Steam temperature compensation heat exchange equipment
By designing the heat exchange box and temperature compensation components in the steam temperature compensation heat exchange equipment, the problem that the existing equipment cannot meet the daily water adding demand and the low efficiency of heating air is solved, and the effects of rapid steam generation and improvement of heating efficiency are achieved.
Patent Information
- Application Number
- CN202420256578.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-02
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-02-02
AI Technical Summary
Existing steam replenishing and heat exchange equipment cannot meet the daily water adding needs when used to replenish preheated water bodies. It needs to be mixed with cold water, which affects the heating and heat exchange efficiency, and the heating air efficiency is low.
A steam-supplemented heat exchange equipment including a shell, a heat exchange box and a heating component is designed. Water is heated through the heat exchange tubes in the heat exchange box. The shape design increases the heating area to meet daily water needs and is transported through steam. The pipe and diverter valve realize steam storage and preheating to avoid adulteration of cold water and improve heating efficiency.
It achieves rapid steam generation to meet daily water needs, improves heating efficiency, reduces heating time, extends equipment service life, and increases air heating speed.
Smart Images

Figure CN221924694U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of steam heat exchangers, and in particular relates to steam temperature compensation heat exchange equipment. Background Art
[0002] Steam heat exchanger is a device that uses steam as a heat source to heat water or air. It can fully replace a large amount of calorific value in the steam to heat water or air. The heated water or air can be centrally transported to various drying equipment.
[0003] At present, the Chinese patent with the publication (announcement) number: CN217464488U discloses an energy-saving steam heating and heat exchange equipment, including a fixed frame, a heat exchange cavity is arranged in the fixed frame, a first heat exchange tube is arranged in the heat exchange cavity, an air inlet pipe joint and an exhaust pipe joint corresponding to the two ends of the first heat exchange tube are arranged on the outer surface of the fixed frame, and a high-temperature water outlet pipe joint connected to the heat exchange cavity is arranged on one side of the outer surface of the fixed frame, a steam delivery pipe connected to the top of the heat exchange cavity is arranged in the fixed frame, a three-way valve is arranged on the steam delivery pipe, a first delivery pipe is installed on the three-way valve, a preheating cavity is arranged in the fixed frame, a heat exchange frame is arranged in the preheating cavity, and one end of the first delivery pipe is connected to the heat exchange frame. In the utility model, through the cooperation of the first heat exchange tube and the heat exchange cavity, a large amount of residual heat carried in the flue gas after the boiler is burned can be absorbed and utilized, and steam and hot water can be generated for daily heating and heating.
[0004] However, the above-mentioned steam reheating heat exchange equipment cannot meet the daily water supply needs when it is used to replenish water through the preheated water body, because the amount of water heated is small and needs to be mixed with some cold water, which affects the heating and heat exchange efficiency, and the efficiency is low when heating the air. Utility Model Content
[0005] In order to solve the above-mentioned technical problems, the purpose of the utility model is to provide a steam compensating heat exchange device to solve the technical defects that the steam compensating heat exchange device mentioned in the above-mentioned technology cannot meet the daily water adding needs when it is used for water replenishment through the preheated water body, because the amount of water heated is small and needs to be mixed with a little cold water, which affects the heating and heat exchange efficiency and has low efficiency when heating the air.
[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a steam compensating heat exchange device, comprising a shell, a heat exchange box, and a compensating component, a heat exchange box is arranged at one end of the lower surface of the inner wall of the shell, a heat exchange tube is arranged in the heat exchange box, an air intake pipe and an exhaust pipe are arranged at both ends of the heat exchange tube, the air intake pipe and the exhaust pipe both pass through one end of the shell, a steam storage box is arranged at the upper end of the heat exchange box, the heat exchange box and one end of the steam storage box are connected to the compensating component, and a hot water joint is arranged at one end of the heat exchange box.
[0007] As a further solution of the utility model, one end of the inner center of the upper surface of the heat exchange box is connected to a steam delivery pipe, and one end of the outer surface of the steam delivery pipe is provided with a temperature detector.
[0008] As a further preferred embodiment of the present invention, a diverter valve is provided at one end of the steam delivery pipe, and a first transport pipe and a second transport pipe are respectively installed at both ends of the diverter valve, the other end of the first transport pipe is connected to one end of the lower surface of the steam storage box, the other end of the second transport pipe is connected to a temperature compensation component, and a steam outlet joint is provided at the other end of the steam storage box.
