe wall, the hinged articulated steel pressure plate is arranged on the outside of the well wall and contacts the concrete pipe wall, two rubber water-stopping plates are arranged on the hinged articulated steel pressure plate at intervals, and a second grouting hole is arranged between the two rubber water-stopping plates.
[0006] Along the circumferential direction of the concrete pipe wall, a plurality of the second grouting holes are evenly spaced and arranged in an array between the two rubber water stop plates.
[0007] The second grouting hole is connected with a ball valve.
[0008] There is polyurethane foam injected through the second grouting hole between the two rubber water stop plates.
[0009] The advantages of the utility model are: on the basis of the traditional tunnel entrance water-stopping device, it simply increases the guarantee for the smooth exit of the jacking pipe from the tunnel by adding grouting holes, ensuring that under complex construction conditions, when the water-stopping device fails, it can still prevent water and sand gushing and successfully complete the exit of the jacking pipe from the tunnel, and the construction is easy to operate, which greatly saves construction costs and reduces the construction risks of the jacking pipe exiting the tunnel. BRIEF DESCRIPTION OF THE DRAWINGS
[0010] Figure 1 It is a schematic diagram of the structure of the utility model;
[0011] Figure 2 It is a plan view of the utility model. DETAILED DESCRIPTION
[0012] The following is a further detailed description of the features of the present invention and other related features through embodiments in conjunction with the accompanying drawings to facilitate understanding by technicians in the same industry:
[0013] like Figure 1-2 As shown, the marks 1-9 in the figure respectively represent: the first grouting hole 1, the hinged steel pressure plate 2, the rubber water stop plate 3, the back pressure sleeve 4, the water stop device 5, the ball valve 6, the second grouting hole 7, the well wall 8, and the concrete pipe wall 9.
[0014] Example: Figure 1 and Figure 2 As shown, in this embodiment, the water-stopping structure of the tunnel entrance and exit of the jacking pipe is used to stop the water in the gap between the well wall 8 and the concrete pipe wall 9.
[0015] Specifically, combined Figure 1 and Figure 2 As shown, the water-stopping structure in this embodiment includes a first grouting hole 1, which is opened on the well wall 8 and passes through the back-pressure sleeve 4 arranged on the well wall 8, so that the outlet position of the first grouting hole 1 is located between the well wall 8 and the concrete pipe wall 9. Water-stopping bodies such as polyurethane foam can be injected through the first grouting hole 1 to achieve water-stopping between the well wall 8 and the concrete pipe wall 9.
[0016] The water-stop structure in this embodiment also includes a water-stop device 5 arranged on the outside of the well wall 8, and the water-stop device 5 includes a hinged articulated steel pressure plate 2 and two rubber water-stop plates 3, wherein the hinged articulated steel pressure plate 2 is fixed to the well wall 8 and two rubber water-stop plates 3 are fixedly installed, and the two rubber water-stop plates 3 are arranged at a certain distance, and each rubber water-stop plate 3 is in contact with the concrete pipe wall 9 to achieve the purpose of water-stopping.
[0017] In this embodiment, water stopping between the well wall 8 and the concrete pipe wall 9 is ensured by the combined structure of the first grouting hole 1 and the water stopping device 5 .
[0018] Combination Figure 1 and Figure 2As shown, in this embodiment, a second grouting hole 7 is further provided between the two rubber waterstop plates 3. The outlet position of the second grouting hole 7 is located in the reserved space between the two rubber waterstop plates 3, and the second grouting hole 7 is connected to the ball valve 6; when the rubber waterstop plate 3 fails, the ball valve 6 is opened to perform grouting through the second grouting hole 7, and polyurethane foam is injected to avoid quicksand and leakage, thereby further improving the waterstopping effect of the waterstop structure, especially realizing emergency waterstopping when the waterstop device 5 fails.
[0019] In this embodiment, if Figure 2 As shown, four second grouting holes 7 are equally and symmetrically arranged along the circumferential direction of the concrete pipe wall 9, and each second grouting hole 7 is independently connected to a ball valve 6 to achieve rapid emergency treatment in case of failure and improve the effect and efficiency of emergency treatment.
[0020] Although the above embodiments have described the concepts and embodiments of the purpose of the utility model in detail with reference to the accompanying drawings, ordinary technicians in this field can recognize that various improvements and modifications can still be made to the utility model without departing from the scope of the claims, so they are not described one by one here.
Claims
1. A water-stopping structure for the entrance and exit of a jacking pipe, used for water-stopping between the well wall and the concrete pipe wall. Features: The water-stop structure includes a first grouting hole, a hinged articulated steel pressure plate, and a rubber water-stop plate, wherein the first grouting hole passes through the well wall and its outlet is located between the well wall and the concrete pipe wall, the hinged articulated steel pressure plate is arranged on the outside of the well wall and in contact with the concrete pipe wall, two rubber water-stop plates are arranged at intervals on the hinged articulated steel pressure plate, and a second grouting hole is arranged between the two rubber water-stop plates.
2. A water-stopping structure for a jacking pipe inlet and outlet tunnel according to claim 1, Features: Along the circumferential direction of the concrete pipe wall, a plurality of the second grouting holes are evenly spaced and arranged in an array between the two rubber water stop plates.
3. A water-stopping structure for a jacking pipe inlet and outlet tunnel according to claim 1, Features: The second grouting hole is connected with a ball valve.