Precast pile end grouting and reaming device

Through the prefabricated pile-pile end grouting device, the pile tip is pushed open with the rotating shaft and pushing rod to form holes and inject slurry, which solves the problem of expanding the prefabricated pile ends in the prior art, and improves the bearing capacity and stability , and ensures the stability of the device and material utilization through automatic pull-off and pre-embedding design.

CN221956701UActive Publication Date: 2024-11-05GUIZHOU JIANGCE ENGINEERING DESIGN CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420485738.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-13
Publication Date
2024-11-05
Estimated Expiration
2034-03-13

AI Technical Summary

Technical Problem

It is difficult for existing prefabricated piles to effectively expand the end of the pile during pile driving, resulting in insufficient bearing capacity and stability, and traditional hole reaming methods have problems such as large damage or soil blockage.

Method used

A prefabricated pile end grouting and reaming device is designed, including hollow prefabricated piles, pulleys, ropes, rotary shafts, push rods, pulley connections and reaming device fixtures, and the piles are pushed open by the cooperation of the rotary shafts and push rods. The tip forms holes, and the grouting pipe is injected into the slurry to expand the pile end, combining bolts and steel bars to ensure the stability of the device.

Benefits of technology

The expansion of prefabricated pile ends has been achieved, the bearing capacity and stability of the pile foundation has been improved, the risk of uneven ends has been avoided, the hole expansion process has been simplified, and the device has been improved by automatically pulling the rope and pre-embedding design. Reliability and material utilization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221956701U_ABST
    Figure CN221956701U_ABST
Patent Text Reader

Abstract

The utility model relates to a spinning bolt type steel pipe pile lap joint structure which comprises a hollow precast pile, a pulley, a rope, a rotating shaft, a pushing rod, a pile tip, a pulley connecting piece, a grouting pipe and a reaming device fixing piece. The rotating shaft is arranged at the bottom of the hollow precast pile; two ends of the rotating shaft are connected with reaming device fixing pieces; the end, away from the rotating shaft, of the pushing rod abuts against the pile tip. The pulley is connected with the rotating shaft through a pulley connecting piece; one end of the rope is connected with the pushing rod, and the other end of the rope penetrates through the pulley to pull the rope to drive the pushing rod to rotate around the rotating shaft and push the pile tip to open to open surrounding soil to form a hole; one end of the grouting pipe abuts against the pile tip. The inclined strut precast pile has the advantages that the pile tip is opened to form a hole for grouting, the end of the precast pile is expanded, the bearing capacity and stability of a pile foundation are remarkably improved, and the risk that the expanded end of the inclined strut precast pile is not uniform due to direct grouting is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of prefabricated piles, and more specifically, to a grouting and hole-expanding device for the end of a prefabricated pile. Background Art

[0002] Precast piles have the advantages of high construction efficiency, convenient transportation, stable quality, economy and environmental protection. With the development of urban space and the continuous improvement and perfection of construction technology, some shallow excavation pits use inclined piles instead of internal supports. The inclined pile support can be made of steel pipes, lattice columns, precast piles and other cross-sectional forms. In recent years, the requirements for the compression and pull-out resistance of precast piles have been continuously improved. The current solution is usually to use precast piles with large diameter and long pile body to improve the bearing capacity and pull-out resistance of the pile body.

[0003] The existing patented technologies are mainly based on prefabricated piles with enlarged heads. Due to the large pile heads, there are gaps between the pile body and the soil during the piling process, which need to be filled, but it is difficult to ensure the quality of the gap filling. In addition, there are methods such as pile end explosive expansion and pile end hole expansion devices. For example, the construction method of prefabricated pipe piles with enlarged heads disclosed in patent publication number CN100516377 is to expand the hole in the middle of the hollow pile tip by placing explosives to detonate the hole. This method causes great damage to the prefabricated piles. For example, the internal support enlarged head pipe pile structure disclosed in patent publication number CN208844544U realizes the expansion of the pile end by pressing down the expansion steel sheet embedded in the pile end through the steel sheet expansion tube. However, when this method is applied to the diagonal brace, there is a problem of shrinkage of the expansion steel sheet and the soil entering the tube to block the hollow pile, making it difficult to expand the pile end. Utility Model Content

[0004] The utility model aims to overcome the deficiencies in the prior art and provides a prefabricated pile end grouting and hole enlarging device, comprising: a hollow prefabricated pile, a pulley, a rope, a rotating shaft, a jacking rod, a pile tip, a pulley connector, a grouting pipe, and a hole enlarging device fixing member;

[0005] Wherein, the rotating shaft is arranged at the bottom of the hollow precast pile, and the four rotating shafts are overlapped with each other; the two ends of the rotating shaft are connected with the hole expansion device fixing parts, and the hole expansion device fixing parts are fixed in the hollow precast pile; the middle part of the rotating shaft is connected with a pushing rod, and the end of the pushing rod away from the rotating shaft is against the pile tip; the pulley is connected to the rotating shaft through a pulley connector; one end of the rope is connected to the pushing rod, and the other end passes through the pulley, and the rope is pulled to drive the pushing rod to rotate around the rotating shaft, and at the same time push the pile tip to open, push the surrounding soil to form a hole; one end of the grouting pipe is against the pile tip, which is used for grouting after the pile tip is opened.

