Production line for automatic assembly of modular integrated building wall
By designing a modular integrated building wall automatic assembly production line, using mold platform flow system and installation robot components, the problems of low output and inaccurate splicing in the existing technology are solved, and efficient and accurate automated production of building walls is achieved.
Patent Information
- Application Number
- CN202420026362.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-05
- Publication Date
- 2024-11-08
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing modular integrated building box production methods have problems such as low output, low production efficiency, inaccurate splicing and high manual operation intensity, which affects the building quality and work efficiency.
A production line for automatic assembly of modular integrated building walls was designed, including mold table flow system, side wall installation robot, roof panel installation robot, side wall transportation silo and roof panel transportation silo. Automatic assembly of walls is achieved through automated assembly lines. , reduce manual operations.
Automatic assembly line operation is realized, production efficiency and splicing accuracy are improved, and building quality and work efficiency are significantly improved.
Smart Images

Figure CN221967322U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building decoration, in particular to a production line for automatic assembly of modular integrated building walls. Background Art
[0002] Modular Integrated Construction (MIC) is a prefabricated building with the highest assembly rate and the highest degree of industrialization. The production of the hexahedral concrete modular integrated building box is through pouring concrete in a mold, then curing the concrete in the mold to solidify and form it, and finally demolding to form the required modular integrated building box.
[0003] The modular integrated building box production method in the prior art has the following disadvantages: low output, which cannot effectively meet the actual market demand; the production line is mostly manually operated, the workers have high labor intensity and low production efficiency; when installing the mold, the wall is transported to the mold installation station and assembled manually, which is prone to inaccurate splicing, thus affecting the quality of the production of modular integrated buildings. Secondly, after assembly, manual demolding is required, which affects work efficiency. Utility Model Content
[0004] In view of the problems existing in the prior art, the utility model provides a production line for automatic assembly of modular integrated building walls.
[0005] In order to achieve the above purpose, the technical solution of the utility model is as follows:
[0006] The utility model provides a production line for automatic assembly of modular integrated building walls, comprising: a mold platform circulation system, a side wall installation robot, a top plate installation robot, a side wall transport silo 1, a side wall transport silo 2 and a top plate transport silo;
[0007] The mold pallet circulation system includes a ground transfer system and an assembly platform arranged on the ground transfer system;
[0008] The side wall installation robot, the top plate installation robot, the side wall transport silo 1, the side wall transport silo 2, and the top plate transport silo are all arranged on the ground transfer system.
[0009] Preferably, the ground transfer system consists of a guide rail, a friction drive wheel mechanism, a lifting mechanism and a formwork platform walking wheel mechanism, and is pre-buried in the concrete structure; the friction drive wheel mechanism and the formwork platform walking wheel mechanism are arranged between the two guide rails; the lifting mechanism is arranged below the friction drive wheel mechanism and the formwork platform walking wheel mechanism, and is used to lift the friction drive wheel mechanism and the formwork platform walking wheel mechanism.
[0010] Preferably, the assembly platform is arranged on the guide rail of the ground transfer system, the wall transport silo 1 is placed next to the assembly platform, and the assembly platform and the wall transport silo 1 are both placed below the side wall installation robot; the top plate installation robot is placed next to the side wall installation robot, and the side wall transport silo 2 and the top plate transport silo are both arranged on the guide rail of the ground transfer system and placed below the top plate installation robot.
[0011] Preferably, the assembly platform comprises a mold platform, a bottom mold arranged on the mold platform, two outer molds 1 and two outer molds 2; the mold platform is arranged on a guide rail.
[0012] Preferably, the bottom mold, two outer molds one and two outer molds two are all arranged on the mold platform, the bottom mold is arranged in the middle of the mold platform, and the two outer molds one and two outer molds two are correspondingly arranged on the four sides of the mold platform; the mold platform is also provided with mold platform slide rails located on the four sides of the bottom mold, and the two outer molds one and two outer molds two are slidably connected to the mold platform through the mold platform slide rails and can move along the direction of the mold platform slide rails.
[0013] Preferably, the outer mold 1 and the outer mold 2 both include a fixed frame arranged on the mold platform slide rail, a movable plate arranged on the fixed frame, clamping claws symmetrically arranged on both sides of the movable plate, and a tensioning shaft arranged on the top of the movable plate; the tensioning shaft is symmetrically arranged at both ends of the movable plate, and the outer mold 2 also includes a multi-stage hydraulic cylinder arranged on the top of the movable plate, and the multi-stage hydraulic cylinder is placed between the two tensioning shafts.
