Discharging platform for constructional engineering
By introducing working platforms, trolleys and folding rack gas rod structures on the unloading platform of construction projects, the problems of low material transportation efficiency and insufficient equipment stability in the existing technology are solved, and more efficient and safer material transportation is achieved process.
Patent Information
- Application Number
- CN202420412929.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-04
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2034-03-04
AI Technical Summary
The existing construction project unloading platform is inefficient during material transportation and causes harm to the staff, and the equipment stability and buffering capacity are insufficient.
A discharge platform including a working platform, a small trolley, a folding rack and a gas rod was designed to facilitate the transportation of materials through a small trolley. The folding rack and a gas rod drove the working platform to lift and lower, improve the transportation efficiency, and pass the movable groove and slide. The rail limits the driving trajectory of the cart and increases safety.
It improves the efficiency and safety of material transportation, reduces the labor intensity of staff, reduces the physical damage caused by long-term handling, and enhances the stability and support capabilities of the equipment.
Smart Images

Figure CN221957225U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction engineering, and in particular to a construction engineering unloading platform. Background Art
[0002] A construction project refers to an engineering entity formed by the construction of various types of buildings and their ancillary facilities and the installation of supporting lines, pipelines, and equipment. In the process of implementing the project, a variety of materials are needed for construction, and manual handling of materials is inefficient, which makes it difficult to complete the project within the scheduled construction period. This requires the use of a construction project unloading platform.
[0003] Patent document CN213449545U discloses a construction engineering unloading platform, "including a buffer pad, a first high-strength bolt, a support seat, a support sleeve, an I-beam, a compression spring, a buffer block and a mounting seat, a buffer pad is pasted on the upper end surface of the bearing platform, a support seat is installed on the lower end surface of the bearing platform, a first high-strength bolt is engaged in the middle position of the upper end surface of the support seat, a support sleeve is installed on the upper end surface of the supporting base plate, a compression spring is clamped inside the support sleeve, mounting seats are symmetrically installed on the left and right sides of the upper end surface of the supporting base plate, a buffer block is installed on the upper end surface of the mounting seat, and an I-beam is installed on the lower end surface of the supporting side plate. This design solves the problem that the original floor-standing unloading platform has poor support stability and lacks buffering capacity. The utility model has a reasonable structure, good support and buffering effect, simple structure and strong practicality."
[0004] The above-mentioned equipment is equipped with a support sleeve on the upper end surface of the support base plate, and a compression spring is installed inside the support sleeve, which can provide a certain buffer when loading and unloading materials, thereby increasing the stability of the equipment. However, when the equipment is transporting and unloading materials, it is necessary to rely on manpower to carry the materials, which easily increases the workload of the staff and has low work efficiency, and long-term transportation will inevitably cause harm to the health of the staff. Utility Model Content
[0005] Therefore, the technical problem to be solved by the utility model is to overcome the low material handling efficiency of a construction engineering unloading platform in the prior art, thereby providing a construction engineering unloading platform.
[0006] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0007] include:
[0008] A working platform, a trolley is overlapped on the top of the working platform, handles are fixedly connected to both sides of the trolley, a baffle is rotatably connected to one side of the top of the working platform, a first movable groove is opened on the surface of the baffle, a trapezoidal slide rail is slidably connected to the inner wall of the baffle, a support plate is fixedly connected to one side of the trapezoidal slide rail, and the surface of the support plate is slidably connected to the inner wall of the baffle, a second movable groove is opened on the surface of the support plate, and a handle is fixedly connected to one side of the support plate.
[0009] As an optional technical solution, the bottom of the working platform is rotatably connected to a folding frame, one side of the folding frame is fixedly connected to a connecting rod, and the inner wall of the connecting rod is rotatably connected to a gas rod.
[0010] As an optional technical solution, one side of the gas rod is fixedly connected to a hose, and one side of the hose is fixedly connected to a pressure pump.
[0011] As an optional technical solution, the bottom of the folding frame is rotatably connected to a base, two sides of the inner wall of the base are provided with sliding grooves, and one side of the folding frame is slidably connected to the inner wall of the sliding groove, and two sides of the base are fixedly connected with rollers.
[0012] As an optional technical solution, a guardrail is fixedly connected to the top of the working platform, and a slot is provided on one side of the guardrail.
[0013] As an optional technical solution, the inner wall of the guardrail is slidably connected with a latch, and the top of the latch is fixedly connected with a push plate.
[0014] As an optional technical solution, two sides of the baffle are fixedly connected with clamping blocks, and the inner wall of the clamping block is provided with a slot.