[0006] Preferably, when the pile tip opening angle reaches a preset threshold, the front rope is automatically broken.

[0007] Preferably, holes are provided at both ends of the rotating shaft, and bolts are passed through the holes to connect the rotating shaft and the fixing member of the reaming device into a whole.

[0008] Preferably, the pulley connector is U-shaped, a pulley is provided in the middle of the pulley connector, and both ends of the pulley connector are circular rings, and the rotating shaft passes through the circular rings to fix the pulley connector and the pulley on the rotating shaft.

[0009] Preferably, one end of the hole expansion device fixing piece is provided with a steel bar connecting hole for clamping the steel bar of the hollow precast pile and pre-burying the hole expansion device fixing piece in the hollow precast pile; the other end of the hole expansion device fixing piece is a slot, and holes are provided on both sides of the slot, and the bolts pass through the slot and the holes of the rotating shaft.

[0010] The beneficial effects of the utility model are:

[0011] 1. The utility model expands the end of the precast pile by opening the pile tip to form a hole for grouting, which not only significantly improves the bearing capacity and stability of the pile foundation, but also avoids the risk of uneven expansion of the end of the diagonal braced precast pile in direct grouting. At the same time, the use of the rotating shaft and the jacking rod allows the pile tip to expand outward to form a larger bearing surface, simplifying the traditional hole expansion process.

[0012] 2. The automatic breaking rope design of the utility model can be disconnected in time when the pile tip reaches the preset opening angle, which not only avoids the possible risks caused by excessive hole expansion, but also the remaining rope can be recycled, increasing the utilization rate of materials and reducing construction costs.

[0013] 3. The utility model connects the rotating shaft and the hole expansion device fixing part by bolts, and pre-buries the hole expansion device fixing part in the hollow prefabricated pile, and clamps the steel bars in the pile through the steel bar connecting holes. This series of designs ensures the stability and reliability of the hole expansion device during the piling and expansion process, and reduces the risk of displacement or falling off of the device. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 A cross-sectional view of the precast pile end grouting and hole enlarging device provided for this application;

[0015] Figure 2 A top view of the prefabricated pile end grouting and hole expansion device provided in this application;

[0016] Figure 3 An overall schematic diagram of the precast pile end grouting and hole expansion device provided in this application;

[0017] Explanation of the accompanying reference numerals: 1. hollow precast pile, 2. pulley, 3. rope, 4. rotating shaft, 5. jacking rod, 6. pile tip, 7. pulley connecting piece, 8. grouting pipe, 9. hole expansion device fixing piece, 10. steel bar connecting hole, 11. bolt. DETAILED DESCRIPTION

[0018] The utility model is further described below in conjunction with the embodiments. The description of the following embodiments is only used to help understand the utility model. It should be pointed out that for ordinary people in this technical field, the utility model can also be modified in some ways without departing from the principle of the utility model, and these improvements and modifications also fall within the scope of protection of the claims of the utility model.

[0019] Embodiment 1:

[0020] The present application provides a precast pile end grouting and hole enlargement device, which can realize the enlargement of the precast pile end without damaging the original precast pile. The device can also avoid the problem of uneven grouting existing in direct grouting. Specifically, Figures 1 to 3 As shown, it includes: a hollow prefabricated pile 1, a pulley 2, a rope 3, a rotating shaft 4, a jacking rod 5, a pile tip 6, a pulley connecting piece 7, a grouting pipe 8, and a hole expansion device fixing piece 9.

[0021] Wherein, the hollow prefabricated pile 1 is a part of the diagonal bracing structure or pile foundation;

[0022] There are four rotating shafts 4, which are arranged at the bottom of the hollow precast pile 1; holes are provided at both ends of the rotating shaft 4, and bolts 11 pass through the holes to connect the rotating shaft 4 and the hole expansion device fixing member 9 into a whole. One end of the hole is open at the top and the other end is open at the bottom, which is used for overlapping the four rotating shafts 4.

