Force transmission fixing device for core penetrating rod method construction

By using a combination of iron box, screw and arc-shaped press plate in the heartbeat fixing device, the problem of insufficient time and fixing of the heartbeat in the prior art is solved, efficient fixing and disassembly are achieved, and construction efficiency is improved.

CN221956535UActive Publication Date: 2024-11-05CHINA 19TH METALLURGICAL CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420014331.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-03
Publication Date
2024-11-05
Estimated Expiration
2034-01-03

AI Technical Summary

Technical Problem

The existing core-piercing rod fixing method takes a long time to weld at high altitude and is troublesome to remove, and the fixing is insufficient, making it easy to loosen.

Method used

Using a force transmission fixing device including an iron box, a screw, a fixing nut and a curved pressure plate, the penetration rod is pressed and fixed in the hole of the iron box through the cooperation of the screw and a curved pressure plate, and a firm connection is ensured by the locking nut and handle. .

Benefits of technology

It improves the tight connection between the heartbeat and the iron box, simplifies the disassembly process, and improves construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221956535U_ABST
    Figure CN221956535U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of bridge cover beam construction, in particular to a force transmission fixing device for cross-core rod method construction, which comprises an iron box, a screw rod, a fixing nut and an arc-shaped pressing plate, a cross-core rod can penetrate through the iron box, one side of the iron box is provided with a through hole communicated with a hole channel, the fixing nut is arranged on the outer side of the iron box, and the arc-shaped pressing plate is arranged on the outer side of the iron box. The screw penetrates through the fixing nut and the through hole and then is rotationally connected with the arc-shaped pressing plate, the arc-shaped pressing plate is provided with an arc-shaped structure matched with the cross-core rod, and the cross-core rod is pressed and fixed to the inner wall of the hole channel through the screw and the arc-shaped pressing plate. The arc-shaped pressing plate is used as a pressing piece, the arc-shaped pressing plate is pressed on the cross-core rod through the screw penetrating through the fixing nut, so that the cross-core rod is pressed and fixed in the hole channel of the iron box, the fixing device can increase the contact area between the cross-core rod and the iron box and the contact area between the cross-core rod and the arc-shaped pressing plate, tight connection between the cross-core rod and the iron box is ensured, and the service life of the cross-core rod is prolonged. And meanwhile, dismantling can be conducted easily in the follow-up dismantling process, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of bridge cover beam construction, in particular to a force transmission and fixing device used for construction using a core rod method. Background Art

[0002] The through-rod cap beam construction technology is a construction technology used in bridge construction. Especially in the construction of cap beams with high piers or low piers but difficult foundation treatment, the through-rod method becomes the first choice for construction. The specific construction process is that during the pouring of the piers, holes for fixing the through-rods are first reserved in the radial direction of the piers, and then the through-rods are inserted into the holes, and finally construction platforms are set up at both ends of the through-rods. During the construction process, in order to ensure that the through-rods can better transmit force and prevent rolling, the through-rods need to be fixed. Currently, there are two main methods: one is to spot weld a piece of iron plate on the through-rod, and connect the iron plates on both sides with steel pipes; the other is to install a hollow iron box after the through-rod is installed, and then use triangular wooden blocks to plug and tighten the four corner gaps after the iron box is covered with steel rods, so as to fix the through-rod and the hollow iron box together. The disadvantage of the first method is that the welding operation is carried out at high altitude, which is not very convenient, time-consuming, and the subsequent dismantling is also troublesome; the disadvantage of the second method is that the firmness of the fixation cannot be guaranteed, and the through rod and the iron box are prone to loosening. Utility Model Content

[0003] In order to overcome the above-mentioned shortcomings of the existing through-rod fixing method, the technical problem to be solved by the utility model is: to provide a kind of through-rod fixing device.

[0004] The technical solution adopted by the utility model to solve its technical problems is:

[0005] A force transmission and fixing device for construction using a through-rod method comprises an iron box, a hole for the through-rod to pass through is provided in the middle of the iron box, a screw, a fixing nut and an arc-shaped pressure plate, a through hole connected to the hole is provided on one side of the iron box, the fixing nut is arranged on the outside of the iron box and is coaxial with the through hole, the screw passes through the fixing nut and the through hole and is rotatably connected to the arc-shaped pressure plate, the arc-shaped pressure plate has an arc-shaped structure matching the through-rod, and the through-rod is pressed and fixed to the inner wall of the hole by the screw and the arc-shaped pressure plate.

[0006] Furthermore, the screw is connected to the arc-shaped pressure plate through a bearing, the outer ring of the bearing is welded and fixed on the arc-shaped pressure plate, and the end of the screw is connected and fixed to the inner ring of the bearing.

[0007] Furthermore, a handle is provided at one end of the screw rod away from the arc-shaped pressing plate.