[0015] The utility model technical solution has the following advantages:
[0016] 1. The utility model can transport materials to various locations on the construction site more effectively and conveniently through the trolley on the top of the working platform, and the use of the trolley is more labor-saving than manual handling. After the baffle is opened and one side of the baffle is overlapped to the surface of the floor, the baffle can provide a platform with good support for the trolley. When the distance is not enough, the support plate can be pulled out, thereby effectively expanding the area of the support platform, making it easier to push the trolley. The first movable groove and the second movable groove can limit the driving trajectory of the trolley to avoid the heavy weight of the trolley after loading, which is easy to fall off from the working platform, thereby improving the safety of the equipment.
[0017] 2. The utility model drives the folding frame to fold and unfold through the extension and retraction of the gas rod. The folding and unfolding of the folding frame drives the top working platform to rise and fall. The lifting and lowering of the working platform makes it convenient for the staff to transport materials to a higher position, thereby improving the work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 A front view of a device provided in a first embodiment of the utility model;
[0019] Figure 2 is a three-dimensional diagram of the gas rod;
[0020] Figure 3 The figure is a three-dimensional diagram of the structure of the working platform;
[0021] Figure 4 This is the structural expansion diagram of the baffle;
[0022] Figure 5 It is a three-dimensional diagram of the structure of the cart.
[0023] In the figure: 1. working platform; 2. trolley; 3. handle; 4. baffle; 5. first movable groove; 6. block; 7. trapezoidal slide rail; 8. support plate; 9. second movable groove; 10. pull handle; 11. folding frame; 12. connecting rod; 13. gas rod; 14. hose; 15. pressure pump; 16. base; 17. roller; 18. guardrail; 19. slot; 20. latch; 21. push plate; 22. slide groove; 23. slot. DETAILED DESCRIPTION
[0024] The technical solution of the utility model will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0025] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0026] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0027] In addition, the technical features involved in the different embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other. Specific implementation method:
[0029] Reference Figure 1 , Figure 3 , Figure 4 and Figure 5 As shown, a construction engineering unloading platform comprises: a working platform 1, a trolley 2 is overlapped on the top of the working platform 1, handles 3 are fixedly connected to both sides of the trolley 2, a baffle 4 is rotatably connected to one side of the top of the working platform 1, a first movable groove 5 is opened on the surface of the baffle 4, a trapezoidal slide rail 7 is slidably connected to the inner wall of the baffle 4, a support plate 8 is fixedly connected to one side of the trapezoidal slide rail 7, and the surface of the support plate 8 is slidably connected to the inner wall of the baffle 4, a second movable groove 9 is opened on the surface of the support plate 8, and a pull handle 10 is fixedly connected to one side of the support plate 8;
[0030] First open the baffle 4, load the materials into the trolley 2, then hold the handle 3 to push the trolley 2 to the surface of the baffle 4, push the trolley 2 to the top of the working platform 1 after passing the baffle 4, and then close the baffle 4. When the working platform 1 reaches the same height as the floor, open the baffle 4 by rotating it, overlap one side of the baffle 4 on the surface of the floor, and then push the trolley 2 into the first movable groove 5 at the top of the baffle 4, and then push the trolley 2 into the floor through the guidance of the first movable groove 5. When the gap between the working platform 1 and the floor is too large, hold the pull handle 10 to pull the support plate 8 out of the baffle 4 through the trapezoidal slide rail 7, overlap one side of the support plate 8 on the surface of the floor, and then push the trolley 2 into the floor through the first movable groove 5 and the second movable groove 9, and then take out the materials in the trolley 2, thereby completing the transportation of materials.
[0031] Reference Figure 1 and Figure 2As shown, the bottom of the working platform 1 is rotatably connected to a folding frame 11, one side of the folding frame 11 is fixedly connected to a connecting rod 12, the inner wall of the connecting rod 12 is rotatably connected to a gas rod 13, one side of the gas rod 13 is fixedly connected to a hose 14, one side of the hose 14 is fixedly connected to a pressure pump 15, the bottom of the folding frame 11 is rotatably connected to a base 16, both sides of the inner wall of the base 16 are provided with slide grooves 22, and one side of the folding frame 11 is slidably connected to the inner wall of the slide groove 22, and both sides of the base 16 are fixedly connected to rollers 17;
[0032] After placing the trolley 2 on the working platform 1, the pressure pump 15 is turned on. The pressure pump 15 inflates the gas rod 13 through the hose 14. After the gas enters the gas rod 13, the gas rod 13 is extended. The gas rod 13 is extended by rotating in the connecting rod 12. Since one side of the bottom of the folding frame 11 rotates on the inner wall of the base 16, and one side of the other group of folding frames 11 is slidably connected to the slide groove 22, the folding frame 11 can be pushed to unfold upward. After the folding frame 11 is unfolded, it supports the bottom of the working platform 1 and drives the working platform 1 to rise.