[0023] A push rod 5 is connected to the middle of the rotating shaft 4 . One end of the push rod 5 is a ring and the other end is against the pile tip 6 . The rotating shaft 4 passes through the ring to fix the push rod 5 . The push rod 5 can rotate around the rotating shaft 4 .

[0024] There are four pulleys 2 installed at the bottom of the hollow precast pile 1, with a round hole in the center. The pulley connector 7 passes through the round hole to fix the pulley 2.

[0025] There are four ropes 3, which are connected to the push rod 5 and pass through the pulley 2. Pulling the rope 3 will drive the push rod 5 to rotate around the rotating shaft 4, and at the same time push the pile tip 6 to open, push the surrounding soil to form a hole, and inject slurry into the hole. The strength of the front end of the rope is relatively small. When the pile tip 6 opens at a large enough angle, the front rope is automatically broken, and the remaining rope can be recycled.

[0026] The pile tip 6 is located at the bottom of the hollow precast pile. When the hollow precast pile 1 is driven to the designed position, the pile tip 6 is opened by the precast pile end grouting and hole expansion device to form a hole for grouting, thereby expanding the end and improving the bearing capacity.

[0027] One end of the grouting pipe 8 is against the pile tip 6, and is used for grouting after the pile tip 6 is opened, filling the gap to form an enlarged end, and improving the pile bearing capacity.

[0028] The pulley connector 7 is U-shaped, a pulley 2 is provided in the middle of the pulley connector 7 , and both ends of the pulley connector 7 are circular rings, through which the rotating shaft 4 passes to fix the pulley connector 7 and the pulley 2 on the rotating shaft 4 .

[0029] The hole-expanding device fixing part 9 is a clamp, and a steel bar connecting hole 10 is provided at one end, which can clamp the steel bar of the hollow precast pile 1, and the hole-expanding device fixing part 9 is pre-buried in the hollow precast pile 1. The other end is a slot, and holes are provided on both sides of the slot. Bolts 11 pass through the slot and the holes of the rotating shaft 4 to fix the entire precast pile end grouting hole-expanding device in the hollow precast pile 1; the steel bar connecting hole 10 is located at one end of the hole-expanding device fixing part 9; the bolts 11 are used to fix the precast pile end grouting hole-expanding device in the hollow precast pile 1.

Claims

1. A prefabricated pile end grouting and hole expansion device, It is characterized in that include: Hollow prefabricated pile (1), pulley (2), rope (3), rotating shaft (4), jacking rod (5), pile tip (6), pulley connecting piece (7), grouting pipe (8), hole expansion device fixing piece (9); The rotating shaft (4) is arranged at the bottom of the hollow precast pile (1), and the four rotating shafts (4) overlap each other; the two ends of the rotating shaft (4) are connected to the hole expansion device fixing parts (9), and the hole expansion device fixing parts (9) are fixed in the hollow precast pile (1); the middle part of the rotating shaft (4) is connected to the push rod (5), and the end of the push rod (5) away from the rotating shaft (4) is against the pile tip (6); the pulley (2) is connected to the rotating shaft (4) through a pulley connecting part (7); one end of the rope (3) is connected to the push rod (5), and the other end passes through the pulley (2), and the rope (3) is pulled to drive the push rod (5) to rotate around the rotating shaft (4), and at the same time push the pile tip (6) to open, push the surrounding soil to form a hole; one end of the grouting pipe (8) is against the pile tip (6), which is used for grouting after the pile tip (6) is opened.

2. The precast pile end grouting and hole enlarging device according to claim 1, It is characterized in that When the opening angle of the pile tip (6) reaches a preset threshold, the front rope (3) is automatically broken.

3. The precast pile end grouting and hole enlarging device according to claim 2, It is characterized in that Holes are provided at both ends of the rotating shaft (4), and bolts (11) are passed through the holes to connect the rotating shaft (4) and the hole expansion device fixing member (9) into a whole.

4. The precast pile end grouting and hole enlarging device according to claim 3, It is characterized in that The pulley connector (7) is U-shaped, a pulley (2) is provided in the middle of the pulley connector (7), both ends of the pulley connector (7) are circular rings, and the rotating shaft (4) passes through the circular rings to fix the pulley connector (7) and the pulley (2) on the rotating shaft (4).

5. The precast pile end grouting and hole enlarging device according to claim 4, It is characterized in that One end of the hole expansion device fixing piece (9) is provided with a steel bar connection hole (10) for clamping the steel bars of the hollow precast pile (1) and pre-burying the hole expansion device fixing piece (9) in the hollow precast pile (1); the other end of the hole expansion device fixing piece (9) is a clamping groove, and holes are provided on both sides of the clamping groove, and the bolt (11) passes through the clamping groove and the hole of the rotating shaft (4).