[0008] Furthermore, a locking nut is provided on the screw rod, and the screw rod passes through the locking nut, the fixing nut and the through hole in sequence and is connected to the arc-shaped pressing plate.

[0009] Furthermore, the arc length of the arc-shaped pressing plate and the through-hole rod is not less than 1 / 3 of the circumference of the through-hole rod.

[0010] Furthermore, a rubber pad is provided on the arc surface where the arc pressure plate fits the core rod.

[0011] Furthermore, the screw rod, locking nut, fixing nut and arc-shaped pressure plate each include at least two sets, and are arranged at intervals along the axis of the channel.

[0012] The beneficial effects of the utility model are: using an arc-shaped pressure plate as a clamping piece, and arranging a fixing nut on the iron box, and using a screw rod passing through the fixing nut to press the arc-shaped pressure plate onto the mandrel rod, thereby pressing and fixing the mandrel rod in the hole of the iron box; the fixing device can increase the contact area between the mandrel rod and the iron box and the arc-shaped pressure plate, ensuring a tight connection between the mandrel rod and the iron box; at the same time, it can also be easily removed during the subsequent disassembly process, thereby improving construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 This is a structural front view of the utility model before the mandrel is fixed;

[0014] Figure 2 This is a front view of the structure of the utility model after the through-rod is fixed;

[0015] Figure 3 It is a side sectional view of the utility model after the through rod is fixed.

[0016] Marked in the figure, 1-iron box, 2-through rod, 3-screw, 4-fixing nut, 5-arc pressure plate, 6-bearing, 7-locking nut, 11-channel, 12-through hole, 31-handle, 51-rubber pad. DETAILED DESCRIPTION

[0017] The utility model is further described below in conjunction with the accompanying drawings.

[0018] It should be noted that if there are directional indication terms in the present invention, such as up, down, left, right, front, and back directions and orientation terms, they are for the purpose of facilitating the description of the relative position relationship between components, and are not for the absolute position of the related components or the position relationship between components. They are only used to explain the relative position relationship and movement of the components in a certain posture. If the specific posture changes, the directional indication will also change accordingly. If there are terms related to quantity in the present invention, such as "multiple", "multiple", "several", etc., they specifically refer to two or more.

[0019] like Figure 1-3As shown, the utility model is used for the force transmission and fixing device of the through-rod method construction, comprising an iron box 1, a hole 11 for the through-rod 2 to pass through is provided in the middle of the iron box 1, and also comprising a screw 3, a fixing nut 4 and an arc-shaped pressing plate 5. A through hole 12 connected to the hole 11 is provided on one side of the iron box 1, and the fixing nut 4 is arranged on the outside of the iron box 1 and is coaxial with the through hole 12. The screw 3 passes through the fixing nut 4 and the through hole 12 and is rotatably connected with the arc-shaped pressing plate 5. The arc-shaped pressing plate 5 has an arc-shaped structure matching the through-rod 2. The through-rod 2 is pressed and fixed on the inner wall of the hole 11 by the screw 3 and the arc-shaped pressing plate 5. Among them, the aperture of the hole 11 should be larger than the outer diameter of the through-rod 2 to ensure that there is enough space to put the arc-shaped pressing plate 5.

[0020] The use process of the utility model is: first, after completing the installation of the through-hole rod 2, an iron box 1 is set at each end of the through-hole rod 2, so that the through-hole rod 2 passes through the hole 11 on the iron box 1. When installing, it is best to make the side with the screw 3 located below the through-hole rod 2 to ensure that the through-hole rod 2 after being pressed is supported on the top of the hole 11, and then the screw 3 is rotated to make the screw 3 drive the arc-shaped pressing plate 5 to move upward until the through-hole rod 2 is pressed and fixed on the inner wall of the hole 11, ensuring that the through-hole rod 2 and the iron box 1 will not rotate, and finally a construction platform can be set up on the iron box. When the construction is completed and the disassembly construction is flat, the screw 3 can be loosened to separate the arc-shaped pressing plate 5 from the through-hole rod 2, so that the iron box 1 and the through-hole rod 2 can be easily disassembled.

[0021] As for the rotation connection between the screw rod 3 and the arc-shaped pressing plate 5, the preferred solution of the utility model is that the screw rod 3 is connected to the arc-shaped pressing plate 5 through the bearing 6, the outer ring of the bearing 6 is welded and fixed on the arc-shaped pressing plate 5, and the end of the screw rod 3 is connected and fixed with the inner ring of the bearing 6. During the manufacturing process, the outer ring of the bearing 6 is first welded and fixed on the arc-shaped pressing plate 5, and then the arc-shaped pressing plate 5 is placed in the channel 11, so that the inner ring of the bearing is aligned with the end of the screw rod 3 passing through the through hole 12, and then the end of the screw rod 3 is fixedly connected with the inner ring of the bearing. The screw rod 3 and the inner ring of the bearing can be fixed by interference fit, welding, bonding or threaded connection.