[0033] Reference Figure 1 , Figure 3 and Figure 4 As shown, a guardrail 18 is fixedly connected to the top of the working platform 1, a card slot 19 is opened on one side of the guardrail 18, a latch 20 is slidably connected to the inner wall of the guardrail 18, a push plate 21 is fixedly connected to the top of the latch 20, and a card block 6 is fixedly connected to both sides of the baffle 4, and a slot 23 is opened on the inner wall of the card block 6;
[0034] Before opening the baffle 4, first pull the push plate 21 upwards. The rise of the push plate 21 drives the latch 20 to rise. After the latch 20 rises, the baffle 4 is opened from one side of the guardrail 18 by rotating. After using the baffle 4, rotate the baffle 4 to overlap the card block 6 into the card slot 19, then hold the push plate 21 to insert the latch 20 into the guardrail 18, and then insert the latch 20 into the slot 23 after resetting, so as to fix the baffle 4.
[0035] Working principle: first open the baffle 4, put the materials into the trolley 2, then hold the handle 3 to push the trolley 2 to the surface of the baffle 4, push the trolley 2 to the top of the working platform 1 after passing the baffle 4, and then close the baffle 4. After placing the trolley 2 on the working platform 1, turn on the pressure pump 15, and the pressure pump 15 inflates the gas rod 13 through the hose 14. After the gas enters the gas rod 13, the gas rod 13 is extended. The gas rod 13 is extended by rotating in the connecting rod 12. Since one side of the bottom of the folding frame 11 rotates on the inner wall of the base 16, and one side of the other set of folding frames 11 is slidably connected to the slide groove 22, the folding frame 11 can be pushed to unfold upward. After the folding frame 11 is unfolded, it can be pulled out from The bottom of the working platform 1 is supported and driven to rise. When the working platform 1 reaches the height consistent with the floor, the baffle 4 is opened by rotation, and one side of the baffle 4 is overlapped on the surface of the floor, and then the trolley 2 is pushed into the first movable groove 5 at the top of the baffle 4, and then the trolley 2 is pushed into the floor through the guidance of the first movable groove 5. When the gap between the working platform 1 and the floor is too large, hold the handle 10 to pull the support plate 8 out of the baffle 4 through the trapezoidal slide rail 7, overlap one side of the support plate 8 on the surface of the floor, and then push the trolley 2 into the floor through the first movable groove 5 and the second movable groove 9, and then take out the materials in the trolley 2, thereby completing the transportation of materials.
[0036] Obviously, the above embodiments are merely examples for the purpose of clear explanation, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived from them are still within the scope of protection of the utility model creation.
Claims
1. A construction engineering unloading platform, comprising a working platform (1), characterized in that: A trolley (2) is overlapped on the top of the working platform (1), and handles (3) are fixedly connected to both sides of the trolley (2). A baffle (4) is rotatably connected to one side of the top of the working platform (1), and a first movable groove (5) is provided on the surface of the baffle (4). A trapezoidal slide rail (7) is slidably connected to the inner wall of the baffle (4), and a support plate (8) is fixedly connected to one side of the trapezoidal slide rail (7), and the surface of the support plate (8) is slidably connected to the inner wall of the baffle (4). A second movable groove (9) is provided on the surface of the support plate (8), and a handle (10) is fixedly connected to one side of the support plate (8).
2. A construction engineering unloading platform according to claim 1, characterized in that: The bottom of the working platform (1) is rotatably connected to a folding frame (11), one side of the folding frame (11) is fixedly connected to a connecting rod (12), and the inner wall of the connecting rod (12) is rotatably connected to a gas rod (13).
3. A construction engineering unloading platform according to claim 2, characterized in that: One side of the gas rod (13) is fixedly connected to a hose (14), and one side of the hose (14) is fixedly connected to a pressure pump (15).
4. A construction engineering unloading platform according to claim 2, characterized in that: The bottom of the folding frame (11) is rotatably connected to a base (16), two sides of the inner wall of the base (16) are provided with sliding grooves (22), and one side of the folding frame (11) is slidably connected to the inner wall of the sliding groove (22), and two sides of the base (16) are fixedly connected to rollers (17).
5. A construction engineering unloading platform according to claim 1, characterized in that: A guardrail (18) is fixedly connected to the top of the working platform (1), and a slot (19) is provided on one side of the guardrail (18).
6. A construction engineering unloading platform according to claim 5, characterized in that: The inner wall of the guardrail (18) is slidably connected with a latch (20), and the top of the latch (20) is fixedly connected with a push plate (21).
7. A construction engineering unloading platform according to claim 1, characterized in that: Blocks (6) are fixedly connected to both sides of the baffle (4), and slots (23) are provided on the inner wall of the block (6).