[0009] As a preferred solution of the utility model, the temperature compensation component includes a hot water storage tank, the hot water storage tank is arranged at one end of the shell, and the other end of the second transport pipe is connected to the hot water storage tank.
[0010] As a further solution of the utility model, a water supply pipe is provided at one end of the upper surface of the hot water storage tank, and a steam transmission pipeline is connected to one end of the upper surface of the hot water storage tank, and the other end of the steam transmission pipeline is connected to one end of the steam storage tank.
[0011] As a further solution of the utility model, one end of the lower surface of the hot water storage tank is connected to a drain pipe, the other end of the drain pipe is connected to one end of the heat exchange tank, and a switch valve is provided at one end of the drain pipe.
[0012] Compared with the prior art, the steam heating and heat exchange equipment provided by the utility model has the following features:
[0013] Beneficial effects:
[0014] 1. Through the heat exchange box arranged in the shell, hot air is allowed to enter through the air inlet pipe arranged at the other end of the heat exchange tube in the heat exchange box, so that the hot air flows through the heat exchange tube. When the hot air flows through the heat exchange tube, it can heat the water in the heat exchange box. The shape of the heat exchange tube increases the heating area, so that the water in the heat exchange box can be heated faster to meet daily water needs. Through the warming component connected to one end of the heat exchange box, after the water in the heat exchange box is used up, water is added through the pre-heated warming component without the need for mixing with cold water. The required capacity for adding water can be fully met, the time consumed in heat exchange can be reduced, the heating efficiency can be improved, and steam can be quickly generated for use.
[0015] 2. Through the steam delivery pipe connected to the upper surface of the heat exchange box and the temperature detector arranged at one end of the outer surface of the steam delivery pipe, the staff can more intuitively observe the temperature of the steam during transportation. Through the diverter valve arranged at one end of the steam delivery pipe, the steam generated in the heat exchange box flows into the steam storage box and the warming component respectively through the diverter valve, so that the water in the warming component is preheated in advance for later use, so that more steam can be stored in the steam storage box, and the steam is discharged through the steam outlet joint connected at the other end, so that the air can be quickly heated.
[0016] 3. The steam generated in the heat exchanger tank flows into the hot water storage tank connected to one end of the second transport pipe, so that the water in the hot water storage tank is preheated in advance, and flows into the heat exchanger tank through the drain pipe to replenish water, which can prevent the steam amount from decreasing, improve the service life of the equipment, and will not affect the heating and heat exchange efficiency. The water flow in the hot water storage tank will also generate steam when the temperature rises, so that the steam generated in the hot water storage tank flows into the steam storage tank at one end through the steam transmission pipeline connected to the upper surface, thereby increasing the air heating speed through the steam stored in the steam storage tank. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] In order to more clearly illustrate the technical solution of the embodiment of the utility model, the drawings required for use in the embodiment will be briefly introduced below. Obviously, the drawings described below are only examples of the embodiment of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0018] Figure 1 It is a three-dimensional schematic diagram of the overall structure of an embodiment of the utility model;
[0019] Figure 2 This is a schematic diagram of the structure of a steam storage box according to an embodiment of the utility model;
[0020] Figure 3 This is a schematic diagram of the structure of the temperature compensation component of an embodiment of the utility model.
[0021] Reference numerals:
[0022] 1. Shell; 2. Heat exchange box; 3. Hot water connector; 4. Heat exchange tube; 5. Steam delivery pipe; 6. Temperature detector; 7. Diverter valve; 8. Steam storage box; 9. Warming component; 10. Steam outlet connector; 11. First transport pipe; 12. Second transport pipe; 901. Hot water storage box; 902. Water adding pipe; 903. Steam delivery pipeline; 904. Switch valve; 905. Drain pipe. DETAILED DESCRIPTION
[0023] In order to make the purpose, technical solution and advantages of the embodiment of the utility model more clear, the following is a further detailed description of the embodiment of the utility model in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the utility model and are not used to limit the utility model.
[0024] In the description of the embodiments of the present invention, it should be understood that the terms "upper", "lower", "front", "back", "inside", "outside", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the embodiments of the present invention and simplifying the description. They do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, they should not be understood as limitations on the embodiments of the present invention.
