Cement measuring hopper for concrete production
By introducing a mud unloading mechanism into the cement metering bucket, using the push cylinder to drive the beat block to form a reciprocating beat effect in the shell, the problem of mud retention and discharge speed is solved, and more efficient mud discharge and cleaning is achieved, and concrete production is improved. efficiency.
Patent Information
- Application Number
- CN202420505203.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-14
- Publication Date
- 2024-11-08
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
When used in the existing cement metering buckets in concrete production, the mud is prone to retention and discharge speed is slow, which affects the convenience of use and efficiency.
A cement metering bucket including a metering bucket body and a mud unloading mechanism is designed. The mud unloading mechanism is composed of a shell, a slap block, a force-bearing component and a push cylinder. By pushing the slap block to move in the shell, forming a reciprocating slap effect. Helps unload cement in the mud collector silo, reduces retention and accelerates discharge.
Through the reciprocating action of the mud unloading mechanism, the retention of mud is significantly reduced, the mud discharge rate is improved, and the efficiency of concrete production is convenient.
Smart Images

Figure CN221968478U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of concrete production, in particular to a cement measuring bucket for concrete production. Background Art
[0002] Concrete is made by mixing various raw materials in certain proportions, adding water and stirring to form a flowing slurry. During the mixing process, the cementitious materials react with the aggregates to gradually form a hard matrix, binding the various materials together into a durable, stone-like material.
[0003] Concrete has many characteristics, including abundant raw materials, low price, simple production process, high compressive strength, good durability, wide range of strength grades, etc. Therefore, concrete is widely used in various civil engineering projects, such as buildings, roads, bridges, tunnels, etc.
[0004] The existing Chinese patent with announcement number CN218535126U discloses a cement metering bucket of a concrete mixing station, including a fixed plate, a processing bin is installed on the upper surface of the fixed plate, an adjustment mechanism is provided on the inner wall of the processing bin, the adjustment mechanism includes a column and a pad, there are two columns, the tops of the two columns are installed on the inner top of the processing bin, the inner walls of the columns are movably installed with connecting blocks, a placement plate is movably installed between the two connection blocks, and a pulling block is fixedly installed on the top of the placement plate, which solves the problem that the device effectively controls the amount of cement according to the gravity of the cement.
[0005] Based on the above situation, the inventors now believe that when the current metering bucket is in use, mud is easily retained on the inner wall, and the mud is discharged slowly by natural gravity, which makes it difficult to increase the mud discharge rate and reduce the amount of mud retention, affecting the convenience and efficiency of use. Utility Model Content
[0006] The utility model aims to provide a cement measuring bucket for concrete production, which can accelerate the falling of mud, reduce the retention amount, facilitate cleaning and improve the use efficiency.
[0007] The above technical purpose of the utility model is achieved through the following technical solutions: A cement measuring bucket for concrete production, comprising a measuring bucket body and a mud unloading mechanism;
[0008] A bracket is arranged outside the measuring bucket body, a sensor is connected between the measuring bucket body and the bracket, and a mud collecting bin is integrally arranged at the bottom outside the measuring bucket body;
[0009] The mud unloading mechanism is installed outside the mud collecting bin to speed up the cement unloading rate in the mud collecting bin. The mud unloading mechanism includes an outer shell, a beater block, a force-bearing component and a push cylinder. The outer shell is fixedly installed on the outside of the mud collecting bin, and the side of the outer shell close to the mud collecting bin is an open structure. The beater block is slidably arranged in the opening of the outer shell, and the outer side of the beater block is in contact with the mud collecting bin through the opening of the outer shell. The force-bearing component is arranged on the beater block, and the beater block is connected to the output end of the push cylinder through the force-bearing component, so as to drive the beater block to move in the outer shell through the push cylinder, and beat the mud collecting bin to help unload the mud.
[0010] By adopting the above technical solution, the reciprocating beating of the mud collecting bin can be achieved to help the mud collecting bin to unload mud, reduce mud retention and accelerate discharge.
[0011] The utility model is further configured as follows: the force-bearing component includes an L-shaped frame, an active cavity and a contact block, one end of the L-shaped frame is fixed to the beat block, an active cavity for the output end of the push cylinder to operate is formed between the L-shaped frame and the mounting surface of the beat block, and a protruding contact block is arranged on one side of the outer side of the L-shaped frame close to the active cavity.
[0012] By adopting the above technical solution, the clapping block can be subjected to force synchronously with the contact block, so as to help the clapping block to move quickly.
[0013] The utility model is further configured as follows: a push block is fixedly mounted on the output end of the push cylinder after the output end of the push cylinder penetrates into the interior of the housing, and the output end of the push cylinder is in sliding contact with the surface of the contact block through the push block.