[0014] Preferably, the side wall installation robot is used to assemble the side wall with splicing onto the outer mold 1 and the two outer molds 2, and the top plate installation robot is used to assemble the top plate wall to be spliced onto the top rod platform of the multi-stage hydraulic cylinder.
[0015] Preferably, the side wall mounting robot and the top plate mounting robot both include a base frame, a Y-axis slide rail arranged on the base frame, a crossbeam arranged on the Y-axis slide rail, an X-axis slide rail arranged on the crossbeam, and a slide table arranged on the X-axis slide rail; the base frame is arranged on the concrete structure.
[0016] Preferably, the side wall transport silo 1, the side wall transport silo 2 and the top plate transport silo all include fixed racks and silos arranged on the fixed racks; the fixed racks are arranged on the concrete structure; and the silos are used to place walls to be spliced.
[0017] The technical solution of the utility model has the following beneficial effects:
[0018] The utility model transports side wall QT1 and side wall QT3 through side wall transport silo one, side wall transport silo two is used to transport side wall QT2 and side wall QT4, top plate transport silo transports top plate QT5, side wall installation robot is used to install side wall QT1 and side wall QT3, side wall QT2 and side wall QT4 on the assembly platform, and the top plate installation robot correspondingly installs the top plate QT5 on the assembly platform, thereby realizing automatic assembly, reducing manual operation, greatly improving work efficiency, and accurately splicing, effectively improving the production quality of modular integrated buildings, thereby realizing automated assembly line operation of modular integrated building walls. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 This is a schematic diagram of the structure of the modular integrated building wall automatic assembly system of the utility model;
[0020] Figure 2 This is a schematic diagram of the structure of the mold platform circulation system of the utility model;
[0021] Figure 3 This is a schematic diagram of the structure of the assembly platform of the utility model;
[0022] Figure 4 This is a schematic diagram of the structure of the side wall installation robot of the utility model;
[0023] Figure 5 This is a schematic diagram of the structure of the top plate installation robot of the utility model;
[0024] Figure 6 This is a structural schematic diagram of a side wall transport silo of the utility model;
[0025] Figure 7 This is a schematic diagram of the second structure of the side wall transport silo of the utility model;
[0026] Figure 8 This is a schematic diagram of the structure of the top plate transport silo system of the utility model;
[0027] Fig. 9 This is a schematic diagram of the modular integrated building wall structure of the utility model. DETAILED DESCRIPTION
[0028] The embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention.
[0029] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0030] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present utility model, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0031] In the present invention, unless otherwise clearly specified and limited, the terms "install", "connect", "connect", "fix" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0032] In the present invention, unless otherwise expressly specified or limited, a first feature is “on” or “below” a second feature.
[0033] “Under” may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, the first feature being “above”, “above”, and “above” the second feature includes the first feature being directly above and obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. The first feature being “under”, “below”, and “below” the second feature includes the first feature being directly below and obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0034] Reference Figures 1 to 9 The utility model provides a production line for automatic assembly of modular integrated building walls, including: a mold platform circulation system 100, a side wall installation robot 200, a top plate installation robot 300, a side wall transport silo 1 400, a side wall transport silo 2 500 and a top plate transport silo 600;
[0035] Reference Fig. 9 , the modular integrated building wall is assembled by side wall QT1, side wall QT2, side wall QT3, side wall QT4 and top plate QT5, wherein the side wall QT1 and the side wall QT3 have prefabricated steel plates on one side, the side wall QT2 has prefabricated steel plates on both sides, the side wall QT1, the side wall QT3 and the side wall QT2 are welded at the joints, the side wall QT1, the side wall QT3 and the side wall QT4 are cast in situ with the side formwork, and the top plate QT5 and the side wall QT1, the side wall QT2, the side wall QT3 and the side wall QT4 are cast in situ with the side formwork;
[0036] The mold pallet circulation system 100 includes a ground transfer system 110 and an assembly platform 120 arranged on the ground transfer system 110; the side wall installation robot 200, the top plate installation robot 300, the side wall transport silo 1 400, the side wall transport silo 2 500, and the top plate transport silo 600 are all arranged on the ground transfer system (110); the side wall transport silo 1 400 is used to transport the side wall QT1 and the side wall QT3, and the side wall transport silo 2 500 is used to transport the side wall QT1 and the side wall QT3. 0 is used to transport side wall QT2 and side wall QT4, the top plate transport silo 600 is used to transport top plate QT5, the side wall installation robot 200 is used to install side wall QT1 and side wall QT3, side wall QT2 and side wall QT4 transported by side wall transport silo one 400 and side wall transport silo two 500 on the assembly platform 120, and the top plate installation robot 300 correspondingly installs the top plate QT5 transported by the top plate transport silo 600 on the assembly platform 120.