[0025] In the description of the embodiments of the present invention, it should be noted that, unless otherwise clearly stipulated and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense. For example, it can be a fixed connection, an integral connection, or a detachable connection; it can be the internal connection of two components; it can be directly connected or indirectly connected through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the embodiments of the present invention can be understood according to specific circumstances.
[0026] See attached Figure 1 -Attached Figure 3 As shown, a steam compensating heat exchange device includes a shell 1, a heat exchange box 2, and a compensating component 9. The heat exchange box 2 is arranged at one end of the lower surface of the inner wall of the shell 1, and a heat exchange tube 4 is arranged in the heat exchange box 2. An air intake pipe and an exhaust pipe are arranged at both ends of the heat exchange tube 4, and the air intake pipe and the exhaust pipe both pass through one end of the shell 1. A steam storage box 8 is arranged at the upper end of the heat exchange box 2, and one end of the heat exchange box 2 and the steam storage box 8 are connected to the compensating component 9, and a hot water connector 3 is arranged at one end of the heat exchange box 2.
[0027] Among them, through the heat exchange box 2 arranged in the shell 1, hot air is allowed to enter through the air inlet pipe arranged at the other end of the heat exchange tube 4 in the heat exchange box 2, so that the hot air flows from the heat exchange tube 4. When the hot air flows from the heat exchange tube 4, it can heat the water in the heat exchange box 2, and the shape of the heat exchange tube 4 increases the heating area, so that the water in the heat exchange box 2 can be heated faster to meet the daily water demand. Through the warming component 9 connected to one end of the heat exchange box 2, after the water in the heat exchange box 2 is used up, water is supplemented through the pre-heated warming component 9 without the need for mixing with cold water, which can fully meet the required capacity for adding water, reduce the time consumed in heat exchange, improve the heating efficiency, and quickly generate steam for use.
[0028] See attached Figure 1 -Attached Figure 2As shown, one end of the inner center of the upper surface of the heat exchange box 2 is connected to a steam delivery pipe 5, one end of the outer surface of the steam delivery pipe 5 is provided with a temperature detector 6, one end of the steam delivery pipe 5 is provided with a diverter valve 7, and the two ends of the diverter valve 7 are respectively installed with a first transport pipe 11 and a second transport pipe 12, the other end of the first transport pipe 11 is connected to one end of the lower surface of the steam storage box 8, the other end of the second transport pipe 12 is connected to a temperature compensation component 9, and the other end of the steam storage box 8 is provided with a steam outlet joint 10.
[0029] Among them, through the steam delivery pipe 5 connected to the upper surface of the heat exchange box 2 and the temperature detector 6 arranged at one end of the outer surface of the steam delivery pipe 5, the staff can more intuitively observe the temperature of the steam during transportation, and through the diverter valve 7 arranged at one end of the steam delivery pipe 5, the steam generated in the heat exchange box 2 flows into the steam storage box 8 and the warming component 9 respectively through the diverter valve 7, so that the water in the warming component 9 is preheated in advance for later use, so that more steam can be stored in the steam storage box 8, and the steam is discharged through the steam outlet joint 10 connected at the other end, so that the air can be quickly heated.
[0030] See attached Figure 3 As shown, the warming component 9 includes a hot water tank 901, which is arranged at one end of the shell 1, and the other end of the second transport pipe 12 is connected to the hot water tank 901. A water adding pipe 902 is arranged at one end of the upper surface of the hot water tank 901, and a steam transmission pipeline 903 is connected to one end of the upper surface of the hot water tank 901. The other end of the steam transmission pipeline 903 is connected to one end of the steam storage tank 8, and one end of the lower surface of the hot water tank 901 is connected to a drain pipe 905, and the other end of the drain pipe 905 is connected to one end of the heat exchange box 2. A switch valve 904 is arranged at one end of the drain pipe 905.
[0031] Among them, the steam generated in the heat exchanger box 2 flows into the hot water storage tank 901 connected to one end of the second transport pipe 12, so that the water flow in the hot water storage tank 901 is preheated in advance, and flows into the heat exchanger box 2 through the drain pipe 905 to replenish water, which can prevent the steam amount from decreasing, improve the service life of the equipment, and will not affect the heating and heat exchange efficiency. The water flow temperature in the hot water storage tank 901 will also generate steam when it rises, so that the steam generated in the hot water storage tank 901 flows into the steam storage tank 8 at one end through the steam transmission pipeline 903 connected to the upper surface, thereby increasing the air heating speed through the steam stored in the steam storage tank 8.