[0014] By adopting the above technical solution, the push block applies force to the contact block along the oblique edge of the contact block, so that the contact block drives the beat block to move synchronously.
[0015] The utility model is further configured as follows: the contact block is in an equilateral trapezoidal structure as a whole, and the end of the push block that contacts the contact block is in a spherical structure.
[0016] By adopting the above technical solution, the beating blocks are put into the same reciprocating displacement state, so that the outer wall of the mud collecting bin can be beaten by the beating blocks reciprocatingly.
[0017] The utility model is further configured as follows: an outwardly extended lengthened bin is integrally arranged on the outer side of the shell, and the outer side of the L-shaped frame is in sliding contact with the inner wall of the lengthened bin.
[0018] By adopting the above technical solution, the space required for the displacement of the L-shaped frame can be obtained by lengthening the compartment, so that the L-shaped frame can stably slide inside the shell.
[0019] The utility model is further configured as follows: a sliding column is vertically fixedly provided on one side of the racket block adjacent to the force-bearing component, a reset component is provided on the outer side of the shell, and the racket block is connected to the reset component through the sliding column.
[0020] By adopting the above technical solution, the reset component can provide a quick and stable reset elastic force for the racket block.
[0021] The utility model is further configured as follows: the reset assembly includes a cylinder, a sliding plate and a spring, the end of the cylinder is fixed to the outer shell, the sliding plate is slidably installed in the cylinder, one side of the sliding plate is vertically fixed to the sliding column, and the other side is connected to the inner wall of the cylinder through a spring.
[0022] By adopting the above technical solution, the beating blocks can beat the outer side of the mud collecting bin to accelerate the falling of the mud.
[0023] The beneficial effects of the utility model are:
[0024] When the metering bucket discharges mud, a mud unloading mechanism is set up so that the piston rod at the output end of the push cylinder can be extended and retracted at the same time, so that the push block can exert force on the contact block in the L-shaped frame, so that the slapping block and the contact block can maintain synchronous movement, and the slapping block is quickly reset through the reset component after being separated from the outer wall of the mud collecting bin, so as to form a reciprocating slapping effect outside the mud collecting bin, so that the mud on the inner wall of the mud collecting bin can be subjected to slapping oscillation, thereby reducing the amount of mud retention to facilitate cleaning, and also increasing the rate of mud discharge to facilitate rapid mud discharge and improve the efficiency of concrete production. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0026] Figure 1 A structural schematic diagram of a cement measuring bucket for concrete production provided by an embodiment of the utility model;
[0027] Figure 2 This is a schematic diagram of the structure of the mud unloading mechanism in the embodiment of the utility model;
[0028] Figure 3 This is a schematic diagram of the structure inside the housing in the embodiment of the utility model;
[0029] Figure 4 It is a schematic diagram of the structure of the reset component in the embodiment of the utility model.
[0030] In the figure, 1, metering bucket body; 2, mud unloading mechanism; 11, bracket; 12, sensor; 13, mud collecting bin; 14, control valve; 21, housing; 22, beat block; 23, force-bearing component; 24, push cylinder; 25, reset component; 26, extension bin; 231, L-shaped frame; 232, movable cavity; 233, contact block; 241, push block; 251, cylinder; 252, sliding plate; 253, spring; 221, sliding column. DETAILED DESCRIPTION
[0031] The technical solution of the utility model will be described clearly and completely below in conjunction with specific embodiments. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of them. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0032] The utility model embodiment specifically provides a cement measuring bucket for concrete production, please refer to Figure 1 , including a metering bucket body 1 and a mud unloading mechanism 2.
[0033] Among them, a bracket 11 is arranged outside the measuring bucket body 1, and the bottom of the bracket 11 contacts the placement surface to support the measuring bucket body 1 through the bracket 11. A sensor 12 is connected between the measuring bucket body 1 and the bracket 11. The type of the sensor 12 is a weighing sensor, and the upper and lower parts of the sensor 12 are respectively fixed to the bracket 11 and the measuring bucket body 1 through connecting ropes, so that when the measuring bucket body 1 is fed, the measuring bucket body 1 can be automatically weighed by the sensor 12 to obtain the weight of the material, so as to scientifically control the feeding and discharging of materials;
[0034] A mud collecting bin 13 is integrally provided at the outer bottom of the metering hopper body 1 , and an electronic control valve 14 is provided at the bottom of the mud collecting bin 13 to discharge the mud from the metering hopper body 1 by automatically opening and closing.