[0037] Reference Figure 2 Furthermore, the ground transfer system 110 is composed of a guide rail 110a, a friction drive wheel mechanism 110b, a lifting mechanism and a mold platform walking wheel mechanism 110c, and is pre-buried in the concrete structure; the friction drive wheel mechanism 110b and the mold platform walking wheel mechanism 110c are arranged between the two guide rails 110a; the lifting mechanism is arranged below the friction drive wheel mechanism 110b and the mold platform walking wheel mechanism 110c, and is used to lift the friction drive wheel mechanism 110b and the mold platform walking wheel mechanism 110c; the friction drive wheel mechanism 110b includes a driving motor and a friction driving wheel installed at the output end of the motor. When the driving motor is working, it can drive the friction driving wheel to move. The lifting mechanism can be set as a lifting cylinder. The mold platform walking wheel mechanism includes a mounting seat and a walking wheel set on the mounting seat. The lifting mechanism is used to drive the friction driving wheel mechanism and its mold platform walking wheel mechanism to lift. The friction driving wheel mechanism is used to provide power to the ground transfer system 110 and the mold platform walking wheel mechanism, and is used to drive the components installed on the guide rail to slide along the guide rail direction.
[0038] Reference Figure 3Furthermore, the assembly platform 120 is arranged on the guide rail of the ground transfer system 110, the wall transport silo 1 400 is placed next to the assembly platform 120, and the assembly platform 120 and the wall transport silo 1 400 are both placed below the side wall installation robot 200; the top plate installation robot 300 is placed next to the side wall installation robot 200, and the side wall transport silo 2 500 and the top plate transport silo 600 are both arranged on the guide rail of the ground transfer system 110 and placed below the top plate installation robot 300; the assembly platform includes a mold table 121, a bottom mold (122) arranged on the mold table 121, two outer molds 1 123 and two outer molds 2 124; the mold table 121 is arranged on the guide rail, and can move in the horizontal direction and the vertical direction under the action of the friction drive wheel mechanism, the lifting mechanism and the mold table walking wheel mechanism. The bottom mold, two outer molds 123 and two outer molds 124 are all arranged on the mold platform, the bottom mold 122 is arranged in the middle of the mold platform 121, the two outer molds 123 and two outer molds 124 are correspondingly arranged on the four sides of the mold platform 121, wherein the two outer molds 123 are arranged opposite to each other, and correspondingly, the two outer molds 124 are also arranged opposite to each other; the mold platform 121 is also provided with mold platform slide rails located on the four sides of the bottom mold 122, the two outer molds 123 and two outer molds 124 are all slidably connected to the mold platform through the mold platform slide rails, and can move along the direction of the mold platform slide rails to open or retract, wherein the outer mold 123 is used to assemble the side wall QT1 and the side wall QT3, and the outer mold 2 124 is used to assemble the side wall QT2 and the side wall QT4.
[0039] Further, the outer mold 1 123 and the outer mold 2 124 each include a fixed frame 1241 arranged on the mold platform slide rail, a movable plate 1242 arranged on the fixed frame 1241, clamping claws 1243 symmetrically arranged on both sides of the movable plate 1242, and a tightening shaft 1244 arranged on the top of the movable plate 1242; the tightening shaft 1244 is symmetrically arranged at both ends of the movable plate 1242, and is used to be inserted into the positioning hole on the wall lifting frame for assembly positioning, and is tightened to fix the wall after assembly. The outer mold 2 124 also includes a clamping claw 1243 arranged on the movable plate 1243. 2 The multi-stage hydraulic cylinder 1245 on the top, the fixed frame 1241 is used to support the side wall, the clamping claw 1243 is used to clamp the side wall to be spliced, the multi-stage hydraulic cylinder 1245 is placed between the two expansion shafts 1244, and the multi-stage hydraulic cylinders are symmetrically distributed about the fixed frame to support the top plate; the side wall installation robot 200 is used to assemble the spliced side wall to the outer mold 1 123 and the two outer molds 124, and the top plate installation robot 300 is used to assemble the top plate wall to be spliced onto the top rod platform of the multi-stage hydraulic cylinder 1245.