[0022] In order to facilitate the rotation of the screw rod 3 , a handle 31 is provided at one end of the screw rod 3 away from the arc-shaped pressing plate 5 .

[0023] Furthermore, in order to prevent the screw rod 3 from loosening after pressing the arc-shaped pressing plate 5, a locking nut 7 is further provided on the screw rod 3, and the screw rod 3 passes through the locking nut 7, the fixing nut 4 and the through hole 12 in sequence and is connected to the arc-shaped pressing plate 5. After the screw rod 3 presses and fixes the arc-shaped pressing plate 5, the locking nut 7 is screwed to press against the fixing nut 4, so that the screw rod 3 and the fixing nut 4 are locked and fixed, and the screw rod 3 is prevented from loosening.

[0024] The utility model provides two preferred solutions for the arc-shaped pressing plate 5. First, in order to increase the contact area, the arc length of the arc-shaped pressing plate 5 and the through-hole rod 2 is not less than 1 / 3 of the circumference of the through-hole rod 2; second, in order to increase the friction coefficient, the arc-shaped pressing plate 5 is provided with a rubber pad 51 on the arc-shaped surface that fits the through-hole rod 2. The two preferred solutions can further increase the reliability of the contact between the through-hole rod 2 and the arc-shaped pressing plate 5, and ensure that the iron box 1 will not rotate relative to the through-hole rod 2.

[0025] Further, such as Figure 3 As shown, in order to increase the bearing surface, the iron box 1 needs to have a certain length. Therefore, in order to enable the longer arc-shaped pressure plate 5 to be evenly pressed on the through-core rod 2, the screw 3, locking nut 7, fixing nut 4 and arc-shaped pressure plate 5 each include at least two sets, and are spaced apart along the axis of the channel 11.

[0026] The utility model utilizes an arc-shaped pressing plate 5 as a pressing member, and arranges a fixing nut 4 on the iron box 1, and utilizes a screw rod 3 passing through the fixing nut 4 to press the arc-shaped pressing plate 5 onto the through-hole rod 2, thereby pressing and fixing the through-hole rod 2 in the channel 11 of the iron box 1. The fixing device can increase the contact area between the through-hole rod 2 and the iron box 1 and the arc-shaped pressing plate 5, ensure the tight connection between the through-hole rod 2 and the iron box 1, and can also be easily removed during the subsequent disassembly process, thereby improving the construction efficiency, and having good practicality and application prospects.

Claims

1. A force transmission and fixing device for construction using a mandrel rod method, comprising an iron box (1), wherein a hole (11) is provided in the middle of the iron box (1) for a mandrel rod (2) to pass through, and characterized in that: It also includes a screw rod (3), a fixing nut (4) and an arc-shaped pressure plate (5); one side of the iron box (1) is provided with a through hole (12) connected to the channel (11); the fixing nut (4) is arranged on the outside of the iron box (1) and is coaxial with the through hole (12); the screw rod (3) passes through the fixing nut (4) and the through hole (12) and is rotatably connected to the arc-shaped pressure plate (5); the arc-shaped pressure plate (5) has an arc-shaped structure matching the through rod (2); the through rod (2) is pressed and fixed on the inner wall of the channel (11) by the screw rod (3) and the arc-shaped pressure plate (5).

2. The force transmission and fixing device for construction using the mandrel method according to claim 1, characterized in that: The screw rod (3) is connected to the arc-shaped pressure plate (5) via a bearing (6); the outer ring of the bearing (6) is welded and fixed to the arc-shaped pressure plate (5); and the end of the screw rod (3) is connected and fixed to the inner ring of the bearing (6).

3. The force transmission and fixing device for construction using the mandrel method according to claim 1, characterized in that: A handle (31) is provided at one end of the screw rod (3) away from the arc-shaped pressing plate (5).

4. The force transmission and fixing device for construction using the mandrel method according to claim 1, characterized in that: The screw rod (3) is also provided with a locking nut (7), and the screw rod (3) passes through the locking nut (7), the fixing nut (4) and the through hole (12) in sequence and is connected to the arc-shaped pressing plate (5).

5. The force transmission and fixing device for construction using the mandrel method according to claim 1, characterized in that: The arc length of the arc-shaped pressing plate (5) fitting with the core-penetrating rod (2) is not less than 1 / 3 of the circumference of the core-penetrating rod (2).

6. The force transmission and fixing device for construction using the mandrel method according to claim 5, characterized in that: The arc-shaped pressing plate (5) is provided with a rubber pad (51) on the arc-shaped surface that fits with the core-penetrating rod (2).

7. The force transmission and fixing device for construction using the mandrel method according to any one of claims 1 to 6, characterized in that: The screw rod (3), locking nut (7), fixing nut (4) and arc-shaped pressure plate (5) each include at least two sets, and are arranged at intervals along the axis of the channel (11).