[0035] For further information, please refer to Figure 1 and Figure 2The mud unloading mechanism 2 is installed outside the mud collecting bin 13 to speed up the cement unloading rate in the mud collecting bin 13. The mud unloading mechanism 2 includes a shell 21, a beater block 22, a force-bearing component 23 and a push cylinder 24. The shell 21 is fixedly mounted on the outside of the mud collecting bin 13, and the side of the shell 21 close to the mud collecting bin 13 is an open structure. The beater block 22 is slidably arranged in the opening of the shell 21, and the outer side of the beater block 22 contacts the mud collecting bin 13 through the opening of the shell 21, so that when the beater block 22 slides inside the shell 21, the outer side of the beater block 22 can contact the mud collecting bin 13, and after the beater block 22 is displaced, a beating effect is formed, so that after the outer wall of the mud collecting bin 13 is subjected to the beating force, the mud on its inner wall can be subjected to the synchronous vibration force to reduce the retention and increase the rate at which the mud falls and is discharged.
[0036] The number of the mud unloading mechanisms 2 can be two or four, so as to contact with each surface of the mud collecting bin 13 and increase the mud dropping rate.
[0037] For details, please refer to Figure 3 The force-bearing component 23 is arranged on the pat block 22, and the pat block 22 is connected with the output end of the push cylinder 24 through the force-bearing component 23, so that the pat block 22 is driven by the push cylinder 24 to move in the shell 21, and the mud collecting bin 13 is beaten to help unload the mud. During implementation, the pat block 22 is connected with the push cylinder 24 through the force-bearing component 22, so that the pat block 22 can be driven by the push cylinder 24 to realize the reciprocating displacement of the pat block 22, so that the pat block 22 can form a reciprocating beating effect on the outer wall of the mud collecting bin 13, thereby meeting the effect of accelerating the falling of the mud.
[0038] Among them, the force-bearing component 23 includes an L-shaped frame 231, an active cavity 232 and a contact block 233. One end of the L-shaped frame 231 is fixed to the beat block 22. An active cavity 232 for the output end of the push cylinder 24 to operate is formed between the L-shaped frame 231 and the mounting surface of the beat block 22. The piston rod of the output end of the push cylinder 24 is retracted and extended along the length direction of the L-shaped frame 231. A protruding contact block 233 is arranged on the outer side of the L-shaped frame 231 close to the active cavity 232. The L-shaped frame 231 contacts the push cylinder 24 through the contact block 233, so that the beat block 22 can maintain synchronous force with the contact block 233, so as to help the beat block 22 to move quickly.
[0039] During implementation, after the output end of the push cylinder 24 penetrates into the interior of the outer shell 21, a push block 241 is fixedly installed thereon. The output end of the push cylinder 24 slides in contact with the surface of the contact block 233 through the push block 241. The contact block 233 is an equilateral trapezoidal structure as a whole. The end of the push block 241 that contacts the contact block 233 is a spherical structure to improve the contact convenience between the contact block 233 and the push block 241.
[0040] There is an installation gap between the output end of the push cylinder 24 and the beat block 22, and the size of the gap is greater than the displacement distance of the beat block 22, so as to provide sufficient space for the subsequent movement of the beat block 22. When the output end of the push cylinder 24 drives the push block 241 to be pushed in along the length direction of the L-shaped frame 231, the push block 241 contacts the surface of the contact block 233, so that the push block 241 applies force to the contact block 233 along the oblique edge of the contact block 233, so that the contact block 233 drives the beat block 22 to move synchronously, so that the beat block 22 is separated from the outer side of the mud collecting bin 13, and then when the push block 241 continues to slide, until After being separated from the contact block 233, the slapping block 22 can be automatically reset by the reset component 25, so that the slapping block 22 can complete a slapping of the outer wall of the mud collecting bin 13. When the push block 241 continues to move and contacts the next contact block 233, the slapping block 22 enters a reciprocating reset state, and when the push block 241 is reset and moved driven by the push cylinder 24, the slapping block 22 enters the same reciprocating reset state, so that the outer wall of the mud collecting bin 13 can be reciprocated by the slapping block 22, so that the mud on its inner wall can fall faster after being subjected to the vibration force.
[0041] Furthermore, an outwardly extended extension bin 26 is integrally provided on the outer side of the shell 21, and the outer side of the L-shaped frame 231 is in sliding contact with the inner wall of the extension bin 26, so that space for the displacement of the L-shaped frame 231 is obtained through the extension bin 26, so that the L-shaped frame 231 can stably slide inside the shell 21.