[0040] Reference Figures 4 to 5Furthermore, the side wall mounting robot 200 and the top plate mounting robot 300 both include a base frame 210 / 310, a Y-axis slide rail arranged on the base frame 210 / 310, a beam 220 / 320 arranged on the Y-axis slide rail, an X-axis slide rail arranged on the beam 220 / 320, and a slide 230 / 330 arranged on the X-axis slide rail; the base frame is arranged on the concrete structure, wherein the beam 220 can slide along the Y-axis slide rail, and the slide 230 / 330 can slide along the X-axis slide rail, and then the slide 230 / 330 can be used to move on the Y-axis and X-axis; wherein the slide 230 / 330 includes a Z-axis cylinder, a telescopic shaft arranged at the output end of the Z-axis cylinder, a rotating cylinder arranged on the telescopic shaft, and a hook installed at the output end of the rotating cylinder.
[0041] Reference Figures 6 to 8 The side wall transport silo 1 400, the side wall transport silo 2 500 and the top plate transport silo 600 all include a fixed rack 410 / 510 / 610 and a silo 420 / 520 / 620 arranged on the fixed rack 410 / 510 / 610; the fixed rack is arranged on the concrete structure; the silo 420 / 520 / 620 is used to place the wall 430 / 530 / 630 to be spliced, and the silo 420 is used to load the side The wall QT1 and the side wall QT3 can be transported to the fixed rack 410 by the AGV transport vehicle and placed on the fixed rack 410. The silo 520 is used to load the side wall QT2 and the side wall QT4, which can be transported to the fixed rack 510 by the AGV transport vehicle and placed on the fixed rack 510. The silo 620 is used to load the top plate QT5, which can be transported to the fixed rack 610 by the AGV transport vehicle and placed on the fixed rack 610.
[0042] Working principle of this utility model:
[0043] At the beginning, the AGV transport vehicles loaded with different walls are parked at the designated location and ready;
[0044] First, the AGV transport vehicle carrying the QT1 side wall and the QT3 side wall moves along the dedicated channel, stops at the designated position of the fixed rack 410 and places the silo 420.
[0045] First, assemble the side wall QT1. The crossbeam and slide 230 of the installation robot 200 move successively and position the lifting frame of the side wall QT1. After positioning, the telescopic shaft on the slide 230 drops a certain distance. After dropping, the hook rotates 90 degrees, and then the telescopic shaft slowly rises until the hook hooks the lifting frame. After hooking, the telescopic shaft continues to rise to drive the side wall QT1 out of the silo. Then, the crossbeam and slide move in coordination to transport the side wall QT1 to its initial assembly position. Subsequently, the crossbeam moves slowly to align the positioning hole on the lifting frame of the side wall QT1 with the expansion shaft. After alignment, the telescopic shaft slowly drops to make the lifting frame of the side wall QT1 fall onto its outer mold fixing frame, and the expansion shaft is tightened. Then, the telescopic shaft continues to drop a certain distance. After dropping, the hook rotates 90 degrees, and finally the telescopic shaft rises, so that the side wall QT1 is assembled.
[0046] Similarly, the side wall QT3 is assembled. After the assembly is completed, the outer molds 123 of the side walls QT1 and QT3 are moved inwards and closed, and the mold platform moves along the guide rail to the next station.
[0047] Then, the AGV transport vehicle carrying the side wall QT2 and the side wall QT4 moves along the dedicated channel, stops at the designated position of the fixed material rack and places the material bin. The assembly process of the side wall installation robot 200 for the side wall QT2 and the side wall QT4 is different from that for the side wall QT1 and the side wall QT3 in only one step, that is, the slide 230 moves slowly to align the positioning hole on the lifting rack with the tensioning shaft. After the assembly is completed, the fixed racks of the outer mold 12 of the side wall QT2 and the side wall QT4 move inward and close, and then the mold table moves horizontally to the next station.
[0048] Then, the AGV transport vehicle carrying the top plate QT5 moves along the dedicated channel, stops at the designated position of the fixed material rack 610 and places the silo 620. The assembly process of the top plate QT5 is different from the above four walls only in the following steps.
[0049] When the top plate QT5 is transported to the assembly position, the multi-stage hydraulic cylinder 1245 extends the first and second telescopic rods in sequence, and the top rod rises to the specified position after all are extended. Subsequently, the telescopic shaft on the slide 230 slowly descends to place the top plate QT5 on the four top rod platforms.
[0050] After the above process is completed, the automatic assembly of the modular integrated building wall is completed.
[0051] The above description is only a preferred embodiment of the utility model, and does not limit the patent scope of the utility model. All equivalent structural changes made by using the contents of the utility model specification and drawings under the utility model concept, or directly / indirectly used in other related technical fields are included in the patent protection scope of the utility model.