[0032] Working principle: hot air enters through the air inlet pipe set at one end of the heat exchange tube 4, so that the hot air enters the heat exchange tube 4 to heat the water in the heat exchange box 2, and the temperature rises to a certain extent to generate steam. The steam passes through the steam delivery pipe 5 connected to the upper surface of the heat exchange box 2, and passes through the diverter valve 7 set at one end of the steam delivery pipe 5. Through the diverter valve 7, the steam generated in the heat exchange box 2 can flow into the steam storage box 8 and the warming component 9 respectively, and the steam generated in the heat exchange box 2 flows into the hot water storage tank 901 connected to one end of the second transport pipe 12, so that the water flow in the hot water storage tank 901 can be preheated in advance , so that the staff turns the switch valve 904, so that the water in the hot water storage tank 901 flows into the heat exchange tank 2 through the drain pipe 905 to replenish water. The water capacity in the hot water storage tank 901 is sufficient to fill the heat exchange tank 2. When the water flow temperature in the hot water storage tank 901 rises, steam will also be generated, so that the steam generated in the hot water storage tank 901 flows into the steam storage tank 8 at one end through the steam transmission pipeline 903 connected to the upper surface, so that more steam can be stored in the steam storage tank 8, and the steam is discharged through the steam outlet joint 10 connected to the other end, so that the air can be quickly heated.
[0033] The above shows and describes the basic principles of the present invention. The above are only preferred embodiments of the present invention and are not intended to limit the present invention. The above embodiments and descriptions in the specification are only intended to illustrate the principles of the present invention. Without departing from the scope of the present invention, any modifications, equivalent substitutions and improvements made within the spirit and scope of the present invention should be included in the protection scope of the present invention.
Claims
1. A steam compensation heat exchange device, characterized in that: The invention comprises a shell (1), a heat exchange box (2), and a temperature compensation component (9); a heat exchange box (2) is arranged at one end of the lower surface of the inner wall of the shell (1); a heat exchange tube (4) is arranged in the heat exchange box (2); an air intake pipe and an exhaust pipe are arranged at both ends of the heat exchange tube (4); the air intake pipe and the exhaust pipe both pass through one end of the shell (1); a steam storage box (8) is arranged at the upper end of the heat exchange box (2); one end of the heat exchange box (2) and the steam storage box (8) are connected to the temperature compensation component (9); and a hot water connector (3) is arranged at one end of the heat exchange box (2).
2. The steam compensation heat exchange equipment according to claim 1, characterized in that: One end of the inner center of the upper surface of the heat exchange box (2) is connected to a steam delivery pipe (5), and one end of the outer surface of the steam delivery pipe (5) is provided with a temperature detector (6).
3. The steam compensation heat exchange equipment according to claim 2, characterized in that: A diverter valve (7) is provided at one end of the steam delivery pipe (5), and a first delivery pipe (11) and a second delivery pipe (12) are respectively installed at both ends of the diverter valve (7). The other end of the first delivery pipe (11) is connected to one end of the lower surface of the steam storage box (8), and the other end of the second delivery pipe (12) is connected to a temperature compensation component (9). The other end of the steam storage box (8) is provided with a steam outlet joint (10).
4. The steam compensation heat exchange equipment according to claim 3, characterized in that: The temperature compensation component (9) comprises a hot water storage tank (901), wherein the hot water storage tank (901) is arranged at one end of the shell (1), and the other end of the second transport pipe (12) is connected to the hot water storage tank (901).
5. The steam compensation heat exchange equipment according to claim 4, characterized in that: A water supply pipe (902) is provided at one end of the upper surface of the hot water storage tank (901), and a steam transmission pipeline (903) is connected to one end of the upper surface of the hot water storage tank (901), and the other end of the steam transmission pipeline (903) is connected to one end of the steam storage tank (8).
6. The steam compensation heat exchange equipment according to claim 5, characterized in that: One end of the lower surface of the hot water storage tank (901) is connected to a drain pipe (905), and the other end of the drain pipe (905) is connected to one end of the heat exchange tank (2). An on-off valve (904) is provided at one end of the drain pipe (905).