[0042] For further information, please refer to Figure 3 and Figure 4 A sliding column 221 is vertically fixed to one side of the adjacent force-bearing component 23 of the racket block 22. The number of the sliding columns 221 is four, and they are respectively arranged at the four corners of the outer side of the racket block 22. A reset component 25 is arranged on the outer side of the shell 21. After the sliding column 221 slides into the shell 21, it is connected with the reset component 25, and the sliding displacement direction of the sliding column 221 and the racket block 22 remains parallel, so that the racket block 22 can stably slide inside the shell 21 through the sliding column 221. The racket block 22 is connected to the reset component 25 through the sliding column 221, so as to provide a quick and stable reset elastic force for the racket block 22 through the reset component 25.
[0043] Specifically, the reset assembly 25 includes a cylinder 251, a sliding plate 252 and a spring 253. The end of the cylinder 251 is fixed to the outer shell 21, and the sliding plate 252 is slidably installed in the cylinder 251. One side of the sliding plate 252 is vertically fixed to the sliding column 221, and the other side is connected to the inner wall of the cylinder 251 through the spring 253. Both ends of the spring 253 are fixed to the sliding plate 252 and the cylinder 251, so that when the beat block 22 is displaced, it can drive the sliding column 221 to push the sliding plate 252, so that the sliding plate 252 presses the spring 253 and provides a reset elastic force for the beat block 22, so that the beat block 22 can beat the outer side of the mud collecting bin 13 to accelerate the falling of mud.
[0044] The control method of the present invention is to control by manually starting and closing the switch. The wiring diagram of the power element and the provision of power supply are common knowledge in the field, and the present invention is mainly used to protect mechanical devices, so the present invention will not explain the control method and wiring arrangement in detail.
Claims
1. A cement measuring bucket for concrete production, Features: It comprises a metering bucket body (1) and a mud unloading mechanism (2); A bracket (11) is arranged outside the measuring bucket body (1), a sensor (12) is connected between the measuring bucket body (1) and the bracket (11), and a mud collecting bin (13) is integrally arranged at the bottom outside the measuring bucket body (1); The mud unloading mechanism (2) is installed outside the mud collecting bin (13) to speed up the cement unloading rate in the mud collecting bin (13). The mud unloading mechanism (2) comprises an outer shell (21), a beater block (22), a force-bearing component (23) and a push cylinder (24). The outer shell (21) is fixedly installed on the outer shell of the mud collecting bin (13), and the side of the outer shell (21) close to the mud collecting bin (13) is an open structure. The beater block (22) is slidably arranged in the opening of the outer shell (21), and the outer side of the beater block (22) contacts the mud collecting bin (13) through the opening of the outer shell (21). The force-bearing component (23) is arranged on the beater block (22), and the beater block (22) is connected to the output end of the push cylinder (24) through the force-bearing component (23), so that the beater block (22) is driven to move in the outer shell (21) through the push cylinder (24), and the mud collecting bin (13) is beaten to help unloading mud.
2. A cement measuring bucket for concrete production according to claim 1, Features: The force-bearing component (23) comprises an L-shaped frame (231), an active cavity (232) and a contact block (233); one end of the L-shaped frame (231) is fixed to the beat block (22); an active cavity (232) for the output end of the push cylinder (24) to operate is formed between the mounting surfaces of the L-shaped frame (231) and the beat block (22); and a protruding contact block (233) is arranged on a side of the outer side of the L-shaped frame (231) close to the active cavity (232).
3. A cement measuring bucket for concrete production according to claim 2, Features: After the output end of the push cylinder (24) penetrates into the interior of the housing (21), a push block (241) is fixedly mounted thereon. The output end of the push cylinder (24) is in sliding contact with the surface of the contact block (233) via the push block (241).
4. A cement measuring bucket for concrete production according to claim 3, Features: The contact block (233) is in an equilateral trapezoidal structure as a whole, and the end of the push block (241) that contacts the contact block (233) is in a spherical structure.
5. A cement measuring bucket for concrete production according to claim 4, Features: An outwardly extending extension bin (26) is integrally provided on the outer side of the housing (21), and the outer side of the L-shaped frame (231) is in sliding contact with the inner wall of the extension bin (26).
6. A cement measuring bucket for concrete production according to claim 5, Features: A sliding column (221) is vertically fixedly provided on one side of the beat block (22) adjacent to the force-bearing component (23), a reset component (25) is provided on the outside of the housing (21), and the beat block (22) is connected to the reset component (25) via the sliding column (221).
7. A cement measuring bucket for concrete production according to claim 6, Features: The reset assembly (25) comprises a cylinder (251), a sliding plate (252) and a spring (253); the end of the cylinder (251) is fixed to the housing (21); the sliding plate (252) is slidably installed in the cylinder (251); one side of the sliding plate (252) is vertically fixed to the sliding column (221); and the other side is connected to the inner wall of the cylinder (251) through the spring (253).