Claims
1. A production line for automatic assembly of modular integrated building walls, characterized in that: include: A mold platform circulation system (100), a side wall installation robot (200), a top plate installation robot (300), a side wall transport silo 1 (400), a side wall transport silo 2 (500) and a top plate transport silo (600); The mold platform circulation system (100) comprises a ground transfer system (110) and an assembly platform (120) arranged on the ground transfer system (110); The side wall installation robot (200), the top plate installation robot (300), the side wall transport silo one (400), the side wall transport silo two (500), and the top plate transport silo (600) are all arranged on the ground transfer system (110).
2. The production line for automatic assembly of modular integrated building walls according to claim 1 is characterized in that: The ground transfer system (110) is composed of a guide rail, a friction drive wheel mechanism, a lifting mechanism and a mold platform walking wheel mechanism, and is pre-buried in the concrete structure; the friction drive wheel mechanism and the mold platform walking wheel mechanism are arranged between two guide rails; the lifting mechanism is arranged below the friction drive wheel mechanism and the mold platform walking wheel mechanism, and is used to lift the friction drive wheel mechanism and the mold platform walking wheel mechanism.
3. The production line for automatic assembly of modular integrated building walls according to claim 2 is characterized in that: The assembly platform (120) is arranged on the guide rail of the ground transfer system (110), the wall transport silo one (400) is placed next to the assembly platform (120), and the assembly platform (120) and the wall transport silo one (400) are both placed below the side wall installation robot (200); the top plate installation robot (300) is placed next to the side wall installation robot (200), and the side wall transport silo two (500) and the top plate transport silo (600) are both arranged on the guide rail of the ground transfer system (110) and are placed below the top plate installation robot (300).
4. The production line for automatic assembly of modular integrated building walls according to claim 3 is characterized in that: The assembly platform comprises a mold platform (121), a bottom mold (122) arranged on the mold platform (121), two outer molds (123) and two outer molds (124); the mold platform is arranged on a guide rail.
5. The production line for automatic assembly of modular integrated building walls according to claim 4 is characterized in that: The bottom mold, two outer molds (123) and two outer molds (124) are all arranged on a mold platform, the bottom mold (122) is arranged in the middle of the mold platform (121), and the two outer molds (123) and two outer molds (124) are correspondingly arranged on four sides of the mold platform (121); the mold platform (121) is also provided with mold platform slide rails located on the four sides of the bottom mold (122), and the two outer molds (123) and two outer molds (124) are slidably connected to the mold platform through the mold platform slide rails and can move along the direction of the mold platform slide rails.
6. The production line for automatic assembly of modular integrated building walls according to claim 5 is characterized in that: The outer mold 1 (123) and the outer mold 2 (124) both include a fixed frame (1241) arranged on the mold platform slide rail, a movable plate (1242) arranged on the fixed frame (1241), clamping claws (1243) symmetrically arranged on both sides of the movable plate (1242), and a tensioning shaft (1244) arranged on the top of the movable plate (1242); the tensioning shaft (1244) is symmetrically arranged at both ends of the movable plate (1242), and the outer mold 2 (124) also includes a multi-stage hydraulic cylinder (1245) arranged on the top of the movable plate (1242), and the multi-stage hydraulic cylinder (1245) is placed between the two tensioning shafts (1244).
7. The production line for automatic assembly of modular integrated building walls according to claim 6, characterized in that: The side wall installation robot (200) is used to assemble the side wall with splicing onto the outer mold 1 (123) and the outer mold 2 (124), and the top plate installation robot (300) is used to assemble the top plate wall to be spliced onto the top rod platform of the multi-stage hydraulic cylinder (1245).
8. The production line for automatic assembly of modular integrated building walls according to claim 7 is characterized in that: The side wall mounting robot (200) and the top plate mounting robot (300) both comprise a base frame (210), a Y-axis slide rail arranged on the base frame (210), a crossbeam (220) arranged on the Y-axis slide rail, an X-axis slide rail arranged on the crossbeam (220), and a slide table (230) arranged on the X-axis slide rail; the base frame is arranged on the concrete structure.
9. The production line for automatic assembly of modular integrated building walls according to claim 3, characterized in that: The side wall transport silo 1 (400), the side wall transport silo 2 (500) and the top plate transport silo (600) all include a fixed material rack and a silo arranged on the fixed material rack; the fixed material rack is arranged on a concrete structure; and the silo is used to place the wall to be spliced.
Citation Information
Cited By
Production line for automatic assembly of modular integrated building wall
CN117655741A
A production line for automatic assembly of modular integrated building wall
CN117655741B